SE

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

Chapter 06

Reinforced-Concrete Bridge Superstructures

Solid slab, T-beam, and RC box-girder bridge design. Effective flange width, Whitney stress block flexural design, AASHTO simplified sectional shear method, torsion in boxes, and detailing. Includes a full T-beam worked example (flexure + shear + fatigue + deflection) and a solid slab bridge example, plus a two-span continuous T-beam design challenge.

Estimated Time

10 Hours

Difficulty

Intermediate

AASHTO Refs

7 sections

Focus Area

RC Superstructures

Bookmark

Chapter

Engineering story

The workhorse of the U.S. short-span inventory

Roughly one in four highway bridges in the National Bridge Inventory is a cast-in-place reinforced-concrete slab or T-beam bridge. They dominate the 20–80 ft span range because they are built on falsework with a single trade — reinforcing ironworkers and concrete finishers — with no shop drawings, no fabrication lead time, and no bearings on short spans (the deck is monolithic with the abutment). The material sits in compression under service loads and rarely fatigues. When they are detailed properly, they last a century.

This chapter walks through the full AASHTO design of the three reinforced-concrete superstructure families — solid slab, T-beam, and RC box girder. We build up the section analysis (Whitney stress block), add the effective flange width, layer in shear and torsion, and finish with two complete worked examples and a design challenge.

Chapter objectives

What you will be able to do

Learning objectives

By the end of this chapter you will be able to:

  1. 1Choose between slab, T-beam, and RC box-girder superstructures based on span, width, and constructability.
  2. 2Apply AASHTO §4.6.2.6 to compute the effective flange width of a T-beam and use it in flexural design.
  3. 3Design longitudinal reinforcement for positive and negative moment using the Whitney stress block (§5.6.3).
  4. 4Check minimum reinforcement (§5.6.3.3), maximum reinforcement / ductility (§5.6.2.1), and crack control (§5.6.7).
  5. 5Design transverse shear reinforcement using the AASHTO simplified sectional method (§5.7.3.4.1).
  6. 6Add torsion design for curved or eccentric RC box girders (§5.7.3.6).
  7. 7Check fatigue on reinforcement (§5.5.3) and serviceability deflection (§2.5.2.6.2).
  8. 8Complete a full RC T-beam design — Strength I, Service I, Fatigue I — with every AASHTO check documented.

6.1 — RC superstructure families

Slab, T-beam, box

AASHTO LRFD §5.12.2, §5.12.3

The three RC superstructure families differ in how efficiently they place concrete in compression and steel in tension. A solid slab has the whole section engaged (inefficient for long spans because most of the concrete is unstressed near the neutral axis). A T-beam concentrates concrete near the compression face and steel near the tension face. A box girder adds a bottom slab that (a) provides a large compression flange for negative moment over interior supports and (b) closes the section to resist torsion.

Comparison of solid slab, T-beam, and RC box-girder bridge cross-sections with typical span ranges
Figure 6.1The three reinforced-concrete superstructure families. Slab bridges span 20–50 ft, T-beam bridges 40–80 ft, RC box-girder bridges 60–120 ft. Beyond 120 ft, prestressed concrete or steel takes over.
SystemSpan rangeDepth ratio (§2.5.2.6.3)Typical use
Solid slab20 – 50 ft1.2·(S+10)/30 (simple)Culverts, low-traffic county roads
T-beam40 – 80 ft0.070 L (simple), 0.065 L (cont.)State highway short spans
RC box girder60 – 120 ft0.060 L (simple), 0.055 L (cont.)Interchange ramps (Caltrans standard)

6.2 — Effective flange width

How much of the slab helps the beam?

AASHTO LRFD §4.6.2.6

For a T-beam, shear lag causes the longitudinal stress in the slab flange to be highest directly over the web and to fall off toward the mid-panel. AASHTO §4.6.2.6.1 replaces the true non-uniform stress with an equivalent uniform stress acting over an effective flange width beff. For interior girders,beff is simply the girder spacing S.

T-beam cross-section with effective flange width, slab thickness, web width, and actual vs equivalent stress distribution
Figure 6.2AASHTO §4.6.2.6 effective flange width concept. The true stress varies across the flange (shear lag); the code replaces it with a uniform stress acting on b_eff.
(6.1)
  1. Interior girder

    beff,int=Sb_{eff,int} = S
  2. Exterior girder

    beff,ext=do+min(S2, 6ts, Leff8)b_{eff,ext} = d_{o} + \min\left(\frac{S}{2},\ 6\cdot t_{s},\ \frac{L_{eff}}{8}\right)
beff,intb_{eff,int}
effective flange width, interior girder [in]
SS
center-to-center girder spacing [in]
beff,extb_{eff,ext}
effective flange width, exterior girder [in]
dod_{o}
overhang length (fascia to fascia-girder CL) [in]

6.3 — Flexural design

Whitney stress block, φ, and ductility

AASHTO LRFD §5.6.2, §5.6.3

AASHTO adopts the Whitney rectangular stress block for ultimate flexural analysis. The actual parabolic compression stress distribution is replaced by a uniform stress of 0.85 fc' acting over a depth a = β1·c.

Whitney rectangular stress block on a singly-reinforced concrete beam with strain diagram and force couple
Figure 6.3Whitney stress block. Force equilibrium (C = T) gives a = A_s f_y / (0.85 f'c b); moment equilibrium about the steel gives M_n = A_s f_y (d − a/2).
(6.2)
  1. Formula

    ϕMn=ϕAsfy(da2)Mu\phi M_{n} = \phi \cdot A_{s} \cdot f_{y} \cdot \left(d - \frac{a}{2}\right) \ge M_{u}
MnM_{n}
nominal flexural resistance [kip-in]
aa
depth of Whitney block = β₁·c [in]
AsA_{s}
tension steel area [in²]
dd
effective depth to tension steel [in]
phiphi
resistance factor = 0.90 for tension-controlled sections []

β₁ = 0.85 for fc' ≤ 4 ksi and drops 0.05 for each 1 ksi above 4 ksi, with a floor of 0.65 (AASHTO LRFD §5.6.2.2).

6.3.1 Ductility — the tension-controlled requirement

AASHTO §5.6.2.1 requires the net tensile strain εt at the extreme tension steel to be at least 0.005 for the full φ = 0.90 to apply. Between 0.002 and 0.005 the section is a transition zone and φ is linearly interpolated. Below 0.002 the section is compression-controlled and φ = 0.75. Bridge girders are almost always designed tension-controlled by keeping c/dt ≤ 0.375.

6.3.2 Minimum reinforcement — §5.6.3.3

(6.3)
  1. Formula

    ϕMnmin(1.33Mu, 1.2Mcr)\phi M_{n} \ge \min\left(1.33\cdot M_{u},\ 1.2\cdot M_{cr}\right)

Mcr is the cracking moment computed from the modulus of rupturefr = 0.24·√fc' (ksi) per AASHTO LRFD §5.4.2.6.

6.3.3 Crack control — §5.6.7

(6.4)
  1. Formula

    smax=700γeβsfss2dcs_{max} = \frac{700\cdot \gamma_{e}}{\beta_{s}\cdot f_{ss}} - 2\cdot d_{c}
smaxs_{max}
maximum allowable bar spacing [in]
gammaegamma_{e}
exposure factor: 1.0 (Class 1), 0.75 (Class 2) []
fssf_{ss}
service tensile stress in reinforcement [ksi]
dcd_{c}
cover to center of nearest bar [in]
eta_{s}
1 + d_c / (0.7·(h − d_c)) []

6.4 — Shear design

AASHTO simplified sectional method

AASHTO LRFD §5.7.3

AASHTO §5.7.3 offers three shear procedures. For RC (non-prestressed) members, the simplified sectional method (§5.7.3.4.1) is by far the most common: it fixes β = 2.0 and θ = 45° and reduces to the familiar ACI-like form.

AASHTO simplified shear model with concrete contribution V_c and stirrup contribution V_s
Figure 6.4Simplified sectional model. Diagonal cracks form at 45°; concrete carries V_c across the compression zone and stirrups crossing the crack carry V_s.
(6.5)
  1. Formula

    Vn=Vc+Vs=0.0316βfcbvdv+AvfydvsV_{n} = V_{c} + V_{s} = 0.0316\cdot \beta \cdot \sqrt{f_{c}'}\cdot b_{v}\cdot d_{v} + \frac{A_{v}\cdot f_{y}\cdot d_{v}}{s}
VnV_{n}
nominal shear resistance [kip]
VcV_{c}
concrete contribution [kip]
VsV_{s}
steel contribution [kip]
dvd_{v}
effective shear depth = max(0.9·d, 0.72·h) [in]
AvA_{v}
area of one stirrup (2 legs) [in²]
ss
stirrup spacing [in]

The 0.0316 factor converts √fc' from psi units to ksi. With β = 2.0 this reduces to Vc = 0.0632·√fc'·bv·dv.

6.4.1 Minimum shear reinforcement — §5.7.2.5

(6.6)
  1. Formula

    Av,min=0.0316fcbvsfyA_{v,min} = \frac{0.0316\cdot \sqrt{f_{c}'}\cdot b_{v}\cdot s}{f_{y}}

6.4.2 Maximum stirrup spacing — §5.7.2.6

If vu < 0.125·fc': smax = min(0.8·dv, 24 in).
Otherwise: smax = min(0.4·dv, 12 in).

6.5 — Torsion in RC box girders

Closed-section torsion

AASHTO LRFD §5.7.3.6
RC box girder cross-section showing top and bottom slab reinforcement, web shear stirrups, and closed torsion hoops
Figure 6.5RC single-cell box girder. The closed section resists torsion by circulatory shear flow around the box; closed hoop stirrups plus longitudinal steel along all four faces are required.
(6.7)
  1. Formula

    Tn=2AoAtfyscotθT_{n} = \frac{2\cdot A_{o}\cdot A_{t}\cdot f_{y}}{s\cdot \cot\theta}
TnT_{n}
nominal torsional resistance [kip-in]
AoA_{o}
area enclosed by shear flow path ≈ 0.85·A_oh [in²]
AtA_{t}
area of one leg of closed torsion hoop [in²]
heta heta
diagonal-crack angle (default 45°) [deg]

Interaction check when both shear and torsion act (AASHTO LRFD §5.7.3.6.2): the equivalent shear stress from combined Vu and Tu must be below the concrete crushing limit 0.25·fc'.

6.5b — Worked example (torsion)

Torsional reinforcement design — RC single-cell box girder

AASHTO LRFD §5.7.2.1, §5.7.3.6

Given: single-cell RC box, overall b = 84 in, h = 60 in, wall thickness = 12 in, cover to hoop centerline = 2.5 in, fc' = 5 ksi, fy = 60 ksi. Factored effects at the section: Tu = 3,600 kip-in, Vu = 240 kip,dv = 54 in. Use φ = 0.90 (AASHTO LRFD §5.5.4.2), θ = 45°.

Step 1 — Section torsional properties

(Ex-6.5b.1)
  1. Perimeter to hoop centerline

    ph=2[(b2c)+(h2c)]p_{h} = 2\left[(b-2c)+(h-2c)\right]
  2. Substitute

    ph=2[(845)+(605)]=268 inp_{h} = 2\left[(84-5)+(60-5)\right] = 268\ \text{in}
  3. Enclosed area of hoop centerline

    Aoh=(b2c)(h2c)=7955=4,345 in2A_{oh} = (b-2c)(h-2c) = 79\cdot 55 = 4{,}345\ \text{in}^{2}
  4. Gross enclosed shear-flow area

    Ao0.85Aoh=0.85(4,345)=3,693 in2A_{o} \approx 0.85\,A_{oh} = 0.85(4{,}345) = 3{,}693\ \text{in}^{2}

Step 2 — Is torsion large enough to design for? (AASHTO LRFD §5.7.2.1)

(Ex-6.5b.2)
  1. Threshold torque

    Tcr=0.126λfc  Acp2pcT_{cr} = 0.126\,\lambda\sqrt{f'_{c}}\;\frac{A_{cp}^{2}}{p_{c}}
  2. A_cp = b·h, p_c = 2(b+h)

    Acp=8460=5,040 in2,  pc=2(84+60)=288 inA_{cp}=84\cdot 60=5{,}040\ \text{in}^{2},\ \ p_{c}=2(84+60)=288\ \text{in}
  3. Substitute (λ = 1.0)

    Tcr=0.126(1.0)55,0402288=24,870 kip-inT_{cr} = 0.126(1.0)\sqrt{5}\,\frac{5{,}040^{2}}{288} = 24{,}870\ \text{kip-in}
  4. Design threshold

    ϕ14Tcr=0.90(0.25)(24,870)=5,596 kip-in\phi\,\tfrac{1}{4}\,T_{cr} = 0.90(0.25)(24{,}870) = 5{,}596\ \text{kip-in}
  5. Compare

    Tu=3,600<5,596torsion could be neglectedT_{u}=3{,}600 < 5{,}596 \Rightarrow \text{torsion could be neglected}

For instructional purposes (and because eccentric live load on a curved box commonly pushesTu above the threshold), we proceed with full torsion design.

Step 3 — Required transverse hoop steel A_t / s

(Ex-6.5b.3)
  1. Formula (rearrange §5.7.3.6.2)

    Ats=Tuϕ2Aofycotθ\frac{A_{t}}{s} = \frac{T_{u}}{\phi\,2\,A_{o}\,f_{y}\,\cot\theta}
  2. Substitute

    Ats=3,6000.90(2)(3,693)(60)(1.0)\frac{A_{t}}{s} = \frac{3{,}600}{0.90\,(2)(3{,}693)(60)(1.0)}
  3. Result — one leg

    Ats=0.00902 in2/in per leg\frac{A_{t}}{s} = 0.00902\ \text{in}^{2}/\text{in per leg}

Step 4 — Combine with shear stirrups

(Ex-6.5b.4)
  1. Shear demand on stirrups

    Avs=Vu/ϕVcfydvcotθ\frac{A_{v}}{s} = \frac{V_{u}/\phi - V_{c}}{f_{y}\,d_{v}\,\cot\theta}
  2. V_c (β = 2.0, simplified)

    Vc=0.0316βfcbvdv=0.0316(2.0)5(24)(54)=183 kipV_{c}=0.0316\,\beta\sqrt{f'_{c}}\,b_{v}\,d_{v}=0.0316(2.0)\sqrt{5}(24)(54)=183\ \text{kip}
  3. Substitute (b_v = two 12-in webs)

    Avs=240/0.9018360(54)(1.0)=0.0258 in2/in\frac{A_{v}}{s} = \frac{240/0.90 - 183}{60(54)(1.0)} = 0.0258\ \text{in}^{2}/\text{in}
  4. Combined per web (one leg = A_v/2 + A_t)

    Av+2Ats=0.0258+2(0.00902)=0.0438 in2/in\frac{A_{v}+2A_{t}}{s} = 0.0258 + 2(0.00902) = 0.0438\ \text{in}^{2}/\text{in}

Try #5 closed hoops (Ab = 0.31 in², two legs → 0.62 in²): s = 0.62 / 0.0438 = 14.2 in. Governing max spacing per AASHTO LRFD §5.7.2.6 is min(0.375·dv, 12 in) = 12 in. Use #5 closed hoops @ 12 in.

Step 5 — Longitudinal torsion steel A_ℓ

(Ex-6.5b.5)
  1. Formula (§5.7.3.6.3)

    A=Atsphcot2θfyfyA_{\ell} = \frac{A_{t}}{s}\,p_{h}\,\cot^{2}\theta\,\frac{f_{y}}{f_{y\ell}}
  2. Substitute

    A=(0.00902)(268)(1.0)2(1.0)=2.42 in2A_{\ell} = (0.00902)(268)(1.0)^{2}(1.0) = 2.42\ \text{in}^{2}
  3. Distribute equally around perimeter

    A/face2.42/4=0.60 in2A_{\ell}/\text{face} \approx 2.42/4 = 0.60\ \text{in}^{2}

Provide 2 – #5 bars in each face (top slab, bottom slab, each web) at hoop corners: 4(0.31) = 1.24 in² per face — well above the 0.60 in² required. Space additional longitudinal bars ≤ 12 in around ph.

Step 6 — Crushing (interaction) check

(Ex-6.5b.6)
  1. Equivalent shear stress

    vu=(Vubvdv)2+(Tuph1.7Aoh2)2v_{u} = \sqrt{\left(\frac{V_{u}}{b_{v}\,d_{v}}\right)^{2} + \left(\frac{T_{u}\,p_{h}}{1.7\,A_{oh}^{2}}\right)^{2}}
  2. Substitute

    vu=(2402454)2+(3,6002681.7(4,345)2)2v_{u} = \sqrt{\left(\frac{240}{24\cdot 54}\right)^{2} + \left(\frac{3{,}600\cdot 268}{1.7(4{,}345)^{2}}\right)^{2}}
  3. Evaluate

    vu=0.1852+0.0302=0.187 ksiv_{u} = \sqrt{0.185^{2} + 0.030^{2}} = 0.187\ \text{ksi}
  4. Limit

    ϕ0.25fc=0.90(0.25)(5)=1.125 ksivu \phi\,0.25\,f'_{c} = 0.90(0.25)(5) = 1.125\ \text{ksi} \gg v_{u}\ \checkmark

Step 7 — Detailing summary

  • Transverse: #5 closed hoops @ 12 in around the full box perimeter (135° hooks lapped in the corners).
  • Longitudinal: Continuous bars distributed around ph with ≥ 1 bar in each corner and spacing ≤ 12 in; total ≥ 2.42 in².
  • Do not use open U-stirrups for torsion — the shear-flow loop must close through the top slab.

6.6 — Worked example 1

Interior RC T-beam — full flexural and shear design

AASHTO LRFD §4.6.2.2, §5.6.3, §5.7.3
Elevation and cross-section of a 60 ft simply-supported RC T-beam bridge with 5 girders at 8 ft, 8.5 in deck, 42 in web
Figure 6.6Design example. Simply-supported 60 ft span, 40 ft roadway, 5 cast-in-place RC T-beam girders at 8 ft o.c., 8.5 in deck slab, 14 in × 42 in web (50.5 in total depth), 3.5 ft overhangs, 32-in barriers. Materials: f'c = 4 ksi, f_y = 60 ksi.

Step 1 — Loads per interior girder (Strength I)

Section geometry: interior girder tributary width = 8.0 ft. Self-weight of the deck (8.5 in × 0.150 kcf) + web (14 in × 42 in × 0.150 kcf) + barrier share.

Formula — DC per girder

wDC = (ts·S/12)·γ + (bw·hw/144)·γ + Wb/N

Substitute

= (8.5·8/12)·0.150 + (14·42/144)·0.150 + 0.470/5

Result

= wDC = 0.850 + 0.613 + 0.094 = 1.56 klf

Formula — DW per girder (2 in FWS × girder width)

wDW = tws·S·γws

Substitute

= (2/12)·8·0.140

Result

= wDW = 0.187 klf

Step 2 — Live-load distribution factor (§4.6.2.2.2b, Type (e))

Formula — moment DF, one lane loaded

gM,1 = 0.06 + (S/14)0.4·(S/L)0.3·(Kg/12·L·ts3)0.1

Substitute

= 0.06 + (8/14)^0.4 · (8/60)^0.3 · 1.03

Result

= gM,1 = 0.51

Formula — moment DF, two-or-more lanes (governs)

gM,2 = 0.075 + (S/9.5)0.6·(S/L)0.2·(Kg/12·L·ts3)0.1

Substitute

= 0.075 + (8/9.5)^0.6 · (8/60)^0.2 · 1.03

Result

= gM = 0.70 (governs)

Step 3 — Midspan moment envelope

Moment and shear envelope for 60 ft simply-supported T-beam under HL-93
Figure 6.7Envelope diagrams. Positive moment peaks at midspan; shear peaks at the support.

Formula — HL-93 midspan (truck + lane)

MLL = gM·(1 + IM)·Mtruck + gM·Mlane

Substitute

= 0.70·1.33·806 + 0.70·288

Result

= MLL+IM = 951 kip-ft

Formula — Strength I midspan

Mu = 1.25·MDC + 1.50·MDW + 1.75·MLL+IM

Substitute

= 1.25·702 + 1.50·84 + 1.75·951

Result

= Mu = 878 + 126 + 1664 = 2668 kip-ft

Step 4 — Effective flange width (§4.6.2.6)

Formula — interior girder

beff = S = 8 ft

Substitute

= 96 in

Result

= beff = 96 in

Step 5 — Flexural design (§5.6.3)

T-beam rebar layout with 8 #10 bars in web and #5 stirrups
Figure 6.8Trial rebar layout: 8 #10 tension bars in two rows (A_s = 10.16 in²), 1.5 in clear cover, d = 46.2 in. #5 stirrups at 6 in wrap the web.

Formula — depth of Whitney block (assume rectangular section, a ≤ t_s)

a = (As·fy) / (0.85·fc'·beff)

Substitute

= (10.16·60) / (0.85·4·96)

Result

= a = 1.87 in ≤ ts = 8.5 in ⇒ T-beam behaves as a wide rectangle ✓

Formula — nominal moment

Mn = As·fy·(da/2)

Substitute

= 10.16·60·(46.2 − 0.93)/12

Result

= Mn = 2299 kip-ft

Formula — factored resistance

φMn = 0.90·Mn

Substitute

= 0.90·2299

Result

= φMn = 2069 kip-ft — INSUFFICIENT (Mu = 2668)

Increase to 10 #10 bars (As = 12.70 in²): a = 2.34 in; φM_n = 0.90·12.70·60·(46.2 − 1.17)/12 = 2572 kip-ft — still short. Try 12 #10 in three rows (As = 15.24 in², revised d = 44.7 in): a = 2.80 in; φM_n = 2966 kip-ft ≥ 2668 ✓. Check c/dt = 0.074 ≤ 0.375 (tension-controlled).

Step 6 — Minimum reinforcement (§5.6.3.3)

Formula — cracking moment

Mcr = fr·Ig/yt

Substitute

fr = 0.24·√4 = 0.48 ksi ; using gross T-section Ig ≈ 190,000 in⁴, yt = 34.6 in

Result

= Mcr = (0.48·190000)/(34.6·12) = 220 kip-ft

Formula — minimum required

φMn ≥ min(1.33·Mu, 1.2·Mcr)

Substitute

min(1.33·2668 ; 1.2·220) = min(3549 ; 264) = 264 kip-ft

Result

= 2966 ≥ 264 ✓

Step 7 — Shear at the critical section (§5.7.3.2 — d_v from support face)

Formula — factored shear at x = d_v

Vu = 1.25·VDC + 1.50·VDW + 1.75·VLL+IM

Substitute

= 1.25·40.2 + 1.50·4.8 + 1.75·64.6

Result

= Vu = 50.3 + 7.2 + 113.1 = 170.6 kip

Formula — effective shear depth

dv = max(0.9·d, 0.72·h)

Substitute

max(0.9·44.7 ; 0.72·50.5)

Result

= dv = 40.2 in

Formula — concrete contribution (β = 2.0)

Vc = 0.0316·2.0·√fc'·bv·dv

Substitute

= 0.0316·2.0·√4·14·40.2

Result

= Vc = 71.1 kip

Formula — required steel contribution

Vs = Vu/φ − Vc

Substitute

= 170.6/0.90 − 71.1

Result

= Vs,req = 118.5 kip

Formula — required stirrup spacing (θ = 45°)

s = Av·fy·dv / Vs

Substitute

= 0.62·60·40.2 / 118.5 (#5 double-leg, Av = 0.62 in²)

Result

= sreq = 12.6 in

Apply the §5.7.2.6 maximum: v_u = V_u/(φ·b_v·d_v) = 170.6/(0.9·14·40.2) = 0.336 ksi < 0.125·f'c = 0.500 ksi ⇒ smax = min(0.8·40.2, 24) = 24 in. Provide #5 stirrups @ 6 in for the first quarter-span, @ 12 in in the middle half.

Step 8 — Crack control (§5.6.7, Class 2 exposure)

Formula — service moment steel stress

fss = Ms·(dk·d/3) / (As·(dk·d/3)·d)

Substitute

Service I Ms = 702 + 84 + 951 = 1737 kip-ft ; k·d = 8.3 in

Result

= fss = 30.9 ksi ≤ 0.6·fy = 36 ksi ✓

Formula — allowable spacing

smax = (700·γe)/(βs·fss) − 2·dc

Substitute

= (700·0.75)/(1.18·30.9) − 2·2.5

Result

= smax = 9.4 in ≥ sprov ≈ 2.4 in (12 bars in a 14 in web) ✓

Step 9 — Fatigue (§5.5.3)

Formula — fatigue live-load moment (Fatigue I, γ = 1.5)

Mf = γ·gM·(1 + IMfatMfatigue-truck

Substitute

= 1.5·0.70·1.15·458

Result

= Mf = 553 kip-ft

Formula — stress range in bottom bar

Δf = Mf·(dk·d/3)/(As·(dk·d/3)·d)

Substitute

Using cracked section n = 8, k = 0.31

Result

= Δf = 9.8 ksi ≤ (ΔF)TH = 26 − 22·(fmin/fy) = 24 ksi ✓

Step 10 — Live-load deflection (§2.5.2.6.2)

Formula — allowable

Δallow = L/800

Substitute

= 60·12/800

Result

= Δallow = 0.90 in

Formula — actual (elastic cracked section, HL-93)

Δ = (5·wLL·L4)/(384·Ec·Icr)

Substitute

using Icr = 88,000 in⁴, Ec = 3605 ksi

Result

= Δ = 0.42 in ≤ 0.90 ✓

AASHTO check summary — RC T-beam Example 1

  • Flexural strength (§5.6.3): φM_n = 2966 ≥ M_u = 2668 kip-ft ✓
  • Ductility (§5.6.2.1): c/d_t = 0.074 ≤ 0.375 (tension-controlled) ✓
  • Minimum reinforcement (§5.6.3.3): φM_n ≥ 1.2 M_cr = 264 kip-ft ✓
  • Crack control (§5.6.7): s_max = 9.4 ≥ 2.4 in provided ✓
  • Shear (§5.7.3): φ(V_c + V_s) = 0.9·(71.1 + 249) = 288 ≥ 170.6 kip ✓
  • Fatigue (§5.5.3): Δf = 9.8 ≤ 24 ksi ✓
  • Deflection (§2.5.2.6.2): Δ = 0.42 ≤ L/800 = 0.90 in ✓

Final section detailing (from computed A_s)

Interior RC T-beam — 14 in web × 42 in web depth (50.5 in total), S = 8 ft, L = 60 ft

LocationA_s requiredBars providedSpacing / detail
Bottom (tension) longitudinal — midspanAs,req = 12.2 in²8 – #11 (A_s = 12.48 in²)2 rows of 4; 1½-in clear cover, 2 in clear between bars
Top flange (deck) longitudinal — over interior girder0.15% of Ag,flange ≈ 1.22 in²/ft#5 @ 6 in top, #5 @ 8 in bottomEffective flange b_eff = 96 in (§4.6.2.6)
Skin steel — side face (§5.6.7)0.012·(d − 30) = 0.20 in²/ft each face#4 @ 12 in each face over lower h/2Stops at mid-height of web
Shear stirrups — end 12 ftAv/s ≥ 0.055 in²/in#4 U-stirrup, two-leg (A_v = 0.40 in²)s = 6 in c/c
Shear stirrups — interior 36 ftAv/s ≥ 0.025 in²/in (min per §5.7.2.5)#4 U-stirrup, two-legs = 12 in c/c (≤ 0.8·d_v = 32 in ✓)
Development: 8-#11 bottom bars extend past face of support with a standard 90° hook (ldh ≈ 22 in per §5.10.8.2). Bar cutoffs staggered to satisfy the envelope of Mu plus the 1.3·Mcr minimum. Distribution steel in the deck follows Ch. 5 (§9.7.3.2).

6.7 — Worked example 2

Solid RC slab bridge — 30 ft simple span

AASHTO LRFD §4.6.2.3, §5.6.3, §5.12.2

Problem statement

Design a simply-supported solid concrete slab bridge. Determine the slab thickness, primary longitudinal reinforcement, distribution steel, and temperature / shrinkage steel per §4.6.2.3 and §5.6.

Given

  • SpanL = 30 ft simply-supported
  • RoadwayW = 30 ft, two 12 ft lanes
  • f'c4.0 ksi
  • fy60 ksi (Grade 60)
  • Wearing surface2 in bituminous, DW = 0.025 ksf
  • Barriers32-in F-shape, 0.470 klf each side
  • Cover2.0 in top, 1.0 in bottom (§5.10.1)

Required

Compute h, primary As, distribution As,dist, and T & S steel.

Step 1 — Minimum thickness (§2.5.2.6.3, Table)

Formula — simple-span solid slab minimum

hmin = 1.2·(S + 10)/30

Substitute

= 1.2·(30 + 10)/30

Result

= hmin = 1.60 ft = 19.2 in ⇒ try h = 20 in

Step 2 — Equivalent strip width (§4.6.2.3)

Formula — one-lane, single-lane loaded

E1 = 10 + 5·√(L1·W1)

Substitute

L1 = min(L, 60) = 30 ft ; W1 = min(W, 30) = 30 ft

Result

= E1 = 10 + 5·√900 = 160 in = 13.3 ft

Formula — multi-lane

Em = 84 + 1.44·√(L1·W1) ≤ 12·W/NL

Substitute

= 84 + 1.44·√900 = 127 in = 10.6 ft ; cap 12·30/2 = 180 in

Result

= Em = 10.6 ft (governs)

Step 3 — Design moments per strip

Formula — self-weight moment per foot

MDC = (ws·L2)/8

Substitute

ws = (20/12)·0.150 = 0.250 klf/ft ; MDC = 0.250·30²/8

Result

= MDC = 28.1 kip-ft/ft

Formula — HL-93 truck moment on E strip

MLL+IM = (1 + IM)·Mtruck/Em

Substitute

Mtruck at midspan = 224 kip-ft ; IM = 0.33

Result

= MLL+IM = 1.33·224/10.6 = 28.1 kip-ft/ft

Formula — Strength I moment

Mu = 1.25·MDC + 1.50·MDW + 1.75·MLL+IM

Substitute

= 1.25·28.1 + 1.50·3.5 + 1.75·28.1

Result

= Mu = 84.6 kip-ft/ft

Step 4 — Primary reinforcement

Formula — required A_s (assume ρ, iterate)

As = Mu/(φ·fy·(da/2))

Substitute

d = 20 − 1 − 0.625 = 18.4 in ; assume a = 2.0 in

Result

= As = 84.6·12/(0.9·60·17.4) = 1.08 in²/ft

Provide #9 @ 8 in (As = 1.50 in²/ft). Recompute a = 1.50·60/(0.85·4·12) = 2.21 in; φM_n = 0.9·1.50·60·(18.4 − 1.10)/12 = 117 kip-ft/ft ≥ 84.6 ✓.

Step 5 — Distribution reinforcement (§5.12.2.1)

Formula — percentage of main steel

% = 100/√L ≤ 50 %

Substitute

= 100/√30

Result

= 18.3 % of main steel

Formula — required transverse A_s

As,dist = 0.183·As,main

Substitute

= 0.183·1.50

Result

= As,dist = 0.275 in²/ft ⇒ #5 @ 12 in (0.31 in²/ft) ✓

Step 6 — Shrinkage & temperature (§5.10.6)

Formula — each face

As,st = 1.30·b·h/(2·(b + hfy)

Substitute

b = 360 in per 30 ft, h = 20 in

Result

= As,st = 0.13 in²/ft ⇒ #4 @ 18 in top and bottom ✓

AASHTO check summary — RC slab Example 2

  • Minimum thickness (§2.5.2.6.3): h = 20 ≥ 19.2 in ✓
  • Flexural strength (§5.6.3): φM_n = 117 ≥ M_u = 84.6 kip-ft/ft ✓
  • Distribution steel (§5.12.2.1): #5 @ 12 in ✓
  • Shrinkage & temperature (§5.10.6): #4 @ 18 in each face ✓
  • Deflection (§2.5.2.6.2): Δ_LL = 0.28 in ≤ L/800 = 0.45 in ✓

Final section detailing (from computed A_s)

Solid RC slab bridge — 20 in thick × 30 ft roadway, L = 30 ft

LocationA_s requiredBars providedSpacing / detail
Primary bottom (longitudinal) — midspanAs,req ≈ 1.60 in²/ft#9 @ 7 in bottom (A_s = 1.71 in²/ft)1-in bottom cover; hooked at abutments
Primary top (longitudinal) — over abutment0.5·A_s,bot for continuity / temperature#6 @ 12 in topExtends 0.3·L past support
Distribution steel (transverse, bottom) — §5.12.2.1As,dist = 100/√L · As,pri ≤ 50% = 0.79 in²/ft#5 @ 12 in bottom (A_s = 0.31 in²/ft → increase to #6 @ 8 in = 0.66 in²/ft)Placed above the primary bars
Shrinkage &amp; temperature (transverse, top) — §5.10.6As,T&S ≥ 0.11 in²/ft each face#4 @ 18 in each faceBoth directions on top mat
Effective strip widths: E1 = 13.3 ft (single-lane), Em = 10.6 ft (multi-lane, governs). All bars Grade 60; 2 in top cover, 1 in bottom cover. Bar clearances and cutoffs per §5.10.8; extend at least ⅓ of positive steel into the support (§5.10.8.1.2b).

6.7b — Design Example 5

Reinforced-concrete deck slab on five steel girders (approximate strip method)

AASHTO LRFD §4.6.2.1, §9.7, §5.7.3

This worked example extracts the full solution from Simplified LRFD Bridge Design(Taylor & Francis, 2008), Example 5. A 48 ft wide, 44 ft 6 in clear-roadway cast-in-place concrete deck is continuous across five W12×65 steel girders spaced at 10 ft with 4 ft overhangs. Every calculation follows the Formula → Substitute → Resultpattern using AASHTO Art. 4.6.2.1 (approximate strip method) and HL-93 live load.

Problem statement

Design the transverse reinforcement for the cast-in-place deck slab of a five-girder simple-span composite bridge using the AASHTO approximate strip method.

Given

  • Bridge width, overall48 ft
  • Clear roadway width44 ft 6 in
  • Slab thickness (structural + IWS)t = 8.5 + 0.5 = 9.0 in
  • Girder spacing, S10 ft (four spans)
  • Deck overhang4 ft (curb/parapet 21 in wide, 32 in tall, A = 3.37 ft²)
  • Future wearing surface, wFWS0.03 kip/ft² (3 in)
  • Concrete unit weight, wc0.150 kip/ft³
  • f'c (28-day)4.5 ksi
  • Fy (reinforcement)60 ksi
  • Live loadAASHTO HL-93 (axles only per §3.6.1.3.3), IM = 33%
(a) Bridge cross section — 5 girders @ 10 ft, 4-ft overhangs, t = 9 in4 ft10 ft10 ft10 ft10 ft4 ftTotal width 48 ftparapet 32″(b) Cantilever curb + parapet — x̄ = 0.66 ft from ext. girder CLparapet CGext girder CLx̄ = 0.66 ftA_C&P = 3.37 ft²
Figure 6.10 (source Fig. 2.50)Concrete deck slab design example. Overall bridge cross-section (top) and cantilever curb-and-parapet geometry (bottom). The parapet centroid is x̄ = 0.66 ft from the exterior girder centerline.

Step 1 — Minimum slab thickness (§9.7.1.1)

The AASHTO minimum concrete deck depth is 7.0 in. Adopt structural depth 8.5 in plus 0.5 in integral wearing surface = t = 9.0 in.

Step 2 — Dead loads on a 1 ft transverse strip

Slab self-weight

wslab=wctw_{slab} = w_c \cdot t

Substitute

=(0.150 kip/ft3)(9.0 in)(1 ft12 in)= (0.150\text{ kip/ft}^3)(9.0\text{ in})\left(\dfrac{1\text{ ft}}{12\text{ in}}\right)

Result

wslab=0.113 kip/ft2w_{slab} = 0.113\ \text{kip/ft}^2

Future wearing surface

wFWS=0.03 kip/ft2 (given)w_{FWS} = 0.03\ \text{kip/ft}^2\ \text{(given)}

Curb + parapet per side (line load along span)

wC&P=wcAC&Pw_{C\&P} = w_c \cdot A_{C\&P}

Substitute

=(0.150 kip/ft3)(3.37 ft2)= (0.150\text{ kip/ft}^3)(3.37\text{ ft}^2)

Result

wC&P=0.506 kip/ft of bridge spanw_{C\&P} = 0.506\ \text{kip/ft of bridge span}

Step 3 — Dead-load force effects (approximate elastic strip, §4.6.2.1)

Model a 1 ft-wide transverse strip as a continuous beam over five rigid girder supports with 4 ft overhangs. Report the reaction RA at the exterior support and moments at A (support), B (0.4S = 4 ft into the first interior span, maximum + moment) and C (first interior support, maximum − moment).

Idealized transverse strip — 1 ft wide, continuous over 5 girder supportsABC4 ft cantilever0.4S = 4 ft6 ftS = 10 ftA = exterior support · B = peak +M · C = first interior support (peak −M)
Figure 6.11 (source Fig. 2.51)Idealized transverse strip. Point A = exterior support, B = 0.4S from A (peak positive DL moment), C = first interior support (peak negative DL moment).
Slab self-weight, cantilevers excludedw_slab = 0.113 k/ft²MA = 0, MB = +0.872, MC = −1.211 kip-ft/ft ; RA = 0.444 kip/ft
Fig. 2.52Slab self-weight applied over spans between girders only (cantilever excluded). Results: MA = 0, MB = +0.872, MC = −1.211 kip-ft/ft, RA = 0.444 kip/ft.
Slab self-weight — cantilevers onlyw_slabw_slabMA = −0.904, MB = −0.439, MC = +0.258 kip-ft/ft ; RA = 0.568 kip/ft
Fig. 2.53Slab dead load acting only on the two cantilevers. Results: MA = −0.904, MB = −0.439, MC = +0.258 kip-ft/ft, RA = 0.568 kip/ft.
Curb + parapet point loads on cantilevers0.5060.506P_C&P = 0.506 k/ft applied at x̄ = 0.66 ft from ext. girder CL
Fig. 2.54Curb + parapet (0.506 kip/ft, applied at x̄ = 0.66 ft). Results: MA = −1.689, MB = −0.821, MC = +0.483 kip-ft/ft, RA = 0.723 kip/ft.
Future wearing surface (FWS) 0.03 k/ft² between curbsw_FWS = 0.030 k/ft²MA = −0.076, MB = +0.195, MC = −0.300 kip-ft/ft ; RA = 0.195 kip/ft
Fig. 2.55FWS (0.03 kip/ft²) between curbs only. Results: MA = −0.076, MB = +0.195, MC = −0.300 kip-ft/ft, RA = 0.195 kip/ft.

Step 4 — Live-load force effects (§3.6.1.3, §4.6.2.1.3)

Under the approximate strip method only the design-truck axles act on the deck (§3.6.1.3.3). Each wheel P = 16 kips, spaced 6 ft transversely. Wheels stay ≥ 1.0 ft from the face of curb (overhang design) and ≥ 2.0 ft from the design-lane edge (interior design). Number of design lanes across the 44.5 ft roadway:

Number of design lanes (§3.6.1.1.1)

NL=int ⁣(w12 ft)N_L = \operatorname{int}\!\left(\dfrac{w}{12\text{ ft}}\right)

Substitute

=int ⁣(44.512)=int(3.71)= \operatorname{int}\!\left(\dfrac{44.5}{12}\right) = \operatorname{int}(3.71)

Result

NL=3 lanes  (m=1.2, 1.0, 0.85 for 1, 2, 3 lanes)N_L = 3\ \text{lanes}\ \ (m = 1.2,\ 1.0,\ 0.85\ \text{for 1, 2, 3 lanes})

4a — Maximum negative LL moment on the overhang

Overhang loading — wheel 1 ft from face of curb → X = 15 in = 1.25 ft from G_AcurbG_A (ext)G_BP = 16 kP = 16 k1.0 ftX = 1.25 ft6 ft wheel gaugeE = 45.0 + 10.0·X = 45 + 12.5 = 57.5 in = 4.79 ft strip
Fig. 2.56Wheel placed 1 ft from face of curb → X = 15 in = 1.25 ft from centerline of girder A.

Equivalent overhang strip width E (Tbl. 4.6.2.1.3-1)

E=45.0+10.0X [in]E = 45.0 + 10.0\,X\ \text{[in]}

Substitute

=45.0+10.0(1.25 ft)=57.5 in= 45.0 + 10.0(1.25\text{ ft}) = 57.5\text{ in}

Result

E=4.79 ftE = 4.79\ \text{ft}

Negative LL moment per foot (m = 1.2, one lane)

MA=mPXEM_A = -\dfrac{m\cdot P\cdot X}{E}

Substitute

=(1.2)(16.0 kips)(1.25 ft)4.79 ft= -\dfrac{(1.2)(16.0\text{ kips})(1.25\text{ ft})}{4.79\text{ ft}}

Result

MA=5.01 ft-kip/ftM_A = -5.01\ \text{ft-kip/ft}
Free body of overhang cut at G_Acut at G_AP = 16 kX = 1.25 ftM_A = −P·X / EM_A = −(1.2·16·1.25)/4.79 = −5.01 ft-kip/ft
Fig. 2.57Free body used to compute MA: P = 16 kips at X = 1.25 ft, cut at A.

4b — Maximum positive LL moment in the first interior span

Single-lane loading — leading wheel at B (0.4S), trailing wheel 6 ft behind16 k16 k6 ft0.4S = 4 ftR_A = 8.16 k · M_B = 32.64 ft-k (per strip); E_+M = 92 in = 7.67 ft
Fig. 2.58Single-lane loading: leading wheel at point B (0.4S = 4 ft), trailing wheel 6 ft away.

Equivalent strip width for interior positive M (Tbl. 4.6.2.1.3-1)

E+M=26.0+6.6S [in]E_{+M} = 26.0 + 6.6\,S\ \text{[in]}

Substitute

=26.0+6.6(10 ft)=92 in= 26.0 + 6.6(10\text{ ft}) = 92\text{ in}

Result

E+M=7.67 ftE_{+M} = 7.67\ \text{ft}

Structural analysis of the strip under one-lane truck axles:

Formula

RA=8.160 kips;MB=32.64 ft-kipR_A = 8.160\ \text{kips};\quad M_B = 32.64\ \text{ft-kip}

Adjust for strip width and m = 1.2 (one lane)

RA=mRAE+M,MB=mMBE+MR'_A = \dfrac{m\,R_A}{E_{+M}},\qquad M'_B = \dfrac{m\,M_B}{E_{+M}}

Substitute

RA=(1.2)(8.16)7.67,MB=(1.2)(32.64)7.67R'_A = \dfrac{(1.2)(8.16)}{7.67},\qquad M'_B = \dfrac{(1.2)(32.64)}{7.67}

Result

RA=1.28 kip/ft,MB=+5.11 ft-kip/ftR'_A = 1.28\ \text{kip/ft},\qquad M'_B = +5.11\ \text{ft-kip/ft}
Two-lane check (m = 1.0) — second axle-pair in span 316 k16 k16 k16 kM_B (2-lane) = 4.43 ft-k/ft < 5.11 → single lane governs
Fig. 2.59Two-lane check (m = 1.0). Second axle pair placed at X = 28/34 ft to maximize the effect at B.

Two-lane check (m = 1.0)

MB=mMBE+MM'_B = \dfrac{m\,M_B}{E_{+M}}

Substitute

=(1.0)(34.01)7.67= \dfrac{(1.0)(34.01)}{7.67}

Result

MB=+4.43 ft-kip/ft < 5.11  single lane governsM'_B = +4.43\ \text{ft-kip/ft}\ <\ 5.11\ \Rightarrow\ \text{single lane governs}

4c — Maximum negative LL moment at the first interior support

Truck straddling support C — max negative moment M_C16 k16 k3 ft3 ftE_-M = 48 + 3·S = 78 in ; M'_C = −5.07 ft-k/ft
Fig. 2.60Truck straddling support C, one lane loaded, produces the maximum negative moment MC.

Equivalent strip width for interior negative M (Tbl. 4.6.2.1.3-1)

EM=48.0+3.0S [in]E_{-M} = 48.0 + 3.0\,S\ \text{[in]}

Substitute

=48.0+3.0(10 ft)=78 in= 48.0 + 3.0(10\text{ ft}) = 78\text{ in}

Result

EM=6.5 ftE_{-M} = 6.5\ \text{ft}

Formula

MC=mMCEMM'_C = \dfrac{m\,M_C}{E_{-M}}

Substitute

=(1.2)(27.48)6.5= \dfrac{(1.2)(-27.48)}{6.5}

Result

MC=5.07 ft-kip/ftM'_C = -5.07\ \text{ft-kip/ft}

4d — Maximum live-load reaction at support A

Wheel placement for max reaction R_A — outer wheel 1 ft from curbG_AG_B16 k16 k1.0 ft6 ftR'_A = (1.2)(25.36)/4.79 = 6.35 k/ft — E = 4.79 ft strip
Fig. 2.61Governing wheel placement (1 ft from curb) for the maximum LL reaction RA. Same E = 4.79 ft as the overhang strip.

Formula

RA=mRAER'_A = \dfrac{m\,R_A}{E}

Substitute

=(1.2)(25.36 kips)4.79 ft= \dfrac{(1.2)(25.36\text{ kips})}{4.79\text{ ft}}

Result

RA=6.35 kip/ftR'_A = 6.35\ \text{kip/ft}
Load case (per ft width)RAMAMBMC
Slab DL (excl. cantilever)0.4440.000+0.872−1.211
Slab DL (cantilever only)0.568−0.904−0.439+0.258
Curb + parapet0.723−1.689−0.821+0.483
FWS (DW)0.195−0.076+0.195−0.300
LL max −M overhang−5.010
LL max +M / R first span1.280+5.110
LL max −M first support C−5.070
LL max reaction at A6.350

Step 5 — Strength I limit state (§1.3.2, §3.4.1)

ηD = ηR = ηI = 1.0, so ηi = 1.0. DC includes slab, cantilever slab and C&P (γp = 1.25 max, 0.90 min); DW = FWS only (γp = 1.50/0.65); LL uses γ = 1.75 with IM = 33 %.

Strength I combination (§1.3.2.1)

Q=ηiγiQi=1.0 ⁣[γDCDC+γDWDW+1.75(1+IM)LL]Q = \sum \eta_i\,\gamma_i\,Q_i = 1.0\!\left[\gamma_{DC}\,DC + \gamma_{DW}\,DW + 1.75\,(1{+}IM)\,LL\right]

Reaction at A

RA=1.25(Rslab+Rcant+RC&P)+1.5RFWS+1.75(1.33)RLLR_A = 1.25(R_{slab}+R_{cant}+R_{C\&P}) + 1.5\,R_{FWS} + 1.75(1.33)\,R_{LL}

Substitute

=1.25(0.444+0.568+0.723)+1.5(0.195)+1.75(1.33)(6.35)= 1.25(0.444+0.568+0.723) + 1.5(0.195) + 1.75(1.33)(6.35)

Result

RA=17.24 kip/ftR_A = 17.24\ \text{kip/ft}

Moment at A (overhang, γDC max, γDW max, LL max)

MA=1.25(Mcant+MC&P)+1.5MFWS+1.75(1.33)MLL,ovM_A = 1.25(M_{cant}+M_{C\&P}) + 1.5\,M_{FWS} + 1.75(1.33)\,M_{LL,ov}

Substitute

=1.25(0.9041.689)+1.5(0.076)+1.75(1.33)(5.010)= 1.25(-0.904-1.689) + 1.5(-0.076) + 1.75(1.33)(-5.010)

Result

MA=15.02 ft-kip/ftM_A = -15.02\ \text{ft-kip/ft}

Moment at B (γp = 0.90 on cantilever + C&P since they reduce +M)

MB=1.25Mslab+0.90(Mcant+MC&P)+1.5MFWS+1.75(1.33)MLL,+M_B = 1.25\,M_{slab} + 0.90(M_{cant}+M_{C\&P}) + 1.5\,M_{FWS} + 1.75(1.33)\,M_{LL,+}

Substitute

=1.25(0.872)+0.90(0.4390.821)+1.5(0.195)+1.75(1.33)(5.110)= 1.25(0.872) + 0.90(-0.439-0.821) + 1.5(0.195) + 1.75(1.33)(5.110)

Result

MB=+12.14 ft-kip/ftM_B = +12.14\ \text{ft-kip/ft}

Moment at C (γp = 0.90 on cantilever + C&P since they reduce −M)

MC=1.25Mslab+0.90(Mcant+MC&P)+1.5MFWS+1.75(1.33)MLL,M_C = 1.25\,M_{slab} + 0.90(M_{cant}+M_{C\&P}) + 1.5\,M_{FWS} + 1.75(1.33)\,M_{LL,-}

Substitute

=1.25(1.211)+0.90(0.258+0.483)+1.5(0.300)+1.75(1.33)(5.070)= 1.25(-1.211) + 0.90(0.258+0.483) + 1.5(-0.300) + 1.75(1.33)(-5.070)

Result

MC=13.10 ft-kip/ftM_C = -13.10\ \text{ft-kip/ft}

Design demands (Strength I)

  • Positive-moment demand Mu+ = +12.14 ft-kip/ft (at B).
  • Negative-moment demand Mu = −15.02 ft-kip/ft (at A, overhang governs over −13.10 at C).
  • Reaction demand Ru = 17.24 kip/ft.

Step 6 — Flexural design for the governing negative moment

Try epoxy-coated #5 bars (db = 0.625 in, Ab = 0.31 in²) with 2.5 in cover. Maximum spacing smax = min(1.5t, 18) = 1.5(8.5) = 12.75 in.

Deck slab section for reinforcement placement (1 ft strip)0.5″ IWS#5 top (2.5″ cover)cover = 2.5″t = 9.0″d = t − t_IWS − c − d_b/2 = 9.0 − 0.5 − 2.5 − 0.31 = 5.68 in
Fig. 2.62Deck slab section for reinforcement placement (1 ft-wide strip).

Effective depth d

d=ttIWScdb2d = t - t_{IWS} - c - \tfrac{d_b}{2}

Substitute

=9.00.52.50.6252= 9.0 - 0.5 - 2.5 - \dfrac{0.625}{2}

Result

d=5.68 ind = 5.68\ \text{in}

Equivalent stress-block depth (§5.7.3.2)

a=Asfy0.85fcba = \dfrac{A_s\,f_y}{0.85\,f'_c\,b}

Substitute

=As(60)(0.85)(4.5)(12)= \dfrac{A_s(60)}{(0.85)(4.5)(12)}

Result

a=1.307As [in, with As in in2/ft]a = 1.307\,A_s\ \text{[in, with }A_s\text{ in in}^2\text{/ft]}

Factored flexural resistance (§5.5.4.2.1, φ = 0.9)

Mr=φAsfy ⁣(da2)M_r = \varphi\,A_s\,f_y\!\left(d - \dfrac{a}{2}\right)

Set Mr = Mu and solve for As

(15.02)(12)=0.9As(60) ⁣(5.681.3072As)(15.02)(12) = 0.9\,A_s(60)\!\left(5.68 - \dfrac{1.307}{2}A_s\right)

Result

As=0.64 in2/ft (required)A_s = 0.64\ \text{in}^2/\text{ft (required)}

Try #5 @ 5.5 in (provided As)

As,prov=Ab ⁣(12s)A_{s,prov} = A_b\!\left(\dfrac{12}{s}\right)

Substitute

=0.31 ⁣(125.5)= 0.31\!\left(\dfrac{12}{5.5}\right)

Result

As,prov=0.68 in2/ft0.64 A_{s,prov} = 0.68\ \text{in}^2/\text{ft} \geq 0.64\ \checkmark

Recompute a with As,prov

a=As,provfy0.85fcba = \dfrac{A_{s,prov}\,f_y}{0.85\,f'_c\,b}

Substitute

=(0.68)(60)(0.85)(4.5)(12)= \dfrac{(0.68)(60)}{(0.85)(4.5)(12)}

Result

a=0.889 ina = 0.889\ \text{in}

Verify Mr

Mr=φAs,provfy ⁣(da2)M_r = \varphi\,A_{s,prov}\,f_y\!\left(d - \dfrac{a}{2}\right)

Substitute

=(0.9)(0.68)(60) ⁣(5.680.8892) ⁣112= (0.9)(0.68)(60)\!\left(5.68 - \dfrac{0.889}{2}\right)\!\dfrac{1}{12}

Result

Mr=16.0 ft-kip/ftMu=15.02 M_r = 16.0\ \text{ft-kip/ft} \geq M_u = 15.02\ \checkmark

Step 7 — Minimum reinforcement (§5.7.3.3.2)

Modulus of rupture (§5.4.2.6)

fr=0.37fcf_r = 0.37\sqrt{f'_c}

Substitute

=0.374.5= 0.37\sqrt{4.5}

Result

fr=0.785 ksif_r = 0.785\ \text{ksi}

Non-composite section modulus (structural 8.5 in)

Snc=bts26S_{nc} = \dfrac{b\,t_s^2}{6}

Substitute

=(12)(8.5)26= \dfrac{(12)(8.5)^2}{6}

Result

Snc=144.5 in3S_{nc} = 144.5\ \text{in}^3

Cracking moment

Mcr=SncfrM_{cr} = S_{nc}\,f_r

Substitute

=(144.5)(0.785)= (144.5)(0.785)

Result

Mcr=113.4 in-kip=9.45 ft-kip/ftM_{cr} = 113.4\ \text{in-kip} = 9.45\ \text{ft-kip/ft}

Governing minimum (min of 1.2 Mcr and 1.33 Mu)

min(1.2Mcr, 1.33Mu)\min(1.2\,M_{cr},\ 1.33\,M_u)

Substitute

=min(11.34, 19.98) ft-kip/ft= \min(11.34,\ 19.98)\ \text{ft-kip/ft}

Result

=11.34 ft-kip/ftMr=16.0 = 11.34\ \text{ft-kip/ft} \leq M_r = 16.0\ \checkmark

Step 8 — Distribution reinforcement (§9.7.3.2)

Effective span (steel girder, tw = 0.39 in for W12×65)

Se=StwS_e = S - t_w

Substitute

=10 ft(0.39 in)(1/12)= 10\text{ ft} - (0.39\text{ in})(1/12)

Result

Se9.97 ft (use 10 ft)S_e \approx 9.97\ \text{ft}\ (\text{use }10\text{ ft})

Percent of positive-moment steel required in secondary direction

p=min ⁣(220Se, 67%)p = \min\!\left(\dfrac{220}{\sqrt{S_e}},\ 67\%\right)

Substitute

=min(220/10, 67%)=min(69.6%, 67%)= \min(220/\sqrt{10},\ 67\%) = \min(69.6\%,\ 67\%)

Result

p=67%p = 67\%

Required distribution steel

As,dist=0.67As,provA_{s,dist} = 0.67\,A_{s,prov}

Substitute

=0.67(0.68)= 0.67(0.68)

Result

A_{s,dist} = 0.46\ \text{in}^2/\text{ft}\ \Rightarrow\ \text{#5 @ 8 in bottom longitudinal}

Step 9 — Shrinkage & temperature (§5.10.8)

Formula

As,temp1.30bh2(b+h)fyA_{s,temp} \geq \dfrac{1.30\,b\,h}{2\,(b+h)\,f_y}

Substitute

=1.30(12)(8.5)2(12+8.5)(60)= \dfrac{1.30(12)(8.5)}{2(12+8.5)(60)}

Result

As,temp=0.054 in2/ft (with 0.11As,temp0.60)A_{s,temp} = 0.054\ \text{in}^2/\text{ft (with } 0.11 \leq A_{s,temp} \leq 0.60 \text{)}

Adopt #4 @ 18 in top longitudinal (As = 0.13 in²/ft), satisfying the code floor of 0.11 in²/ft and the 3t / 18 in maximum spacing.

Design summary — Deck slab reinforcement

  • Primary (transverse) bottom & top: #5 @ 5.5 in (As = 0.68 in²/ft).
  • Distribution (longitudinal) bottom: #5 @ 8 in (0.46 in²/ft).
  • Shrinkage / temperature (longitudinal) top: #4 @ 18 in (0.13 in²/ft).
  • Total slab thickness: 9.0 in (8.5 in structural + 0.5 in integral wearing surface).
  • Governing checks: φMn = 16.0 ≥ Mu = 15.02 ft-kip/ft; 1.2 Mcr = 11.34 ≤ φMn.

6.8 — Detailing must-knows

Cover, splices, and cutoffs

AASHTO LRFD §5.10
  • Concrete cover (§5.10.1): 2 in top of deck (Class 2), 1 in bottom of deck, 1.5 in on stirrups, 3 in bottom of footings, 2 in for columns exposed to earth.
  • Development length (§5.10.8.2): ℓ_d = 1.25·A_b·f_y/√f'c ≥ 12 in. For #10 in 4 ksi concrete, ℓ_d ≈ 57 in.
  • Class B splice (§5.10.8.4): ℓ_s = 1.3·ℓ_d.
  • Bar cutoff (§5.10.8.1.2b): extend past theoretical cutoff by max(d, 15·d_b, L/20). At least ⅓ of positive-moment steel must extend into the support.
  • Skin reinforcement (§5.6.7): required in webs ≥ 3 ft deep; #4 @ 12 in on each face for ≥ h/2 from the tension face.

6.9 — Design challenge

Two-span continuous RC T-beam bridge

Design the two-span continuous RC T-beam bridge shown below. Each span is 70 ft, 44 ft roadway with four T-beam girders at 12 ft spacing, 9 in deck slab, 32 in barriers, and integral abutments plus an integral pier. Materials: f'c = 4.5 ksi, f_y = 60 ksi.

Design challenge — two-span continuous RC T-beam bridge, 70 ft each span, 44 ft wide, 4 girders at 12 ft
Figure 6.9Design-challenge bridge. Two 70 ft continuous spans, 44 ft roadway, 4 RC T-beam girders at 12 ft o.c., 9 in deck, 32 in barriers, integral abutments and integral pier.

Required deliverables — every AASHTO check, both critical sections

  1. Load calculation: DC, DW, LL+IM per interior and exterior girder. State formula first, then substitute.
  2. LLDF (§4.6.2.2.2): Type (e) — one-lane and multi-lane distribution factors for moment and shear; lever rule check on exterior girder.
  3. Envelopes: Strength I positive-moment envelope (midspan of each span) and negative-moment envelope (over the pier). Include Fatigue I.
  4. Effective flange width (§4.6.2.6): interior and exterior. For negative-moment region, treat as rectangular b_w.
  5. Positive-moment flexural design: longitudinal steel at midspan of Span 1.
  6. Negative-moment flexural design: top steel over the pier (rectangular section, b_w only).
  7. Minimum reinforcement (§5.6.3.3), ductility (§5.6.2.1), and crack control (§5.6.7).
  8. Shear design (§5.7.3.4.1): stirrup schedule from support to midspan for both spans. Include §5.7.2.5 minimum and §5.7.2.6 maximum spacing.
  9. Fatigue check (§5.5.3) on the bottom bars at midspan and on the top bars over the pier.
  10. Deflection (§2.5.2.6.2): live-load deflection ≤ L/800 both spans.
  11. Rebar drawings: longitudinal elevation with bar cutoffs (§5.10.8), transverse cross-sections at midspan, pier, and support, plus stirrup schedule.
  12. Bill of materials & mass estimate.

Submit your design challenge

Chapter 6 challenge — Two-span continuous RC T-beam bridge

You must be signed in to upload a submission.

Sign in →

Chapter summary

Key takeaways

  • RC slab, T-beam, and box girders cover the 20 – 120 ft span range and remain the workhorses of the U.S. short-span inventory.
  • AASHTO §4.6.2.6 effective flange width converts the true shear-lag stress distribution into a uniform design stress for T-beam flexure.
  • Whitney stress block (§5.6.2, §5.6.3) gives φM_n = φ·A_s·f_y·(d − a/2); tension-controlled requires c/d_t ≤ 0.375.
  • Simplified shear (§5.7.3.4.1) uses β = 2.0, θ = 45° — cleanly separates concrete and stirrup contributions.
  • Box girders add torsion (§5.7.3.6) and require closed hoops plus longitudinal steel around the entire perimeter.
  • Every calculation follows the formula-first, substitute-then-result pattern — no exceptions.

Section 2

Fully Worked Examples

Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.

Worked Example 1

Flexural capacity of a T-beam
Basic

Problem

Compute φM_n and verify tension-controlled behavior.

Step-by-Step

a=Asfy/(0.85fcbf)=7.6260/(0.85484)=1.60ina = A_{s}\cdot f_{y}/(0.85\cdot f'_{c}\cdot b_{f}) = 7.62\cdot 60/(0.85\cdot 4\cdot 84) = 1.60 in
1.60<7.0rectangularbehaviorwithb=bf.1.60 < 7.0 \rightarrow rectangular behavior with b = b_{f}. \checkmark

Design Verification

Because a < t_s, all compression is in the flange — treat as a rectangular beam with width b_f.

Discussion

If a > t_s, use the flanged-section equations (compression in flange + web). Errors here are the most common cause of T-beam capacity over-estimates.

Worked Example 2

Shear design of an RC girder
Intermediate

Problem

Determine V_c, required V_s, and #4 stirrup spacing.

Step-by-Step

Vc=0.0316βfcbvdv=0.03162.021431V_{c} = 0.0316\cdot \beta \cdot \sqrt{f}'_{c}\cdot b_{v}\cdot d_{v} = 0.0316\cdot 2.0\cdot 2\cdot 14\cdot 31
Result
Vc=54.9kipV_{c} = 54.9 kip
0.9054.9=49.4kip;Vu>ϕVc stirrups required0.90\cdot 54.9 = 49.4 kip; V_{u} > \phi V_{c} \rightarrow \ \text{stirrups required}

Design Verification

Check s_max: 0.8·d_v = 24.8 in and 24 in → 5-in spacing OK. ✓

Discussion

Non-prestressed members can adopt β = 2, θ = 45° per §5.7.3.4.2 without iteration — the price is slightly heavier stirrups vs full MCFT.

Worked Example 3

Serviceability crack-control check (Class 1 exposure)
Intermediate

Problem

Verify §5.6.7 rebar spacing limit for Class 1 exposure (γ_e = 1.00).

Step-by-Step

βs=1+2.5/(0.7(362.5))=1+0.106\beta _{s} = 1 + 2.5/(0.7\cdot (36-2.5)) = 1 + 0.106
Result
βs=1.11\beta _{s} = 1.11
smax=700γe/(βsfss)2dc=700/(1.1136)5=17.55s_{max} = 700\cdot \gamma _{e}/(\beta _{s}\cdot f_{ss}) - 2\cdot d_{c} = 700/(1.11\cdot 36) - 5 = 17.5 - 5
Result
smax=12.5ins_{max} = 12.5 in

Design Verification

Class 2 (γ_e = 0.75) reduces s_max to 9.4 in — still OK. ✓

Discussion

Crack-control governs bar spacing before flexural capacity for many decks and shallow slabs. Always check §5.6.7 even when φM_n is fine.

Section 3

Guided Practice

Complete the missing steps. Use Hints for AASHTO article pointers and setup logic before revealing the full step. Submit at the end to send your work to your instructor.

Guided Problem 1

Rectangular RC beam — moment capacity

Interior girder rectangular RC beam: b=16 inb = 16\ \text{in}, d=32 ind = 32\ \text{in}, As=6.32 in2A_{s} = 6.32\ \text{in}^{2} (4-#10), fc=4 ksif'_{c} = 4\ \text{ksi}, fy=60 ksif_{y} = 60\ \text{ksi}.

Step 1

Depth of the equivalent stress block aa (in). a=Asfy0.85fcba = \dfrac{A_{s} f_{y}}{0.85 f'_{c} b}.

Step 2

Neutral-axis depth cc (in). β1=0.85\beta_{1} = 0.85 for fc=4 ksif'_{c} = 4\ \text{ksi}.

Step 3

Tension-controlled check: strain in extreme steel. εt=0.003dcc\varepsilon_{t} = 0.003 \dfrac{d-c}{c}.

Step 4

Design moment ϕMn\phi M_{n} (k-ft). ϕ=0.90\phi = 0.90.

Guided Problem 2

T-beam interior girder — effective flange width

Interior T-girder: web bw=14 inb_{w} = 14\ \text{in}, deck ts=8 int_{s} = 8\ \text{in}, S=9 ftS = 9\ \text{ft} c/c, span L=90 ftL = 90\ \text{ft}.

Step 1

L/4L/4 in inches.

Step 2

12ts+bw12 t_{s} + b_{w} (in).

Step 3

Girder spacing in inches.

Step 4

Effective flange width beffb_{\text{eff}} (in) = min of the three.

Guided Problem 3

Shear design — one-way concrete beam

bw=14 inb_{w} = 14\ \text{in}, dv=30 ind_{v} = 30\ \text{in}, Vu=220 kipV_{u} = 220\ \text{kip}, fc=4 ksif'_{c} = 4\ \text{ksi}. Use AASHTO simplified β=2\beta = 2, θ=45°\theta = 45°.

Step 1

Vc=0.0316βfcbwdvV_{c} = 0.0316 \beta \sqrt{f'_{c}}\, b_{w} d_{v} (kip). fcf'_{c} in ksi.

Step 2

Required Vs=Vu/ϕVcV_{s} = V_{u}/\phi - V_{c} (kip). ϕ=0.90\phi = 0.90.

Step 3

Stirrup spacing s=AvfydvVss = \dfrac{A_{v} f_{y} d_{v}}{V_{s}} (in) for #4 double-leg (Av=0.40 in2A_{v} = 0.40\ \text{in}^{2}).

Step 4

Max stirrup spacing per §5.7.2.6 if vu<0.125fcv_{u} < 0.125 f'_{c} (in).

Guided Problem 4

Crack control — Class 2 exposure spacing

Bottom of deck slab, γe=0.75\gamma_{e} = 0.75 (Class 2). fss=36 ksif_{ss} = 36\ \text{ksi} (Service I), dc=1.25 ind_{c} = 1.25\ \text{in}, h=8 inh = 8\ \text{in}.

Step 1

βs=1+dc0.7(hdc)\beta_{s} = 1 + \dfrac{d_{c}}{0.7(h-d_{c})}.

Step 2

Denominator βsfss\beta_{s} f_{ss} (ksi).

Step 3

smax=700γeβsfss2dcs_{\max} = \dfrac{700 \gamma_{e}}{\beta_{s} f_{ss}} - 2 d_{c} (in).

Step 4

Actual bar spacing (in) using #5 @ 8-in c/c satisfying smaxs_{\max}?

Section 4

Independent Practice

Every problem randomizes its inputs. Work each step, submit for immediate feedback, request new values to practice again.

Practice 1

Whitney stress-block depth a
A_s
As = 6.5 in²
f_y
fy = 60 ksi
f′_c
fc = 7 ksi
b
b = 22 in
Step 1a = A_s·f_y / (0.85·f′_c·b).
Randomized inputs, symbolic grading (±2%).

Practice 2

Nominal moment capacity M_n
A_s
As = 10 in²
f_y
fy = 70 ksi
d
d = 18 in
a
a = 3.5 in
Step 1A_s·f_y·(d − a/2)/12 in k-ft.
Randomized inputs, symbolic grading (±2%).

Practice 3

Tension-controlled strain check
d
d = 18 in
c
c = 5.1000000000000005 in
Step 1ε_t = 0.003(d−c)/c.
Randomized inputs, symbolic grading (±2%).

Practice 4

Minimum reinforcement ratio
f′_c
fc = 3 ksi
f_y
fy = 75 ksi
Step 13·√f′_c/f_y (ACI/AASHTO lower bound).
Randomized inputs, symbolic grading (±2%).

Practice 5

V_c simplified
f′_c
fc = 3 ksi
b_w
bw = 19 in
d_v
dv = 59 in
Step 10.0316·2·√f′_c·b_w·d_v (kip).
Randomized inputs, symbolic grading (±2%).

Practice 6

Stirrup spacing
V_s
Vs = 195 kip
A_v
Av = 0.4 in²
f_y
fy = 80 ksi
d_v
dv = 49 in
Step 1s = A_v·f_y·d_v/V_s (in).
Randomized inputs, symbolic grading (±2%).

Practice 7

Development length (tension #6 bar)
d_b
db = 1.375 in
f_y
fy = 65 ksi
f′_c
fc = 5.5 ksi
Step 1l_d ≈ 2.4·d_b·f_y/√f′_c.
Randomized inputs, symbolic grading (±2%).

Practice 8

Crack-control spacing
γ_e
ge = 1 -
d_c
dc = 1.25 in
h
h = 11.5 in
f_ss
fss = 47 ksi
Step 1β_s = 1 + d_c/(0.7(h−d_c)).
Step 2s_max = 700·γ_e/(β_s·f_ss) − 2·d_c.
Randomized inputs, symbolic grading (±2%).

Practice 9

Modulus of elasticity of concrete
f′_c
fc = 4.5 ksi
Step 1E_c = 33·(150)^1.5·√f′_c ≈ 1820·√f′_c (ksi).
Randomized inputs, symbolic grading (±2%).

Practice 10

Deck slab dead-load moment
t
t = 9 in
S
S = 11 ft
Step 1w = 0.150·(t/12) klf/ft.
Step 2M = w·S²/10 (continuous).
Randomized inputs, symbolic grading (±2%).

Practice 11

Effective flange width (min rule)
Span
L = 105 ft
t_s
ts = 9 in
b_w
bw = 18 in
S
S = 11.5 ft
Step 1L/4 (in).
Step 212 t_s + b_w.
Step 3S in inches.
Step 4b_eff = min of three.
Randomized inputs, symbolic grading (±2%).

Practice 12

Modulus of rupture and cracking moment
f′_c
fc = 3 ksi
I_g (in⁴)
Ig = 10500 in^4
y_t (in)
yt = 11 in
Step 1f_r = 0.24·√f′_c (ksi).
Step 2M_cr = f_r·I_g/y_t /12 in k-ft.
Randomized inputs, symbolic grading (±2%).

Bridge Engineering and Design Using AASHTO LRFD

Graduate interactive textbook for civil engineering students. Aligned to AASHTO LRFD Bridge Design Specifications, 10th Edition (2024).

Regional focus

Maryland & Mid-Atlantic — MDOT SHA, VDOT, PennDOT, FHWA.

Educational notice

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

© 2026 Dr. Steve Efe, Ph.D. All Rights Reserved.

Developed for engineering education. Unauthorized reproduction, distribution, or commercial use is prohibited.

v1.0 · Reference edition · Aligned to AASHTO LRFD, 10th Edition (2024)