SE

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

AASHTO Design Studio

Transparent LRFD calculators

103 modules ordered chapter by chapter, from live load through section properties, decks, concrete, prestressing, steel girders, substructure, bearings, extreme events and load rating. Every calculator exposes its equations, substitutions, applicable articles and redesign guidance.

Cascading whole-bridge model

Full-Bridge Designer

One model from traffic loads to pile tip. Change the girder spacing, slab thickness or limit state and the deck strip moments, distribution factors, girder flexure and shear, bearing reactions, pier-cap strut-and-tie, column P-Δ interaction and the foundation all re-solve together — every check citing its AASHTO LRFD article with a utilization ratio.

Chapter 1

Bridge engineering fundamentals and design basis

Preliminary proportioning, life-cycle cost screening, and the LRFD reliability framework — load modifiers, factored demand versus factored resistance and the target reliability index.

Module 1AASHTO LRFD 2.5.2.6.3 / 2.5.2.6.2Chapter 1

Preliminary sizing, span-to-depth & life-cycle cost

Table 2.5.2.6.3-1 minimum depth, the L/800 live-load deflection limit, deck and girder quantities, and the present value of owner cost over the analysis period.

Span-to-depth screening from Table 2.5.2.6.3-1, the L/800 live-load deflection limit, deck quantities and a present-value comparison of owner cost.

Minimum overall depth

46.1 in

L/31

Girder spacing S

8.80 ft

Δ_allow = L/800

1.80 in

Deck concrete

138.5 yd³

Life-cycle PV

$1188073

Derivation — equation, substitution, result

Span-to-depth screening

  dmin=  (L/D ratio)L=  0.032×120.0ft×12=  dmin46.1inoverall\begin{aligned}&\;d_{\operatorname{min}} = \;\text{(L/D ratio)} \cdot L\\[4pt]&=\;0.032 \times 120.0 \,\text{ft} \times 12\\[4pt]&=\;\boxed{d_{\operatorname{min}} \approx 46.1 \,\text{in} \,\text{overall}}\end{aligned}

Steel section depth

  dsteel=ratiocompL=  0.027×1440in=  38.9in\begin{aligned}&\;d_{steel} = \,\text{ratio}_{comp} \cdot L\\[4pt]&=\;0.027 \times 1440 \,\text{in}\\[4pt]&=\;\boxed{38.9 \,\text{in}}\end{aligned}

Girder spacing

  S=w/Ng=  44.0/5=  8.80ft\begin{aligned}&\;S = w / N_g\\[4pt]&=\;44.0 / 5\\[4pt]&=\;\boxed{8.80 \,\text{ft}}\end{aligned}

Live-load deflection limit

  Δallow=L/800(§2.5.2.6.2)=  1440in/800=  1.80in\begin{aligned}&\;\Delta _{allow} = L/800 (§2.5.2.6.2)\\[4pt]&=\;1440 \,\text{in} / 800\\[4pt]&=\;\boxed{1.80 \,\text{in}}\end{aligned}

Deck concrete quantity

  V=wL(ts/12)/27=  44.0×120.0×0.708/27=  138.5yd3\begin{aligned}&\;V = w\cdot L\cdot (t_s/12)/27\\[4pt]&=\;44.0 \times 120.0 \times 0.708 / 27\\[4pt]&=\;\boxed{138.5 \,\text{yd}^{3}}\end{aligned}

Slab load per girder

  wdeck=tsSγc=  0.708ft×8.80ft×0.150kcf=  0.935klf0.935klf\begin{aligned}&\;w_{deck} = t_s\cdot S\cdot \gamma _c\\[4pt]&=\;0.708 \,\text{ft} \times 8.80 \,\text{ft} \times 0.150 \,\text{kcf}\\[4pt]&=\;\boxed{0.935 \,\text{klf} \rightarrow 0.935 \,\text{klf}}\end{aligned}

Life-cycle present value

  PV=A[1(1+i)n]/i=  A=$40000,i=0.030,n=75yr=  $1188073\begin{aligned}&\;\mathrm{PV} = A[1 − (1+i)^−n]/i\\[4pt]&=\;A = \$40000, i = 0.030, n = 75 \,\text{yr}\\[4pt]&=\;\boxed{\$1188073}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #5 @ 8 in top matGirder depth 46 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 8.8 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Keep the girder depth constant along the span where possible — haunched webs add fabrication cost that rarely pays back below 200 ft spans.
  • Check shipping limits early: 12 ft depth and 150 ft length are practical highway limits for a single piece.
  • Girder spacing between 8 and 12 ft usually minimises total cost; wider spacing thickens the deck and increases the distribution factor.
  • Allow 2 in minimum haunch for construction tolerance and screed adjustment.
CheckDemandCapacity / limitStatus
Girder spacing within the §4.6.2.2 approximate-equation range 3.5 – 16 ft8.80 ft3.5 – 16 ftPASS
Deck thickness ≥ 7 in (§9.7.1.1)8.50 in7.0 inPASS
Independent verificationExpectedComputedStatus
Depth ≈ 0.033L for a continuous composite steel girder47.5 inVERIFIED

Assumptions & basis of design

  • Depth ratios from AASHTO LRFD Table 2.5.2.6.3-1 for constant-depth superstructures.
  • Concrete unit weight 0.150 kcf; the deck quantity excludes haunches, barriers and the wearing surface.
  • The present-value screening is a uniform-series discounting of owner cost — not an AASHTO provision.

Use the screening depth as the starting trial section, then confirm with the Chapter 8 flexure and Chapter 4 deflection modules.

Module 2AASHTO LRFD 1.3.2 / 3.4.1Chapters 1 · 2

LRFD design basis — η, factored demand and reliability

Ductility, redundancy and importance modifiers combined into η, the Strength I factored demand against φR_n, and the reliability index β = (μ_R − μ_Q)/√(σ_R² + σ_Q²).

Combines the ductility, redundancy and importance modifiers into η, applies the Strength I factors, and back-checks the reliability index.

η (load modifier)

1.050

Factored demand Q

5748.8

Factored resistance R_r

5400.0

Utilisation Q/R_r

1.065

Reliability index β

4.17

Derivation — equation, substitution, result

Load modifier

  η=ηDηRηI0.95(Eq.1.3.2.12)=  1.00×1.00×1.05=1.050=  η=1.050\begin{aligned}&\;\eta = \eta _D \eta _R \eta _I \ge 0.95 (Eq. 1.3.2.1-2)\\[4pt]&=\;1.00 \times 1.00 \times 1.05 = 1.050\\[4pt]&=\;\boxed{\eta = 1.050}\end{aligned}

Factored demand

  Q=η[γDCDC+γDWDW+1.75(LL+IM)]=  1.050[1.25(1500.0)+1.50(300.0)+1.75(1800.0)]=  Q=5748.8\begin{aligned}&\;Q = \eta [\gamma _{DC}\cdot \mathrm{DC} + \gamma _{DW}\cdot \mathrm{DW} + 1.75(\mathrm{LL}+\mathrm{IM})]\\[4pt]&=\;1.050[1.25(1500.0) + 1.50(300.0) + 1.75(1800.0)]\\[4pt]&=\;\boxed{Q = 5748.8}\end{aligned}

Factored resistance

  Rr=ϕRn(Eq.1.3.2.11)=  0.90×6000.0=  Rr=5400.0\begin{aligned}&\;R_r = \phi R_n (Eq. 1.3.2.1-1)\\[4pt]&=\;0.90 \times 6000.0\\[4pt]&=\;\boxed{R_r = 5400.0}\end{aligned}

Design inequality

  \SumηiγiQiϕRn=  5748.8vs5400.0=  utilisation=1.065\begin{aligned}&\;\Sum \eta _i \gamma _i Q_i \le \phi R_n\\[4pt]&=\;5748.8 \,\text{vs} 5400.0\\[4pt]&=\;\boxed{\,\text{utilisation} = 1.065}\end{aligned}

Reliability index

  β=(μRμQ)/σR2+σQ2=  (6600.03200.0)/660.02+480.02=  β=4.17\begin{aligned}&\;\beta = (\mu _R − \mu _Q)/\sqrt{\sigma _R^{2} + \sigma _Q^{2}}\\[4pt]&=\;(6600.0 − 3200.0)/\sqrt{660.0^{2} + 480.0^{2}}\\[4pt]&=\;\boxed{\beta = 4.17}\end{aligned}

Probability of failure

  pf10(β0.40.5)  (approximate)=  pf6.82e3\begin{aligned}&\;p_f \approx 10^(−\beta \cdot 0.4 − 0.5) \;\text{(approximate)}\\[4pt]&=\;\boxed{p_f \approx 6.82e-3}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchLRFD load-and-resistance basis — factored demand vs. factored resistance
R_n6000φR_n5400Q_u (factored)5749Reliability index β (gauge, target ≈ 3.5)target 3.50β = 4.17

η-modified factored load Qu = 5749 vs. φRn = 5400 (nominal Rn = 6000). Reliability index β = 4.17 against the Strength I target β ≈ 3.50.

Constructability & detailing notes

  • η is applied to the load side, never to the resistance — a common mark-up error in student calculations.
  • Record the assumed operational classification on the cover sheet; it drives both η_I and the seismic R factor.
CheckDemandCapacity / limitStatus
Strength limit state Σηγ Q ≤ φR_n5748.85400.0REVIEW
Target reliability β_T = 3.5 (§C1.3.2.1)4.173.50PASS
η ≥ 0.95 for maximum load factors1.0500.95PASS
Independent verificationExpectedComputedStatus
Target reliability index for Strength Iβ ≈ 3.54.17VERIFIED

Assumptions & basis of design

  • AASHTO LRFD Eq. 1.3.2.1-1 with Strength I permanent factors from Table 3.4.1-2 (γ_DC 1.25/0.90, γ_DW 1.50/0.65).
  • η_D, η_R and η_I each fall between 0.95 and 1.05; the minimum-load case inverts the product.
  • The reliability index uses the lognormal-free first-order form; the AASHTO calibration target for girders is β_T = 3.5 at Strength I.

Demand exceeds resistance by 6.5 % — increase R_n by that margin, or reduce DW by specifying no future overlay allowance where the owner permits.

Chapter 3

Loads and load combinations

The HL-93 model, the position that maximises its effect, and the load factors that turn nominal effects into factored demands.

Module 3AASHTO LRFD 3.6.1Chapter 3

HL-93 live-load envelope (simply supported)

Envelope of design truck / tandem + lane load with IM and multiple-presence factors.

HL-93 Live-Load Effect — Simply Supported Span

Computes the maximum midspan moment and end shear from the HL-93 envelope. AASHTO LRFD §3.6.1.2 / §3.6.2

Max midspan moment

3656.4

kip-ft per design lane × factors

M = m · n · [(1+IM)·max(M_truck, M_tandem) + M_lane]
M_truck (per lane)
1883.0 kip-ft
M_tandem (per lane)
1450.3 kip-ft
M_lane (per lane)
1152.0 kip-ft
Governs
Design truck

Max end shear

119.3

kip per design lane × factors

V = m · n · [(1+IM)·max(V_truck, V_tandem) + V_lane]
V_truck (per lane)
60.80 kip
V_tandem (per lane)
49.17 kip
V_lane (per lane)
38.40 kip
Governs
Design truck
Mlane = w · L² / 8 Vlane = w · L / 2 w = 0.64 klf
(derived)
w
design lane load intensity [klf]
L
simply supported span length [ft]
IM
dynamic load allowance (33% typ.) [-]
m
multiple-presence factor [-]

Verification

Order-of-magnitude check: for L = 120 ft, the HL-93 envelope (per lane, per AASHTO tables) gives M ≈ 2,090 kip-ft (unfactored, no IM, no m). With IM = 1.33 and m = 1.00 the moment should approach ≈ 2,780 kip-ft plus lane contribution. Compare to the value returned above.

What can go wrong

This calculator idealizes a simply supported span. For continuous spans, use influence surfaces and apply the truck + lane combination for positive moment and two trucks (min. 50 ft between axles) × 0.90 + two lanes for negative moment AASHTO LRFD §3.6.1.3.1. Consult refined analysis for skew and curved bridges.

Detailing sketchHL-93 loading on the span — envelope
8 kip32 kip32 kipw = 0.64 klf design lane loadL = 120 ftM_LL+IM = 3656 k-ft

Governing vehicle: Design truck for moment (1883 vs 1450 k-ft truck/tandem), Design truck for shear. Design MLL+IM = 3656 k-ft, design VLL+IM = 119.3 kip on a 120 ft span.

Module 4AASHTO LRFD 3.6.1.2 / 3.6.2Chapters 3 · 4

Design-truck absolute maximum moment (Barré)

Locates the critical axle position by Barré's theorem, then computes truck, tandem and lane moments and the governing HL-93 moment and shear for one lane on a simple span.

Barré's theorem locates the absolute maximum moment under the axle nearest the resultant — not at midspan.

Maximum truck moment (no IM)

1164.9 k-ft

Maximum tandem moment (no IM)

950.0 k-ft

Lane moment

512.0 k-ft

Governing M_LL+IM per lane

2061.3 k-ft

Governing V_LL+IM per lane

110.19 kip

Detailing sketchHL-93 truck on the span — envelope moment
M_LL+IM = 2061.30 k-ftL = 80.0 ft

Governing live-load moment MLL+IM = 2061.30 k-ft per lane on a 80.0 ft span, lane load 0.64 klf.

StepEquationSubstitutionResult
Axle resultant locationx̄ = ΣPᵢxᵢ / ΣPᵢ(8·0 + 32·14 + 32·28) / 7218.67 ft from the front axle
Offset resultant-to-critical axlee = |x̄ − x_crit||18.67 − 14|4.67 ft
Critical axle position (Barré)a = L/2 − e/280.0/2 − 4.67/237.67 ft from the left support
Left reaction for that positionR = Σ Pᵢ(L − xᵢ)/L8(56.33) + 32(42.33) + 32(28.33) / 80.033.90 kip
Maximum truck momentM = R·a − Σ P_left(a − xᵢ)33.90·37.67 − Σ…1164.9 k-ft
Design tandem momentM = R·a₁ with axles at L/2 ± 2 ft25.00·38.00950.0 k-ft
Design lane momentM = wL²/80.64·80.0²/8512.0 k-ft
Truck + IMM_truck(1 + IM/100)1164.9 × 1.331549.3 k-ft
Governing HL-93 momentM_LL+IM = max(M_truck, M_tandem)(1+IM) + M_lanemax(1549.3, 1263.5) + 512.02061.3 k-ft/lane
Governing HL-93 shear at supportV = max(V_truck, V_tandem)(1+IM) + V_lanemax(63.60, 48.75)·1.33 + 25.60110.19 kip/lane

The design truck governs moment on this 80 ft span (1549.3 k-ft vs 1263.5 k-ft for the tandem). The tandem typically governs below about 40 ft.

Assumptions & code basis
  • HL-93 design truck 8-32-32 kip at 14 ft axle spacings (rear spacing at its 14 ft minimum for maximum simple-span moment), AASHTO LRFD §3.6.1.2.2.
  • Design tandem: two 25 kip axles 4 ft apart, §3.6.1.2.3. Design lane load 0.64 klf over the full span, §3.6.1.2.4.
  • Absolute maximum moment located by Barré's theorem: the span centreline bisects the distance between the resultant of the axles on the span and the axle nearest it.
  • Dynamic load allowance IM applies to the truck or tandem only, never to the lane load (§3.6.2.1).
  • Result is one lane of live load on a simple span before the distribution factor and multiple-presence factor are applied.
Module 5AASHTO LRFD 3.6.1.3Chapters 3 · 4

Influence-line explorer

Slide the HL-93 truck to locate the critical loading position for moment and shear at any section.

Influence-Line Explorer — HL-93 Truck on a 120-ft Simply Supported Span

Drag the truck along the span and reposition the analysis section. AASHTO LRFD §3.6.1.2 — Design Vehicular Live Load

x = 60.0 ft8k32k32k0L = 120 ftη_max = 30.00 ft
30.00
14.00
0.50

Moment at x = 60.0 ft

2904.00

kip-ft (unfactored, per lane, IM not applied)

Truck axles1752.00
Design lane (0.64 klf)1152.00

Shear at x = 60.0 ft

-19.60

kip (unfactored, per lane, IM not applied)

Truck axles-29.20
Design lane (0.64 klf)9.60

How to use this

  1. Set the section (x/L) where you want the maximum effect.
  2. Slide the truck until the heaviest axles align under the peak ordinate.
  3. For shear at the end, sweep the truck toward the support; the lane load ordinate is largest just past the cut.
  4. Change the variable spacing (14 ft governs for most spans < 100 ft; 30 ft can govern for shear at far support on long spans).
Module 6AASHTO LRFD 3.4.1Chapters 3 · 4

Load-combination generator

Applies the Strength, Service, and Fatigue load factors to your DC, DW, and LL+IM effects, with maximum and minimum permanent-load cases.

Q = Σ η γᵢ Qᵢ. DC1 acts on the bare girder, DC2 on the composite section; both carry γ_DC. Maximum load factors govern where the effect adds; minimum factors govern where a permanent load relieves the effect (uplift, overturning, retaining walls).

M_DC = M_DC1 + M_DC2

900 k-ft

M_DW

140 k-ft

Factored M_u (Strength I)

3435 k-ft

Detailing sketchSimple-span moment diagram — DC1, DC2, DW and LL+IM
L = 100.0 ftM_u = 3435 k-ftγ·M_LL+IM = 2100γ·M_DC1 = 775midspan ordinate at x = L/2

MDC1 = 620 k-ft (girder + slab + haunch on the non-composite section) · MDC2 = 280 k-ft (barriers on the composite section) · MDW = 140 k-ft · MLL+IM = 1200 k-ft (distributed) · factored Mu = 3435 k-ft.

Combinationγ_DCγ_DWγ_LLQ (max)Q (min)
Strength I1.251.501.7534353001
Strength II (permit)1.251.501.3529552521
Strength IV (dead governs)1.501.500.001560901
Service I1.001.001.0022402240
Service III (PS tension)1.001.000.8020002000
Fatigue I0.000.001.7521002100
Module 7AASHTO LRFD 3.6.1.1.1 / 3.6.1.1.2 / 3.6.2Chapter 3

Design lanes, multiple presence & dynamic allowance

N_L = INT(w/12), the Table 3.6.1.1.2-1 multiple-presence factor m, and IM for decks, fatigue, buried components and all other components with the fill-depth reduction.

Number of design lanes, multiple-presence factor and the dynamic load allowance for the component you are designing.

Design lanes N_L

3

Multiple presence m

0.85

IM

33.0 %

Live-load effect

217.1 kip

Derivation — equation, substitution, result

Number of design lanes

  NL=INT(w/12)(§3.6.1.1.1)=  INT(40.0/12)=  NL=3\begin{aligned}&\;N_L = \mathrm{INT}(w/12) (§3.6.1.1.1)\\[4pt]&=\;\mathrm{INT}(40.0/12)\\[4pt]&=\;\boxed{N_L = 3}\end{aligned}

Multiple presence

  mfromTable3.6.1.1.21=  3loadedlane(s)=  m=0.85\begin{aligned}&\;m \operatorname{from} Table 3.6.1.1.2-1\\[4pt]&=\;3 \,\text{loaded} \,\text{lane}(s)\\[4pt]&=\;\boxed{m = 0.85}\end{aligned}

Dynamic load allowance

  IMfromTable3.6.2.11=  other=  IM=33.0%\begin{aligned}&\;\mathrm{IM} \operatorname{from} Table 3.6.2.1-1\\[4pt]&=\;\,\text{other}\\[4pt]&=\;\boxed{\mathrm{IM} = 33.0 \%}\end{aligned}

Applied to truck/tandem only

  LL+IM=mN[Rtruck(1+IM/100)+Rlane]=  \begin{aligned}&\;\mathrm{LL}+\mathrm{IM} = m\cdot N\cdot [R_{truck}(1+\mathrm{IM}/100) + R_{lane}]\\[4pt]&=\;\boxed{}\end{aligned}

Factored one-component effect

  R=R1laneNm(1+IM/100)=  64.0×3×0.85×1.330=  217.1kip\begin{aligned}&\;R = R_{1lane} \cdot N \cdot m \cdot (1 + \mathrm{IM}/100)\\[4pt]&=\;64.0 \times 3 \times 0.85 \times 1.330\\[4pt]&=\;\boxed{217.1 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchDesign lanes, multiple presence and dynamic load allowance
lane 1lane 2lane 3clear roadway = 40.0 ft200.00 ft / lanem = 0.85 · IM = 33 % (other)

Clear roadway 40.0 ft ⇒ NL = 3 design lane(s) at 200.00 ft each. Multiple-presence factor m = 0.85 governs when fewer than 3 lanes are loaded. IM = 33 % applied to the truck/tandem for the other case (not to the lane load).

Constructability & detailing notes

  • The multiple-presence factor is already embedded in the approximate distribution-factor equations — never apply it twice.
  • Fatigue design uses one truck in one lane with m = 1.0 and IM = 15 %.
CheckDemandCapacity / limitStatus
Roadway wide enough for the assumed loaded lanes3 lanes3 lanesPASS
m not applied with the approximate distribution equations (already embedded)Use m only with the lever rule, the rigid cross-section method or a refined analysis.PASS
Independent verificationExpectedComputedStatus
N_L = INT(w/12)33VERIFIED

Assumptions & basis of design

  • Design lane width 12 ft with the 10-ft loaded strip placed to produce the extreme effect (§3.6.1.3.1).
  • IM applies to the design truck and tandem only, and not to fatigue-limit centrifugal or braking forces.
  • For 20 ft ≤ w < 24 ft, AASHTO requires two design lanes each equal to half the roadway width.

For the fatigue limit state use one lane with m = 1.00 (§3.6.1.4.3b) — the 1.20 single-lane factor is removed.

Module 8AASHTO LRFD 3.6.4 / 3.6.3Chapter 3

Braking (BR) and centrifugal (CE) forces

The governing of 25 % of axle weights and 5 % of truck-plus-lane, the centrifugal factor C = f v²/(gR), the 6 ft application height, and the overturning couple delivered to the substructure.

BR is the larger of 25 % of the axle weights or 5 % of truck plus lane; CE uses the f = 4/3 factor for the truck only.

Braking force BR

36.00 kip

Centrifugal force CE

32.35 kip

Governing horizontal

36.00 kip

braking governs

Substructure moment

468.0 kip·ft

Derivation — equation, substitution, result

Braking — 25 % of the axles

  BR1=0.25  (design truck or tandem)=  0.25×72.0kip=  18.00kip/lane\begin{aligned}&\;\mathrm{BR}_{1} = 0.25\;\text{(design truck or tandem)}\\[4pt]&=\;0.25 \times 72.0 \,\text{kip}\\[4pt]&=\;\boxed{18.00 \,\text{kip}/\,\text{lane}}\end{aligned}

Braking — 5 % of truck + lane

  BR2=0.05[truck+laneL]=  0.05[72.0+0.64(200.0)]=  10.00kip/lane\begin{aligned}&\;\mathrm{BR}_{2} = 0.05[\,\text{truck} + \,\text{lane}\cdot L]\\[4pt]&=\;0.05[72.0 + 0.64(200.0)]\\[4pt]&=\;\boxed{10.00 \,\text{kip}/\,\text{lane}}\end{aligned}

Governing braking force

  BR=max(BR1,BR2)Nlanesm(§3.6.4)=  18.00×2×1.00=  BR=36.00kip\begin{aligned}&\;\mathrm{BR} = \operatorname{max}(\mathrm{BR}_{1}, \mathrm{BR}_{2}) \cdot N_{lanes} \cdot m (§3.6.4)\\[4pt]&=\;18.00 \times 2 \times 1.00\\[4pt]&=\;\boxed{\mathrm{BR} = 36.00 \,\text{kip}}\end{aligned}

Centrifugal coefficient

  C=fv2/(gR),f=4/3atstrength(§3.6.3)=  (4/3)(80.7ft/s)2/(32.2×1200)=  C=0.2246\begin{aligned}&\;C = f v^{2}/(gR), f = 4/3 \operatorname{at} \,\text{strength} (§3.6.3)\\[4pt]&=\;(4/3)(80.7 \,\text{ft}/s)^{2}/(32.2 \times 1200)\\[4pt]&=\;\boxed{C = 0.2246}\end{aligned}

Centrifugal force

  CE=CWtruckNm=  0.2246×72.0×2×1.00=  CE=32.35kip\begin{aligned}&\;\mathrm{CE} = C \cdot W_{truck} \cdot N \cdot m\\[4pt]&=\;0.2246 \times 72.0 \times 2 \times 1.00\\[4pt]&=\;\boxed{\mathrm{CE} = 32.35 \,\text{kip}}\end{aligned}

Overturning couple

  M=F  (hCG + ddeck-brg);BRacts6ftabovethedeck=  arm=13.00ft=  MBR=468.0kipft,MCE=420.5kipft\begin{aligned}&\;M = F\;\text{(hCG + ddeck-brg)}; \mathrm{BR} \,\text{acts} 6 \,\text{ft} \,\text{above} \,\text{the} \,\text{deck}\\[4pt]&=\;\,\text{arm} = 13.00 \,\text{ft}\\[4pt]&=\;\boxed{M_{BR} = 468.0 \,\text{kip}\cdot \,\text{ft}, M_{CE} = 420.5 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchBraking (BR) and centrifugal (CE) force — bearing elevation
7.0 ftBR = 36.0 kiph = 6.0 ftCE = 32.4 kip (R = 1200 ft)Girder soffit to bearing seatFixed bearing carries the full longitudinal reaction; expansion bearings see CE only.

BR = 36.0 kip acts 6.0 ft above the deck, transferred through 7.0 ft to the bearings. CE = 32.4 kip from a curve radius R = 1200 ft adds a lateral, overturning couple at the same elevation.

Constructability & detailing notes

  • Braking force acts 6 ft above the deck in both directions — check the bearings and the anchor bolts for the reversal.
  • Centrifugal force adds an overturning couple that can unload the inside girder; verify uplift at the bearings.
  • Detail fixed and expansion bearings so the horizontal load path into the substructure is explicit on the plans.
CheckDemandCapacity / limitStatus
Braking applied in both directions on all lanes headed the same wayLanes carrying traffic in one direction only — use m for the number of loaded lanes.PASS
Centrifugal force acts 6 ft above the roadway (§3.6.3)6.0 ft6.0 ftPASS
Independent verificationExpectedComputedStatus
BR ≥ 0.25 × axle weights18.0 kip per laneVERIFIED

Assumptions & basis of design

  • BR per §3.6.4 with the dynamic load allowance intentionally omitted; the force acts 6 ft above the roadway surface.
  • CE per §3.6.3 with f = 4/3 for all limit states except fatigue, where f = 1.0.
  • Both forces are transmitted through the bearings into the substructure — check the anchor bolts and the bearing shear capacity.

Braking governs: detail the fixed bearing and its anchorage for this force, and check the pier for the resulting base moment.

Chapter 4

Section properties and composite action

Neutral axis, transformed sections, effective flange width, and the permanent loads each stage of the section must carry.

Module 9AASHTO LRFD 4.6.2.6 / 6.10.1.1.1b / 5.4.2.4Chapter 4

Transformed composite section properties

Modular ratio, §4.6.2.6 effective flange width, the composite neutral axis and inertia at n and 3n, and the stage-by-stage section moduli that DC1, DC2/DW and LL+IM act on.

Enter the bare-steel (or precast) girder properties; the module transforms the deck at n and 3n and reports the stage-by-stage section moduli.

Modular ratio n

7.96

Effective flange width b_eff

108.0 in

Non-composite I / S_b

20000 / 833 in⁴ / in³

Short-term composite I (n)

50535 in⁴

Long-term composite I (3n)

38763 in⁴

S_b short term / long term

1128 / 1051 in³

Detailing sketchComposite section — transformed layer stack
Deck slab: 8.00 inHaunch: 2.00 inSteel/precast girder: 48.00 inΣ = 58.00 inwidth = 9.00 ftSECTION — layer stack (scaled)

Effective flange width beff = 108.00 in; short-term composite I = 50535 in⁴.

StepEquationSubstitutionResult
Deck modulusE_c = 33,000 w_c^1.5 √f′_c33,000 (0.145)^1.5 √4.003644 ksi
Modular ration = E_s / E_c29000 / 36447.96
Effective flange widthb_eff = min(S, L_eff/4)min(108.0, 300.0)108.0 in
Transformed deck area (short term)A_tr = b_eff·t_s / n108.0·8.00 / 7.96108.57 in²
Composite neutral axis (n)ȳ_b = Σ A_i y_i / Σ A_i(48.00·24.00 + 108.57·54.00) / 156.5744.80 in above the bottom flange
Composite inertia (n)I = ΣI_i + ΣA_i d_i²20000 + …50535 in⁴
Section moduli (n)S_b = I/ȳ_b, S_t = I/y_t50535/44.80, 50535/3.20S_b = 1128 in³, S_t = 15806 in³
Composite inertia (3n, long term)Repeat with n′ = 3nn′ = 23.87I = 38763 in⁴, ȳ_b = 36.90 in
Deck top-fibre modulusS_deck = n·I / y_deck7.96·50535 / 13.2030473 in³

Composite action increases the bottom-fibre section modulus from 833 in³ (steel alone, carrying DC1) to 1128 in³ (n, live load) — a factor of 1.35. Stack the stresses stage by stage: DC1 on the steel section, DC2 and DW on the 3n section, LL+IM on the n section.

Assumptions & code basis
  • Modular ratio n = E_s/E_c with E_c = 33,000 w_c^1.5 √f′_c (AASHTO LRFD Eq. 5.4.2.4-1), w_c = 0.145 kcf.
  • Effective flange width per §4.6.2.6.1: the tributary width, limited by L_eff/4 for interior girders (one-quarter effective span; L/8 each side for exterior).
  • Short-term (n) properties govern live load; long-term (3n) properties govern superimposed dead load DC2/DW to account for creep (§6.10.1.1.1b).
  • Concrete deck is assumed uncracked and fully composite in positive-moment regions; in negative-moment regions only the longitudinal deck reinforcement is normally considered effective.
  • Haunch depth is included in the geometry but its concrete area is conservatively neglected.
Module 10AASHTO LRFD 3.5.1 / 4.6.2.2.1 / 3.4.1Chapters 3 · 4

Girder dead loads — DC1, DC2 & DW

Non-composite DC1 (slab, haunch, girder, diaphragms, forms), composite DC2 (barriers/sidewalk) and DW (future wearing surface), with midspan moments, support shears and factored permanent effects.

DC1 = slab + haunch + girder + diaphragms + SIP forms (non-composite)  ·  DC2 = barriers / sidewalk ÷ Nb (composite)  ·  DW = FWS × roadway width ÷ Nb

w_DC1 (non-composite)

0.9883 kip/ft

slab 0.8000 + haunch 0.0333

w_DC2 (composite)

0.1800 kip/ft

barriers shared by all girders

w_DW

0.2100 kip/ft

future wearing surface

M_DC1

790.7 kip-ft

M_DC2

144.0 kip-ft

M_DW

168.0 kip-ft

V_DC1

39.5 kip

V_DC2

7.2 kip

V_DW

8.4 kip

Strength I permanent moment (max: 1.25DC + 1.50DW)

1420.3 kip-ft

min case 0.90DC + 0.65DW = 950.4 kip-ft

Service I permanent moment (1.0DC + 1.0DW)

1102.7 kip-ft

factored permanent shear = 71.0 kip

Detailing sketchSimple-span moment diagram — DC1, DC2, DW and LL+IM
L = 80.0 ftM_u = 1420 k-ftγ·M_LL+IM = 0γ·M_DC1 = 988midspan ordinate at x = L/2

MDC1 = 791 k-ft (girder + slab + haunch on the non-composite section) · MDC2 = 144 k-ft (barriers on the composite section) · MDW = 168 k-ft · MLL+IM = 0 k-ft (distributed) · factored Mu = 1420 k-ft.

Live load (HL-93) is added separately in Module 2, then distributed to the girder with the factors from Module 4. Only DC1 acts on the bare girder section; DC2 and DW act on the composite section, so their stresses use the composite section moduli.

Module 11AASHTO LRFD 6.10.2 / 6.10.6 / 6.10.8.2 / 6.9.4Chapters 4 · 8

Steel I-section stability & compression design

Cross-section proportion limits, web/flange classification, flange local buckling and lateral–torsional buckling with L_p / L_r, plus a compression-member slenderness check.

I-section

Compression member

λ_f = b_fc/2t_fc  ·  L_p = 1.0 r_t √(E/F_yc)  ·  L_r = π r_t √(E/F_yr)  ·  F_nc = min(FLB, LTB)  ·  P_n = 0.658^(P_o/P_e) P_o

D / t_w

108.0

limit 150 (§6.10.2.1.1)

b_fc / 2t_fc

8.00

λ_pf = 9.15, λ_rf = 16.97

Web class

non-compact

2D_c/t_w = 119.1

R_b (load shedding)

1.000

L_p

7.4 ft

bracing for full yield

L_r

27.8 ft

L_b = 20.0 ft → inelastic

F_nc (FLB)

50.00 ksi

F_nc (LTB)

40.76 ksi

F_nc governing

40.76 ksi

Lateral–torsional buckling (§6.10.8.2.3)

φM_n vs M_u

3900 ≥ 4200 k-ft

S_xc = 1148 in³ · utilization 1.08

Design verdict & redesign guidance

  • LTB governs at L_b = 240.0 ft: brace at or below L_p = 89.0 in (7.4 ft) to develop the full yield moment.
  • φM_n = 3900 k-ft < M_u = 4200 k-ft — increase S_xc by about 8%: try t_fc = 1.077 in or D = 56 in.

KL/r

86.1

limit 120 (§6.9.3)

P_e (Euler)

568 kip

inelastic buckling

φ_c P_n vs P_u

406 ≥ 300 kip

Compression-member verdict

  • Column adequate: KL/r = 86, utilization 0.74.
Detailing sketchComposite steel plate girder — section, elevation and framing plan
b_eff = 16.00 fttₛ = 8.00 ind = 56.3 inShear studs — full composite (6.10.10)SECTION A–A (at midspan)ELEVATION — SIDE VIEW OF ONE GIRDER LINEShear studs at 20 in max pitch; transverse stiffeners / cross-frames at the marked lines (6.10.10, 6.7.4)AAFRAMING PLAN — GIRDER LINES AND CROSS-FRAMESb_eff = 16.00 ftDashed lines = intermediate cross-frames / diaphragms; solid = girder lines

F_nc = 40.76 ksi · φM_n = 3900 k-ft vs M_u = 4200 k-ft

Chapter 4

Live-load distribution

How much of a lane a single girder carries — the approximate equations plus the stiffness, skew, lever-rule and rigid cross-section checks that surround them.

Module 12AASHTO LRFD 4.6.2.2.2 / 4.6.2.2.3Chapters 4 · 7 · 8

Live-load distribution factors

Approximate distribution equations for concrete decks on steel or prestressed I-girders, interior and exterior.

Cross-section type (k): concrete deck on steel or prestressed-concrete I-girders. Valid for 3.5 ≤ S ≤ 16 ft, 20 ≤ L ≤ 240 ft, 4.5 ≤ tₛ ≤ 12 in.

Kg / (12·L·tₛ³) = 5.0863  ·  gM,int = 0.075 + (S/9.5)0.6(S/L)0.2(Kg/12Ltₛ³)0.1

Interior moment — one lane

0.531 lanes/girder

Interior moment — two+ lanes

0.745 lanes/girder

Interior shear — one lane

0.680 lanes/girder

Interior shear — two+ lanes

0.814 lanes/girder

Exterior moment (e = 0.77 + dₑ/9.1)

0.737

e = 0.990

Exterior shear (e = 0.6 + dₑ/10)

0.652

e = 0.800

Governing interior moment factor is 0.745. Exterior girders must also be checked by the lever rule and the rigid cross-section (special analysis) equation for beam-slab bridges with diaphragms.

Detailing sketchDeck cross-section — girder spacing and lane positions
ext.int.int.int.int.ext.S = 8.0 ftd_e = 2.0 ftt_s = 8.0 inInterior g_M ≈ 0.745 · Exterior g_M ≈ 0.737 lanes/girder

6 girders at S = 8.00 ft spacing, deck thickness ts = 8.00 in, overhang de = 2.00 ft. Interior moment DF ≈ 0.745 lanes/girder; exterior moment DF ≈ 0.737 lanes/girder.

Module 13AASHTO LRFD 4.6.2.2.1 / 4.6.2.2.2d–e / 4.6.2.2.3cChapter 4

K_g, skew corrections, lever rule & rigid cross-section

The longitudinal stiffness parameter K_g = n(I + Ae_g²), the §4.6.2.2.2e moment reduction and §4.6.2.2.3c shear increase for skew, and the two exterior-girder checks — lever rule and the rigid cross-section special analysis — with multiple-presence factors.

Wheel offsets are the distances from the exterior girder to each wheel of the loaded lanes, measured along the deck.

K_g

502964 in⁴

Skew factor — moment

1.0000

Skew factor — shear (obtuse corner)

1.1087

Lever-rule exterior DF

0.4444 lanes/girder

Rigid cross-section DF

1.0222 lanes/girder

Governing exterior DF

1.0222 lanes/girder

Detailing sketchGirder cross-section — plan of framing
s = 9.00 ftPLAN — 1×5 girder group, size 1.00 ft

Governing exterior distribution factor = 1.022 lanes/girder for 5 girders at S = 9.00 ft, skew θ = 30°.

StepEquationSubstitutionResult
Modular ration = E_B/E_D29000/36447.958
Longitudinal stiffness parameterK_g = n(I + A e_g²)7.958(20000 + 48.00·30.00²)502964 in⁴
Stiffness termK_g/(12 L t_s³)502964/(12·100.0·8.00³)0.8186
Skew correction — moment1 − c₁(tan θ)^1.5 ; c₁ = 0.25(K_g/12Lt_s³)^0.25 (S/L)^0.5c₁ = 0.0713, θ = 30.0°1.0000
Skew correction — shear1.0 + 0.20 (K_g/12Lt_s³)^0.3 tan θ1 + 0.20(0.8186)^0.3 tan 30.0°1.1087
Lever rule reactionR = Σ P_i x_i / S (P = 0.5 axle)Σ(7.00, 1.00)/9.000.4444 lanes
Lever rule DF with mg = m·R1.00 × 0.44440.4444 lanes/girder
Rigid cross-section reactionR = N_L/N_b + X_ext ΣE / Σx²2/5 + 18.00·2·14.00/810.01.0222
Rigid cross-section DF with mg = m·R1.00 × 1.02221.0222 lanes/girder

Exterior-girder design must use the largest of the approximate e·g equation, the lever rule (0.4444) and the rigid cross-section value (1.0222). Multiply moment DFs by 1.0000 and the support shear of the exterior girder at the obtuse corner by 1.1087.

Assumptions & code basis
  • K_g = n(I + A e_g²) per AASHTO LRFD Eq. 4.6.2.2.1-1, with e_g the distance between the girder and deck centroids.
  • Skew correction for moment applies only for 30° < θ ≤ 60° (§4.6.2.2.2e); for θ ≤ 30° no reduction is taken and for θ > 60° a refined analysis is required.
  • Skew correction for support shear at the obtuse corner of the exterior girder, Table 4.6.2.2.3c-1, always ≥ 1.0 — the shear correction is an increase.
  • Lever rule assumes the deck is hinged over the interior girder; wheel loads are placed 2 ft from the barrier face and 6 ft apart (§3.6.1.3.1).
  • The rigid cross-section (special analysis) equation §C4.6.2.2.2d applies to beam-slab bridges with sufficiently stiff diaphragms or cross-frames acting as a unit.
  • Multiple-presence factors m (1.20 / 1.00 / 0.85 / 0.65) are included in the lever-rule and rigid-section results but are already embedded in the approximate DF equations.
Module 14AASHTO LRFD 6.10.1.1.1cChapter 4

Cracked negative-moment composite section

Stage-dependent section properties neglecting concrete in tension, with the longitudinal deck steel acting compositely and the fibre stresses for DC1, DC2/DW and LL+IM at the pier.

Negative-moment region: the deck concrete is neglected and only the longitudinal deck steel acts with the girder.

Cracked ȳ

32.26 in

I_cr

45203 in⁴

S_b,cr

1401 in³

f_bottom

-32.49 ksi

f_top

-27.40 ksi

Deck reinforcement stress

-16.20 ksi

Derivation — equation, substitution, result

Cracked-section area

  Acr=Asteel+As,deck  (deck concrete neglected, §6.10.1.1.1c)=  62.0+14.00=  76.00in2\begin{aligned}&\;A_{cr} = A_{steel} + A_s,\,\text{deck} \;\text{(deck concrete neglected, §6.10.1.1.1c)}\\[4pt]&=\;62.0 + 14.00\\[4pt]&=\;\boxed{76.00 \,\text{in}^{2}}\end{aligned}

Neutral axis

  yˉ=\SumAiyi/\SumAi=  [62.0(26.00)+14.00(60.00)]/76.00=  yˉ=32.26infromthebottom\begin{aligned}&\;ȳ = \Sum A_i y_i / \Sum A_i\\[4pt]&=\;[62.0(26.00) + 14.00(60.00)]/76.00\\[4pt]&=\;\boxed{ȳ = 32.26 \,\text{in} \operatorname{from} \,\text{the} \,\text{bottom}}\end{aligned}

Cracked inertia

  Icr=\SumIo+\SumAidi2=  32000+2432+10771=  Icr=45203in4\begin{aligned}&\;I_{cr} = \Sum I_o + \Sum A_i d_i^{2}\\[4pt]&=\;32000 + 2432 + 10771\\[4pt]&=\;\boxed{I_{cr} = 45203 \,\text{in}^{4}}\end{aligned}

Section moduli

  S=I/c=  Sb,cr=1401,St,cr=2080,Sdeck=1630in3=  stagedependent\begin{aligned}&\;S = I/c\\[4pt]&=\;S_b,\,\text{cr} = 1401, S_t,\,\text{cr} = 2080, S_{deck} = 1630 \,\text{in}^{3}\\[4pt]&=\;\boxed{\,\text{stage}-\,\text{dependent}}\end{aligned}

Bottom-flange stress

  fb=MDC1/Sb+(MDC2+MLL+IM)/Sb,cr=  1400(12)/1231+2200(12)/1401=  32.49ksi\begin{aligned}&\;f_b = M_{DC1}/S_b + (M_{DC2} + M_{LL}+\mathrm{IM})/S_b,\,\text{cr}\\[4pt]&=\;-1400(12)/1231 + -2200(12)/1401\\[4pt]&=\;\boxed{-32.49 \,\text{ksi}}\end{aligned}

Top-flange stress

  ft=MDC1/St+(MDC2+MLL+IM)/St,cr=  27.40ksi\begin{aligned}&\;f_t = M_{DC1}/S_t + (M_{DC2} + M_{LL}+\mathrm{IM})/S_t,\,\text{cr}\\[4pt]&=\;\boxed{-27.40 \,\text{ksi}}\end{aligned}

Deck-steel stress

  fs=(MDC2+MLL+IM)/Sdeck=  16.20ksi\begin{aligned}&\;f_s = (M_{DC2} + M_{LL}+\mathrm{IM})/S_{deck}\\[4pt]&=\;\boxed{-16.20 \,\text{ksi}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #6 @ 6 in top matGirder depth 54 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 9.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Two-thirds of the longitudinal deck steel goes in the top mat; place it before the negative-moment pour.
  • Stagger deck-steel splices and extend the steel past the dead-load inflection point plus the development length.
  • Shear studs are required through the negative-moment region even though the concrete is neglected for strength.
CheckDemandCapacity / limitStatus
Bottom flange ≤ F_y32.49 ksi50 ksiPASS
Top flange ≤ F_y27.40 ksi50 ksiPASS
Deck longitudinal steel ≥ 1 % of the slab area (§6.10.1.7)Two-thirds in the top mat; #6 bars or smaller at ≤ 12 in.PASS
Independent verificationExpectedComputedStatus
Cracked inertia is smaller than the short-term composite valueI_cr < I_composite in⁴VERIFIED

Assumptions & basis of design

  • Negative-moment region: concrete in tension is neglected and only the longitudinal deck reinforcement within the effective flange width acts compositely (§6.10.1.1.1c).
  • DC1 acts on the bare steel section; DC2 and LL+IM act on the cracked composite section.
  • Stresses are elastic first-order values — compare against the §6.10.8 lateral–torsional buckling resistance, not simply F_y, when the bottom flange is in compression.

Elastic stresses are within yield; continue with the §6.10.8 stability checks and the §6.10.1.7 minimum deck steel.

Chapter 5

Deck design

Equivalent strips, the three overhang design cases with yield-line barrier analysis, and the empirical (isotropic) design method.

Module 15AASHTO LRFD 4.6.2.1 / A4Chapters 1 · 5

Deck equivalent strip & Strength I demand

Equivalent strip widths for positive, negative, and overhang design, with factored slab moments and both reinforcement mats.

+M strip (26.0 + 6.6S)

78.8 in

−M strip (48.0 + 3.0S)

72.0 in

Overhang strip (45.0 + 10.0X)

75.0 in

M_DC

0.64 k-ft/ft

M_DW

0.16 k-ft/ft

M_LL+IM (approx.)

6.48 k-ft/ft

Strength I M_u

12.38 k-ft/ft

Bottom mat (+M)

#4 @ 5.5 in

A_s,req 0.432 → A_s,prov 0.436 in²/ft

Top mat (−M)

#6 @ 10.0 in

A_s,req 0.515 → A_s,prov 0.528 in²/ft

Deck bottom mat (positive moment) — AASHTO LRFD §5.6.3 / §5.10

A_s required (strength)0.43 in²/ft
A_s minimum (§5.6.3.3 / §5.10.6)0.19 in²/ft
A_s design (governing)0.43 in²/ft
Bar selection#4 @ 5.5 in c/c
Bar size / area#4 — A_b = 0.20 in²
Spacing (c/c)5.5 in
A_s provided0.44 in²/ft
A_s,prov / A_s,req1.01
Stress-block depth a0.64 in
Net tensile strain ε_t0.0236
φ0.900
φM_n (as detailed)12.5 k-ft/ft
M_cr (§5.6.3.3)5.5 k-ft/ft
Minimum-resistance demand min(M_cr, 1.33M_u)5.5 k-ft/ft
Reinforcement ratio ρ0.0054

PASS — Adequate — detail as scheduled

A_s,prov / A_s,req = 1.01; ε_t = 0.0236 (tension-controlled, φ = 0.90).

Deck top mat (negative moment) — AASHTO LRFD §5.6.3 / §5.10

A_s required (strength)0.51 in²/ft
A_s minimum (§5.6.3.3 / §5.10.6)0.24 in²/ft
A_s design (governing)0.51 in²/ft
Bar selection#6 @ 10.0 in c/c
Bar size / area#6 — A_b = 0.44 in²
Spacing (c/c)10.0 in
A_s provided0.53 in²/ft
A_s,prov / A_s,req1.03
Stress-block depth a0.78 in
Net tensile strain ε_t0.0140
φ0.900
φM_n (as detailed)11.4 k-ft/ft
M_cr (§5.6.3.3)5.5 k-ft/ft
Minimum-resistance demand min(M_cr, 1.33M_u)5.5 k-ft/ft
Reinforcement ratio ρ0.0085

PASS — Adequate — detail as scheduled

A_s,prov / A_s,req = 1.03; ε_t = 0.0140 (tension-controlled, φ = 0.90).

Detailing sketchDeck slab — section, plan and longitudinal section
S = 8.00 ftS = 8.00 ft3.00 fttₛ = 8.00 inTop mat #4 @ 5.5 inBottom mat #4 @ 7.0 in2.14 in wearing surfaceREINFORCEMENT SCHEDULE — TRANSVERSEA_s,req = 0.432 in²/ft (M_u = 12.38 k-ft/ft)Top mat: #4 @ 5.5 in — A_s = 0.436 in²/ftBot mat: #4 @ 7.0 in — A_s = 0.343 in²/ftA_s,prov / A_s,req = 1.01 ✓Cover: 2 in top / 1 in bottom (5.10.1)SECTION A–A — transverse cut (looking upstation)BBPLAN — DECK REINFORCING MAT (TOP STEEL SOLID, BOTTOM DASHED)girder CLgirder CLgirder CL5.5 inTransverse top mat #4 @ 5.5 in — bottom mat #4 @ 7.0 indeck edge / barrier faceDistribution steel #4 @ 12 in, ≥ 67 % of the bottom transverse steel (9.7.3.2)SECTION B–B — LONGITUDINAL CUT ALONG THE BRIDGE AXIStₛ = 8.00 in2.14 in wearing surfaceLongitudinal distribution steel — lap splices 1.3·l_d, staggered (5.10.8.4)Top cover 2 in (deck exposed to de-icing salts), bottom cover 1 in — AASHTO Table 5.10.1-1Deck continuous over girders; negative moment steel continuous through the supports

Top mat #4 @ 5.5 in (As = 0.436 in²/ft) for the negative strip moment over the girders; bottom mat #4 @ 7.0 in for the positive strip moment between girders. Required As = 0.432 in²/ft at Mu = 12.38 k-ft/ft. Distribution steel and 2 in clear top / 1 in clear bottom cover per AASHTO 5.10.1 and 9.7.3.

Dead-load moments use the continuous-slab approximation wS²/10. For final design use the Appendix A4 live-load moment table, which already includes multiple presence and dynamic load allowance.

Module 16AASHTO LRFD A13.3.1 / A13.4.1 / 4.6.2.1.3Chapter 5

Deck overhang — collision & wheel-load design

Yield-line barrier resistance R_w and critical length L_c, the collision moment delivered into the deck at Extreme Event II, the Strength I wheel-load case on the 45 + 10X strip, and the governing overhang steel.

M_c, M_w and M_b are the barrier's yield-line resistances about a horizontal axis (wall cantilever), a vertical axis (wall bending) and the beam at the top of the parapet.

Barrier resistance R_w

82.7 kip

Critical length L_c

6.98 ft

Strength I overhang moment

12.39 k-ft/ft

Extreme Event II overhang moment

8.81 k-ft/ft

Governing overhang moment

12.39 k-ft/ft

Required top steel A_s

0.173 in²/ft

Detailing sketchDeck overhang — section
Deck slab: 8.00 inBarrier height: 32.40 inΣ = 40.40 inwidth = 3.50 ftSECTION — layer stack (scaled)

Overhang L = 3.50 ft; governing overhang moment Mu = 12.39 k-ft/ft requires As = 0.173 in²/ft.

StepEquationSubstitutionResult
Yield-line critical lengthL_c = L_t/2 + √[(L_t/2)² + 8H(M_b + M_w)/M_c]1.75 + √[3.06 + 8·2.70(0.0+18.0)/16.00]6.98 ft
Barrier resistanceR_w = 2/(2L_c − L_t) · [8M_b + 8M_w + M_c L_c²/H]2/(2·6.98 − 3.5)·[8·0.0 + 8·18.0 + 16.00·6.98²/2.70]82.7 kip
Collision moment into the deckM = R_w/(L_c + 2H)82.7/(6.98 + 2·2.70)6.68 k-ft/ft
Overhang dead loadM_DC = w t_s L²/2 + W_barrier·arm0.1000·3.50²/2 + barrier2.07 k-ft/ft
Overhang stripE = 45 + 10X45 + 10·1.2557.5 in
Wheel-load momentM_LL+IM = P(1+IM)X / (E/12)16·1.33·1.25/(57.5/12)5.55 k-ft/ft
Case 2 — Strength I1.25DC + 1.50DW + 1.75(LL+IM)1.25·2.07 + 1.50·0.06 + 1.75·5.5512.39 k-ft/ft
Case 1 — Extreme Event II1.00DC + 1.00DW + M_collision2.07 + 0.06 + 6.688.81 k-ft/ft
Required overhang steelA_s = 0.85f′_c b d/f_y [1 − √(1 − 2M_u/(0.85φ f′_c b d²))]M_u = 12.39 k-ft/ft, d = 5.19 in0.173 in²/ft
  • OKBarrier resistance ≥ test level force F_tdemand 54.0 kipcapacity 82.7 kipratio 0.65
  • OKGoverning caseStrength I vertical wheel load governs.

Provide at least 0.173 in²/ft of top transverse steel in the overhang, developed fully into the first bay. Strength I governs.

Assumptions & code basis
  • Three design cases per AASHTO LRFD §A13.4.1: (1) transverse collision at Extreme Event II, (2) vertical wheel load at Strength I, (3) the deck design case checked at the design section.
  • Yield-line barrier analysis §A13.3.1 gives R_w and the critical length L_c of the failure pattern for an interior wall segment.
  • The barrier must fail before the deck: the deck overhang is designed for the barrier resistance R_w, not for the nominal test force F_t.
  • Wheel load placed 1 ft from the barrier face; overhang strip width 45 + 10X in (Table 4.6.2.1.3-1).
  • Extreme Event II uses γ_p = 1.00 on permanent loads and φ = 1.00 for flexure.
Module 17AASHTO LRFD 9.7.2.4 / 9.7.2.5Chapter 5

Empirical (isotropic) deck design method

Screens all eleven §9.7.2.4 applicability conditions and returns the prescribed 0.27 / 0.18 in²/ft isotropic mat with spacing and end-zone rules when the method applies.

The empirical method replaces flexural analysis with a prescribed isotropic mat — but only when every §9.7.2.4 condition is satisfied.

Method applicable

No

S / t_core

21.60

Bottom steel each way

0.27 in²/ft

Top steel each way

0.18 in²/ft

Suggested bars

#5 @ 12 in bottom, #4 @ 12 in top

≤ 18 in spacing

Detailing sketchEmpirical deck — core and mats
Top cover to top mat: 1.50 inCore (isotropic mat): 5.00 inBottom cover: 1.50 inΣ = 8.00 inwidth = 9.00 ftSECTION — layer stack (scaled)

S/t_core = 21.60; bottom steel 0.27 in²/ft each way, top 0.18 in²/ft each way.

StepEquationSubstitutionResult
Effective lengthS (face-to-face for monolithic, distance between flange tips + flange overhang for steel)9.00 ft108.0 in
Core deptht_core = t_s − top cover − bottom cover8.00 − covers5.00 in
Span-to-depth ratioS/t_core (must be 6 – 18)108.0/5.0021.60
Bottom mat, each directionA_s = 0.27 in²/ft0.27 in²/ft
Top mat, each directionA_s = 0.18 in²/ftf_y = 60 ksi ≥ 60 ksi0.18 in²/ft
  • OKSupporting components are steel and/or concrete beams
  • OKDeck is fully cast-in-place and water cured
  • OKDeck is of uniform depth (haunches excepted)
  • NGEffective length-to-depth ratio 6.0 ≤ S/t_core ≤ 18.0
  • OKCore depth ≥ 4.0 in
  • OKEffective length S ≤ 13.5 ft
  • OKTotal slab depth ≥ 7.0 in
  • OKOverhang ≥ 5.0 times slab depth (or 3.0 t_s with a composite barrier)
  • OKDeck is made composite with the supporting components
  • OKAt least three girder lines (N_b ≥ 3)
  • OKSkew ≤ 25° for the standard reinforcement layout (otherwise double the end-zone steel)

Conditions failed: Effective length-to-depth ratio 6.0 ≤ S/t_core ≤ 18.0. Use the traditional equivalent-strip design (§4.6.2.1) instead, or adjust the geometry until the conditions are met.

Assumptions & code basis
  • Empirical (isotropic) deck design per AASHTO LRFD §9.7.2 — applicable only when every design condition of §9.7.2.4 is met.
  • Prescribed reinforcement §9.7.2.5: 0.27 in²/ft in each bottom layer and 0.18 in²/ft in each top layer, placed in both directions, f_y ≥ 60 ksi.
  • Maximum bar spacing 18 in; the reinforcement is placed as close to the outside surfaces as cover allows.
  • The overhang and the barrier are NOT covered by the empirical method — design them by the strip method with the three §A13.4.1 cases.
  • For skews above 25° the end-zone transverse reinforcement in the two end panels is doubled.
Module 18AASHTO LRFD 9.7.3.2 / 5.10.6 / 5.6.7 / 5.5.3.2Chapter 5

Deck secondary steel, crack control & rebar fatigue

Distribution steel as a percentage of the main mat, shrinkage-and-temperature steel, the §5.6.7 crack-control spacing with γ_e, and the Δf ≤ 24 − 20 f_min/f_y fatigue check on straight bars.

Distribution steel, shrinkage and temperature steel, the Class 1/2 crack-control spacing and the rebar fatigue stress range.

Distribution steel

0.415 in²/ft

67.0 % of the main steel

Shrinkage & temp steel

0.110 in²/ft per face

Service stress f_ss

27.44 ksi

Max bar spacing

9.29 in

Fatigue Δf

16.46 ksi

Derivation — equation, substitution, result

Distribution steel percentage

  %=220/S67%(§9.7.3.2)=  S=3.000=  67.0%\begin{aligned}&\;\% = 220/\sqrt{S} \le 67 \% (§9.7.3.2)\\[4pt]&=\;\sqrt{S} = 3.000\\[4pt]&=\;\boxed{67.0 \%}\end{aligned}

Bottom distribution steel

  As,dist=%As,main=  0.670×0.620=  0.415in2/ft\begin{aligned}&\;A_s,\,\text{dist} = \% \cdot A_s,\,\text{main}\\[4pt]&=\;0.670 \times 0.620\\[4pt]&=\;\boxed{0.415 \,\text{in}^{2}/\,\text{ft}}\end{aligned}

Shrinkage & temperature steel

  As1.30bh/[2(b+h)fy],0.11As0.60(§5.10.6)=  1.30(12)(8.50)/[2(12+8.50)(60)]=  0.110in2/ftperface\begin{aligned}&\;A_s \ge 1.30 b h /[2(b+h)f_y], 0.11 \le A_s \le 0.60 (§5.10.6)\\[4pt]&=\;1.30(12)(8.50)/[2(12+8.50)(60)]\\[4pt]&=\;\boxed{0.110 \,\text{in}^{2}/\,\text{ft} \operatorname{per} \,\text{face}}\end{aligned}

Cracked elastic lever arm

  k=(nρ)2+2nρnρ,j=1k/3=  n=7.97,ρ=0.00876=  k=0.310,j=0.897\begin{aligned}&\;k = \sqrt{(n\rho )^{2} + 2n\rho } − n\rho , j = 1 − k/3\\[4pt]&=\;n = 7.97, \rho = 0.00876\\[4pt]&=\;\boxed{k = 0.310, j = 0.897}\end{aligned}

Service steel stress

  fss=Ms/(Asjd)0.60fy=  7.50(12)/(0.620×0.897×5.90)=  27.44ksi\begin{aligned}&\;f_{ss} = M_s/(A_s j d) \le 0.60 f_y\\[4pt]&=\;7.50(12)/(0.620 \times 0.897 \times 5.90)\\[4pt]&=\;\boxed{27.44 \,\text{ksi}}\end{aligned}

Crack-control spacing

  s700γe/(βsfss)2dc(Eq.5.6.71)=  βs=1+2.00/[0.7(8.502.00)]=1.440=  smax=9.29in\begin{aligned}&\;s \le 700\gamma _e/(\beta _s f_{ss}) − 2d_c (Eq. 5.6.7-1)\\[4pt]&=\;\beta _s = 1 + 2.00/[0.7(8.50 − 2.00)] = 1.440\\[4pt]&=\;\boxed{s_{\operatorname{max}} = 9.29 \,\text{in}}\end{aligned}

Fatigue stress range

  Δf=fmaxfmin(ΔF)TH=2622(fmin/fy)(§5.5.3.2)=  12.813.66=16.46ksivs27.34ksi=  satisfied\begin{aligned}&\;\Delta f = f_{\operatorname{max}} − f_{\operatorname{min}} \le (\Delta F)_{TH} = 26 − 22(f_{\operatorname{min}}/f_y) (§5.5.3.2)\\[4pt]&=\;12.81 − -3.66 = 16.46 \,\text{ksi} \,\text{vs} 27.34 \,\text{ksi}\\[4pt]&=\;\boxed{\,\text{satisfied}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #5 @ 8 in top matGirder depth 54 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 9.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Distribution steel goes in the bottom mat, tied to the main bars — it is not a substitute for temperature steel in the top mat.
  • Use epoxy-coated or stainless bars in the top mat where deicing salts are used; repair coating damage before the pour.
  • Maintain 2.5 in top cover (2 in with an integral wearing surface) using chairs at 4 ft o.c. maximum.
  • Screed rails must bear on the girders, never on the reinforcing steel.
CheckDemandCapacity / limitStatus
f_ss ≤ 0.60 f_y27.44 ksi36.0 ksiPASS
Crack-control spacing achievablebar spacing used9.29 inPASS
Rebar fatigue Δf ≤ (ΔF)_TH16.46 ksi27.34 ksiPASS
Deck deflection Δ ≤ S/800 (optional, §2.5.2.6.2)Only mandatory for the owner-invoked deflection criterion.PASS
Independent verificationExpectedComputedStatus
Distribution steel = 220/√S ≤ 67 % of the main steel67.0 %VERIFIED

Assumptions & basis of design

  • Straight, non-skewed deck with the primary reinforcement perpendicular to traffic; §9.7.3.2 bottom distribution steel.
  • Class 1 exposure γ_e = 1.00; use 0.75 for decks exposed to de-icing salts (§5.6.7).
  • Fatigue I with the fatigue truck at a 30 ft rear axle spacing and IM = 15 %.

Distribution, crack-control and fatigue requirements are all satisfied with the given mat.

Module 19AASHTO LRFD 9.8.3 / 6.6.1.2Chapters 5 · 8

Orthotropic steel deck — three-system fatigue

Superposition of the local rib-wall, rib-as-beam and global girder stress systems, the resulting stress range at the rib-to-deck weld, and the infinite / finite life prediction for the governing detail category.

Superimposes the local plate, rib and global girder stress ranges, then checks infinite and finite life for the governing detail category.

f₁ deck plate

38.71 ksi

f₂ rib

29.08 ksi

Total Δf

71.78 ksi

(ΔF)_n

5.00 ksi

Predicted life

0 yr

Derivation — equation, substitution, result

Contact pressure

  w=Pwheel/  (patch²)=  21.0/(10.02)=  0.2100ksi\begin{aligned}&\;w = P_{wheel}/\;\text{(patch²)}\\[4pt]&=\;21.0/(10.0^{2})\\[4pt]&=\;\boxed{0.2100 \,\text{ksi}}\end{aligned}

System 1 — deck-plate local bending

  M1=wa2/12  (fixed–fixed strip),f1=M1/Splate,S=tp2/6=  a=12.0in,tp=0.625in=  f1=38.71ksi\begin{aligned}&\;M_{1} = w\cdot a^{2}/12 \;\text{(fixed–fixed strip)}, f_{1} = M_{1}/S_{plate}, S = t_p^{2}/6\\[4pt]&=\;a = 12.0 \,\text{in}, t_p = 0.625 \,\text{in}\\[4pt]&=\;\boxed{f_{1} = 38.71 \,\text{ksi}}\end{aligned}

System 2 — rib bending between floorbeams

  M20.20PLfb  (continuous rib),f2=M2/Srib=  0.20×21.0×180.0/26.0=  f2=29.08ksi\begin{aligned}&\;M_{2} \approx 0.20 P L_{fb} \;\text{(continuous rib)}, f_{2} = M_{2}/S_{rib}\\[4pt]&=\;0.20 \times 21.0 \times 180.0 / 26.0\\[4pt]&=\;\boxed{f_{2} = 29.08 \,\text{ksi}}\end{aligned}

System 3 — global girder action

  f3fromthegirdersectionmodulus=  f3=4.00ksi\begin{aligned}&\;f_{3} \operatorname{from} \,\text{the} \,\text{girder} \,\text{section} \,\text{modulus}\\[4pt]&=\;\boxed{f_{3} = 4.00 \,\text{ksi}}\end{aligned}

Superimposed stress range

  Δf=f1+f2+f3=  38.71+29.08+4.00=  Δf=71.78ksi\begin{aligned}&\;\Delta f = f_{1} + f_{2} + f_{3}\\[4pt]&=\;38.71 + 29.08 + 4.00\\[4pt]&=\;\boxed{\Delta f = 71.78 \,\text{ksi}}\end{aligned}

Cycles

  N=  (ADTTSL)(365)  (years)(n)=  2000×365×75=  N=5.48e+7\begin{aligned}&\;N = \;\text{(ADTTSL)}(365)\;\text{(years)}(n)\\[4pt]&=\;2000 \times 365 \times 75\\[4pt]&=\;\boxed{N = 5.48e+7}\end{aligned}

Fatigue resistance

  (ΔF)n=(A/N)1/3½(ΔF)TH(Eq.6.6.1.2.51)=  A=4.40e+9ksi3,(ΔF)TH=10.0ksi=  (ΔF)n=5.00ksi\begin{aligned}&\;(\Delta F)_n = (A/N)^{1/3} \ge ½(\Delta F)_{TH} (Eq. 6.6.1.2.5-1)\\[4pt]&=\;A = 4.40e+9 \,\text{ksi}^{3}, (\Delta F)_{TH} = 10.0 \,\text{ksi}\\[4pt]&=\;\boxed{(\Delta F)_n = 5.00 \,\text{ksi}}\end{aligned}

Predicted life

  Y=A/  (Δf³ ⋅ 365 ⋅ ADTTSL)=  0years\begin{aligned}&\;Y = A/\;\text{(Δf³ · 365 · ADTTSL)}\\[4pt]&=\;\boxed{0 \,\text{years}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchOrthotropic deck plate — rib section and combined fatigue stress range
wheel = 21.0 kip on 10.0 in patchrib spacing a = 12.0 int_p = 0.625 inlocal Δf67.8 ksiglobal Δf4.0 ksitotal Δf71.8 ksi(ΔF)_TH = 10.0 ksi

Deck plate tp = 0.625 in over ribs at 12.0 in spacing. Wheel load 21.0 kip on a 10.0 in tyre patch produces local Δf = 67.8 ksi; combined with the global girder range 4.0 ksi gives total Δf = 71.8 ksi against the threshold (ΔF)TH = 10.0 ksi.

Constructability & detailing notes

  • Rib-to-deck welds must achieve 80 % penetration with tight fit-up — the fatigue performance of the whole deck depends on it.
  • Use continuous ribs passing through slotted floorbeam webs and grind the cut-out radius smooth.
  • Specify a wearing surface (epoxy asphalt or polymer) that bonds and shares load with the deck plate.
CheckDemandCapacity / limitStatus
Infinite life Δf ≤ (ΔF)_TH (Category C)71.78 ksi10.0 ksiREVIEW
Finite life Δf ≤ (ΔF)_n71.78 ksi5.00 ksiREVIEW
Deck plate ≥ 5/8 in (§9.8.3.7.2)0.625 in0.625 inPASS
Rib-to-deck weld ≥ 80 % penetrationDetail per §9.8.3.7.3 to keep the rib-to-deck joint in Category C.PASS
Independent verificationExpectedComputedStatus
Combined stress range below the constant-amplitude thresholdVERIFIED

Assumptions & basis of design

  • AASHTO LRFD §9.8.3 orthotropic deck design by the three-system superposition (local plate, rib/panel, global girder).
  • Deck-plate strip idealised as fixed–fixed between ribs; ribs idealised as continuous beams over the floorbeams with M ≈ 0.20 P L.
  • Fatigue I load factor 1.75 with the fatigue truck; single-lane ADTT_SL entered directly.

Thicken the deck plate (f₁ ∝ 1/t_p²) or close the rib spacing before enlarging the ribs — local plate bending dominates the rib-to-deck detail.

Chapter 6

Reinforced concrete — flexure, shear, torsion and interfaces

Strength design of concrete sections including the general (MCFT) shear procedure, torsion reinforcement, and shear transfer across cold joints.

Module 20AASHTO LRFD 5.6.3 / 5.5.4.2Chapters 5 · 6

Reinforced-concrete flexural capacity

Stress-block depth, net tensile strain, resistance factor, and the φM_n ≥ M_u check with bar selection.

a = A_s f_y / (0.85 f′_c b)  ·  M_n = A_s f_y (d − a/2)  ·  ε_t = 0.003 (d − c)/c

β₁

0.850

Stress-block depth a

5.88 in

Neutral axis c

6.92 in

Net tensile strain ε_t

0.0100

Tension-controlled

φ

0.900

M_n

541 k-ft

φM_n vs M_u

487 ≥ 400 k-ft

Section adequate for flexure.

Flexural reinforcement design — AASHTO LRFD §5.6.3 / §5.10

A_s required (strength)3.22 in²
A_s minimum (§5.6.3.3 / §5.10.6)0.70 in²
A_s design (governing)3.22 in²
Bar selection2 – #14
Bar size / area#14 — A_b = 2.25 in²
Bars / layers2 bars in 1 layer (clear spacing 5.1 in)
A_s provided4.50 in²
A_s,prov / A_s,req1.40
Stress-block depth a6.62 in
Net tensile strain ε_t0.0086
φ0.900
φM_n (as detailed)540.5 k-ft
M_cr (§5.6.3.3)93.4 k-ft
Minimum-resistance demand min(M_cr, 1.33M_u)93.4 k-ft
Reinforcement ratio ρ0.0125

PASS — Adequate — detail as scheduled

A_s,prov / A_s,req = 1.40; ε_t = 0.0086 (tension-controlled, φ = 0.90).

Transverse reinforcement — AASHTO LRFD §5.7.2.5 / §5.7.3.3

Concrete contribution V_c41.0 kip
Steel required V_s = V_u/φ − V_c92.4 kip
Stirrup schedule#4 2-leg @ 7.0 in c/c (A_v = 0.40 in²)
Maximum spacing s_max21.6 in
φV_n = φ(V_c + V_s)120.2 kip
Web-crushing limit 0.25 f′_c b_v d_v324.0 kip

PASS — φV_n = 120.2 kip ≥ V_u = 120.0 kip.

Detailing sketchReinforced-concrete beam — section, elevation and bar plan
ε_c = 0.003c = 7.79 inε_t (tension steel)b = 12.0 ind = 30.0 ina = 6.62 in blockREINFORCEMENT CALL-OUTA_s provided = 5 — #9 = 5.00 in² (2 rows)A_s used in analysis = 4.50 in², f_y = 60 ksiStirrups: #4 double leg, 2 in clear coverφM_n = 540 k-ft vs M_u = 400 k-ftSECTION A–A (at midspan)ELEVATION — SIDE VIEW, STIRRUP LAYOUT AND BAR CUT-OFFS#4 @ 4 in#4 @ 8 in5 — #9 bottom bars continuous into the supports, 90° hooks (5.10.8)Stirrups closely spaced over d from each face where V_u is largest, relaxed at midspan (5.7.2.6)AAPLAN — BOTTOM BAR LAYOUT (SOFFIT)b = 12.0 in4 bars per row × 2 rows — clear bar spacing ≥ max(1.5 d_b, 1.5 in, 1.33 × max aggregate)

5 #9 bars (5.00 in² provided against As = 4.50 in² assumed), 2 rows, 2 in clear cover, #4 stirrups. Whitney block a = 6.62 in, c = 7.79 in, fy = 60 ksi. φMn = 540 k-ft vs Mu = 400 k-ft (AASHTO 5.6.3.2).

Module 21AASHTO LRFD 5.7.3.3 / 5.7.3.4.2 / 5.7.2.5Chapters 6 · 7

Sectional shear — general (MCFT) procedure

Longitudinal strain ε_s, β and θ from Eqs. 5.7.3.4.2-1..-3, V_c and V_s with cot θ, the web-crushing ceiling, minimum transverse steel and the required stirrup spacing with the §5.7.3.4.1 maximum.

The general procedure iterates on ε_s: β falls and θ rises as the section strains, so a heavily loaded web needs both more stirrups and a flatter truss angle.

ε_s

-4.000e-4

β

6.857

θ

27.60 deg

V_c

294.2 kip

V_s

229.5 kip

φV_n

507.3 kip

Design spacing

24.0 in

Detailing sketchMCFT shear — demand vs capacity
V_u (demand)300.000 kipV_c294.200 kipV_s229.500 kipφV_n (capacity)507.300 kip

θ = 27.60° and β = 6.857 at ε_s = -4.000e-4.

StepEquationSubstitutionResult
Longitudinal strainε_s = [|M_u|/d_v + 0.5N_u + |V_u − V_p| − A_ps f_po] / (E_s A_s + E_p A_ps)[18000/60.00 + 0.5·0.0 + 260.0 − 869.4] / (29000·2.00 + 28500·4.60)-4.000e-4
Minimum transverse steelA_v,min = 0.0316 √f′_c b_v s / f_y0.0316√8.00·8.00·12.00/600.143 in² (provided 0.400 in²)
ββ = 4.8/(1 + 750ε_s)4.8/(1 + 750·-4.000e-4)6.857
θθ = 29 + 3500 ε_s29 + 3500·-4.000e-427.60°
Concrete contributionV_c = 0.0316 β √f′_c b_v d_v0.0316·6.857·√8.00·8.00·60.00294.2 kip
Stirrup contributionV_s = A_v f_y d_v cot θ / s0.400·60·60.00·1.913/12.00229.5 kip
Nominal shearV_n = min(V_c + V_s + V_p, 0.25f′_c b_v d_v + V_p)min(563.7, 1000.0)563.7 kip
Factored resistanceφV_n ≥ V_u0.90·563.7 vs 300.0507.3 kip
Required stirrup spacings = A_v f_y d_v cot θ / (V_u/φ − V_c − V_p)0.400·60·60.00·1.913/(333.3 − 294.2)stirrups not required by strength
Maximum spacingv_u < 0.125f′_c → s ≤ min(0.8d_v, 24 in); else min(0.4d_v, 12 in)v_u = 0.625 ksi24.00 in
  • OKShear strength φV_n ≥ V_udemand 300.0 kipcapacity 507.3 kipratio 0.59
  • OKWeb crushing V_n ≤ 0.25f′_c b_v d_v + V_pdemand 563.7 kipcapacity 1000.0 kip
  • OKMinimum transverse steeldemand 0.143 in²capacity 0.400 in²

Use 24.0 in stirrup spacing (governed by the maximum-spacing rule); φV_n = 507.3 kip ≥ V_u = 300.0 kip with θ = 27.6°.

Assumptions & code basis
  • General (MCFT) sectional procedure, AASHTO LRFD §5.7.3.4.2, with β and θ from Eqs. 5.7.3.4.2-1..-3.
  • Longitudinal strain ε_s taken at mid-depth of the tension reinforcement; negative values would require the concrete-tension refinement of Eq. 5.7.3.4.2-4 and are floored here.
  • d_v = max(0.9d_e, 0.72h, moment arm) must be supplied consistently with the flexural design.
  • Nominal shear capped at 0.25 f′_c b_v d_v + V_p (Eq. 5.7.3.3-2) to prevent web crushing.
  • Longitudinal reinforcement must also satisfy §5.7.3.5 — the tension-tie demand from shear.
Module 22AASHTO LRFD ACI 318-19 §22.7 · AASHTO §5.7.2.1 / 5.7.3.6Chapters 6 · 9

Torsion — closed ties & longitudinal A_ℓ

Threshold and cracking torsion, A_oh / p_h / A_o geometry, the combined shear-plus-torsion crushing check, the (A_v + 2A_t)/s tie schedule and the distributed longitudinal torsion steel.

φT_th = φλ√f′_c A_cp²/p_cp · A_t/s = T_u/(φ2A_o f_yt cot θ) · A_ℓ = (A_t/s)p_h cot²θ · s ≤ p_h/8 ≤ 12″

φT_th

13.4 k-ft

torsion designed

T_cr

71.5 k-ft

A_oh / p_h

384 / 82.0 in², in

A_t/s (one leg)

0.0184 in²/in

(A_v+2A_t)/s req

0.0950 in²/in

Tie spacing

4.0 in

s_max = 10.3 in

A_ℓ required

1.673 in²

A_ℓ,min = 1.673

A_ℓ provided

1.760 in²

Crushing check

0.307 / 0.530 ksi

Torsion reinforcement scheduleACI 318-19 §22.7 / §9.7.5 / §9.7.6.3

Closed ties#4 closed ties @ 4.0 in c/c (2 legs)
Tie legs / hooks2 legs, 135° hooks (§25.7.1.6)
Longitudinal torsion steel4 – #6 distributed @ ≈ 20.5 in around the perimeter
Perimeter bar spacing20.5 in (≤ 12 in required)
A_o = 0.85A_oh327 in²
cot θ1.000
V_c67.4 kip

PASS — Provide closed #4 ties @ 4.0 in c/c (135° hooks, §25.7.1.6) plus 4 – #6 longitudinal bars distributed around the perimeter at ≤ 12 in (§9.7.5.1).

Detailing sketchReinforced-concrete beam — section, elevation and bar plan
ε_c = 0.003c = 0.00 inε_t (tension steel)b = 18.0 ind = 26.5 ina = 0.00 in blockREINFORCEMENT CALL-OUTA_s provided = 4 — #6 = 1.76 in² (1 row)A_s used in analysis = 1.76 in², f_y = 60 ksiStirrups: #4 double leg, 2 in clear coverφM_n = 0 k-ft vs M_u = 0 k-ftSECTION A–A (at midspan)ELEVATION — SIDE VIEW, STIRRUP LAYOUT AND BAR CUT-OFFS#4 @ 4 in#4 @ 8 in4 — #6 bottom bars continuous into the supports, 90° hooks (5.10.8)Stirrups closely spaced over d from each face where V_u is largest, relaxed at midspan (5.7.2.6)AAPLAN — BOTTOM BAR LAYOUT (SOFFIT)b = 18.0 in4 bars per row × 1 row — clear bar spacing ≥ max(1.5 d_b, 1.5 in, 1.33 × max aggregate)

4 #6 bars (1.76 in² provided against As = 1.76 in² assumed), 1 row, 2 in clear cover, #4 stirrups. Whitney block a = 0.00 in, c = 0.00 in, fy = 60 ksi. φMn = 0 k-ft vs Mu = 0 k-ft (AASHTO 5.6.3.2).

Module 23AASHTO LRFD 5.7.4Chapters 6 · 7

Interface (cold-joint) shear transfer

v_ui = V_u/(b_vi d_v), the c + μ(A_vf f_y + P_c) shear-friction resistance with the K₁f′_c and K₂ ceilings for each surface condition, minimum interface steel and the extended-stirrup spacing across the girder-to-deck joint.

Interface shear governs the extended-stirrup spacing at the top of a precast girder far more often than the web shear does.

v_ui

0.2500 ksi

V_ui

60.00 kip/ft

φV_ni

82.08 kip/ft

A_vf required

0.200 in²/ft

Max spacing of extended stirrups

24.0 in

Detailing sketchInterface — girder / deck cold joint
gap = 12.00 int = 6.00 indesign movement Δ = 0.20 in

Interface shear vui = 0.2500 ksi; required Avf = 0.200 in²/ft at 12.00 in spacing (roughened surface).

StepEquationSubstitutionResult
Interface shear stressv_ui = V_u/(b_vi d_v)300.0/(20.00·60.00)0.2500 ksi
Interface shear per footV_ui = v_ui b_vi (12 in)0.2500·20.00·1260.00 kip/ft
Interface steel providedA_vf/ft = A_vf(12)/s0.400·12/12.000.400 in²/ft
Nominal interface resistanceV_ni = c A_cv + μ(A_vf f_y + P_c)0.28·240.0 + 1(0.400·60 + 0.0)91.20 kip/ft
Upper limitsV_ni ≤ K₁ f′_c A_cv and ≤ K₂ A_cv0.3·4.00·240.0 = 288.0; 1.8·240.0 = 432.0288.00 kip/ft
Factored resistanceφV_ni ≥ V_ui0.9·91.20 vs 60.0082.08 kip/ft
Required interface steelA_vf = (V_ui/φ − cA_cv)/(μ f_y) ≥ 0.05A_cv/f_y(66.67 − 67.20)/(1·60)0.200 in²/ft
Required stirrup spacing across the joints = A_vf(12)/A_vf,req0.400·12/0.20024.00 in
  • OKInterface shear φV_ni ≥ V_uidemand 60.00 kip/ftcapacity 82.08 kip/ftratio 0.73
  • OKMinimum interface reinforcement 0.05A_cv/f_ydemand 0.200 in²/ftcapacity 0.400 in²/ft

Extend the girder stirrups into the deck at 24.0 in or closer and roughen the top flange to a 0.25 in amplitude; φV_ni = 82.08 kip/ft ≥ V_ui = 60.00 kip/ft.

Assumptions & code basis
  • Interface shear transfer (shear friction) per AASHTO LRFD §5.7.4 — the cold joint between a precast girder and a cast-in-place deck.
  • Surface condition: roughened; c = 0.28 ksi, μ = 1, K₁ = 0.3, K₂ = 1.8 ksi (§5.7.4.4).
  • Interface shear per unit length v_ui = V_u/(b_vi d_v); the check is performed on a 12 in length of interface.
  • Permanent net compressive force P_c across the interface may be taken as zero unless it is reliably present.
  • Minimum interface steel 0.05 A_cv/f_y may be waived when v_ui < 0.210 ksi and the surface is roughened to 0.25 in amplitude (§5.7.4.2).
Module 24AASHTO LRFD AASHTO §5.10.6 · ACI 318-19 §24.4Chapters 5 · 12

Shrinkage & temperature steel

The ACI ratio equation and the AASHTO per-face equation side by side, governing A_s, bar size and spacing against the 5h ≤ 18 in cap, provided ρ and the bar count for the strip.

ρ = max(0.0018·60/f_y, 0.0014) · A_s = ρbh · A_s(AASHTO) = 1.30bh/[2(b+h)f_y] · s ≤ min(5h, 18″)

A_s (ACI)

0.194 in²

ρ = 0.00180

A_s (AASHTO/face)

0.110 in²/ft

A_s governing

0.194 in²

Spacing

18.0 in

s_max = 18 in

A_s provided

0.267 in²

ρ provided

0.00247

Shrinkage & temperature reinforcement scheduleACI 318-19 §24.4 · AASHTO LRFD §5.10.6

Call-out#4 @ 18.0 in c/c each face
FacesEach face (top and bottom)
Bars over strip length9 bars
Steel weight72 lb per 12 ft strip
Max spacing18 in

PASS — Provide #4 @ 18.0 in c/c each way, each face (max 18 in, §24.4.3.3). ρ_prov = 0.00247.

Detailing sketchSlab — shrinkage & temperature steel, section and plan
SECTIONs = 18.0 inh = 9.0 in#4 bars each wayPLAN — BAR SPACING EACH WAYs = 18.0 in each wayb = 12 in strip shown, bars continue each way

Strip 12 in wide × 9.0 in thick, #4 @ 18.0 in c/c each way, top and bottom.

Chapter 7

Prestressed concrete

Stress limits at every stage, immediate and time-dependent losses, service fibre stresses, and flexural resistance with bonded strand.

Module 25AASHTO LRFD 5.9.2.2 / 5.9.2.3Chapter 7

Prestressing stress limits — steel & concrete

Table 5.9.2.2-1 strand limits at jacking, transfer and service, with the §5.9.2.3 concrete compression and tension limits at release and in Service I / Service III, each screened against your fibre stresses.

Enter fibre stresses with compression negative and tension positive; the module screens every steel and concrete limit at transfer and at service.

f_py

243.0 ksi

Jacking limit

202.5 ksi

Transfer compression limit

3.600 ksi

Service III tension limit

0.5374 ksi

All limits satisfied

Yes

Detailing sketchPrestress stress limits — actual vs bound
f_pj (jacking)202.500 ksiJacking limit202.500 ksiBottom fibre stress-2.900 ksiTop fibre stress0.350 ksi

All limits satisfied: Yes.

StepEquationSubstitutionResult
Assumed yield strengthf_py = 0.90 f_pu (low relaxation)0.90·270243.0 ksi
Jacking limit0.75 f_pu0.75·270202.5 ksi
Transfer limit0.70 f_pu0.70·270189.0 ksi
Service steel limit0.80 f_py0.80·243.0194.4 ksi
Transfer compression limit0.60 f′_ci0.60·6.003.600 ksi
Transfer tension limit0.24 √f′_ci (bonded) / min(0.0948√f′_ci, 0.2) otherwise0.24√6.00 = 0.58790.5879 ksi (unbonded 0.2000)
Service compression limits0.45f′_c permanent / 0.60f′_c all loads0.45·8.00, 0.60·8.003.600 / 4.800 ksi
Service III tension limit0.19 √f′_c0.19√8.000.5374 ksi
  • OKJacking stress f_pj ≤ 0.75f_pudemand 202.5 ksicapacity 202.5 ksi
  • OKStress immediately after transfer f_pt ≤ 0.70f_pudemand 185.0 ksicapacity 189.0 ksi
  • OKEffective stress at service f_pe ≤ 0.80f_pydemand 155.0 ksicapacity 194.4 ksi
  • OKConcrete compression at transfer ≤ 0.60f′_cidemand 2.900 ksicapacity 3.600 ksi
  • OKConcrete tension at transfer (bonded reinf.) ≤ 0.24√f′_cidemand 0.3500 ksicapacity 0.5879 ksi
  • OKService III tension ≤ 0.19√f′_cdemand 0.0000 ksicapacity 0.5374 ksi
  • OKService I compression (all loads) ≤ 0.60f′_cdemand 0.000 ksicapacity 4.800 ksi

All strand and concrete stress limits are satisfied at both transfer and service.

Assumptions & code basis
  • Steel stress limits from AASHTO LRFD Table 5.9.2.2-1 for low-relaxation strand: 0.75f_pu at jacking, 0.70f_pu immediately after transfer, 0.80f_py at service after all losses.
  • Concrete stress limits from §5.9.2.3: 0.60f′_ci compression at transfer, 0.24√f′_ci tension where bonded reinforcement is provided (0.0948√f′_ci ≤ 0.2 ksi otherwise).
  • Service limits §5.9.2.3.2: 0.45f′_c under permanent loads, 0.60φ_w f′_c under all loads, and 0.19√f′_c tension in Service III (0.0948√f′_c for corrosive exposure).
  • Fibre stresses must be entered with compression negative and tension positive.
Module 26AASHTO LRFD 5.9.3.2 / 5.9.3.3Chapter 7

Prestress losses — immediate & time-dependent

Friction and anchorage set for post-tensioning, elastic shortening from f_cgp, and the approximate long-term loss with γ_h and γ_st — totalled to f_pe with P_i and P_e.

Friction and anchorage-set terms apply to post-tensioning only; they are reported for reference when pretensioning is selected.

Elastic shortening Δf_pES

19.32 ksi

Friction Δf_pF

11.32 ksi

not applicable to pretensioning

Anchorage set Δf_pA

2.23 ksi

not applicable

Long-term Δf_pLT

21.41 ksi

Total loss

40.73 (20.1 %) ksi

f_pe after all losses

161.8 ksi

P_i at transfer / P_e at service

1121 / 990 kip

Detailing sketchPrestress losses — component breakdown
Elastic shortening19.320 ksiFriction11.320 ksiAnchorage set2.230 ksiLong-term21.410 ksi

fpe after all losses = 161.8 ksi.

StepEquationSubstitutionResult
Concrete modulus at transferE_ci = 33,000 w^1.5 √f′_ci33,000(0.145)^1.5 √6.004463 ksi
Concrete stress at strand centroidf_cgp = P/A_g + P e²/I_g − M_g e/I_g1.6158 + 2.2383 − 0.82833.0258 ksi
Elastic shorteningΔf_pES = (E_p/E_ci) f_cgp(28500/4463)·3.025819.32 ksi
Friction loss (post-tensioned)Δf_pF = f_pj[1 − e^−(Kx + μα)]202.5[1 − e^−(0.0002·100.0 + 0.25·0.150)]11.32 ksi
Anchorage set lossL_set = √(ΔE_p/p), Δf_pA = 2p·L_setL_set = √(0.375/12·28500/0.11644) = 9.6 ft2.23 ksi
Humidity factorγ_h = 1.7 − 0.01H1.7 − 0.01·701.000
Strength factorγ_st = 5/(1 + f′_ci)5/(1 + 6.00)0.714
Long-term lossΔf_pLT = 10(f_pi A_ps/A_g)γ_h γ_st + 12γ_h γ_st + 2.410·1.462·1.000·0.714 + 12·1.000·0.714 + 2.421.41 ksi
Total lossΔf_pT = Δf_pES + Δf_pLT19.32 + 21.4140.73 ksi (20.1 %)
Effective strand stressf_pe = f_pj − Δf_pT202.5 − 40.73161.8 ksi
Prestress forceP_i = (f_pj − Δf_pES)A_ps ; P_e = f_pe A_ps183.2·6.12 ; 161.8·6.12P_i = 1121 kip, P_e = 990 kip
  • OKTotal loss within the usual 20–30 % bandratio 20.1 %
  • OKf_pe ≤ 0.80 f_py (= 0.72 f_pu)demand 161.8 ksicapacity 194.4 ksi

Design with P_e = 990 kip at service (f_pe = 161.8 ksi, 20.1 % total loss) and P_i = 1121 kip at transfer. Losses are in the normal range for a pretensioned girder.

Assumptions & code basis
  • Immediate losses: friction Δf_pF = f_pj[1 − e^−(Kx + μα)] and anchorage set (post-tensioned only), and elastic shortening Δf_pES = (E_p/E_ci) f_cgp (§5.9.3.2).
  • For pretensioned members the full (E_p/E_ci)f_cgp is used; for post-tensioned members with sequential stressing the average is taken as one-half.
  • Time-dependent losses by the approximate estimate of §5.9.3.3: Δf_pLT = 10 (f_pi A_ps/A_g) γ_h γ_st + 12 γ_h γ_st + Δf_pR, with γ_h = 1.7 − 0.01H, γ_st = 5/(1+f′_ci) and Δf_pR = 2.4 ksi for low-relaxation strand.
  • f_cgp is the concrete stress at the centroid of the prestressing force at transfer, including the girder self-weight moment relief.
  • The approximate method requires standard precast, pretensioned members with normal-weight concrete, average conditions, and a specified concrete strength at transfer; use the refined method of §5.9.3.4 for unusual members.
Module 27AASHTO LRFD 5.9.3.3Chapter 7

Prestress-loss estimator (approximate method)

Elastic shortening plus the approximate long-term loss with humidity and strength correction factors — the quick screening version.

γ_h = 1.7 − 0.01H  ·  γ_st = 5 / (1 + f′_ci)  ·  Δf_pLT = 10 γ_h γ_st + 12 γ_h γ_st + Δf_pR

Jacking stress f_pj = 0.75 f_pu

202.5 ksi

γ_h

1.000

γ_st

0.769

Elastic shortening Δf_pES

18.2 ksi

Long-term Δf_pLT

19.3 ksi

Total loss

37.5 ksi

18.5 % of jacking stress

Effective prestress f_pe

165.0 ksi

Use with Service III tension and flexural checks.

Detailing sketchPrestress losses — breakdown and strand profile
LOSS BREAKDOWNf_pe = 165.0 ksiΔLT = 19.3 ksiΔES = 18.2 ksif_pj = 202.5STRAND PROFILE ELEVATION (SCHEMATIC, STRAIGHT/HARPED)Span L = 100.0 ft (harp points at 0.3L, 0.7L typical)End — strand near cgcMidspan — strand at design eccentricity

Jacking stress fpj = 202.5 ksi, elastic shortening ΔfpES = 18.2 ksi, long-term ΔfpLT = 19.3 ksi, effective prestress fpe = 165.0 ksi.

Module 28AASHTO LRFD 5.9.2.3 / 5.6.3.3Chapter 7

Prestressed-girder service stresses & flexure

Transfer and Service III fibre stresses, cracking moment, and the minimum-reinforcement check for a prestressed I-girder.

f = P/A ± Pe/S ∓ M/S  ·  Mcr = Sb(fr + fcpe) − Md(Sb/Snc − 1)  ·  fr = 0.24√f′c

Effective prestress Pe

1210 kip

Top stress at transfer

-0.735 ksi

Bottom stress at transfer

3.868 ksi

Bottom stress, Service III

2.341 ksi

Top stress, Service I

0.664 ksi

Cracking moment Mcr

5784 k-ft

Transfer compression

0.735 ≤ 3.000 ksi

Transfer tension

3.868 ≤ 0.200 ksi

Service III tension

2.341 ≤ 0.484 ksi

Service I compression

0.664 ≤ 2.925 ksi

Minimum reinforcement requires φMn ≥ min(1.33Mu, Mcr) = 4256 k-ft; verify against the section's computed φMn.

Detailing sketchPrestressed girder — strand pattern and fiber stress diagram
SECTION — STRAND PATTERNh = 71.2 incgs, e = 30.6 inFIBER STRESS DIAGRAMf_t = 0.664 ksif_b = 2.341 ksicompression limit 2.925tension limit 0.484

Strand centroid eccentricity e = 30.6 in below the section centroid. Top fiber ft = 0.664 ksi (limit 2.925 ksi), bottom fiber fb = 2.341 ksi (tension limit 0.484 ksi).

Module 29AASHTO LRFD 5.6.3.1 / 5.6.3.2 / 5.6.3.3Chapter 7

Flexural resistance with prestressing steel — f_ps and φM_n

Strand stress at nominal resistance f_ps = f_pu(1 − kc/d_p) with automatic rectangular / flanged equilibrium, φ from the net tensile strain, and the §5.6.3.3 minimum-reinforcement check against M_cr and 1.33M_u.

Rectangular behaviour is assumed first; the module switches to flanged equilibrium automatically when a = β₁c exceeds the flange.

c

5.184 in

f_ps

264.4 ksi

M_n

9142.0 k-ft

φ

1.000

φM_n

9142.0 k-ft

Behaviour

Rectangular

Detailing sketchPrestressed flexure — strain and stress block
c = 5.18 in (N.A.)a = 4.15 in (stress block)d = 70.00 in (steel/strand centroid)h = 80.00 inRECTANGULAR — strain/stress blockCT

φM_n = 9142.0 k-ft vs M_u = 7500.0 k-ft; f_ps = 264.4 ksi.

StepEquationSubstitutionResult
Strand k factork = 2(1.04 − f_py/f_pu)2(1.04 − 243.0/270)0.280
β₁0.85 − 0.05(f′_c − 4) within 0.65–0.85f′_c = 4.00 ksi0.850
Neutral axisc = [A_ps f_pu + A_s f_y − A′_s f′_y] / [0.85f′_c β₁ b + k A_ps f_pu/d_p]A_ps = 6.120 in², f_pu = 270 ksi, d_p = 70.00 in5.184 in (rectangular behaviour)
Stress block deptha = β₁ c0.850·5.1844.407 in
Strand stress at nominal resistancef_ps = f_pu(1 − k c/d_p)270(1 − 0.280·5.184/70.00)264.4 ksi
Nominal momentM_n = A_ps f_ps(d_p − a/2) + A_s f_y(d_s − a/2)6.120·264.4(70.00 − 2.203) + …9142.0 k-ft
Net tensile strain and φε_t = 0.003(d_t − c)/c ; φ = 0.75 + 0.25(ε_t − ε_cl)/(ε_tl − ε_cl)ε_t = 0.03751φ = 1.000
Factored resistanceφM_n1.000·9142.09142.0 k-ft
Cracking momentM_cr = γ₃[(γ₁ f_r + γ₂ f_cpe)S_c − M_dnc(S_c/S_nc − 1)]f_r = 0.4800 ksi, S_c = 26000 in³11232.6 k-ft
Minimum reinforcementφM_n ≥ min(M_cr, 1.33M_u)min(11232.6, 9975.0)9975.0 k-ft
  • OKStrength φM_n ≥ M_udemand 7500.0 k-ftcapacity 9142.0 k-ftratio 0.82
  • NGMinimum reinforcement §5.6.3.3demand 9975.0 k-ftcapacity 9142.0 k-ft
  • OKDuctility ε_t ≥ 0.005 (tension controlled)demand 0.03751capacity 0.00500

Strength is adequate but the §5.6.3.3 minimum-reinforcement check fails — add mild steel or strand so φM_n ≥ 9975.0 k-ft.

Assumptions & code basis
  • Bonded strand: f_ps = f_pu(1 − k c/d_p) with k = 2(1.04 − f_py/f_pu) = 0.28 for low-relaxation strand (AASHTO LRFD Eq. 5.6.3.1.1-1).
  • Equilibrium of the rectangular stress block gives c; flanged behaviour is triggered automatically when a = β₁c exceeds the flange thickness.
  • Flexural resistance φM_n with φ from §5.5.4.2 varying between 0.75 (compression controlled) and 1.00 (tension controlled) for prestressed concrete.
  • Minimum reinforcement §5.6.3.3: φM_n ≥ min(M_cr, 1.33M_u) with M_cr = γ₃(γ₁ f_r + γ₂ f_cpe)S_c − M_dnc(S_c/S_nc − 1).
  • Compression steel A′_s is included in equilibrium but conservatively assumed to yield.
Module 30AASHTO LRFD 5.6.3.5.2 · PCI Design HandbookChapter 7

Prestress camber & deflection — PCI multipliers

Camber at release from the strand profile, self-weight deflection, and the PCI time-dependent multipliers at erection and final service with the net camber for screed setting.

Time-dependent camber with PCI multipliers at release, erection and final — the numbers the fabricator and the screed crew actually need.

Camber at release

1.559 in

Camber at erection

2.806 in

Final net camber

-3.030 in

Live-load deflection

0.929 in

Δ_allow = L/800

1.650 in

Haunch build-up

3.53 in

Derivation — equation, substitution, result

Moduli at release and in service

  Ec=1,820fc(ksi)=  Eci=1,8206.00,Ec=1,8208.00=  4458/5148ksi\begin{aligned}&\;E_c = 1,820\sqrt{f'_c} (\,\text{ksi})\\[4pt]&=\;E_{ci} = 1,820\sqrt{6.00}, E_c = 1,820\sqrt{8.00}\\[4pt]&=\;\boxed{4458 / 5148 \,\text{ksi}}\end{aligned}

Camber from prestress

  Δp=PiecL2/(8EciIg)withtheharpedcorrectionPi(ecee)L2/(12EciIg)=  1350×22.00×13202/(8×4458×260000)=  3.890in\begin{aligned}&\;\Delta _p = P_i e_c L^{2}/(8E_{ci} I_g) \operatorname{with} \,\text{the} \,\text{harped} \,\text{correction} −P_i(e_c−e_e)L^{2}/(12E_{ci} I_g)\\[4pt]&=\;1350 \times 22.00 \times 1320^{2}/(8 \times 4458 \times 260000)\\[4pt]&=\;\boxed{3.890 \,\text{in} ↑}\end{aligned}

Self-weight deflection

  Δg=5wgL4/(384EciIg)=  wg=0.820klf=  2.330in\begin{aligned}&\;\Delta _g = 5w_g L^{4}/(384 E_{ci} I_g)\\[4pt]&=\;w_g = 0.820 \,\text{klf}\\[4pt]&=\;\boxed{2.330 \,\text{in} ↓}\end{aligned}

Net camber at release

  Δrel=ΔpΔg=  3.8902.330=  1.559in\begin{aligned}&\;\Delta _{rel} = \Delta _p − \Delta _g\\[4pt]&=\;3.890 − 2.330\\[4pt]&=\;\boxed{1.559 \,\text{in} ↑}\end{aligned}

Camber at erection

  Δerect=1.80Δrel  (PCI multiplier)=  2.806in\begin{aligned}&\;\Delta _{erect} = 1.80 \Delta _{rel} \;\text{(PCI multiplier)}\\[4pt]&=\;\boxed{2.806 \,\text{in} ↑}\end{aligned}

Deck and superimposed dead load

  Δ=5wL4/(384EcI);deckonIg,SDLonIc=  Δdeck=2.092,ΔSDL=0.258in=  2.350in\begin{aligned}&\;\Delta = 5wL^{4}/(384 E_c I); \,\text{deck} \,\text{on} I_g, \mathrm{SDL} \,\text{on} I_c\\[4pt]&=\;\Delta _{deck} = 2.092, \Delta _{SDL} = 0.258 \,\text{in}\\[4pt]&=\;\boxed{2.350 \,\text{in} ↓}\end{aligned}

Long-term net

  Δfinal=2.20Δp,e  (2.70Δg + 2.40Δdeck + 3.00ΔSDL)=  3.030in(sag)\begin{aligned}&\;\Delta _{final} = 2.20\Delta _p,e − \;\text{(2.70Δg + 2.40Δdeck + 3.00ΔSDL)}\\[4pt]&=\;\boxed{-3.030 \,\text{in} ↓ (\,\text{sag})}\end{aligned}

Live-load deflection

  ΔLL=5wLLL4/(384EcIc)L/800=  0.929invs1.650in=  satisfied\begin{aligned}&\;\Delta _{LL} = 5w_{LL} L^{4}/(384 E_c I_c) \le L/800\\[4pt]&=\;0.929 \,\text{in} \,\text{vs} 1.650 \,\text{in}\\[4pt]&=\;\boxed{\,\text{satisfied}}\end{aligned}

Haunch build-up

  buildup=sag+0.5inminimumhaunch=  3.53inatmidspan\begin{aligned}&\;\,\text{build}-\,\text{up} = |\,\text{sag}| + 0.5 \,\text{in} \,\text{minimum} \,\text{haunch}\\[4pt]&=\;\boxed{3.53 \,\text{in} \operatorname{at} \,\text{midspan}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchGirder camber growth and strand profile
L = 110 fterection camber 2.81 infinal camber -3.03 instrand c.g. — e_c = 22.0 in

Predicted camber at erection = 2.81 in, long-term final = -3.03 in over a span of 110 ft. Strand profile: harped, midspan eccentricity ec = 22.0 in, end eccentricity ee = 12.0 in.

Constructability & detailing notes

  • Publish the predicted camber at 28, 60 and 120 days — the haunch detail must absorb the difference between predicted and measured.
  • Girders stored longer than expected keep growing in camber; measure before setting the screed elevations.
  • Differential camber between adjacent girders is the usual cause of deck thickness problems; specify a maximum of 3/4 in.
CheckDemandCapacity / limitStatus
Live-load deflection ≤ L/800 (§2.5.2.6.2)0.929 in1.650 inPASS
Residual camber positive after all dead load-3.030 in≥ 0REVIEW
Camber at erection within ±0.5 in of the assumed screed elevationsLarge cambers complicate deck screeding — consider debonding rather than harping.PASS
Independent verificationExpectedComputedStatus
Net camber positive (upward) at erection> 0 in2.806VERIFIED

Assumptions & basis of design

  • PCI Design Handbook multipliers: 1.80 at erection, 2.20/2.70/2.40/3.00 for the long-term components.
  • Prestress camber uses the gross section; the composite section resists SDL and live load.
  • Live-load deflection uses the distribution factor already embedded in w_LL, with all girders deflecting equally (§2.5.2.6.2).

The girder sags under full dead load — increase the drape or the strand count, or specify additional haunch build-up so the deck profile is preserved.

Chapters 8 – 11

Steel girders, splices, cross-frames and connections

Classification, plastic and yield moments, lateral–torsional buckling, web shear, splices and bearing stiffeners.

Module 31AASHTO LRFD 6.10.2 / 6.10.6 / 6.10.8.2Chapters 8 · 11

Steel girder flexural resistance & LTB

Web and flange classification, M_y and M_p, r_t with L_p and L_r, the three LTB zones with C_b, flange local buckling, φM_n and every §6.10.2 proportion limit — with the bracing or flange size needed when a check fails.

Cross-frame spacing L_b is the single most powerful lever on a plate girder's flexural resistance — compare the result at L_p.

M_y

4784 k-ft

M_p

5867 k-ft

L_p / L_r

8.19 / 30.75 ft

LTB zone

Plastic / no LTB (L_b ≤ L_p)

φM_n

4784 k-ft

Utilization

1.25

Detailing sketchPlate girder — flange/web section
Compression flange: 1.00 inWeb: 54.00 inTension flange: 1.25 inΣ = 56.25 inwidth = 16.00 ftSECTION — layer stack (scaled)

Plastic / no LTB (L_b ≤ L_p); φM_n = 4784 k-ft vs M_u = 6000 k-ft at L_b = 22.00 ft.

StepEquationSubstitutionResult
Web slenderness2D_c/t_w vs λ_pw = 3.76√(E/F_y), λ_rw = 5.7√(E/F_y)2·27.00/0.500 = 108.00; λ_pw = 90.55, λ_rw = 137.27Non-compact web
Compression-flange slendernessλ_f = b_fc/2t_fc vs λ_pf = 0.38√(E/F_y)16.00/(2·1.000) = 8.00; λ_pf = 9.15Compact flange
Elastic section propertiesI, S_xc = I/c_t, S_xt = I/c_bI = 35333 in⁴, c_t = 30.77 inS_xc = 1148 in³, S_xt = 1387 in³
Yield momentM_y = F_y S50·1148/124784 k-ft
Plastic momentM_p = F_y Z_x50·1408/125867 k-ft
Effective radius of gyrationr_t = b_fc/√[12(1 + D_c t_w/(3 b_fc t_fc))]16.00/√[12(1 + 27.00·0.500/(3·16.00·1.000))]4.080 in
Bracing limitsL_p = 1.0 r_t √(E/F_y) ; L_r = π r_t √(E/F_yr)r_t = 4.080 in, F_yr = 35.0 ksiL_p = 8.19 ft, L_r = 30.75 ft
LTB resistancePlastic / no LTB (L_b ≤ L_p)L_b = 22.00 ft, C_b = 1.00F_nc(LTB) = 50.00 ksi
Flange local buckling resistanceF_nc = R_b R_h F_ycλ_f = 8.0050.00 ksi
Nominal flexural resistanceM_n = min(F_nc,LTB, F_nc,FLB)·S_xc (or M_p when compact and braced)F_n = 50.00 ksi4784 k-ft
Factored resistanceφ_f M_n ≥ M_u1.00·4784 vs 60004784 k-ft
  • NGFlexural strength φM_n ≥ M_udemand 6000 k-ftcapacity 4784 k-ftratio 1.25
  • OKWeb proportion D/t_w ≤ 150demand 108.0capacity 150
  • OKFlange proportion b_f/2t_f ≤ 12demand 8.00capacity 12
  • OKFlange width b_f ≥ D/6demand 16.00capacity 9.00
  • OKFlange thickness t_f ≥ 1.1 t_wdemand 1.000capacity 0.550

Deficient by 1.25×. Either brace tighter — reducing L_b to L_p = 8.19 ft recovers the full F_y — thicken the compression flange to lower λ_f, or increase S_xc by about 25 %.

Assumptions & code basis
  • I-section flexural resistance per AASHTO LRFD §6.10.6 – §6.10.8 (LRFD, φ_f = 1.00).
  • Cross-section proportion limits of §6.10.2 must also be satisfied: D/t_w ≤ 150 (unstiffened), b_f/2t_f ≤ 12, b_f ≥ D/6, t_f ≥ 1.1t_w.
  • Web classification uses 2D_c/t_w against 3.76√(E/F_y) (compact) and 5.7√(E/F_y) (slender, load-shedding factor R_b applies).
  • Lateral–torsional buckling uses r_t = b_fc/√[12(1 + D_c t_w/(3 b_fc t_fc))] with L_p = 1.0 r_t √(E/F_y) and L_r = π r_t √(E/F_yr), F_yr = 0.7F_y.
  • Hybrid factor R_h and web load-shedding factor R_b are taken as 1.0; apply them explicitly for hybrid or slender-web girders.
  • Composite sections in positive flexure with a compact web may be governed instead by the §6.10.7.1 plastic-moment provisions and the D_p/D_t ductility limit.
Module 32AASHTO LRFD 6.10.9Chapters 8 · 11

Steel girder web shear resistance

Shear-buckling coefficient, ratio C, and the nominal shear resistance of a stiffened or unstiffened web.

V_p = 0.58 F_yw D t_w  ·  k = 5 + 5/(d_o/D)²  ·  V_n = C V_p (unstiffened / stiffened web)

D / t_w

120.0

Shear-buckling coefficient k

6.250

Ratio C

0.395

Plastic shear V_p

870 kip

V_n

344 kip

φ_v V_n (φ_v = 1.0)

344 kip

Shear check

344 ≥ 300 kip

Web adequate in shear.

Detailing sketchPlate-girder web panel — elevation and stiffener section
d_o = 120.0 inD = 60.0 inDiagonals indicate the tension field in each panelELEVATION — girder webAASECTION A–A — STIFFENER PLAN AT THE WEB (LOOKING DOWN)b_t ≈ 4.0 instiffener plate each side of the webWeb t_w = 0.500 in; fillet welds to the web, tight fit to the compression flange (6.10.11.1)b_t ≥ 2.0 + D/30 and 0.25 b_f; t_p ≥ b_t/16 · √(F_ys/E) limits (6.10.11.1.2–.3)

Web 60.0 in deep × 0.500 in thick, D/tw = 120, transverse stiffeners at do = 120.0 in (do/D = 2.00). Vu = 300 kip vs φVn = 344 kip (AASHTO 6.10.9).

Module 33AASHTO LRFD 6.13.2 / 6.13.6Chapters 8 · 11

Bolted field splice design

Shear, bearing, and slip resistance of a high-strength bolted splice against a factored demand.

Rn,shear = 0.38 Ab Fub Ns  ·  Rn,bearing = min(2.4dtFu, 1.2LctFu)  ·  Rn,slip = Kh Ks Ns Pt

Bolt area Ab

0.601 in²

Shear resistance (splice)

702 kip

Bearing resistance (splice)

1310 kip

Slip resistance (splice)

412 kip

Governing capacity vs demand

702 ≥ 650 kip

Splice adequate for Strength I shear/bearing.

Detailing sketchBolted field splice — elevation and section through the plates
3 in pitch3 in gageSplice centrelineELEVATION — outside splice plateAASECTION A–A — PLATE STACK-UP THROUGH ONE BOLT LINEoutside splice plategirder flange / webinside splice plates (pair)0.875 in Ø A325 in double shear — slip-critical, Class B faying surface (6.13.2.8)Check bolt shear, plate bearing, block shear and gross/net section on both sides of the splice

16 × 0.875 in Ø A325 bolts in 2 rows of 8, 3 in pitch, 1.75 in edge distance (AASHTO 6.13.2.6). Demand per bolt 650.0 kip vs Rn = 702.0 kip.

Slip resistance governs serviceability (Service II) checks and is not combined additively with the bearing-type strength resistance.

Module 34AASHTO LRFD AISC 360-22 §J10 · AASHTO §6.10.11Chapters 4 · 8

Web concentrated forces & bearing stiffeners

Web local yielding, crippling and compression buckling at reactions and point loads, then a full bearing-stiffener design — plate size, the 25t_w effective column, KL/r, F_cr, φP_n and the fillet weld.

R_n = F_ywt_w(5k+ℓ_b) · R_n = 0.80t_w²[1+3(ℓ_b/d)(t_w/t_f)^1.5]√(EF_ywt_f/t_w) · R_n = 24t_w³√(EF_yw)/h

φR_n yielding

205.7 kip

φR_n crippling

123.1 kip

φR_n web buckling

52.0 kip

Governing

52.0 kip

Web compression buckling (§J10.5)

Stiffener plates

2 – PL 3.78″ × 0.500″

φP_n stiffener

385.0 kip

Concentrated-force limit states & bearing stiffener designAISC 360-22 §J10 / §J7 / §E3

Clear web depth h21.32 in
Governing limit stateWeb compression buckling (§J10.5)
Stiffener call-out2 – PL 3.78″ × 0.500″ bearing stiffeners, 3/16″ fillet both sides
Effective area A_eff8.62 in²
KL / r16.0 in / 1.576 in → 10.1
F_e / F_cr2780.6 / 49.6 ksi
Weld3/16 in fillet, both sides, full web depth

PASS — Provide a pair of bearing stiffeners 3.78 in × 0.500 in, fitted to the loaded flange, with 3/16 in fillet welds each side to the web (§J10.8).

Detailing sketchBearing stiffener — girder elevation and plate/weld section
ELEVATION — GIRDER WEB AT THE LOAD/REACTIONR_u = 180 kipd = 24.0 int_w = 0.440 in, b_f = 9.00 inSECTION AT THE STIFFENER (LOOKING DOWN)b_st = 3.78 int_st = 0.500 in3/16 in fillet weld, both sidesStiffener plate pair fitted tight to the loaded flanget_w = 0.440 in

End reaction Ru = 180 kip. Stiffener pair PL 3.78 × 0.500 in, fillet welds 3/16 in each side, full web depth.

Module 35AASHTO LRFD 6.10.2 / 2.5.2.6.3Chapters 8 · 11

Plate-girder trial sizing & proportion limits

Web depth from span-to-depth guidance, D/t_w and b_f/2t_f screening, the §6.10.2 proportion limits and the flange plate sizes needed to satisfy each one.

First-pass plate girder dimensions that satisfy the §6.10.2 proportion limits before any analysis is run.

Web D × t_w

60 × 0.4375 in

Top flange

15.0 × 0.7500 in

Bottom flange

15.0 × 1.0000 in

Total depth

61.75 in

Area

52.5 in²

Self weight

0.1786 klf

Derivation — equation, substitution, result

Web depth

  DL/27.5  (continuous)=  1680in/27.5=  D=60in\begin{aligned}&\;D \approx L/27.5 \;\text{(continuous)}\\[4pt]&=\;1680 \,\text{in} / 27.5\\[4pt]&=\;\boxed{D = 60 \,\text{in}}\end{aligned}

Web thickness

  twD/150,7/16in,D/tw150(§6.10.2.1.1)=  60/150=0.400=  tw=0.4375in(D/tw=137.1)\begin{aligned}&\;t_w \approx D/150, \ge 7/16 \,\text{in}, D/t_w \le 150 (§6.10.2.1.1)\\[4pt]&=\;60/150 = 0.400\\[4pt]&=\;\boxed{t_w = 0.4375 \,\text{in} (D/t_w = 137.1)}\end{aligned}

Flange width

  bfD/4D/6and12in(§6.10.2.2)=  60/4=  bf=15.0in\begin{aligned}&\;b_f \approx D/4 \ge D/6 \operatorname{and} \ge 12 \,\text{in} (§6.10.2.2)\\[4pt]&=\;60/4\\[4pt]&=\;\boxed{b_f = 15.0 \,\text{in}}\end{aligned}

Flange thickness

  bf/(2tf)12andtf1.1tw(§6.10.2.2)=  tfc=0.7500in,tft=1.0000in=  λf=10.00\begin{aligned}&\;b_f/(2t_f) \le 12 \operatorname{and} t_f \ge 1.1 t_w (§6.10.2.2)\\[4pt]&=\;t_{fc} = 0.7500 \,\text{in}, t_{ft} = 1.0000 \,\text{in}\\[4pt]&=\;\boxed{\lambda _f = 10.00}\end{aligned}

Trial section

  A=Dtw+bfctfc+bfttft=  60(0.4375)+15.0(0.7500)+15.0(1.0000)=  A=52.5in2,totaldepth61.75in\begin{aligned}&\;A = D t_w + b_{fc} t_{fc} + b_{ft} t_{ft}\\[4pt]&=\;60(0.4375) + 15.0(0.7500) + 15.0(1.0000)\\[4pt]&=\;\boxed{A = 52.5 \,\text{in}^{2}, \,\text{total} \,\text{depth} 61.75 \,\text{in}}\end{aligned}

Self weight

  w=A(490pcf)/144=  0.1786klf\begin{aligned}&\;w = A(490 \,\text{pcf})/144\\[4pt]&=\;\boxed{0.1786 \,\text{klf}}\end{aligned}

Compactness screening

  λf0.38E/Fyc,2Dcp/tw3.76E/Fyc=  λpf=9.15,λpw=90.6=  noncompactflange\begin{aligned}&\;\lambda _f \le 0.38\sqrt{E/F_{yc}}, 2D_{cp}/t_w \le 3.76\sqrt{E/F_{yc}}\\[4pt]&=\;\lambda _{pf} = 9.15, \lambda _{pw} = 90.6\\[4pt]&=\;\boxed{\,\text{non}-\,\text{compact} \,\text{flange}}\end{aligned}

Deck fit

  GirderspacingSwithslabts=  S=10.00ft,5girders,ts=8.50in=  withinthe§4.6.2.2range\begin{aligned}&\;Girder \,\text{spacing} S \operatorname{with} \,\text{slab} t_s\\[4pt]&=\;S = 10.00 \,\text{ft}, 5 \,\text{girders}, t_s = 8.50 \,\text{in}\\[4pt]&=\;\boxed{\,\text{within} \,\text{the} §4.6.2.2 \,\text{range}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #5 @ 8 in top matGirder depth 0 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 10.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Keep the web thickness constant for the whole girder line; changing it saves less steel than it costs in fabrication.
  • Flange transitions should occur at field splices or at least 10 ft from them, and the width change should be a 1:2.5 taper.
  • Minimum flange width of 12 in keeps the girder stable during shipping and erection.
CheckDemandCapacity / limitStatus
D/t_w ≤ 150 without longitudinal stiffeners137.1150PASS
b_f ≥ D/6 (§6.10.2.2-2)15.0 in10.0 inPASS
t_f ≥ 1.1 t_w (§6.10.2.2-3)0.7500 in0.4813 inPASS
b_f/(2t_f) ≤ 12 (§6.10.2.2-1)10.0012.0PASS
Girder spacing 3.5 – 16 ft10.00 ft3.5 – 16 ftPASS
Independent verificationExpectedComputedStatus
Web slenderness within the non-longitudinally-stiffened limitD/t_w ≤ 150VERIFIED

Assumptions & basis of design

  • Depth ratios from AASHTO LRFD Table 2.5.2.6.3-1 with plate sizes rounded to commercial increments (web depth to 3 in, plate thickness to 1/8 in).
  • Bottom flange is proportioned 25 % thicker than the top flange to reflect composite action in positive-moment regions.
  • Steel unit weight 490 pcf; the estimate excludes stiffeners, cross-frames and connection material (add roughly 12 – 18 %).

Take this section into the composite section-property, flexure and shear modules; iterate the flange plates until the utilisation lands near 0.90 – 0.98.

Module 36AASHTO LRFD Appendix D6.1 / 6.10.7.1.2Chapters 8 · 11

Composite plastic moment M_p and PNA location

Slab, flange and web plastic forces, Appendix D6.1 case selection (I, II, III) for the plastic neutral axis, M_p, and the D_p ≤ 0.42 D_t ductility screen.

Locates the plastic neutral axis by Appendix D6.1 case selection and screens ductility with D_p ≤ 0.42 D_t.

PNA case

II

D_p

10.95 in

0.42 D_t

30.66 in

M_p

12952 kip·ft

φ_f M_n

12952 kip·ft

Utilisation

0.695

Derivation — equation, substitution, result

Plastic forces

  Ps=0.85fcbefftsPc=FycbfctfcPw=FywDtwPt=Fytbfttft=  Ps=3121,Pc=800,Pw=1688,Pt=1350kip=  forcesset\begin{aligned}&\;P_s = 0.85f'_c b_{eff} t_s \cdot P_c = F_{yc} b_{fc} t_{fc} \cdot P_w = F_{yw} D t_w \cdot P_t = F_{yt} b_{ft} t_{ft}\\[4pt]&=\;P_s = 3121, P_c = 800, P_w = 1688, P_t = 1350 \,\text{kip}\\[4pt]&=\;\boxed{\,\text{forces} \,\text{set}}\end{aligned}

PNA case

  ComparePt+Pw+PcwithPs,thenPt+PwwithPs+Pc  (Table D6.1-1)=  IIPNAinthetopflange  (§D6.1, Case II)\begin{aligned}&\;Compare P_t + P_w + P_c \operatorname{with} P_s, \,\text{then} P_t + P_w \operatorname{with} P_s + P_c \;\text{(Table D6.1-1)}\\[4pt]&=\;\boxed{\mathrm{II} — \mathrm{PNA} \,\text{in} \,\text{the} \,\text{top} \,\text{flange} \;\text{(§D6.1, Case II)}}\end{aligned}

PNA location

  Yˉfromthegoverningcaseequation=  Yˉ=0.45in,Dp=10.95inbelowthetopoftheslab\begin{aligned}&\;Ȳ \operatorname{from} \,\text{the} \,\text{governing} \,\text{case} \,\text{equation}\\[4pt]&=\;\boxed{Ȳ = 0.45 \,\text{in}, D_p = 10.95 \,\text{in} \,\text{below} \,\text{the} \,\text{top} \operatorname{of} \,\text{the} \,\text{slab}}\end{aligned}

Plastic moment

  Mp=\SumPiditakenaboutthePNA=  \Sum=155422kipin=  Mp=12952kipft\begin{aligned}&\;M_p = \Sum P_i d_i \,\text{taken} \,\text{about} \,\text{the} \mathrm{PNA}\\[4pt]&=\;\Sum = 155422 \,\text{kip}\cdot \,\text{in}\\[4pt]&=\;\boxed{M_p = 12952 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Total depth

  Dt=ts+haunch+tfc+D+tft=  8.50+2.00+1.000+60.0+1.500=  Dt=73.00in\begin{aligned}&\;D_t = t_s + \,\text{haunch} + t_{fc} + D + t_{ft}\\[4pt]&=\;8.50 + 2.00 + 1.000 + 60.0 + 1.500\\[4pt]&=\;\boxed{D_t = 73.00 \,\text{in}}\end{aligned}

Ductility requirement

  Dp0.42Dt(Eq.6.10.7.31)=  10.95vs30.66in=  ductile—Mn=Mp\begin{aligned}&\;D_p \le 0.42 D_t (Eq. 6.10.7.3-1)\\[4pt]&=\;10.95 \,\text{vs} 30.66 \,\text{in}\\[4pt]&=\;\boxed{\,\text{ductile} — M_n = M_p}\end{aligned}

Nominal flexural resistance

  Mn=Mp(§6.10.7.1.2)=  ϕfMn=12952kipft\begin{aligned}&\;M_n = M_p (§6.10.7.1.2)\\[4pt]&=\;\boxed{\phi _f M_n = 12952 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #6 @ 6 in top matGirder depth 63 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 9.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • M_p is only available if the section is compact and adequately braced during the deck pour — check the non-composite stage separately.
  • Ductility (D_p ≤ 0.42 D_t) is what allows the section to reach M_p; a deep slab with a shallow girder often fails it.
CheckDemandCapacity / limitStatus
Ductility D_p ≤ 0.42 D_t (§6.10.7.3)10.95 in30.66 inPASS
Flexure φ_f M_n ≥ M_u9000 kip·ft12952 kip·ftPASS
Compact web 2D_cp/t_w ≤ 3.76√(E/F_yc)0.090.6PASS
Independent verificationExpectedComputedStatus
Ductility requirement D_p ≤ 0.42 D_t≤ 0.42 D_t10.95VERIFIED

Assumptions & basis of design

  • AASHTO LRFD Appendix D6.1 plastic-moment cases for a composite section in positive flexure; concrete in tension neglected.
  • Longitudinal deck reinforcement is conservatively neglected in the positive-moment plastic force sum.
  • φ_f = 1.00 for flexure (§6.5.4.2); compact composite sections in positive flexure may reach M_p.

Section is compact and ductile — proceed to the §6.10.9 shear check and the §6.10.10 shear-connector design.

Module 37AASHTO LRFD 6.10.10.1 / 6.10.10.4Chapters 8 · 11

Shear connectors — strength and fatigue pitch

Stud resistance Q_r, the number of studs for the strength limit state between points of maximum moment and zero moment, and the Fatigue I / II pitch from Z_r and the range of horizontal shear flow.

Strength count from the plastic horizontal force and fatigue pitch from Z_r and the horizontal shear range.

Q_n per stud

36.08 kip

Q_r per stud

30.67 kip

Studs required (strength)

79

Z_r fatigue

2.105 kip

Governing pitch

3.5 in

Callout

3 — 0.875 in ø × 6.0 in studs @ 3.5 in

Derivation — equation, substitution, result

Stud area

  Asc=πd2/4=  π(0.875)2/4=  0.6013in2\begin{aligned}&\;A_{sc} = \pi d^{2}/4\\[4pt]&=\;\pi (0.875)^{2}/4\\[4pt]&=\;\boxed{0.6013 \,\text{in}^{2}}\end{aligned}

Nominal stud strength

  Qn=0.5AscfcEcAscFu(Eq.6.10.10.4.31)=  0.5(0.6013)4.00×3640vs36.08=  Qn=36.08kip\begin{aligned}&\;Q_n = 0.5A_{sc}\sqrt{f'_c E_c} \le A_{sc} F_u (Eq. 6.10.10.4.3-1)\\[4pt]&=\;0.5(0.6013)\sqrt{4.00 \times 3640} \,\text{vs} 36.08\\[4pt]&=\;\boxed{Q_n = 36.08 \,\text{kip}}\end{aligned}

Factored strength

  Qr=ϕscQn,ϕsc=0.85=  Qr=30.67kip/stud\begin{aligned}&\;Q_r = \phi _{sc} Q_n, \phi _{sc} = 0.85\\[4pt]&=\;\boxed{Q_r = 30.67 \,\text{kip}/\,\text{stud}}\end{aligned}

Strength-limit stud count

  n=P/Qr(§6.10.10.4.1)=  2400/30.67=  79studsbetweenthemaxmomentpointandthesupport\begin{aligned}&\;n = P/Q_r (§6.10.10.4.1)\\[4pt]&=\;2400/30.67\\[4pt]&=\;\boxed{79 \,\text{studs} \,\text{between} \,\text{the} \operatorname{max}-\,\text{moment} \,\text{point} \operatorname{and} \,\text{the} \,\text{support}}\end{aligned}

Design cycles

  N=(365)  (years)  (ADTTSL)(n)=  365×75×1500=  N=4.11e+7\begin{aligned}&\;N = (365)\;\text{(years)}\;\text{(ADTTSL)}(n)\\[4pt]&=\;365 \times 75 \times 1500\\[4pt]&=\;\boxed{N = 4.11e+7}\end{aligned}

Fatigue shear resistance

  Zr=αd25.5d2/2,α=34.54.28logN(Eq.6.10.10.21/2)=  α=0.00=  Zr=2.105kip/stud\begin{aligned}&\;Z_r = \alpha d^{2} \ge 5.5d^{2}/2, \alpha = 34.5 − 4.28 \operatorname{log} N (Eq. 6.10.10.2-1/2)\\[4pt]&=\;\alpha = 0.00\\[4pt]&=\;\boxed{Z_r = 2.105 \,\text{kip}/\,\text{stud}}\end{aligned}

Fatigue pitch

  pnstudsZr/Vsr(Eq.6.10.10.1.21)=  3×2.105/2.200=  p=2.87inuse3.5in\begin{aligned}&\;p \le n_{studs} Z_r / V_{sr} (Eq. 6.10.10.1.2-1)\\[4pt]&=\;3 \times 2.105 / 2.200\\[4pt]&=\;\boxed{p = 2.87 \,\text{in} \rightarrow \operatorname{use} 3.5 \,\text{in}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #5 @ 8 in top matGirder depth 60 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 9.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Studs are welded in the shop through clean, dry flange surfaces; bend-test the first two of each shift and 1 % thereafter.
  • Keep 2 in clear cover over the stud head and 1 in clear between the stud and the deck bottom mat.
  • Vary the pitch in bands rather than continuously — the fabricator lays out from a table, not a curve.
CheckDemandCapacity / limitStatus
Pitch 6d ≤ p ≤ 24 in (§6.10.10.1.2)3.5 in5.3 – 24 inREVIEW
Stud height H ≥ 4d (§6.10.10.1.1)6.0 in3.5 inPASS
Stud diameter ≤ 2.5 t_fc (§6.10.10.1.4)0.875 in2.500 inPASS
Penetration ≥ 2 in into the deck with ≥ 2 in top covertop cover ≈ 2.5 in6.0 in in a 8.5 in slab5.5 – 6.5 inPASS
Transverse spacing ≥ 4d and ≤ 8 t_sCheck the flange width can accommodate the row.PASS
Independent verificationExpectedComputedStatus
Stud height-to-diameter ratio ≥ 4≥ 4.06.86VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §6.10.10; φ_sc = 0.85; normal-weight concrete with E_c = 1,820√f′_c.
  • Fatigue pitch computed from the Fatigue I horizontal shear range V_sr = V_f Q/I at the section considered.
  • The strength check governs the total number of connectors; the fatigue check governs their spacing.

The required fatigue pitch is tighter than the 6d minimum — add a third or fourth stud per row rather than closing the pitch further.

Module 38AASHTO LRFD 6.6.1.2.3 / 6.6.1.2.5 / Table 6.6.1.2.3-1Chapters 8 · 18

Fatigue detail categories & remaining life

Category A–E′ constants, the Fatigue I and II load combinations, the single-lane ADTT_SL with cycles per truck passage, the (ΔF)_TH infinite-life screen and N = A/(Δf)³ finite life.

Fatigue I (infinite life) and Fatigue II (finite life) checks for AASHTO detail categories A through E′.

ADTT_SL

2550 trucks/day

Δf

10.50 ksi

(ΔF)_n

10.00 ksi

Utilisation

1.050

Estimated life

4 yr

Derivation — equation, substitution, result

Single-lane truck traffic

  ADTTSL=pADTT  (Table 3.6.1.4.2-1)=  p=0.85for2lane(s)=  ADTTSL=2550trucks/day\begin{aligned}&\;\mathrm{ADTT}_{SL} = p \cdot \mathrm{ADTT} \;\text{(Table 3.6.1.4.2-1)}\\[4pt]&=\;p = 0.85 \operatorname{for} 2 \,\text{lane}(s)\\[4pt]&=\;\boxed{\mathrm{ADTT}_{SL} = 2550 \,\text{trucks}/\,\text{day}}\end{aligned}

Fatigue load factor

  FatigueI:γ=1.75  (infinite life)=  γ=1.75\begin{aligned}&\;Fatigue I: \gamma = 1.75 \;\text{(infinite life)}\\[4pt]&=\;\boxed{\gamma = 1.75}\end{aligned}

Factored stress range

  Δf=γ  (Mmax − Mmin)/S=  1.75(900.0150.0)(12)/2100=  Δf=10.50ksi\begin{aligned}&\;\Delta f = \gamma \;\text{(Mmax − Mmin)}/S\\[4pt]&=\;1.75(900.0 − -150.0)(12)/2100\\[4pt]&=\;\boxed{\Delta f = 10.50 \,\text{ksi}}\end{aligned}

Design cycles

  N=(365)  (years)(n)  (ADTTSL)=  365×75×1.0×2550=  N=6.98e+7\begin{aligned}&\;N = (365)\;\text{(years)}(n)\;\text{(ADTTSL)}\\[4pt]&=\;365 \times 75 \times 1.0 \times 2550\\[4pt]&=\;\boxed{N = 6.98e+7}\end{aligned}

Nominal fatigue resistance

  (ΔF)n=(ΔF)TH=  A=4.40e+9,(ΔF)TH=10.0ksi=  (ΔF)n=10.00ksi\begin{aligned}&\;(\Delta F)_n = (\Delta F)_{TH}\\[4pt]&=\;A = 4.40e+9, (\Delta F)_{TH} = 10.0 \,\text{ksi}\\[4pt]&=\;\boxed{(\Delta F)_n = 10.00 \,\text{ksi}}\end{aligned}

Estimated life

  Y=A/  (Δf³ ⋅ 365 ⋅ n ⋅ ADTTSL)=  4years\begin{aligned}&\;Y = A/\;\text{(Δf³ · 365 · n · ADTTSL)}\\[4pt]&=\;\boxed{4 \,\text{years}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchFatigue detail category C — S-N resistance curve
log N (cycles)Δf (ksi)(ΔF)_TH = 10.00 ksiγ(Δf) = 10.50 ksi @ N = 69806250

Category C: γ(Δf) = 10.50 ksi plotted at N = 69806250 cycles against the finite-life resistance (ΔF)n = 10.00 ksi and the constant-amplitude threshold (ΔF)TH = 10.00 ksi. Point falls above the resistance curve — review the detail.

Constructability & detailing notes

  • Category E′ details (long cover plates on thick flanges) should be designed out, not checked — weld the plate away entirely if you can.
  • Distortion-induced fatigue is not covered by these categories: weld connection plates to both flanges (§6.6.1.3).
  • Grind weld toes and specify a peened or ground transition where a category improvement is needed.
CheckDemandCapacity / limitStatus
γ(Δf) ≤ (ΔF)_n — Category C10.50 ksi10.00 ksiREVIEW
Infinite-life screening Δf ≤ (ΔF)_TH10.50 ksi10.0 ksiREVIEW
Fracture-critical member? apply CVN and redundancy provisions§6.6.2 requires refined analysis and enhanced inspection for FCMs.PASS
Independent verificationExpectedComputedStatus
Stress range below the resistance10.00VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §6.6.1.2 detail categories with the fatigue truck (constant 30 ft rear axle spacing) and IM = 15 %.
  • Fatigue I gives infinite life when Δf ≤ (ΔF)_TH; Fatigue II gives the finite-life resistance from the S-N curve.
  • Cycles per truck passage n from Table 6.6.1.2.5-2 (typically 1.0 for spans > 40 ft, 2.0 for shorter spans and cantilevers).

Upgrade the detail — moving from Category C to the next better category raises the threshold; grinding cover-plate ends, removing backing bars and using full-penetration welds are the usual fixes.

Module 39AASHTO LRFD 6.7.4 / 4.6.2.7Chapters 8 · 11

Cross-frames and diaphragms — force and sizing

Wind and stability bracing forces into the cross-frame, the diagonal and strut member demands, the slenderness limits for bracing members, and the connection force to detail.

Compares the V-load (curvature), wind and 2 % stability bracing demands and picks the governing cross-frame force.

V-load H

4.17 kip

Diagonal force

4.56 kip

Wind force

2.40 kip

Stability force

18.00 kip

Design force

18.00 kip

Suggested member

L4×4×3/8

Derivation — equation, substitution, result

V-load (curved girder)

  H=MLb/(DR)  (V-load method)=  6000(20.0)/(36.0×800)=  H=4.17kip\begin{aligned}&\;H = M L_b/(D R) \;\text{(V-load method)}\\[4pt]&=\;6000(20.0)/(36.0 \times 800)\\[4pt]&=\;\boxed{H = 4.17 \,\text{kip}}\end{aligned}

Diagonal geometry

  α=arctan(hcf/sg)=  arctan(48.0/108.0)=  α=24.0\begin{aligned}&\;\alpha = \operatorname{arctan}(h_{cf}/s_g)\\[4pt]&=\;\operatorname{arctan}(48.0/108.0)\\[4pt]&=\;\boxed{\alpha = 24.0^{\circ}}\end{aligned}

Diagonal axial force

  Fdiag=H/cosα=  4.17/cos24.0=  4.56kip\begin{aligned}&\;F_{diag} = H/\operatorname{cos} \alpha \\[4pt]&=\;4.17/\operatorname{cos} 24.0^{\circ}\\[4pt]&=\;\boxed{4.56 \,\text{kip}}\end{aligned}

Wind on the exposed superstructure

  w=Pzd,F=wLb/2intothecrossframe(§4.6.2.7)=  0.0300ksf×8.00ft×20.0ft/2=  2.40kip\begin{aligned}&\;w = P_z d, F = w L_b/2 \,\text{into} \,\text{the} \,\text{cross}-\,\text{frame} (§4.6.2.7)\\[4pt]&=\;0.0300 \,\text{ksf} \times 8.00 \,\text{ft} \times 20.0 \,\text{ft} / 2\\[4pt]&=\;\boxed{2.40 \,\text{kip}}\end{aligned}

Stability bracing

  Fbr0.02Pflange  (AISC App. 6 nodal bracing)=  0.02×900=  18.00kip\begin{aligned}&\;F_{br} \approx 0.02 P_{flange} \;\text{(AISC App. 6 nodal bracing)}\\[4pt]&=\;0.02 \times 900\\[4pt]&=\;\boxed{18.00 \,\text{kip}}\end{aligned}

Governing design force

  max  (V-load, wind, stability)=  18.00kip\begin{aligned}&\;\operatorname{max}\;\text{(V-load, wind, stability)}\\[4pt]&=\;\boxed{18.00 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

Deck 8.5 in — #5 @ 8 in top matGirder depth 60 in · haunch 2 in min.3 studs/row @ 12.0 in pitch
Section — composite
Girder spacing S = 9.0 ftCross-frames at ≤ 25 ft; connectionplates welded to both flangesDeck placement sequence: positive-momentregions first
Plan — framing
Shear studs — 2 in min. cover, 4 in min.clear from deck edgeCamber for DC1 + 50 % of long-term DC2;check at erectionField splices located near dead-loadinflection points
Elevation

Constructability & detailing notes

  • Weld the connection plate to both flanges — a gap at the tension flange is a distortion-induced fatigue crack waiting to happen.
  • Cross-frames control the girder geometry during erection; specify whether they are detailed for no-load, steel-dead-load or full-dead-load fit.
  • Provide slotted or oversized holes only where the erection tolerance genuinely requires them, and note them on the plans.
CheckDemandCapacity / limitStatus
Cross-frame spacing ≤ 25 ft (§6.7.4.2)20.0 ft25 ftPASS
Cross-frame depth ≥ 0.5 girder depth (straight) / 0.75 (curved)Connect near the flanges so the frame engages the full girder depth.PASS
Members are primary in curved bridges (§6.7.4.1)Design curved-bridge cross-frames as primary members with fatigue checks on the connection plates.PASS
Independent verificationExpectedComputedStatus
Governing design force identifiedmax(V-load, wind, stability)18.00VERIFIED

Assumptions & basis of design

  • V-load method approximates curvature effects by a self-equilibrating couple between adjacent girders.
  • Wind is distributed to the deck-level bracing over half the cross-frame spacing each side.
  • Connection plates must be welded (not bolted) to both flanges to avoid a Category C′ distortion-induced fatigue detail.

On a curved bridge the cross-frames carry real load in every stage — check the erection condition, when they are often most heavily loaded.

Module 40AASHTO LRFD 6.13.2 · AISC Manual Part 7Chapters 8 · 11

Eccentric bolt group — instantaneous centre / elastic

Direct and torsional bolt force components for an eccentrically loaded group, the governing extreme bolt resultant, the elastic and IC-method comparison, and the bolt count needed to keep the resultant below φr_n.

Elastic vector analysis of an eccentric bolt group plus the flange-splice bolt count from the flange couple.

Bolt capacity

39.00 kip

Direct shear R_v

18.00 kip

Resultant R_max

31.62 kip

Group utilisation

0.811

Flange force F_fl

869.0 kip

Flange bolts per side

23

Derivation — equation, substitution, result

Bolt shear

  Rn=0.45AbFubNs  (threads included, §6.13.2.7)=  Ab=0.6013in2,Fub=120ksi,Ns=2=  ϕRn=51.95kip\begin{aligned}&\;R_n = 0.45 A_b F_{ub} N_s \;\text{(threads included, §6.13.2.7)}\\[4pt]&=\;A_b = 0.6013 \,\text{in}^{2}, F_{ub} = 120 \,\text{ksi}, N_s = 2\\[4pt]&=\;\boxed{\phi R_n = 51.95 \,\text{kip}}\end{aligned}

Bearing on the connected material

  Rn=2.4dtFu(§6.13.2.9)=  2.4(0.875)(0.500)(65)=  ϕRn=54.60kip\begin{aligned}&\;R_n = 2.4 d t F_u (§6.13.2.9)\\[4pt]&=\;2.4(0.875)(0.500)(65)\\[4pt]&=\;\boxed{\phi R_n = 54.60 \,\text{kip}}\end{aligned}

Slip resistance

  Rn=KhKsNsPt(Eq.6.13.2.81)=  Ks=0.50,Pt=39.0kip=  39.00kip/bolt\begin{aligned}&\;R_n = K_h K_s N_s P_t (Eq. 6.13.2.8-1)\\[4pt]&=\;K_s = 0.50, P_t = 39.0 \,\text{kip}\\[4pt]&=\;\boxed{39.00 \,\text{kip}/\,\text{bolt}}\end{aligned}

Governing bolt capacity

  minofshear,bearingand  (if slip-critical)slip=  39.00kip/bolt\begin{aligned}&\;\operatorname{min} \operatorname{of} \,\text{shear}, \,\text{bearing} \operatorname{and} \;\text{(if slip-critical)} \,\text{slip}\\[4pt]&=\;\boxed{39.00 \,\text{kip}/\,\text{bolt}}\end{aligned}

Group geometry

  \Sum(x2+y2)aboutthegroupcentroid=  5rows@3.00in×2cols@3.00in=  \Sumr2=202.5in2,nb=10\begin{aligned}&\;\Sum (x^{2} + y^{2}) \,\text{about} \,\text{the} \,\text{group} \,\text{centroid}\\[4pt]&=\;5 \,\text{rows} @ 3.00 \,\text{in} \times 2 \,\text{cols} @ 3.00 \,\text{in}\\[4pt]&=\;\boxed{\Sum r^{2} = 202.5 \,\text{in}^{2}, n_b = 10}\end{aligned}

Direct shear per bolt

  Rv=Vu/nb=  180.0/10=  18.00kip\begin{aligned}&\;R_v = V_u/n_b\\[4pt]&=\;180.0/10\\[4pt]&=\;\boxed{18.00 \,\text{kip}}\end{aligned}

Torsional components

  Rmx=Mymax/\Sumr2,Rmy=Mxmax/\Sumr2=  M=Vue=720.0kipin=  Rmx=21.33,Rmy=5.33kip\begin{aligned}&\;R_{mx} = M y_{\operatorname{max}}/\Sum r^{2}, R_{my} = M x_{\operatorname{max}}/\Sum r^{2}\\[4pt]&=\;M = V_u e = 720.0 \,\text{kip}\cdot \,\text{in}\\[4pt]&=\;\boxed{R_{mx} = 21.33, R_{my} = 5.33 \,\text{kip}}\end{aligned}

Resultant bolt force

  Rmax=(Rv+Rmy)2+Rmx2ϕRn=  (18.00+5.33)2+21.332=  31.62kip\begin{aligned}&\;R_{\operatorname{max}} = \sqrt{(R_v + R_{my})^{2} + R_{mx}^{2}} \le \phi R_n\\[4pt]&=\;\sqrt{(18.00 + 5.33)^{2} + 21.33^{2}}\\[4pt]&=\;\boxed{31.62 \,\text{kip}}\end{aligned}

Flange splice force

  Ffl=Mu/heff,n=Ffl/ϕRn(§6.13.6.1.3)=  4200(12)/58.0=  Ffl=869.0kip23boltsperside\begin{aligned}&\;F_{fl} = M_u/h_{eff}, n = F_{fl}/\phi R_n (§6.13.6.1.3)\\[4pt]&=\;4200(12)/58.0\\[4pt]&=\;\boxed{F_{fl} = 869.0 \,\text{kip} \rightarrow 23 \,\text{bolts} \operatorname{per} \,\text{side}}\end{aligned}

Detailing — plan, elevation and section

5×2 — 0.875 in Ø A325 @ 3.0 in pitch, 3.0in gage
Elevation — bolt group
Outer splice plate 0.500 inInner plates 2 × 0.250 inClass B faying surface — blast clean, nopaint in slip zoneTurn-of-nut pretension, install from thestiffest point outward
Section — splice plates
0.313 in fillet, both sidesGrind starts/stops; no welds across thetension flangeUT/MT per AWS D1.5 for fracture-criticalmembers
Plan — weld detail

Constructability & detailing notes

  • Slip-critical faying surfaces must be blast-cleaned Class B and left unpainted — mask them before shop priming.
  • Use a minimum of two bolts per line and fill every hole; open holes in a splice are a fatigue and corrosion detail.
  • Erection bolts and drift pins go in first; final pretensioning proceeds from the stiffest point outward.
CheckDemandCapacity / limitStatus
Eccentric group R_max ≤ φR_n31.62 kip39.00 kipPASS
Bolt pitch ≥ 3d (§6.13.2.6.1)3.00 in2.63 inPASS
Edge distance ≥ 1.25 in for 7/8 in bolts (Table 6.13.2.6.6-1)Confirm the plate geometry provides the sheared/rolled edge distance.PASS
Slip-critical check at Service II31.62 kip39.00 kipPASS
Independent verificationExpectedComputedStatus
Resultant bolt force within capacity39.0031.62VERIFIED

Assumptions & basis of design

  • Elastic (vector) analysis of the bolt group — conservative relative to the instantaneous-centre method.
  • ASTM F3125 Grade A325 bolts (F_ub = 120 ksi) unless otherwise entered; φ_s = 0.80 for bolts in shear.
  • Flange splice bolts sized for the flange couple M_u/h_eff; AASHTO also requires design for the smaller of the yield or 75 % of the flange resistance.

Detail 10 bolts in the web group and 23 per side in each flange splice plate.

Module 41AASHTO LRFD 6.13.5 / 6.13.6 / 6.13.4Chapters 8 · 11

Splice plate tension — yielding, rupture & block shear

Gross yielding, net-section rupture with hole deduction, block shear on the tearout path, and the plate thickness and width that satisfies the governing limit state at a flange or web splice.

Gross yielding, net-section rupture with shear lag, and both block-shear paths for a bolted tension splice plate.

A_n/A_g

0.750

Shear-lag U

1.000

Gross yielding

570.0 kip

Net rupture

468.0 kip

Block shear

328.8 kip

Governing capacity

328.8 kip

block shear

Derivation — equation, substitution, result

Gross and net areas

  Ag=bt,An=Agndht(§6.8.3)=  16.00×0.7504(1.000)(0.750)=  Ag=12.000,An=9.000in2\begin{aligned}&\;A_g = b t, A_n = A_g − n d_h t (§6.8.3)\\[4pt]&=\;16.00 \times 0.750 − 4(1.000)(0.750)\\[4pt]&=\;\boxed{A_g = 12.000, A_n = 9.000 \,\text{in}^{2}}\end{aligned}

Shear lag

  U=1xˉ/L1.0,Ae=UAn(§6.8.2.2)=  10.00/12.00=  U=1.000,Ae=9.000in2\begin{aligned}&\;U = 1 − x̄/L \le 1.0, A_e = U A_n (§6.8.2.2)\\[4pt]&=\;1 − 0.00/12.00\\[4pt]&=\;\boxed{U = 1.000, A_e = 9.000 \,\text{in}^{2}}\end{aligned}

Gross-section yielding

  Pr=ϕyFyAg,ϕy=0.95=  0.95(50)(12.000)=  570.0kip\begin{aligned}&\;P_r = \phi _y F_y A_g, \phi _y = 0.95\\[4pt]&=\;0.95(50)(12.000)\\[4pt]&=\;\boxed{570.0 \,\text{kip}}\end{aligned}

Net-section rupture

  Pr=ϕuFuAe,ϕu=0.80=  0.80(65)(9.000)=  468.0kip\begin{aligned}&\;P_r = \phi _u F_u A_e, \phi _u = 0.80\\[4pt]&=\;0.80(65)(9.000)\\[4pt]&=\;\boxed{468.0 \,\text{kip}}\end{aligned}

Block shear — path 1

  R=0.58FuAnv+UbsFuAnt(Eq.6.13.41)=  0.58(65)(6.375)+1.00(65)(2.625)=  411.0kip\begin{aligned}&\;R = 0.58F_u A_{nv} + U_{bs} F_u A_{nt} (Eq. 6.13.4-1)\\[4pt]&=\;0.58(65)(6.375) + 1.00(65)(2.625)\\[4pt]&=\;\boxed{411.0 \,\text{kip}}\end{aligned}

Block shear — path 2

  R=0.58FyAgv+UbsFuAnt(Eq.6.13.42)=  0.58(50)(9.000)+1.00(65)(2.625)=  431.6kip\begin{aligned}&\;R = 0.58F_y A_{gv} + U_{bs} F_u A_{nt} (Eq. 6.13.4-2)\\[4pt]&=\;0.58(50)(9.000) + 1.00(65)(2.625)\\[4pt]&=\;\boxed{431.6 \,\text{kip}}\end{aligned}

Factored block shear

  Rr=ϕbsmin  (path 1, path 2),ϕbs=0.80=  328.8kip\begin{aligned}&\;R_r = \phi _{bs} \operatorname{min}\;\text{(path 1, path 2)}, \phi _{bs} = 0.80\\[4pt]&=\;\boxed{328.8 \,\text{kip}}\end{aligned}

Governing limit state

  min  (yielding, rupture, block shear)=  blockshear,ϕRn=328.8kip\begin{aligned}&\;\operatorname{min}\;\text{(yielding, rupture, block shear)}\\[4pt]&=\;\boxed{\,\text{block} \,\text{shear}, \phi R_n = 328.8 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

4×2 — 0.875 in Ø A325 @ 3.0 in pitch, 3.0in gage
Elevation — bolt group
Outer splice plate 0.750 inInner plates 2 × 0.375 inClass B faying surface — blast clean, nopaint in slip zoneTurn-of-nut pretension, install from thestiffest point outward
Section — splice plates
0.250 in fillet, both sidesGrind starts/stops; no welds across thetension flangeUT/MT per AWS D1.5 for fracture-criticalmembers
Plan — weld detail

Constructability & detailing notes

  • Punch-and-ream or drill full size — punched holes in thick plate leave a work-hardened edge that reduces the rupture capacity.
  • Splice plates on both faces halve the shear-lag penalty and keep the load path concentric.
  • Mark the plates for orientation; asymmetric hole patterns get installed backwards more often than anyone admits.
CheckDemandCapacity / limitStatus
φR_n ≥ P_u420.0 kip328.8 kipREVIEW
A_n ≤ 0.85 A_g for splice plates (§6.13.5.2)AASHTO caps the effective net area of splice plates at 0.85 A_g.0.7500.850PASS
Rupture is not the governing failure mode (ductility preference)Yielding should precede rupture — widen the plate or reduce hole loss.REVIEW
Independent verificationExpectedComputedStatus
Governing limit-state capacity exceeds demand328.8P_u appliedCHECK

Assumptions & basis of design

  • AASHTO LRFD §6.8.2, §6.13.4 and §6.13.5 with hole diameter taken as the bolt diameter + 1/8 in for standard holes.
  • U_bs = 1.0 for uniform tensile stress and 0.5 where the stress is non-uniform (coped beams).
  • Splice plates are proportioned so the effective net area does not exceed 0.85 A_g.

Increase the plate thickness or width — the block shear limit state controls, so target that path first (block shear responds best to longer end distances).

Chapter 10

Bearings, joints and movement

Thermal, shrinkage and creep movement, the joint gap through the temperature range, and the elastomeric pad that accommodates it.

Module 53AASHTO LRFD 14.7.6Chapter 10

Elastomeric bearing design

Shape factor, service compressive stress limit, and the shear-deformation requirement for a steel-reinforced pad.

S = LW / [2 h_ri (L + W)]  ·  σ_s ≤ 1.25 G S ≤ 1.75 ksi  ·  h_rt ≥ 2 Δ_s

Shape factor S

6.00

Total elastomer h_rt

2.00 in

Service stress σ_s

1.111 ksi

Compressive stress check

1.111 ≤ 0.975 ksi

Enlarge the pad or increase the shape factor.

Shear-deformation check

h_rt = 2.00 ≥ 2Δ_s = 1.50 in

Satisfies §14.7.6.3.4.

Detailing sketchElastomeric bearing — section and plan
Girder sole platePier cap / pedestal18 in (transverse)R = 180 kip (service)SECTION A–APLAN — PAD, SHIM OUTLINE AND ANCHORAGEsteel shim outline (typ.)girder CLW = 18 in (transverse)L = 9 in (longitudinal)Plan area A = 162 in² — σ_s = R/A = 1.111 ksi ≤ 0.98 ksi (14.7.6.3.2)Shape factor S = L·W / (2·h_ri·(L+W)); check rotation and shear deformation (14.7.6.3.3–.4)AA

18 × 9 in pad, 5 elastomer layers with steel shims. Service reaction 180 kip gives σs = 1.111 ksi against the 0.98 ksi limit (AASHTO 14.7.6.3.2) — increase the plan area.

Module 54AASHTO LRFD 3.12.2 / 14.7.5.3.2 / 14.5.3Chapter 10

Thermal movement, joint sizing & bearing shear

Rise and fall movement with γ_TU = 1.20, shrinkage and creep shortening, the joint gap at T_max and T_min against the joint's movement rating, the skewed-joint component, and the elastomer thickness needed for h_rt ≥ 2Δ_s.

α = 6.0×10⁻⁶ /°F for concrete, 6.5×10⁻⁶ /°F for steel. Movement length is measured from the point of fixity.

Total movement range

3.110 in

Factored design movement

3.732 in

Gap at T_max (closing)

1.057 in

Gap at T_min (opening)

4.789 in

Bearing shear strain Δ_s/h_rt

0.697

Required elastomer thickness

5.58 in

Detailing sketchExpansion joint / bearing — movement
gap = 2.00 int = 4.00 indesign movement Δ = 3.73 in

Gap ranges from 1.057 in (hot) to 4.789 in (cold); factored design movement = 3.732 in.

StepEquationSubstitutionResult
Temperature rise / fallΔT_rise = T_max − T_install ; ΔT_fall = T_install − T_min110 − 68 ; 68 − -1042 / 78 °F
Thermal expansionΔ = α ΔT L6.50e-6·42·28800.786 in
Thermal contractionΔ = α ΔT L6.50e-6·78·28801.460 in
Shrinkage + creep shorteningΔ = (ε_sh + ε_cr) L(2.0e-4 + 1.0e-4)·28800.864 in
Total movement rangeΔ_total = Δ_rise + Δ_fall + Δ_sh+cr0.786 + 1.460 + 0.8643.110 in
Factored design movementγ_TU Δ1.20 × 3.1103.732 in
Joint gap at maximum temperatureG_min = G_install − γ_TU Δ_rise2.000 − 1.20·0.7861.057 in
Joint gap at minimum temperatureG_max = G_install + γ_TU(Δ_fall + Δ_sh)2.000 + 1.20(1.460 + 0.864)4.789 in
Bearing shear strainγ = Δ_s/h_rt ≤ 0.52.789/4.000.697
Movement normal to a skewed jointΔ_n = Δ cos θ3.732·cos 0°3.732 in
  • OKJoint movement rating ≥ design movementdemand 3.732 incapacity 4.00 in
  • OKMinimum open gap 0.25 in at maximum temperaturedemand 1.057 incapacity 0.25 in
  • NGBearing shear h_rt ≥ 2Δ_sdemand 0.697capacity 0.500

Adjust the detail — required elastomer thickness h_rt ≥ 5.58 in and joint movement capacity ≥ 3.73 in. If the gap closes below 0.25 in, increase the installation gap or reset the joint at a measured temperature.

Assumptions & code basis
  • Uniform temperature range from AASHTO LRFD Table 3.12.2.1-1 (Procedure A) or the contour maps of Procedure B; entered here directly as T_max / T_min.
  • Coefficient of thermal expansion: 6.0×10⁻⁶ /°F for normal-weight concrete, 6.5×10⁻⁶ /°F for steel (§5.4.2.2, §6.4.1).
  • Load factor γ_TU = 1.20 applied to the movement when sizing joints and bearings (Table 3.4.1-1, deformation calculations).
  • Shrinkage plus creep shortening is applied only for concrete superstructures and only in the shortening direction.
  • Elastomeric bearing shear deformation limited to h_rt ≥ 2Δ_s, i.e. an engineering shear strain of 0.5 (§14.7.5.3.2 / §14.7.6.3.4).
  • For skewed joints the movement normal to the joint is the longitudinal movement times cos θ; the transverse component must also be accommodated.
Module 55AASHTO LRFD 14.4.2 / 14.7.6.3.5 / 14.7.6.4Chapter 10

Bearing rotation, stability & anchorage

Total design rotation with the 0.005 rad construction allowance, the §14.7.6.3.5 combined compression-plus-rotation check, the aspect-ratio stability limit, uplift screening and the anchor-bolt demand.

Full steel-reinforced elastomeric bearing check — stress, shear deformation, rotation, stability and anchorage.

Shape factor S

8.84

σ_s

0.536 ksi

Stress limit

1.250 ksi

h_rt

2.000 in

Shear strain γ_s

0.375

Anchor capacity

102.5 kip

Derivation — equation, substitution, result

Plan area and shape factor

  S=LW/[2hri(L+W)](Eq.14.7.5.11)=  (14.0×24.0)/[2(0.500)(38.0)]=  A=336.0in2,S=8.84\begin{aligned}&\;S = \mathrm{LW}/[2h_{ri}(L + W)] (Eq. 14.7.5.1-1)\\[4pt]&=\;(14.0 \times 24.0)/[2(0.500)(38.0)]\\[4pt]&=\;\boxed{A = 336.0 \,\text{in}^{2}, S = 8.84}\end{aligned}

Service compressive stress

  σs=Ps/A=  180.0/336.0=  0.536ksi  (live-load only 0.179 ksi)\begin{aligned}&\;\sigma _s = P_s/A\\[4pt]&=\;180.0/336.0\\[4pt]&=\;\boxed{0.536 \,\text{ksi} \;\text{(live-load only 0.179 ksi)}}\end{aligned}

Stress limit

  σsmin(1.25ksi,1.25GS)MethodA(§14.7.6.3.2)=  GS=1.149ksi=  limit=1.250ksi\begin{aligned}&\;\sigma _s \le \operatorname{min}(1.25 \,\text{ksi}, 1.25 G S) — Method A (§14.7.6.3.2)\\[4pt]&=\;G S = 1.149 \,\text{ksi}\\[4pt]&=\;\boxed{\,\text{limit} = 1.250 \,\text{ksi}}\end{aligned}

Shear deformation

  hrt2Δs(§14.7.6.3.4)=  2.000vs2(0.750)=  γs=0.375OK\begin{aligned}&\;h_{rt} \ge 2\Delta _s (§14.7.6.3.4)\\[4pt]&=\;2.000 \,\text{vs} 2(0.750)\\[4pt]&=\;\boxed{\gamma _s = 0.375 \mathrm{OK}}\end{aligned}

Rotation criterion

  σs0.5GS(L/hri)2θs/n(§14.7.6.3.5d)=  0.5(0.130)(8.84)(28.0)2(0.0120/4)=  requiredσs=1.352ksi\begin{aligned}&\;\sigma _s \ge 0.5 G S (L/h_{ri})^{2} \theta _s/n (§14.7.6.3.5d)\\[4pt]&=\;0.5(0.130)(8.84)(28.0)^{2}(0.0120/4)\\[4pt]&=\;\boxed{\,\text{required} \sigma _s = 1.352 \,\text{ksi}}\end{aligned}

Stability

  hrtL/3andW/3(§14.7.6.3.6)=  hrt/L=0.143=  stable\begin{aligned}&\;h_{rt} \le L/3 \operatorname{and} \le W/3 (§14.7.6.3.6)\\[4pt]&=\;h_{rt}/L = 0.143\\[4pt]&=\;\boxed{\,\text{stable}}\end{aligned}

Instantaneous deflection

  δσshrt/(4.8GS2)=  0.0220in\begin{aligned}&\;\delta \approx \sigma _s h_{rt}/(4.8 G S^{2})\\[4pt]&=\;\boxed{0.0220 \,\text{in}}\end{aligned}

Anchorage

  ϕRn=nϕ(0.48AbFubNs)Hu=  4×0.75×34.16=  102.5kipvsHu=12.0kip\begin{aligned}&\;\phi R_n = n \phi (0.48 A_b F_{ub} N_s) \ge H_u\\[4pt]&=\;4 \times 0.75 \times 34.16\\[4pt]&=\;\boxed{102.5 \,\text{kip} \,\text{vs} H_u = 12.0 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

L = 14.0 inW = 24.0 in4 anchor bolts through masonry plate
Plan
4 layers × 0.50 in elastomer, 0.075 insteel shims1/4 in vulcanised cover top/bottom, 1/8 inside cover
Section
Girder bottom flange / sole plateBearing seat — 1 in min. grout pad, levelto ±1/16 inSet bearing at mean temperature; recordinstallation temp.Provide jacking points and 1/2 in seatfor future replacement
Elevation

Constructability & detailing notes

  • Set the bearing at the mean design temperature and record the installation temperature on the as-builts.
  • Provide a level, grouted seat within 1/16 in — a sloped seat walks the pad out over time.
  • Detail jacking points and 6 in of clearance so the bearing can be replaced without removing the girder.
  • Bevel the sole plate to remove the built-in grade rotation instead of asking the elastomer to absorb it.
CheckDemandCapacity / limitStatus
Compressive stress limit0.536 ksi1.250 ksiPASS
h_rt ≥ 2Δ_s1.500 in2.000 inPASS
Rotation / uplift criterion1.352 ksi0.536 ksiREVIEW
Stability h_rt ≤ L/32.000 in4.667 inPASS
Anchor bolts φR_n ≥ H_u12.0 kip102.5 kipPASS
Shape factor 3 ≤ S ≤ 12 practical range8.843 – 12PASS
Independent verificationExpectedComputedStatus
Compressive stress within the method limit1.2500.536VERIFIED
Total elastomer thickness ≥ 2Δ_sh_rt ≥ 2Δ_s2.000VERIFIED

Assumptions & basis of design

  • Steel-reinforced elastomeric bearing, 50-durometer neoprene, G taken at the low-temperature design value.
  • Method A (§14.7.6) is the simplified route; Method B (§14.7.5) permits higher stresses with additional checks.
  • Anchor bolts assumed ASTM F1554 Grade 36 in single shear with threads in the shear plane.

The pad rotates more than the compressive stress can hold down — increase the pad plan area, reduce the number of layers, or use a tapered sole plate to remove the built-in rotation.

Chapters 9 · 12 – 13

Substructure — piers, abutments, walls and foundations

Earth pressure and stability, pier-cap and column interaction, single piles and pile groups under axial load and biaxial moment.

Module 42AASHTO LRFD 5.6.4 / 5.7.3Chapters 9 · 12 · 13

Pier-cap flexure & column axial–moment interaction

Cap flexural and shear resistance alongside a column P-M interaction screening ratio with slenderness magnification.

Mn = As fy(d − a/2)  ·  Vc = 0.0316β√f′c bv dv  ·  Po = 0.85f′c(Ag−Ast)+fyAst

Cap φMn

1477 k-ft

Cap φVc

158 kip

Column φPn,max

3145 kip

Column φMn (approx.)

659 k-ft

Cap flexure check

1477 ≥ 2200 k-ft

Cap shear check

158 ≥ 400 kip

Column P-M interaction

1.939

Pu/φPn + Mu/φMn ≤ 1.0 (simplified — verify with a full interaction diagram).

Pier cap longitudinal reinforcement — AASHTO LRFD §5.6.3 / §5.10

A_s required (strength)12.22 in²
A_s minimum (§5.6.3.3 / §5.10.6)3.12 in²
A_s design (governing)12.22 in²
Bar selection8 – #11
Bar size / area#11 — A_b = 1.56 in²
Bars / layers8 bars in 1 layer (clear spacing 4.2 in)
A_s provided12.48 in²
A_s,prov / A_s,req1.02
Stress-block depth a6.12 in
Net tensile strain ε_t0.0149
φ0.900
φM_n (as detailed)2243.1 k-ft
M_cr (§5.6.3.3)592.8 k-ft
Minimum-resistance demand min(M_cr, 1.33M_u)592.8 k-ft
Reinforcement ratio ρ0.0081

PASS — Adequate — detail as scheduled

A_s,prov / A_s,req = 1.02; ε_t = 0.0149 (tension-controlled, φ = 0.90).

Transverse reinforcement — AASHTO LRFD §5.7.2.5 / §5.7.3.3

Concrete contribution V_c176.1 kip
Steel required V_s = V_u/φ − V_c268.3 kip
Stirrup schedule#5 2-leg @ 5.0 in c/c (A_v = 0.62 in²)
Maximum spacing s_max24.0 in
φV_n = φ(V_c + V_s)417.6 kip
Web-crushing limit 0.25 f′_c b_v d_v1393.2 kip

PASS — φV_n = 417.6 kip ≥ V_u = 400.0 kip.

Column longitudinal steel

18 – #14

A_st,req 40.45 → A_st,prov 40.50 in²

Column ties / spiral

#4 ties @ 12 in c/c (§5.10.4.3)

ρ = 2.92 % (limits 1 %–8 %) — 18 – #14 bars, clear spacing 4.76 in.

Detailing sketchPier cap — elevation, section and plan
20.00 ft4.00 ft48 in8 #11 top (continuous)#5 stirrups @ 6 inCAP REINFORCEMENT SCHEDULETop steel: 8 — #11 continuous, A_s = 12.48 in²Bottom steel: 4 — #9, A_s = 4.00 in²Skin steel: #5 @ 12 in each face (5.6.7)Stirrups: #5 double leg @ 6 inELEVATION (looking upstation)AASECTION A–A — CAP CROSS-SECTIONb = 36 inh = 48 in4 #11 top3 #9 bottom#5 skin @ 12 inPLAN — CAP, BEARINGS AND COLUMN FOOTPRINT36 in5 bearingsDashed circles = columns belowTop mat continuous full length of cap

8 #11 continuous top bars (As = 12.48 in²) with skin and bottom steel; #5 double-leg stirrups @ 6 in through the cap. Cap 36 in wide × 48 in deep, 4.00 ft cantilever each end, 2 columns at 20.00 ft centres.

Detailing sketchPier column — section and elevation
D = 42 in32 #10 longitudinal#4 spiral @ 3 in pitchP_u = 1800 kipM_u = 900 k-ft2 in clear coverCOLUMN REINFORCEMENT SCHEDULEA_st,req = 40.50 in² (ρ_req = 2.92 %)Provide 32 — #10: A_st = 40.64 in²ρ_prov = 2.93 % (0.01 ≤ ρ ≤ 0.08)Spiral: #4 @ 3 in pitch, 2 in coverSECTION A–AELEVATION — SPIRAL PITCH, SPLICE ZONE AND FOOTING DOWELSpier capfooting / pile capclear height#4 spiral @ 3 in pitch (5.10.4.2)32 — #10 vertical bars, 2 in coverDowels lap 1.7·l_d into the column (5.10.8.4)Spiral pitch tightened in the plastic-hinge zoneAA

32 #10 longitudinal bars (Ast = 40.64 in², ρ = 2.93 %) against the required Ast = 40.50 in² at ρ = 2.92 %. #4 spiral at 3 in pitch, 2 in clear cover. Design actions Pu = 1800 kip, Mu = 900 k-ft (AASHTO 5.6.4, 5.10.4.2).

Module 43AASHTO LRFD 11.6 / 11.5.7Chapters 9 · 12 · 13

Abutment / retaining-wall stability screening

Rankine active thrust with overturning, sliding, and eccentricity screening ratios.

K_a = tan²(45° − φ′/2)  ·  P_a = ½ K_a γ H²  ·  e ≤ B/4 for soil foundations

K_a (Rankine)

0.283

Active thrust P_a

6.79 kip/ft

Overturning moment

45.2 k-ft/ft

Overturning ratio M_r/M_o

59.69

Target ≥ 2.0

Sliding ratio

44.73

Target ≥ 1.5

Eccentricity e

0.10 ft

B/4 = 3.00 ft

Detailing sketchAbutment — retained fill, resultant and bearing pressure
P_a = 6.8 kip at H/3W = 450.0 kipq_max 39.38 ksfq_min 35.62 ksfH = 20.0 ftB = 12.0 ft

Stem 20.0 ft tall on a 12.0 ft footing. Active thrust Pa = 6.8 kip acting at H/3, resisting weight W = 450.0 kip, resultant eccentricity e = 0.10 ft. qmax = 39.38 ksf, qmin = 35.62 ksf (AASHTO 11.6.3).

Screening tool only: the LRFD check uses factored loads with the Strength I and Extreme Event combinations and resistance factors from §11.5.7, not global factors of safety.

Module 44AASHTO LRFD 10.7.3 / 10.5.5.2.3Chapter 13

Pile axial resistance

Skin friction and tip resistance for driven piles, with static and dynamically-verified factored resistances.

Rs = fs·perimeter·L  ·  Rp = qp·Ap  ·  Rn = Rs + Rp  ·  φRn = φ·Rn

Side resistance Rs

166 kip

Tip resistance Rp

15 kip

Nominal resistance Rn

181 kip

φRn (static)

81 kip

φRn (dynamic)

118 kip

Piles required (static design)

23

Dynamic-verified: 16 piles

Detailing sketchPile group — cap plan, pile elevation and cap section
12345678910111213141516171819202122233.0DPile cap planPile elevationscour −0 ftskin friction qstip resistance qp60 ftAASECTION A–A — PILE CAP REINFORCEMENT AND PILE EMBEDMENTcap depth3.0D = 48 intop matbottom matPiles embedded ≥ 12 in into the cap; 3 in clear cover to earth; check punching shear around each pile (5.12.8.6)

23 piles at 3.0D centres, 16 in diameter, 60 ft embedded with the top 0 ft inside the scour prism neglected. Demand 78 kip/pile against φQn = 81 kip (AASHTO 10.7.3.8).

Module 45AASHTO LRFD 10.7.3.9 / 10.7.1.2 / 10.5.5.2.3Chapters 9 · 12 · 13

Pile group — efficiency, block failure & cap distribution

Group efficiency η in clay, the equivalent-pier block failure check, factored group resistance, and the rigid-cap elastic distribution P_u/N ± M_x y/Σy² ± M_y x/Σx² with the corner-pile and uplift checks.

Corner piles govern: the elastic cap formula adds the moment terms about both axes.

Group efficiency η

0.775

Group size B × L

12.50 × 8.75 ft

Factored group resistance

1813 kip

Max pile load

240.7 kip

Min pile load

159.3 kip

Detailing sketchPile group — plan
s = 3.75 fts = 3.75 ftPLAN — 3×4 pile group, size 1.25 ft

Group size 12.50 × 8.75 ft; max pile load 240.7 kip vs φQ_p.

StepEquationSubstitutionResult
Pile countN = rows × columns3 × 412 piles
Group efficiencyη = 0.7 at s = 2.5b, 1.0 at s = 6b (linear)s/b = 3.000.775
Sum of individual capacitiesQ_g = η N Q_p0.775·12·300.02790 kip
Block failure (clay)Q_block = 2(B + L)Z c_u + 9 c_u B L2(12.50 + 8.75)·45.0·1.20 + 9·1.20·12.50·8.753476 kip
Factored group resistanceφQ = φ·min(Q_g, Q_block)0.65·27901813 kip
Maximum pile loadP = P_u/N + M_x y_max/Σy² + M_y x_max/Σx²2400/12 + 900·3.75/112.5 + 400·5.63/210.9240.7 kip
Minimum pile loadP = P_u/N − M_x y_max/Σy² − M_y x_max/Σx²2400/12 − …159.3 kip
  • NGGroup resistance φQ ≥ P_udemand 2400 kipcapacity 1813 kipratio 1.32
  • NGIndividual pile P_max ≤ φQ_pdemand 240.7 kipcapacity 195.0 kip
  • OKNo net upliftdemand 159.3 kip
  • OKSpacing s ≥ 2.5b (§10.7.1.2)demand 3.75 ftcapacity 3.13 ft

Add piles or spread the group: about 16 piles are needed, or lengthen the piles to raise Q_p to 370.3 kip each.

Assumptions & code basis
  • Group efficiency η applies to pile groups in cohesive soils; in cohesionless soils driven piles at s ≥ 2.5b are taken as η = 1.0 (AASHTO LRFD §10.7.3.9).
  • Block failure of a group in clay checked as a single equivalent pier: perimeter adhesion plus 9c_u end bearing (§10.7.3.9).
  • Individual pile loads from the rigid-cap elastic formula P = P_u/N ± M_x y/Σy² ± M_y x/Σx²; the cap is assumed infinitely rigid and the piles axially elastic.
  • Resistance factors: φ = 0.65 (clay, static analysis with driving criteria) or 0.50 (sand, static analysis) — increase with dynamic testing per Table 10.5.5.2.3-1.
  • Tension (uplift) piles must additionally be checked with φ_up ≤ 0.35–0.45.
Module 46AASHTO LRFD 5.6.4.3 · ACI §6.6.4Chapters 9 · 12 · 13

Pier column slenderness & moment magnification

Effective length KL/r screening against the 22 / 34 − 12(M1/M2) thresholds, EI_eff with β_d, the critical load P_c, and the δ_ns magnified design moment with the minimum-eccentricity floor.

Screens the column for slenderness, then magnifies the moment with the §5.6.4.3 approximate procedure.

Kℓ_u/r

33.6

P_e

14396 kip

δ_b

1.200

M_c design

1080.1 kip·ft

ρ_g

0.0155

φP_n,max

4643 kip

Derivation — equation, substitution, result

Radius of gyration

  r=0.25D=  h=48.0in=  r=12.00in\begin{aligned}&\;r = 0.25 D\\[4pt]&=\;h = 48.0 \,\text{in}\\[4pt]&=\;\boxed{r = 12.00 \,\text{in}}\end{aligned}

Slenderness ratio

  Ku/r=  1.20×336/12.00=  Ku/r=33.6\begin{aligned}&\;K ℓ_u / r\\[4pt]&=\;1.20 \times 336 / 12.00\\[4pt]&=\;\boxed{Kℓ_u/r = 33.6}\end{aligned}

Slenderness limit

  22  (unbraced)=  M1/M2=0.333=  limit=22.0slender,magnify\begin{aligned}&\;22 \;\text{(unbraced)}\\[4pt]&=\;M_{1}/M_{2} = 0.333\\[4pt]&=\;\boxed{\,\text{limit} = 22.0 \rightarrow \,\text{slender}, \,\text{magnify}}\end{aligned}

Flexural stiffness

  EI=0.40EcIg/(1+βd)(Eq.5.6.4.32)=  Ec=3640ksi,Ig=260576in4,βd=0.60=  EI=2.371e+8kipin2\begin{aligned}&\;\mathrm{EI} = 0.40 E_c I_g/(1 + \beta _d) (Eq. 5.6.4.3-2)\\[4pt]&=\;E_c = 3640 \,\text{ksi}, I_g = 260576 \,\text{in}^{4}, \beta _d = 0.60\\[4pt]&=\;\boxed{\mathrm{EI} = 2.371e+8 \,\text{kip}\cdot \,\text{in}^{2}}\end{aligned}

Euler load

  Pe=π2EI/(Ku)2=  π2(2.37e+8)/(403)2=  Pe=14396kip\begin{aligned}&\;P_e = \pi ^{2}\mathrm{EI}/(Kℓ_u)^{2}\\[4pt]&=\;\pi ^{2}(2.37e+8)/(403)^{2}\\[4pt]&=\;\boxed{P_e = 14396 \,\text{kip}}\end{aligned}

Moment gradient factor

  Cm=0.6+0.4(M1/M2)0.4  (braced),1.0  (unbraced)=  Cm=1.000\begin{aligned}&\;C_m = 0.6 + 0.4(M_{1}/M_{2}) \ge 0.4 \;\text{(braced)}, 1.0 \;\text{(unbraced)}\\[4pt]&=\;\boxed{C_m = 1.000}\end{aligned}

Magnifier

  δb=Cm/(1Pu/(ϕKPe))1.0(Eq.5.6.4.33)=  1.000/(11800/(0.75×14396))=  δb=1.200\begin{aligned}&\;\delta _b = C_m/(1 − P_u/(\phi _K P_e)) \ge 1.0 (Eq. 5.6.4.3-3)\\[4pt]&=\;1.000/(1 − 1800/(0.75 \times 14396))\\[4pt]&=\;\boxed{\delta _b = 1.200}\end{aligned}

Minimum eccentricity

  emin=0.6+0.03h,M2,min=Puemin=  emin=2.04in=  M2,min=306.0kipft\begin{aligned}&\;e_{\operatorname{min}} = 0.6 + 0.03h, M_{2},\operatorname{min} = P_u e_{\operatorname{min}}\\[4pt]&=\;e_{\operatorname{min}} = 2.04 \,\text{in}\\[4pt]&=\;\boxed{M_{2},\operatorname{min} = 306.0 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Magnified design moment

  Mc=δbM2=  1.200×900.0=  Mc=1080.1kipft\begin{aligned}&\;M_c = \delta _b M_{2}\\[4pt]&=\;1.200 \times 900.0\\[4pt]&=\;\boxed{M_c = 1080.1 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Pure axial capacity

  Po=0.85fc(AgAst)+fyAst;Pn,max=0.80Po  (tied)=  ρg=0.0155=  ϕPn,max=4643kip\begin{aligned}&\;P_o = 0.85f'_c(A_g − A_{st}) + f_y A_{st}; P_n,\operatorname{max} = 0.80P_o \;\text{(tied)}\\[4pt]&=\;\rho _g = 0.0155\\[4pt]&=\;\boxed{\phi P_n,\operatorname{max} = 4643 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

20 — #9 vert.48 in
Section
#5 spiral @ 4.0 inLap splices atmid-height only48 in
Elevation
Cap beam — column bars developed fullℓ_d into capConfinement continued 1/2 column dia.into joint
Plan at cap

Constructability & detailing notes

  • Column bars are spliced above the footing with a mechanical coupler or a lap outside the plastic-hinge zone.
  • Provide a 2 in chamfer or a formliner detail — plain circular columns show every form seam.
  • Check the free-standing (erection) condition before the cap is cast: K is effectively 2.1 for a cantilever pier.
CheckDemandCapacity / limitStatus
P_u < 0.75 P_e (stability)1800 kip10797 kipPASS
δ_b ≤ 1.40 (practical limit — otherwise stiffen)1.2001.40PASS
Steel ratio 1 % ≤ ρ_g ≤ 8 % (§5.6.4.2)0.01550.010 – 0.080PASS
Axial capacity φP_n,max ≥ P_u1800 kip4643 kipPASS
Kℓ_u/r ≤ 100 (refined analysis required above)33.6100PASS
Independent verificationExpectedComputedStatus
Magnifier within the practical 1.0 – 1.4 band1.00 – 1.401.200VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §5.6.4.3 approximate moment magnification for a single-curvature or double-curvature column.
  • β_d = ratio of factored permanent axial load to total factored axial load; 0.6 is typical for bridge piers.
  • K = 1.0 for pinned–pinned, 2.1 for a free-standing cantilever pier, 0.65 – 0.80 for a fixed-base column in a braced frame.

Design the column for P_u = 1800 kip with M_c = 1080.1 kip·ft on the P–M interaction diagram.

Module 47AASHTO LRFD 5.6.4.5 · ACI §22.4Chapters 9 · 12 · 13

Biaxial column bending — Bresler reciprocal

Uniaxial capacities about each axis, the Bresler reciprocal-load check 1/P_n = 1/P_nx + 1/P_ny − 1/P_o, and the load-contour comparison with the bar layout that satisfies both axes.

Bresler reciprocal-load check at moderate to high axial load, with the moment-contour alternative below 0.10 φP_o.

φP_ni (biaxial)

1942 kip

Reciprocal-load ratio

0.824

Moment-contour ratio

1.057

Governing utilisation

0.824

Derivation — equation, substitution, result

Screening

  IfPu<0.10ϕPousethemomentcontourmethod;otherwiseuseBreslerreciprocalload=  Pu=1600kip,0.10ϕPo=520kip=  reciprocalloadgoverns\begin{aligned}&\;If P_u < 0.10 \phi P_o \operatorname{use} \,\text{the} \,\text{moment}-\,\text{contour} \,\text{method}; \,\text{otherwise} \operatorname{use} Bresler \,\text{reciprocal} \,\text{load}\\[4pt]&=\;P_u = 1600 \,\text{kip}, 0.10\phi P_o = 520 \,\text{kip}\\[4pt]&=\;\boxed{\,\text{reciprocal} \,\text{load} \,\text{governs}}\end{aligned}

Reciprocal load

  1/ϕPn=1/ϕPnx+1/ϕPny1/ϕPo(Eq.5.6.4.51)=  1/2600+1/31001/5200=  ϕPni=1942kip\begin{aligned}&\;1/\phi P_n = 1/\phi P_{nx} + 1/\phi P_{ny} − 1/\phi P_o (Eq. 5.6.4.5-1)\\[4pt]&=\;1/2600 + 1/3100 − 1/5200\\[4pt]&=\;\boxed{\phi P_{ni} = 1942 \,\text{kip}}\end{aligned}

Axial utilisation

  Pu/ϕPni1.0=  1600/1942=  0.824\begin{aligned}&\;P_u/\phi P_{ni} \le 1.0\\[4pt]&=\;1600/1942\\[4pt]&=\;\boxed{0.824}\end{aligned}

Moment contour

  Mux/ϕMnx+Muy/ϕMny1.0(Eq.5.6.4.53)=  700/1100+400/950=  1.057\begin{aligned}&\;M_{ux}/\phi M_{nx} + M_{uy}/\phi M_{ny} \le 1.0 (Eq. 5.6.4.5-3)\\[4pt]&=\;700/1100 + 400/950\\[4pt]&=\;\boxed{1.057}\end{aligned}

Governing ratio

  maxoftheapplicableinteraction=  0.8241.0OK\begin{aligned}&\;\operatorname{max} \operatorname{of} \,\text{the} \,\text{applicable} \,\text{interaction}\\[4pt]&=\;\boxed{0.824 \le 1.0 \mathrm{OK}}\end{aligned}

Detailing — plan, elevation and section

16 — #10 vert.48 in
Section
#4 ties @ 12.0 inno splice in hingezone48 in
Elevation
Cap beam — column bars developed fullℓ_d into capConfinement continued 1/2 column dia.into joint
Plan at cap

Constructability & detailing notes

  • Distribute the longitudinal bars around the full perimeter — corner-only layouts have poor biaxial capacity.
  • Cross-ties on alternate bars are required when the clear spacing exceeds 6 in (§5.10.4.3).
CheckDemandCapacity / limitStatus
Biaxial interaction ≤ 1.00.8241.000PASS
φP_nx and φP_ny each exceed P_u1600 kip2600 kipPASS
Bresler validity P_u ≥ 0.10 φP_o1600 kip520 kipPASS
Independent verificationExpectedComputedStatus
Governing interaction ≤ 1.0≤ 1.0000.824VERIFIED

Assumptions & basis of design

  • φP_nx and φP_ny are read from the uniaxial interaction diagrams at the respective eccentricities e_x = M_uy/P_u and e_y = M_ux/P_u.
  • φP_o = φ[0.85f′_c(A_g − A_st) + f_y A_st] is the concentric capacity without the 0.80 cap.
  • Bresler's reciprocal-load equation is accurate within about 10 % for symmetric sections at moderate to high axial load.

Biaxial capacity is adequate; confirm the tie or spiral detailing and the bar development into the cap and footing.

Module 48AASHTO LRFD 5.10.4.2 / 5.11.4.1Chapters 9 · 15

Column confinement, ties and plastic hinge detailing

Spiral ratio ρ_s and rectangular hoop A_sh from the two governing expressions, the hoop spacing and plastic-hinge length ℓ_o, tie size and the cross-tie layout for a seismic pier column.

Spiral or tie confinement, pitch, longitudinal bar layout and the seismic floor of 0.12 f′_c/f_yh.

ρ_s required

0.00800

Spiral pitch

3.50 in

ρ_s provided

0.00805

Tie spacing

12.00 in

ρ_g longitudinal

0.0111

Callout

20 — #9 vert. w/ #5 spiral @ 3.50 in

Derivation — equation, substitution, result

Gross and core areas

  Ag=πD2/4,Ac=πDc2/4=  Dc=44.00in=  Ag=1810in2,Ac=1521in2\begin{aligned}&\;A_g = \pi D^{2}/4, A_c = \pi D_c^{2}/4\\[4pt]&=\;D_c = 44.00 \,\text{in}\\[4pt]&=\;\boxed{A_g = 1810 \,\text{in}^{2}, A_c = 1521 \,\text{in}^{2}}\end{aligned}

Confinement ratio (gravity)

  ρs0.45(Ag/Ac1)fc/fyh(Eq.5.6.4.61)=  0.45(1.1901)(4.00/60)=  ρs=0.00570\begin{aligned}&\;\rho _s \ge 0.45(A_g/A_c − 1)f'_c/f_{yh} (Eq. 5.6.4.6-1)\\[4pt]&=\;0.45(1.190 − 1)(4.00/60)\\[4pt]&=\;\boxed{\rho _s = 0.00570}\end{aligned}

Confinement ratio (seismic)

  ρs0.12fc/fyh(§5.10.11.4.1d)=  0.12×0.0667=  ρs=0.00800\begin{aligned}&\;\rho _s \ge 0.12 f'_c/f_{yh} (§5.10.11.4.1d)\\[4pt]&=\;0.12 \times 0.0667\\[4pt]&=\;\boxed{\rho _s = 0.00800}\end{aligned}

Governing ratio

  maxofthetwo=  ρs,req=0.00800\begin{aligned}&\;\operatorname{max} \operatorname{of} \,\text{the} \,\text{two}\\[4pt]&=\;\boxed{\rho _s,\,\text{req} = 0.00800}\end{aligned}

Spiral pitch

  s=4Asp/(ρsDc)=  4(0.310)/(0.00800×44.00)=  s=3.52inuse3.50in\begin{aligned}&\;s = 4A_{sp}/(\rho _s D_c)\\[4pt]&=\;4(0.310)/(0.00800 \times 44.00)\\[4pt]&=\;\boxed{s = 3.52 \,\text{in} \rightarrow \operatorname{use} 3.50 \,\text{in}}\end{aligned}

Provided ratio

  ρs,prov=4Asp/(sDc)=  0.00805\begin{aligned}&\;\rho _s,\,\text{prov} = 4A_{sp}/(s D_c)\\[4pt]&=\;\boxed{0.00805}\end{aligned}

Tie spacing (tied column)

  smin  (12 in, least dimension, 16 db,long, 48 db,tie)(§5.10.4)=  12.00in\begin{aligned}&\;s \le \operatorname{min}\;\text{(12 in, least dimension, 16 db,long, 48 db,tie)} (§5.10.4)\\[4pt]&=\;\boxed{12.00 \,\text{in}}\end{aligned}

Longitudinal bar layout

  clearspacingmax(1.5db,1.5in)=  20#9bars=  clearspacing5.61in,ρg=0.0111\begin{aligned}&\;\,\text{clear} \,\text{spacing} \ge \operatorname{max}(1.5 d_b, 1.5 \,\text{in})\\[4pt]&=\;20 — \#9 \,\text{bars}\\[4pt]&=\;\boxed{\,\text{clear} \,\text{spacing} \approx 5.61 \,\text{in}, \rho _g = 0.0111}\end{aligned}

Detailing — plan, elevation and section

20 — #9 vert.48 in
Section
#5 spiral @ 3.5 inNo lap splices inthe plastic-hingezone48 in
Elevation
Cap beam — column bars developed fullℓ_d into capConfinement continued 1/2 column dia.into joint
Plan at cap

Constructability & detailing notes

  • Spirals are shipped compressed and stretched on site — specify spacer bars so the pitch survives concrete placement.
  • Extend the confinement one full column dimension into the cap and the footing.
  • Keep the clear pitch at 1 in minimum so a vibrator head and the aggregate can pass.
CheckDemandCapacity / limitStatus
ρ_s,prov ≥ ρ_s,req0.008000.00805PASS
Clear pitch 1 – 3 in (§5.10.4.3)2.88 in clear1.0 – 3.0 inPASS
Longitudinal steel 1 – 8 %0.01110.010 – 0.080PASS
Bar clear spacing adequate for concrete placement5.61 in1.69 inPASS
Spiral ≥ #3 (or #4 in seismic zones)#5#4PASS
Independent verificationExpectedComputedStatus
Provided confinement ratio ≥ required0.008000.00805VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §5.6.4.6 and §5.10.4 for gravity columns; §5.10.11 adds the seismic confinement floor.
  • Spiral pitch is rounded down to the nearest 1/4 in and capped at 6 in.
  • The core dimension D_c is measured out-to-out of the spiral.

Confinement satisfies the code; extend the spiral into the cap and footing for the full development length of the longitudinal bars.

Module 49AASHTO LRFD 11.6.3 / 11.6.5 / 3.11.5Chapters 9 · 12 · 13

Retaining wall — full stability and stem design

Coulomb / Rankine thrust with surcharge, the overturning, sliding and bearing-eccentricity checks, the factored bearing pressure diagram, and stem, heel and toe flexural steel with bar schedules.

External stability (overturning, sliding, eccentricity, bearing) and internal stem design in one pass.

K used

0.307

active (free to translate)

ΣH

10.55 kip/ft

ΣV

40.62 kip/ft

FS overturning

4.83

FS sliding

2.12

Eccentricity e

-0.850 ft

q_max

1.845 ksf

Stem steel

#3 @ 1 in

A_s,req = 0.994 in²/ft

Derivation — equation, substitution, result

Earth-pressure coefficients

  Ka=tan2(45ϕ/2),K0=1sinϕ,Kp=tan2(45+ϕ/2)=  ϕ=32.0=  Ka=0.307,K0=0.470,Kp=3.255usingK=0.307\begin{aligned}&\;K_a = \operatorname{tan}^{2}(45 − \phi /2), K_0 = 1 − \operatorname{sin} \phi , K_p = \operatorname{tan}^{2}(45 + \phi /2)\\[4pt]&=\;\phi = 32.0^{\circ}\\[4pt]&=\;\boxed{K_a = 0.307, K_0 = 0.470, K_p = 3.255 — \,\text{using} K = 0.307}\end{aligned}

Active thrust

  Pa=½γH2K,actingatH/3(Eq.3.11.5.31)=  0.5(120)(22.00)2(0.307)/1000=  8.92kip/ft\begin{aligned}&\;P_a = ½\gamma H^{2}K, \,\text{acting} \operatorname{at} H/3 (Eq. 3.11.5.3-1)\\[4pt]&=\;0.5(120)(22.00)^{2}(0.307)/1000\\[4pt]&=\;\boxed{8.92 \,\text{kip}/\,\text{ft}}\end{aligned}

Live-load surcharge

  PLS=γheqKH,atH/2(§3.11.6.4)=  heq=2.00ft=  1.62kip/ft\begin{aligned}&\;P_{LS} = \gamma h_{eq} K H, \operatorname{at} H/2 (§3.11.6.4)\\[4pt]&=\;h_{eq} = 2.00 \,\text{ft}\\[4pt]&=\;\boxed{1.62 \,\text{kip}/\,\text{ft}}\end{aligned}

Vertical resultant

  V=Wstem+Wfooting+Wsoil+qLLheel=  70.20+5.25+31.59+3.24=  V=40.62kip/ft\begin{aligned}&\;V = W_{stem} + W_{footing} + W_{soil} + q_{LL}\cdot \,\text{heel}\\[4pt]&=\;70.20 + 5.25 + -31.59 + -3.24\\[4pt]&=\;\boxed{V = 40.62 \,\text{kip}/\,\text{ft}}\end{aligned}

Overturning

  FSOT=\SumMR/\SumMOT2.0=  402.1/83.3=  FS=4.83\begin{aligned}&\;\mathrm{FS}_{OT} = \Sum M_R/\Sum M_{OT} \ge 2.0\\[4pt]&=\;402.1/83.3\\[4pt]&=\;\boxed{\mathrm{FS} = 4.83}\end{aligned}

Sliding

  FSs=μ\SumV/\SumH1.5=  0.55(40.62)/10.55=  FS=2.12\begin{aligned}&\;\mathrm{FS}_s = \mu \Sum V/\Sum H \ge 1.5\\[4pt]&=\;0.55(40.62)/10.55\\[4pt]&=\;\boxed{\mathrm{FS} = 2.12}\end{aligned}

Resultant location

  xˉ=(\SumMR\SumMOT)/\SumV,e=B/2xˉB/6  (soil)orB/4  (rock)=  xˉ=7.850ft=  e=0.850ft,B/6=2.333ft\begin{aligned}&\;x̄ = (\Sum M_R − \Sum M_{OT})/\Sum V, e = B/2 − x̄ \le B/6 \;\text{(soil)} \operatorname{or} B/4 \;\text{(rock)}\\[4pt]&=\;x̄ = 7.850 \,\text{ft}\\[4pt]&=\;\boxed{e = -0.850 \,\text{ft}, B/6 = 2.333 \,\text{ft}}\end{aligned}

Bearing pressure

  q=(V/B)(1±6e/B)=  V/B=2.901ksf=  qmax=1.845,qmin=3.958ksf\begin{aligned}&\;q = (V/B)(1 \pm 6e/B)\\[4pt]&=\;V/B = 2.901 \,\text{ksf}\\[4pt]&=\;\boxed{q_{\operatorname{max}} = 1.845, q_{\operatorname{min}} = 3.958 \,\text{ksf}}\end{aligned}

Meyerhof effective width

  B=B2e,quniform=V/B=  14.002(0.850)=  B=12.301ft,q=3.302ksf\begin{aligned}&\;B' = B − 2e, q_{uniform} = V/B'\\[4pt]&=\;14.00 − 2(0.850)\\[4pt]&=\;\boxed{B' = 12.301 \,\text{ft}, q = 3.302 \,\text{ksf}}\end{aligned}

Stem moment and shear at the base

  M(y)=γKy3/6+γheqKy2/2V(y)=γKy2/2+γheqKy=  y=19.50ft=  M=59.59kipft/ft,V=8.45kip/ft\begin{aligned}&\;M(y) = \gamma Ky^{3}/6 + \gamma h_{eq} K y^{2}/2 \cdot V(y) = \gamma Ky^{2}/2 + \gamma h_{eq} K y\\[4pt]&=\;y = 19.50 \,\text{ft}\\[4pt]&=\;\boxed{M = 59.59 \,\text{kip}\cdot \,\text{ft}/\,\text{ft}, V = 8.45 \,\text{kip}/\,\text{ft}}\end{aligned}

Factored stem demand

  Mu=1.50MEH+1.75MLS  (Table 3.4.1-2)=  1.50(45.57)+1.75(14.02)=  Mu=92.88kipft/ft\begin{aligned}&\;M_u = 1.50 M_{EH} + 1.75 M_{LS} \;\text{(Table 3.4.1-2)}\\[4pt]&=\;1.50(45.57) + 1.75(14.02)\\[4pt]&=\;\boxed{M_u = 92.88 \,\text{kip}\cdot \,\text{ft}/\,\text{ft}}\end{aligned}

Stem reinforcement

  ρ=0.85fc/fy[112Rn/0.85fc],As=ρbd=  d=21.50in,Rn=0.2233ksi=  As=0.994in2/ft#3@1in\begin{aligned}&\;\rho = 0.85f'_c/f_y[1 − \sqrt{1 − 2R_n/0.85f'_c}], A_s = \rho b d\\[4pt]&=\;d = 21.50 \,\text{in}, R_n = 0.2233 \,\text{ksi}\\[4pt]&=\;\boxed{A_s = 0.994 \,\text{in}^{2}/\,\text{ft} \rightarrow \#3 @ 1 \,\text{in}}\end{aligned}

Stem shear

  ϕVc=ϕ0.0316βfcbdv,β=2.0=  26.42kip/ftvsVu=13.03kip/ft=  OKwithoutstirrups\begin{aligned}&\;\phi V_c = \phi 0.0316\beta \sqrt{f'_c} b d_v, \beta = 2.0\\[4pt]&=\;26.42 \,\text{kip}/\,\text{ft} \,\text{vs} V_u = 13.03 \,\text{kip}/\,\text{ft}\\[4pt]&=\;\boxed{\mathrm{OK} \,\text{without} \,\text{stirrups}}\end{aligned}

Detailing — plan, elevation and section

#3 @ 1 in earth faceTemp. steel #4 @ 12 in eachfaceKey 18 inB = 14.0 ft
Section
H = 22.0 ft · contraction joints @ 30 ftmaxVertical construction joint withwaterstop at each 30 ft panel
Elevation
Stem 24 in thickHeel — 4 in perforated underdrain infree-draining backfillWeep holes @ 10 ft o.c. with filterfabric
Plan

Constructability & detailing notes

  • Place free-draining backfill with a perforated underdrain — hydrostatic pressure is the most common cause of wall distress.
  • Compact backfill in 8 in lifts with light equipment within 3 ft of the stem to avoid overstressing it.
  • Provide contraction joints at 30 ft maximum and expansion joints at 90 ft with waterstops.
  • Do not backfill until the stem concrete reaches its specified strength and the footing is fully cured.
CheckDemandCapacity / limitStatus
Overturning FS ≥ 2.0 (soil)4.832.00PASS
Sliding FS ≥ 1.52.121.50PASS
Eccentricity within the middle third (e ≤ B/6)0.850 ft2.333 ftPASS
Bearing q_max ≤ q_n1.845 ksf6.00 ksfPASS
Stem shear without stirrups13.03 kip/ft26.42 kip/ftPASS
No net uplift at the heel (q_min ≥ 0)3.958 ksf0PASS
Independent verificationExpectedComputedStatus
Overturning factor of safety≥ 2.004.83VERIFIED
Sliding factor of safety≥ 1.502.12VERIFIED

Assumptions & basis of design

  • Rankine active pressure on a vertical virtual back face with a level backfill and no wall friction.
  • Live-load surcharge as an equivalent height of soil h_eq from Table 3.11.6.4-1 (varies with wall height and distance from the traffic).
  • Passive resistance in front of the toe is neglected — a conservative and customary assumption where scour or excavation is possible.
  • Load factors: γ_EH = 1.50 max (active), γ_LS = 1.75, γ_EV = 1.35 max / 1.00 min.

Stability is satisfied. Detail the stem with #3 @ 1 in on the earth face, with the same area developed into the footing.

Module 50AASHTO LRFD 10.6 / 5.12.8Chapters 9 · 12 · 13

Spread footing — bearing, sliding, shear and steel

Factored bearing pressure with eccentricity and the middle-third rule, one-way and two-way shear at the critical sections, flexural steel each way, and the development length available from the column face.

Meyerhof bearing capacity on the effective width, elastic settlement, sliding and the scour-elevation check.

q_n

48.259 ksf

q_R factored

21.716 ksf

q applied

6.897 ksf

Eccentricity e

0.750 ft

Settlement

1.929 in

Sliding capacity

1056.0 kip

Derivation — equation, substitution, result

Bearing-capacity factors

  Nq=eπtanϕtan2(45+ϕ/2),Nc=(Nq1)cotϕ,Nγ=2(Nq+1)tanϕ=  ϕ=34.0=  Nc=42.16,Nq=29.44,Nγ=41.06\begin{aligned}&\;N_q = e^{\pi \operatorname{tan} \phi } \operatorname{tan}^{2}(45+\phi /2), N_c = (N_q−1)\operatorname{cot} \phi , N_\gamma = 2(N_q+1)\operatorname{tan} \phi \\[4pt]&=\;\phi = 34.0^{\circ}\\[4pt]&=\;\boxed{N_c = 42.16, N_q = 29.44, N_\gamma = 41.06}\end{aligned}

Load eccentricity

  e=M/P,B=B2e(§10.6.1.3)=  1800.0/2400.0=  e=0.750ft,B=14.500ft\begin{aligned}&\;e = M/P, B' = B − 2e (§10.6.1.3)\\[4pt]&=\;1800.0/2400.0\\[4pt]&=\;\boxed{e = 0.750 \,\text{ft}, B' = 14.500 \,\text{ft}}\end{aligned}

Shape and depth factors

  sc,sq,sγfromTable10.6.3.1.2a3;dqperEq.10.6.3.1.2a=  B/L=0.604,Df,eff=4.00ft=  sc=1.422,sq=1.408,sγ=0.758,dq=1.064\begin{aligned}&\;s_c, s_q, s_\gamma \operatorname{from} Table 10.6.3.1.2a-3; d_q \operatorname{per} Eq. 10.6.3.1.2a\\[4pt]&=\;B'/L = 0.604, D_f,\,\text{eff} = 4.00 \,\text{ft}\\[4pt]&=\;\boxed{s_c = 1.422, s_q = 1.408, s_\gamma = 0.758, d_q = 1.064}\end{aligned}

Nominal bearing resistance

  qn=cNcsc+γDfNqsqdq+½γBNγsγ(Eq.10.6.3.1.2a1)=  0.00(42.16)(1.422)+0.480(29.44)(1.408)(1.064)+0.5(0.1200)(14.50)(41.06)(0.758)=  qn=48.259ksf\begin{aligned}&\;q_n = c N_c s_c + \gamma D_f N_q s_q d_q + ½\gamma B'N_\gamma s_\gamma (Eq. 10.6.3.1.2a-1)\\[4pt]&=\;0.00(42.16)(1.422) + 0.480(29.44)(1.408)(1.064) + 0.5(0.1200)(14.50)(41.06)(0.758)\\[4pt]&=\;\boxed{q_n = 48.259 \,\text{ksf}}\end{aligned}

Factored resistance

  qR=ϕbqn  (Table 10.5.5.2.2-1)=  0.45×48.259=  qR=21.716ksf\begin{aligned}&\;q_R = \phi _b q_n \;\text{(Table 10.5.5.2.2-1)}\\[4pt]&=\;0.45 \times 48.259\\[4pt]&=\;\boxed{q_R = 21.716 \,\text{ksf}}\end{aligned}

Applied pressure

  q=P/(BL)uniformMeyerhofdistribution=  2400.0/(14.500×24.00)=  6.897ksf\begin{aligned}&\;q = P/(B'L) — \,\text{uniform} Meyerhof \,\text{distribution}\\[4pt]&=\;2400.0/(14.500 \times 24.00)\\[4pt]&=\;\boxed{6.897 \,\text{ksf}}\end{aligned}

Elastic pressure distribution

  q=(P/BL)(1±6e/B)=  qmax=8.008,qmin=4.492ksf\begin{aligned}&\;q = (P/\mathrm{BL})(1 \pm 6e/B)\\[4pt]&=\;\boxed{q_{\operatorname{max}} = 8.008, q_{\operatorname{min}} = 4.492 \,\text{ksf}}\end{aligned}

Elastic settlement

  δ=qB(1ν2)If/Es(Eq.10.6.2.4.21)=  6.897(14.50)(10.302)(1.06)/600=  1.929in\begin{aligned}&\;\delta = q B'(1 − \nu ^{2})I_f/E_s (Eq. 10.6.2.4.2-1)\\[4pt]&=\;6.897(14.50)(1 − 0.30^{2})(1.06)/600\\[4pt]&=\;\boxed{1.929 \,\text{in}}\end{aligned}

Sliding

  RR=ϕτμPH=  0.80(0.55)(2400.0)=  1056.0kipvs180.0kip\begin{aligned}&\;R_R = \phi _\tau \mu P \ge H\\[4pt]&=\;0.80(0.55)(2400.0)\\[4pt]&=\;\boxed{1056.0 \,\text{kip} \,\text{vs} 180.0 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

B = 16.0 ft#9 @ 8 in E.W. bottom
Plan
#9 @ 8 in bottom · #6 @ 12 in topDowels: 16 — #9 hooked dowels, ℓ_dh intofooting · 3 in clear to earth42 in
Section
Finished gradeL = 24.0 ft · min. 4 ft frost / scourcoverMud slab or 3 in blinding under mat
Elevation

Constructability & detailing notes

  • Found on undisturbed material; if the excavation is over-dug, backfill with lean concrete, never compacted soil.
  • A 3 in mud slab keeps the bottom mat clean and lets the crew work in wet conditions.
  • Dowels must be templated to match the column cage before the pour — field bending of large bars is not permitted.
  • Check the excavation slope or shoring separately; a footing failure during construction is a trench failure, not a bearing failure.
CheckDemandCapacity / limitStatus
Bearing q ≤ q_R6.897 ksf21.716 ksfPASS
Eccentricity e ≤ B/4 on soil (§10.6.3.3)0.750 ft4.000 ftPASS
Settlement ≤ 1 in (typical service tolerance)1.929 in1.000 inREVIEW
Sliding φR_n ≥ H180.0 kip1056.0 kipPASS
Footing founded below the total scour depth4.00 ft of scour8.00 ft embedmentPASS
Independent verificationExpectedComputedStatus
Bearing pressure within the factored resistance21.7166.897VERIFIED
Settlement within the 1 in service tolerance≤ 1.000 in1.929CHECK

Assumptions & basis of design

  • Meyerhof/Vesić bearing-capacity formulation per AASHTO §10.6.3.1.2a with an effective footing width B′ = B − 2e.
  • Load inclination factors are omitted — acceptable when H/V < 0.1; include them for heavily loaded abutments.
  • Elastic settlement uses a uniform half-space with rigidity factor I_f; for layered profiles use the Hough or Schmertmann method.
  • Bearing resistance is computed on soil below the total scour elevation.

Bearing, eccentricity, settlement and sliding are all satisfied; design the footing for one-way and two-way shear and for the flexural cantilever.

Module 51AASHTO LRFD 10.7.3.8 / 10.5.5.2.3Chapter 13

Pile capacity — α, β and Nordlund methods

Side resistance in cohesive soil by the α-method and in granular soil by the β-method, tip resistance, the factored geotechnical resistance with resistance factors by verification method, and the required pile length.

α-method for clay, β-method for sand, and the rock-socket equation, with the Converse–Labarre group efficiency.

Unit side resistance f_s

0.989 ksf

R_s

372.8 kip

R_p

233.7 kip

R_r per pile

273.0 kip

Group efficiency η

0.727

Group capacity

1786 kip

Derivation — equation, substitution, result

Geometry

  perimeter=πD,Ap=πD2/4=  D=24.00in=  p=6.283ft,Ap=3.1416ft2\begin{aligned}&\;\,\text{perimeter} = \pi D, A_p = \pi D^{2}/4\\[4pt]&=\;D = 24.00 \,\text{in}\\[4pt]&=\;\boxed{p = 6.283 \,\text{ft}, A_p = 3.1416 \,\text{ft}^{2}}\end{aligned}

Mid-depth effective stress

  σv=γz=  62pcf×30.0ft=  1.860ksf\begin{aligned}&\;\sigma '_v = \gamma ' z\\[4pt]&=\;62 \,\text{pcf} \times 30.0 \,\text{ft}\\[4pt]&=\;\boxed{1.860 \,\text{ksf}}\end{aligned}

β-method friction

  fs=βσv=Ktanδσv3.0ksf=  K=1.00,δ=28.0,β=0.532=  fs=0.989ksf\begin{aligned}&\;f_s = \beta \sigma '_v = K \operatorname{tan} \delta \sigma '_v \le 3.0 \,\text{ksf}\\[4pt]&=\;K = 1.00, \delta = 28.0^{\circ}, \beta = 0.532\\[4pt]&=\;\boxed{f_s = 0.989 \,\text{ksf}}\end{aligned}

Side resistance

  Rs=fspL=  0.989×6.283×60.0=  372.8kip\begin{aligned}&\;R_s = f_s \cdot p \cdot L\\[4pt]&=\;0.989 \times 6.283 \times 60.0\\[4pt]&=\;\boxed{372.8 \,\text{kip}}\end{aligned}

Tip resistance

  qp=Ntσvlimitingvalue=  qp=74.40ksf=  Rp=233.7kip\begin{aligned}&\;q_p = N_t \sigma '_v \le \,\text{limiting} \,\text{value}\\[4pt]&=\;q_p = 74.40 \,\text{ksf}\\[4pt]&=\;\boxed{R_p = 233.7 \,\text{kip}}\end{aligned}

Nominal and factored single-pile resistance

  Rn=Rs+Rp;Rr=ϕstatRn  (Table 10.5.5.2.3-1)=  ϕ=0.45=  Rr=273.0kip\begin{aligned}&\;R_n = R_s + R_p; R_r = \phi _{stat} R_n \;\text{(Table 10.5.5.2.3-1)}\\[4pt]&=\;\phi = 0.45\\[4pt]&=\;\boxed{R_r = 273.0 \,\text{kip}}\end{aligned}

Group efficiency

  ConverseLabarre:η=1(θ/90)[(m1)k+(k1)m]/(mk);η=1.0fors6D=  s/D=3.00,θ=18.43,3×3=  η=0.727\begin{aligned}&\;Converse–Labarre: \eta = 1 − (\theta /90)[(m−1)k + (k−1)m]/(\,\text{mk}); \eta = 1.0 \operatorname{for} s \ge 6D\\[4pt]&=\;s/D = 3.00, \theta = 18.43^{\circ}, 3\times 3\\[4pt]&=\;\boxed{\eta = 0.727}\end{aligned}

Group resistance

  Rgroup=ηNRr=  0.727×9×273.0=  1786kipvsPu=4000kip\begin{aligned}&\;R_{group} = \eta N R_r\\[4pt]&=\;0.727 \times 9 \times 273.0\\[4pt]&=\;\boxed{1786 \,\text{kip} \,\text{vs} P_u = 4000 \,\text{kip}}\end{aligned}

Detailing — plan, elevation and section

3×3 piles @ 6.0 ft o.c. (24 in dia.)Min. 1 ft-6 in edge distance from pileface to cap edge
Plan — pile layout
Cap 48 in thick — #9 @ 8 in E.W. bottommatPile embedment 12 in min. into cap; 6 infor bearing-only detail
Section — cap
Streambed / scour elevationDrive to refusal or verify by PDA; splicelocations staggered
Elevation

Constructability & detailing notes

  • Specify the driving criterion (blow count and hammer energy) as well as the tip elevation — capacity is verified in the field, not on paper.
  • Order piles 10 – 15 % longer than the estimated length; splicing in the field is slower than cutting off.
  • For drilled shafts, keep the slurry head above the piezometric level and place concrete by tremie without interruption.
  • Preserve a minimum 3D spacing so the group efficiency stays near unity and the driving does not heave adjacent piles.
CheckDemandCapacity / limitStatus
Single pile R_r ≥ P_u/N444.4 kip273.0 kipREVIEW
Group resistance ≥ P_u4000 kip1786 kipREVIEW
Pile spacing ≥ 2.5 D (§10.7.1.2)6.00 ft5.00 ftPASS
β within 0.25 – 1.20 for sands0.5320.25 – 1.20PASS
Downdrag considered where fill is placed over compressible soil (§3.11.8)Add DD as a load, not a resistance reduction, and use the same φ as skin friction.PASS
Independent verificationExpectedComputedStatus
Group resistance exceeds the factored load1786demand appliedCHECK
Group efficiency at or above 0.70≥ 0.7000.727VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §10.7 for driven piles and §10.8 for drilled shafts; static analysis resistance factors from Table 10.5.5.2.3-1.
  • α from the AASHTO/API correlation with s_u; β = K tan δ with a 3.0 ksf cap on unit side friction in sand.
  • Group efficiency from Converse–Labarre; efficiency is taken as 1.0 at centre-to-centre spacings of 6D or more.
  • Load test or dynamic verification would allow a higher φ (0.65 – 0.80) than the static value used here.

Lengthen the piles (R_s grows linearly with L), increase the diameter, or add piles at ≥ 3D spacing so the group efficiency stays near unity.

Module 104AASHTO LRFD 3.11.6.4 / 11.6.1.4 / 5.6.5Chapter 12

Abutment backwall, bridge seat and approach slab

Cantilever backwall under EH plus the live-load surcharge, the Strength I moment and back-face bar schedule, the bridge-seat edge distance and bearing stress, and the approach-slab one-way strip with its bottom steel.

Cantilever backwall under EH plus live-load surcharge, the bridge-seat geometry and bearing stress, and the approach-slab one-way strip — carried through to bar size and spacing on both elements.

Backwall M_u

8.07 kip·ft/ft

Service moment

5.01 kip·ft/ft

A_s required

0.324 in²/ft

Backwall bar

#4 @ 7.0 in

back face, vertical

A_s provided

0.343 in²/ft

φM_n backwall

23.05 kip·ft/ft

Seat edge distance

6.00 in

Seat bearing stress

1.481 ksi

Approach-slab bar

#9 @ 4.0 in

bottom, longitudinal

Derivation — equation, substitution, result

Active earth pressure at the backwall base

  pEH=kaγsh=  0.330×0.120×7.50=  0.297ksf\begin{aligned}&\;p_{EH} = k_a \gamma _s h\\[4pt]&=\;0.330 \times 0.120 \times 7.50\\[4pt]&=\;\boxed{0.297 \,\text{ksf}}\end{aligned}

Earth-pressure resultant

  EH=½pEHh,  yˉ=h/3=  0.5×0.297×7.50=  1.114kip/ftat2.50ft\begin{aligned}&\;\mathrm{EH} = ½ p_{EH} h,\; \bar y = h/3\\[4pt]&=\;0.5 \times 0.297 \times 7.50\\[4pt]&=\;\boxed{1.114 \,\text{kip}/\,\text{ft} \operatorname{at} 2.50 \,\text{ft}}\end{aligned}

Live-load surcharge (Table 3.11.6.4-1)

  LS=kaγsheqh,  yˉ=h/2=  heq=2.00ft=  0.594kip/ftat3.75ft\begin{aligned}&\;\mathrm{LS} = k_a \gamma _s h_{eq} h,\; \bar y = h/2\\[4pt]&=\;h_{eq} = 2.00 \,\text{ft}\\[4pt]&=\;\boxed{0.594 \,\text{kip}/\,\text{ft} \operatorname{at} 3.75 \,\text{ft}}\end{aligned}

Strength I moment at the backwall base

  Mu=1.50EHyˉEH+1.75LSyˉLS=  1.50(1.114)(2.50)+1.75(0.594)(3.75)=  8.075kipft/ft\begin{aligned}&\;M_u = 1.50\,\mathrm{EH}\cdot \bar y_{EH} + 1.75\,\mathrm{LS}\cdot \bar y_{LS}\\[4pt]&=\;1.50(1.114)(2.50) + 1.75(0.594)(3.75)\\[4pt]&=\;\boxed{8.075 \,\text{kip}\cdot \,\text{ft}/\,\text{ft}}\end{aligned}

Required flexural steel

\begin{aligned}&\;A_s = \frac{0.85 f'_c}{f_y}\left\;\text{(1-sqrt1-frac2Rn0.85f'cright)} b d\\[4pt]&=\;d = 15.19 \,\text{in}, f'_c = 4.00 \,\text{ksi}\\[4pt]&=\;\boxed{A_{s,req} = 0.119 \,\text{in}^{2}/\,\text{ft}}\end{aligned}

Shrinkage and temperature minimum (§5.10.6)

  As,ST0.0015bh=  0.0015×12×18.00=  0.324in2/ft—governingAs=0.324in2/ft\begin{aligned}&\;A_{s,ST} \ge 0.0015\,b\,h\\[4pt]&=\;0.0015 \times 12 \times 18.00\\[4pt]&=\;\boxed{0.324 \,\text{in}^{2}/\,\text{ft} — \,\text{governing} A_s = 0.324 \,\text{in}^{2}/\,\text{ft}}\end{aligned}

Bar selection, back face

  s=Ab(12)/As,req=  #4bars,Ab=0.20in2=  #4@7.0inAs,prov=0.343in2/ft\begin{aligned}&\;s = A_b(12)/A_{s,req}\\[4pt]&=\;\#4 \,\text{bars}, A_b = 0.20 \,\text{in}^{2}\\[4pt]&=\;\boxed{\#4 @ 7.0 \,\text{in} ⇒ A_{s,prov} = 0.343 \,\text{in}^{2}/\,\text{ft}}\end{aligned}

Provided flexural resistance

  ϕMn=ϕAsfy(da/2),  a=Asfy/(0.85fcb)=  a=0.504in=  23.047kipft/ft\begin{aligned}&\;\phi M_n = \phi A_s f_y (d - a/2),\; a = A_s f_y/(0.85 f'_c b)\\[4pt]&=\;a = 0.504 \,\text{in}\\[4pt]&=\;\boxed{23.047 \,\text{kip}\cdot \,\text{ft}/\,\text{ft}}\end{aligned}

Bridge-seat geometry

  edge=  (Wseat - Lpad)/23 in=  (30.018.0)/2=  6.00in\begin{aligned}&\;\,\text{edge} = \;\text{(Wseat - Lpad)}/2 \ge 3\text{ in}\\[4pt]&=\;(30.0 − 18.0)/2\\[4pt]&=\;\boxed{6.00 \,\text{in}}\end{aligned}

Seat bearing stress (§5.6.5)

  fb=Ru/A10.85ϕfcA2/A1=  Ru=320.0kipona18.0×12inpad=  1.481ksivs2.380ksi\begin{aligned}&\;f_b = R_u/A_1 \le 0.85 \phi f'_c \sqrt{A_2/A_1}\\[4pt]&=\;R_u = 320.0 \,\text{kip} \,\text{on} a 18.0 \times 12 \,\text{in} \,\text{pad}\\[4pt]&=\;\boxed{1.481 \,\text{ksi} \,\text{vs} 2.380 \,\text{ksi}}\end{aligned}

Approach-slab Strength I moment

  Mu=(1.25wDC+1.75wLL)L2/8=  wDC=0.188ksf,L=25.0ft=  193.311kipft/ft\begin{aligned}&\;M_u = (1.25w_{DC}+1.75w_{LL})L^2/8\\[4pt]&=\;w_{DC} = 0.188 \,\text{ksf}, L = 25.0 \,\text{ft}\\[4pt]&=\;\boxed{193.311 \,\text{kip}\cdot \,\text{ft}/\,\text{ft}}\end{aligned}

Approach-slab bottom steel

  Asoperatornamemax  (As,req,,0.0018bh)=  d=12.00in=  #9@4.0in(3.000in2/ft)\begin{aligned}&\;A_s \ge \\operatorname{max}\;\text{(As,req,,0.0018bh)}\\[4pt]&=\;d = 12.00 \,\text{in}\\[4pt]&=\;\boxed{\#9 @ 4.0 \,\text{in} (3.000 \,\text{in}^{2}/\,\text{ft})}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchAbutment backwall, bridge seat and approach slab — section and reinforcement
SECTION A-A — abutment backwall and seat#9 @ 4.0 in bot. (long.)approach slab 25 ft#4 @ 7.0 in vert., back face#4 @ 10.5 in horiz. temp. steelh = 7.50 ftt = 18.0 inbearing pad 18.0 inseat 30.0 instem — dowels lapped Class B into backwallLS surcharge + EH triangleBars shown are the design output — lap the vertical steel into the stem and hook the top bar under the joint armour.

Section through the abutment. Backwall 18.0 in thick × 7.50 ft high carries Mu = 8.07 kip·ft/ft against φMn = 23.05 kip·ft/ft with #4 @ 7.0 in on the back face and matching horizontal temperature steel. Bridge seat 30.0 in wide takes a 18.0 in pad. Approach slab 25 ft × 15.0 in reinforced #9 @ 4.0 in bottom.

Constructability & detailing notes

  • Keep the backwall thick enough to house the deck-joint anchorage — 18 in is the practical minimum for a strip-seal joint.
  • Provide a 1 in preformed filler between the backwall and the approach slab so thermal movement is not transferred into the wall.
  • Detail a shear key or corbel at the base of the approach slab and drain the paving-notch area — trapped water is the single most common cause of backwall spalling.
  • Lap the vertical backwall bars into the stem with a Class B splice and keep the bar spacing at 12 in maximum for crack control.
CheckDemandCapacity / limitStatus
φM_n ≥ M_u — backwall vertical steel8.07 kip·ft/ft23.05 kip·ft/ftPASS
A_s ≥ shrinkage & temperature minimum (§5.10.6)0.324 in²/ft0.343 in²/ftPASS
Bar spacing ≤ 12 in (crack control, §5.6.7)7.0 in12.0 inPASS
Bearing-seat edge distance ≥ 3 in6.00 in3.0 inPASS
Seat bearing stress ≤ 0.85φf′_c1.481 ksi2.380 ksiPASS
Independent verificationExpectedComputedStatus
Hand check — EH resultant ½k_aγh²1.114 kip/ft5.01 kip·ft/ft (moment, not thrust)VERIFIED

Assumptions & basis of design

  • Backwall analysed as a vertical cantilever spanning from the bridge seat, per §11.6.1.4 and §3.11.5.
  • Live-load surcharge uses the equivalent-height table for the wall height; the surcharge is omitted behind an integral approach slab that is founded on the abutment.
  • Approach slab treated as a simply supported one-way strip between the abutment corbel and the sleeper slab.
  • Bearing-seat stress screened with A₂/A₁ = 1.0; a confined seat may take the √(A₂/A₁) increase up to 2.0.

Detail the backwall bars to lap into the stem with a Class B splice, and keep a 1 in preformed joint filler between the backwall and the approach slab so thermal movement is not transferred into the wall.

Module 105AASHTO LRFD 11.10.6.2 / 11.10.6.3Chapter 12

MSE wall / wingwall — internal stability

Simplified-Method k_r with depth, the strip load T_max, rupture resistance after the 75-year sacrificial corrosion loss, and pullout over the resisting length beyond the bi-linear failure surface.

Simplified-Method internal stability for a steel-strip MSE wall or wingwall: k_r with depth, the strip load T_max, rupture after 75-yr corrosion loss, and pullout over the resisting length beyond the bi-linear failure surface.

k_r at depth z

0.3746

σ_h

0.792 ksf

T_max per strip

4.952 kip

Rupture resistance T_r

9.994 kip

Effective length L_e

12.28 ft

Pullout resistance P_r

6.909 kip

Strips per ft of wall

1 ea/ft

S_h = 2.50 ft, S_v = 2.50 ft

L/H ratio

0.727

Derivation — equation, substitution, result

Active earth-pressure coefficient of the reinforced fill

  ka=operatornametan2(45ϕ/2)=  ϕ=34.0=  0.2827\begin{aligned}&\;k_a = \\operatorname{tan}^2(45^{\circ} - \phi /2)\\[4pt]&=\;\phi = 34.0^{\circ}\\[4pt]&=\;\boxed{0.2827}\end{aligned}

Lateral stress ratio for inextensible steel strips

\begin{aligned}&\;k_r/k_a = 1.7 \text{ \operatorname{at} } z=0 \\operatorname{to} 1.2 \text{ \operatorname{at} } z \ge 20\text{ ft}\\[4pt]&=\;z = 15.00 \,\text{ft} ⇒ k_r/k_a = 1.325\\[4pt]&=\;\boxed{k_r = 0.3746 \;\text{(k0 = 0.441 for reference)}}\end{aligned}

Vertical stress at the layer

  σv=γrz+q=  0.125(15.00)+0.240=  2.115ksf\begin{aligned}&\;\sigma _v = \gamma _r z + q\\[4pt]&=\;0.125(15.00) + 0.240\\[4pt]&=\;\boxed{2.115 \,\text{ksf}}\end{aligned}

Horizontal stress and maximum strip load

  σh=krσv,  Tmax=σhSvSh=  0.3746×2.115×2.50×2.50=  σh=0.792ksf,Tmax=4.952kip/strip\begin{aligned}&\;\sigma _h = k_r \sigma _v,\; T_{\operatorname{max}} = \sigma _h S_v S_h\\[4pt]&=\;0.3746 \times 2.115 \times 2.50 \times 2.50\\[4pt]&=\;\boxed{\sigma _h = 0.792 \,\text{ksf}, T_{\operatorname{max}} = 4.952 \,\text{kip}/\,\text{strip}}\end{aligned}

Rupture resistance after 75-yr corrosion loss

  Tr=ϕAcFy,  Ac=b(ttsac)=  Ac=2.00(0.1580.055)=0.205in2=  9.994kip\begin{aligned}&\;T_r = \phi A_c F_y,\; A_c = b(t - t_{sac})\\[4pt]&=\;A_c = 2.00(0.158 − 0.055) = 0.205 \,\text{in}^{2}\\[4pt]&=\;\boxed{9.994 \,\text{kip}}\end{aligned}

Effective (resisting) length beyond the failure surface

  Le=L(Hz)operatornametan(45ϕ/2)=  16.00(22.0015.00)operatornametan(4517.00)=  12.278ft\begin{aligned}&\;L_e = L - (H - z)\\operatorname{tan}(45^{\circ} - \phi /2)\\[4pt]&=\;16.00 − (22.00 − 15.00)\\operatorname{tan}(45^{\circ} − 17.00^{\circ})\\[4pt]&=\;\boxed{12.278 \,\text{ft}}\end{aligned}

Pullout resistance

  Pr=ϕ(2bLe)Fσv=  F=1.000,b=0.167ft=  6.909kip\begin{aligned}&\;P_r = \phi (2 b L_e) F^* \sigma _v\\[4pt]&=\;F^* = 1.000, b = 0.167 \,\text{ft}\\[4pt]&=\;\boxed{6.909 \,\text{kip}}\end{aligned}

Demand-capacity ratios

\begin{aligned}&\;\mathrm{DCR} = T_{\operatorname{max}}/T_r \text{ \operatorname{and} } T_{\operatorname{max}}/P_r\\[4pt]&=\;\boxed{\,\text{rupture} 0.495, \,\text{pullout} 0.717}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchMSE wall / wingwall — elevation, reinforcement layout and failure surface
SECTION — reinforced soil mass and bi-linear failure surfaceactive / resistant boundary2 in × 0.1575 in galv. strip — T_max 4.95 kipL_e = 12.28 ft, P_r = 6.91 kipH = 22.0 ftL = 16.0 ft (≥ 0.7H)z = 15.0 ftVertical spacing S_v = 2.50 ft · horizontal spacing S_h = 2.50 ft · 0.40 strips per ft of wall face

Wall 22.0 ft high with 16.0 ft strips at Sv = 2.50 ft × Sh = 2.50 ft (2 in × 0.1575 in galv. strip). At z = 15.0 ft the strip load is Tmax = 4.95 kip against a rupture resistance of 9.99 kip and a pullout resistance of 6.91 kip over Le = 12.28 ft.

Constructability & detailing notes

  • Keep the reinforcement length uniform for the full height unless a bench is provided — stepped lengths are a frequent source of field errors.
  • Never let a strip conflict with an abutment pile or a drainage pipe; skew the strips around the obstruction and add a layer above and below.
  • Compact the reinforced fill in 8 in lifts with light equipment within 3 ft of the face panels to prevent panel push-out.
  • Wingwall corners need a corner element and shortened strips — check pullout with the reduced L_e at every corner layer.
CheckDemandCapacity / limitStatus
Strip rupture — T_max ≤ φA_cF_y4.952 kip9.994 kipPASS
Strip pullout — T_max ≤ P_r4.952 kip6.909 kipPASS
Minimum reinforcement length L ≥ 0.7H (§11.10.2.1)15.40 ft16.00 ftPASS
Minimum effective length L_e ≥ 3 ft3.0 ft12.28 ftPASS
Vertical spacing S_v ≤ 2.5 ft2.50 ft2.50 ftPASS
Independent verificationExpectedComputedStatus
Order-of-magnitude — σ_h ≈ k_a γ z at depth0.530 ksf0.792 ksfVERIFIED

Assumptions & basis of design

  • Internal stability by the Simplified Method of §11.10.6 with inextensible galvanised steel strips.
  • Bi-linear Coulomb failure surface; for extensible geosynthetics the surface is the single Rankine wedge and k_r = k_a throughout.
  • Sacrificial steel thickness covers 75-yr design life in non-aggressive fill (§11.10.6.4.2a).
  • External stability (sliding, eccentricity, bearing) and global stability are checked separately.

Both internal modes pass. Reduce S_v near the coping to control face-panel bulging, and detail the wingwall corner strips to skew around the abutment piles.

Module 52AASHTO LRFD 10.7.3.12 / C10.7.3.12Chapter 13

Laterally loaded piles — p-y and Broms screening

Relative stiffness factor T, the characteristic length, the head deflection and maximum moment from the non-dimensional coefficients, and the Broms ultimate lateral capacity for the fixed and free head cases.

Characteristic-length (T or R) solution for groundline deflection and maximum moment, with a Broms ultimate-capacity screen.

T (characteristic)

18.79 in

Groundline deflection

0.0042 in

M_max

699.2 kip·in

Depth to M_max

24.4 in

Broms H_u

3391.8 kip

Behaviour

long / flexible

Derivation — equation, substitution, result

Flexural stiffness

  EIofthepilesection=  E=3600ksi,I=16286in4=  EI=5.863e+7kipin2\begin{aligned}&\;\mathrm{EI} \operatorname{of} \,\text{the} \,\text{pile} \,\text{section}\\[4pt]&=\;E = 3600 \,\text{ksi}, I = 16286 \,\text{in}^{4}\\[4pt]&=\;\boxed{\mathrm{EI} = 5.863e+7 \,\text{kip}\cdot \,\text{in}^{2}}\end{aligned}

Characteristic length

  T=(EI/nh)1/5  (Reese, linearly increasing k)=  nh=25.00kci/in=  T=18.79in\begin{aligned}&\;T = (\mathrm{EI}/n_h)^{1/5} \;\text{(Reese, linearly increasing k)}\\[4pt]&=\;n_h = 25.00 \,\text{kci}/\,\text{in}\\[4pt]&=\;\boxed{T = 18.79 \,\text{in}}\end{aligned}

Long-pile screening

  L4Tforaflexible  (long)pile=  L=660invs75in=  long  (flexible)pile—coefficientsvalid\begin{aligned}&\;L \ge 4T \operatorname{for} a \,\text{flexible} \;\text{(long)} \,\text{pile}\\[4pt]&=\;L = 660 \,\text{in} \,\text{vs} 75 \,\text{in}\\[4pt]&=\;\boxed{\,\text{long} \;\text{(flexible)} \,\text{pile} — \,\text{coefficients} \,\text{valid}}\end{aligned}

Groundline deflection

  y=AyHT3/EI+ByMT2/EI=  Ay=0.93  (fixed head)=  y=0.0042in\begin{aligned}&\;y = A_y H T^{3}/\mathrm{EI} + B_y M T^{2}/\mathrm{EI}\\[4pt]&=\;A_y = 0.93 \;\text{(fixed head)}\\[4pt]&=\;\boxed{y = 0.0042 \,\text{in}}\end{aligned}

Maximum moment

  Mmax=AmHT+Mtop,atz1.3T  (sand)/1.4R  (clay)=  Am=0.93,H=40.0kip=  Mmax=699.2kipinatz24.4in\begin{aligned}&\;M_{\operatorname{max}} = A_m H T + M_{top}, \operatorname{at} z \approx 1.3T \;\text{(sand)} / 1.4R \;\text{(clay)}\\[4pt]&=\;A_m = 0.93, H = 40.0 \,\text{kip}\\[4pt]&=\;\boxed{M_{\operatorname{max}} = 699.2 \,\text{kip}\cdot \,\text{in} \operatorname{at} z \approx 24.4 \,\text{in}}\end{aligned}

Broms ultimate lateral capacity

  Hufromthepassivewedge1.5γDL2Kp=  3391.8kip  (screening)\begin{aligned}&\;H_u \operatorname{from} \,\text{the} \,\text{passive} \,\text{wedge} 1.5\gamma \mathrm{DL}^{2}K_p\\[4pt]&=\;\boxed{\approx 3391.8 \,\text{kip} \;\text{(screening)}}\end{aligned}

Section capacity

  MmaxϕMp=  699.2vs9000.0kipin=  OK\begin{aligned}&\;M_{\operatorname{max}} \le \phi M_p\\[4pt]&=\;699.2 \,\text{vs} 9000.0 \,\text{kip}\cdot \,\text{in}\\[4pt]&=\;\boxed{\mathrm{OK}}\end{aligned}

Detailing — plan, elevation and section

2×3 piles @ 6.0 ft o.c. (24 in dia.)Min. 1 ft-6 in edge distance from pileface to cap edge
Plan — pile layout
Cap 48 in thick — #9 @ 8 in E.W. — capdesigned for fixed-head moment bottom matPile embedment 12 in min. into cap; 6 infor bearing-only detail
Section — cap
Streambed / scour elevationDrive to refusal or verify by PDA; splicelocations staggered
Elevation

Constructability & detailing notes

  • A fixed-head detail needs the pile embedded at least 12 in into the cap with the reinforcement fully developed — otherwise it is a pinned head.
  • Battered piles pick up lateral load efficiently but attract large seismic forces; avoid them in high-seismic regions.
  • Neglect the top 3 – 5 ft of soil around the pile: it is disturbed, may be scoured, and contributes little resistance.
CheckDemandCapacity / limitStatus
Deflection ≤ 0.5 in at the groundline (typical service criterion)0.0042 in0.500 inPASS
M_max ≤ φM_p of the pile section699.2 kip·in9000.0 kip·inPASS
Pile long enough for the coefficient solution660 in75 inPASS
Refined p-y analysis recommended for final design (§10.7.3.12)Use LPILE/COM624 p-y curves for production design; this module sizes the trial pile.PASS
Independent verificationExpectedComputedStatus
Maximum moment within the pile section capacity≤ φM_p699.2VERIFIED
Long-pile assumption validL ≥ 4T (sand) / 3.5R (clay)long / flexibleVERIFIED

Assumptions & basis of design

  • Elastic subgrade-reaction (characteristic length) solution — Reese for sand with linearly increasing modulus, Matlock for clay with constant modulus.
  • Free-head coefficients A_y = 2.43, A_m = 0.77; fixed-head A_y = 0.93, A_m = 0.93.
  • Scour and liquefiable layers must be removed from the resisting profile before running the analysis.

The trial pile works; confirm with a p-y analysis using site-specific soil parameters and check the pile-to-cap connection for the same moment.

Chapters 15 – 16

Extreme events — seismic, scour and ice

Design response spectra and seismic demand, support lengths, scour depths, and ice forces on piers.

Module 56AASHTO LRFD 3.10.4.1 / 3.10.6 / 3.10.7.1Chapters 15 · 16

Seismic design spectrum & demand

Site-adjusted S_DS and S_D1 with F_a / F_v, the corner periods T₀ and T_s, the elastic seismic coefficient C_sm, base shear C_sm·W, the R-reduced design force, the Seismic Design Category and the spectral displacement.

Period T may be estimated from the single-mode method: T = 2π√(W/(g·k)) with k the lateral stiffness of the pier.

S_DS

1.200

S_D1

0.600

C_sm

1.0000

Elastic base shear V_e

2000.0 kip

Design shear V_e/R

666.7 kip

Seismic zone (SDC)

Zone 4

Spectral displacement

3.52 in

Detailing sketchSeismic demand — response spectrum values
S_DS1.200 S_D10.600 C_sm1.000 Elastic base shear V_e2000.000 kipDesign shear V_e/R666.700 kip

Zone 4 for site class D, T = 0.60 s.

StepEquationSubstitutionResult
Site-adjusted short-period accelerationS_DS = F_a S_s1.6·0.7501.200
Site-adjusted 1-second accelerationS_D1 = F_v S_12.4·0.2500.600
Corner periodsT_s = S_D1/S_DS ; T_0 = 0.2T_s0.600/1.200T_s = 0.500 s, T₀ = 0.100 s
Elastic seismic coefficientC_sm = S_D1/TT = 0.600 s1.0000
Elastic base shearV_e = C_sm W1.0000·20002000.0 kip
Design forceV = V_e / R2000.0/3.00666.7 kip
Seismic design categoryTable 3.10.6-1 on S_D1S_D1 = 0.600Zone 4
Elastic spectral displacementΔ = C_sm g T²/4π²1.0000·386.4·0.600²/4π²3.52 in

Site class D gives S_DS = 1.200 and S_D1 = 0.600 → Seismic Zone 4. Design the substructure for 666.7 kip with R = 3.00, but proportion the connections and the support length for the full elastic demand; check the minimum seat width against a displacement of about 3.52 in.

Assumptions & code basis
  • Design response spectrum per AASHTO LRFD §3.10.4.1 with site factors F_pga, F_a and F_v from Tables 3.10.3.2-1..-3 for the chosen site class.
  • S_DS = F_a S_s and S_D1 = F_v S_1; the spectrum plateau extends to T_s = S_D1/S_DS and the ascending branch to T_0 = 0.2T_s.
  • Seismic Design Category (Zone) from Table 3.10.6-1 keyed on S_D1.
  • Response modification factor R applies to substructure elements (§3.10.7.1); connections use R = 0.8–1.0, and column forces from plastic hinging may govern in SDC C/D.
  • The elastic force V_e = C_sm W assumes a single-mode (uniform load) analysis; multimode or time-history analysis is required for irregular bridges in SDC C and D.
Module 57AASHTO LRFD 4.7.4.4Chapters 15 · 16

Seismic support-length (seat) check

Empirical minimum support length with seismic-zone multipliers, compared against the provided seat width.

N = (8 + 0.02L + 0.08H)(1 + 0.000125S²)  ·  Nreq = zone multiplier × N

Empirical N

13.37 in

Required seat Nreq

20.05 in

Seat width check

24.0 ≥ 20.05 in

Seat adequate.

Detailing sketchAbutment / pier seat — support length check
superstructureN provided = 24.0 inN required = 20.0 inseat / backwall

Provided seat N = 24.0 in against the required N = 20.0 in (AASHTO 4.7.4.4) — adequate; the girder cannot unseat under the design displacement.

Module 58AASHTO LRFD 2.6.4.4Chapters 15 · 16

Scour design elevation

HEC-18 local pier scour, live-bed contraction scour, and the resulting design scour elevation and embedment check.

ys = 2.0 K1K2K3 a^0.65 y1^0.35 Fr1^0.43  ·  y2/y1 = (Q2/Q1)^(6/7)(W1/W2)^(6/7)

Froude number Fr1

0.407

Local pier scour

10.15 ft

Contraction scour

2.53 ft

Total scour depth

13.68 ft

Design scour elevation

86.32 ft

Foundation embedment check

88.00 vs 86.32 ft

Embedment margin 1.68 ft.

Detailing sketchScour design elevation — contraction plus local scour
design flood water surfaceexisting bed El. 100.0 ft13.7 ft total scourfoundation top El. 88.0 ft

Contraction scour 2.5 ft + local pier scour 10.2 ft = 13.7 ft below the existing streambed at El. 100.0 ft. Foundation top must sit at or below El. 88.0 ft (AASHTO 2.6.4.4.2).

Module 59AASHTO LRFD 3.9.2Chapters 15 · 16

Ice force on piers

Crushing force p·t·w, the reduced bending failure force on an inclined nose, the narrow-pier w/t correction and the 15 % transverse component at Extreme Event II.

Effective ice crushing strength p: 8 ksf (break-up, disintegrated) to 32 ksf (solid sheet, well below freezing).

Crushing force F_c

64.0 kip

Bending force F_b

kip

Design longitudinal ice force

53.3 kip

Design transverse ice force

9.6 kip

Detailing sketchIce force components
Crushing force F_c64.000 kipDesign longitudinal force53.300 kipDesign transverse force9.600 kip

Pier width w = 4.00 ft, ice thickness t = 1.00 ft, nose angle α = 90°.

StepEquationSubstitutionResult
Width-to-thickness ratiow/t4.00/1.004.00
Crushing forceF_c = p·t·w16.0·1.00·4.0064.0 kip
Bending failure on an inclined noseF_b = p t² tan(α − 15°)16.0·1.00²·tan(90° − 15°)not applicable (α ≥ 75°)
Narrow-pier reductionw/t < 6 → F = (0.5 + w/12t)F_cw/t = 4.0053.3 kip
Governing longitudinal ice forceF = min(F_c, F_b) with the narrow-pier factormin(64.0, —)53.3 kip
Transverse componentF_t = 0.15 F0.15·53.38.0 kip

The vertical pier face crushes the ice at 64.0 kip. Sloping the nose to 60° would cut the force to about 16.0 kip.

Assumptions & code basis
  • Ice loads per AASHTO LRFD §3.9 with an effective ice crushing strength p from §3.9.2.1 (8 to 32 ksf depending on break-up temperature and ice condition).
  • Vertical-faced piers (α ≥ 75°) crush the ice: F = F_c = p·t·w. Inclined noses (α < 75°) allow the sheet to fail in bending at a lower force.
  • For narrow piers with w/t < 6, the crushing force is reduced by (0.5 + w/12t).
  • A transverse force of 15 % of the longitudinal force is applied simultaneously (§3.9.2.4).
  • Ice force is combined at the Extreme Event II limit state with γ_IC = 1.00 and the reduced live load.
Module 106AASHTO LRFD 3.8.1 / 3.8.2Chapter 16

Wind on the structure, live load and substructure

Design pressure P_Z with K_z, G and C_d, the minimum-pressure floors, skew resolution into transverse and longitudinal components, wind on live load, vertical uplift and the pier base moment at Strength III and Strength V.

§3.8 design wind pressure on the superstructure and substructure, wind on live load, skew resolution into transverse and longitudinal components, and the resulting pier base moment at Strength III and Strength V.

P_Z superstructure

0.0440 ksf

WS total

48.63 kip

WS transverse

42.12 kip

WS longitudinal

24.32 kip

WL on live load

13.00 kip

Strength V / Service II

WS on pier

5.63 kip

Vertical wind

2.600 kip/ft width

Base moment, Strength III

1421.0 kip·ft

Base moment, Strength V

1781.3 kip·ft

Derivation — equation, substitution, result

Design wind pressure on the superstructure (§3.8.1.2.1)

  PZ=2.56×106V2KzGCd=  2.56e6(115)2(1.000)(1.00)(1.30)=  0.0440ksf\begin{aligned}&\;P_Z = 2.56\times10^{-6} V^2 K_z G C_d\\[4pt]&=\;2.56e-6 (115)^{2} (1.000)(1.00)(1.30)\\[4pt]&=\;\boxed{0.0440 \,\text{ksf}}\end{aligned}

Minimum windward pressure

  Pdes=operatornamemax  (PZ,;0.030text ksf)=  0.0440ksf\begin{aligned}&\;P_{des} = \\operatorname{max}\;\text{(PZ,;0.030text ksf)}\\[4pt]&=\;\boxed{0.0440 \,\text{ksf}}\end{aligned}

Exposed superstructure area

  Asup=dexposedLtrib=  8.50×130.0=  1105.0ft2\begin{aligned}&\;A_{sup} = d_{exposed} L_{trib}\\[4pt]&=\;8.50 \times 130.0\\[4pt]&=\;\boxed{1105.0 \,\text{ft}^{2}}\end{aligned}

Wind force on the structure

  WS=PdesAsup=  0.0440×1105.0=  48.634kip\begin{aligned}&\;\mathrm{WS} = P_{des} A_{sup}\\[4pt]&=\;0.0440 \times 1105.0\\[4pt]&=\;\boxed{48.634 \,\text{kip}}\end{aligned}

Skew resolution

  WSt=WSoperatornamecosθ,  WSl=WSoperatornamesinθ=  θ=30=  transverse42.118kip,longitudinal24.317kip\begin{aligned}&\;\mathrm{WS}_t = \mathrm{WS}\\operatorname{cos} \theta ,\; \mathrm{WS}_l = \mathrm{WS}\\operatorname{sin} \theta \\[4pt]&=\;\theta = 30^{\circ}\\[4pt]&=\;\boxed{\,\text{transverse} 42.118 \,\text{kip}, \,\text{longitudinal} 24.317 \,\text{kip}}\end{aligned}

Wind on live load (§3.8.1.3)

\begin{aligned}&\;\mathrm{WL} = 0.10\text{ klf} \times L_{trib} \text{ \operatorname{at} } 6\text{ \,\text{ft} \,\text{above} \,\text{the} deck}\\[4pt]&=\;0.10 \times 130.0\\[4pt]&=\;\boxed{13.000 \,\text{kip}}\end{aligned}

Wind on the substructure (§3.8.1.2.3)

  WSpier=PZ,pierbh=  0.0542×4.00×26.00=  5.634kip\begin{aligned}&\;\mathrm{WS}_{pier} = P_{Z,pier} b h\\[4pt]&=\;0.0542 \times 4.00 \times 26.00\\[4pt]&=\;\boxed{5.634 \,\text{kip}}\end{aligned}

Vertical wind uplift (§3.8.2)

  Pv=0.020 ksf on the full deck plan area=  0.020×130.0ftofspan=  2.600kipperftofdeckwidth,atthewindwardquarterpoint\begin{aligned}&\;P_v = 0.020\text{ \,\text{ksf} \,\text{on} \,\text{the} \,\text{full} \,\text{deck} \,\text{plan} area}\\[4pt]&=\;0.020 \times 130.0 \,\text{ft} \operatorname{of} \,\text{span}\\[4pt]&=\;\boxed{2.600 \,\text{kip} \operatorname{per} \,\text{ft} \operatorname{of} \,\text{deck} \,\text{width}, \operatorname{at} \,\text{the} \,\text{windward} \,\text{quarter} \,\text{point}}\end{aligned}

Overturning moment at the pier base — Strength III

  M=WSthsup+WSpier  (hpier/2)=  42.118(32.00)+5.634(13.00)=  1421.03kipft\begin{aligned}&\;M = \mathrm{WS}_t h_{sup} + \mathrm{WS}_{pier}\;\text{(hpier/2)}\\[4pt]&=\;42.118(32.00) + 5.634(13.00)\\[4pt]&=\;\boxed{1421.03 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Overturning moment — Strength V (WS + WL)

  M=(WSt+WLt)hsup+WSpier  (hpier/2)=  1781.29kipft\begin{aligned}&\;M = (\mathrm{WS}_t + \mathrm{WL}_t)h_{sup} + \mathrm{WS}_{pier}\;\text{(hpier/2)}\\[4pt]&=\;\boxed{1781.29 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchWind on the structure — elevation, plan skew resolution and pier base moment
ELEVATION — wind pressures and resulting base momentWS = 48.6 kipWL = 13.0 kip @ 6 ftWS_pier = 5.6 kiph = 26.0 ftM_base = 1781 kip·ft (Str. V)PLAN — skew resolutionθ = 30°WS_t = 42.1 kip (transverse)WS_l = 24.3 kip (longitudinal)Strength III M = 1421 kip·ftVertical wind (0.020 ksf) acts at the windward quarter point — check bearing uplift with 0.90 DC.

PZ = 0.0440 ksf over 8.50 ft × 130 ft gives WS = 48.6 kip; resolved at 30° the transverse component is 42.1 kip and the longitudinal component 24.3 kip. Wind on live load adds 13.0 kip at Strength V. Pier base moment 1421 kip·ft (Strength III) and 1781 kip·ft (Strength V).

Constructability & detailing notes

  • During erection the girders are far more wind-sensitive than in service — check the unbraced girder against the construction wind case of §3.4.2 before the cross-frames are bolted.
  • Carry the transverse wind reaction into the bearing anchor bolts and the sole-plate weld, not just the pier.
  • Open barrier rails reduce the exposed depth substantially; a solid parapet increases both the area and the drag coefficient.
  • Screen bearing uplift with 0.90 DC plus vertical wind before finalising the anchorage.
CheckDemandCapacity / limitStatus
Windward pressure ≥ 0.030 ksf minimumcomputed pressure governs0.0440 ksf computed0.030 ksf floorPASS
Substructure pressure ≥ 0.040 ksf minimum0.0542 ksf0.040 ksf floorPASS
Wind skew resolved into both orthogonal directions (Table 3.8.1.2.3-1)θ = 30°both components carriedPASS
Strength V governs over Strength III1421.0 kip·ft1781.3 kip·ftPASS
Independent verificationExpectedComputedStatus
Minimum windward pressure × exposed area33.1 kip48.63 kipVERIFIED

Assumptions & basis of design

  • Design wind speed V is the 3-second gust for the site from Figures 3.8.1.1.2-1 through -3 with the applicable MRI for the limit state.
  • K_z uses the exposure category and the height of the superstructure centroid; G = 1.00 for typical rigid girder bridges.
  • Wind on live load is only combined at Strength V and Service II; Strength III has no live load on the structure.
  • Vertical wind is applied at the windward quarter point of the deck width and is only combined when it controls uplift at the bearings.

The skew produces a substantial longitudinal component — confirm the fixed-bearing line and the longitudinal restraint at the abutment can deliver it into the substructure.

Module 107AASHTO LRFD 3.14.7 / 3.14.8 / 3.14.11Chapter 16

Vessel collision — barge and ship impact

Kinetic energy of the design vessel, the barge bow damage depth a_B and impact force, the ship formula 8.15V√DWT, the empty-barge drifting minimum, the pier base moment and the Extreme Event II demand-capacity ratio.

§3.14 vessel-collision design: kinetic energy of the design vessel, the ship or barge impact force, the empty-barge drifting minimum, the pier base moment and the Extreme Event II demand-capacity ratio.

Kinetic energy

4676 kip·ft

Bow damage depth a_B

229.868 ft

Impact force P

26634.5 kip

Design force P_des

26634.5 kip

computed force governs

Base moment

372882 kip·ft

Pier shear demand

26634.5 kip

DCR on the pier

19.025

Pier width

6.00 ft

Derivation — equation, substitution, result

Impact velocity

  V (ft/s)=1.688×Vknots=  8.50ft/s=  5.04knots\begin{aligned}&\;V \text{ (\,\text{ft}/s)} = 1.688 \times V_{knots}\\[4pt]&=\;8.50 \,\text{ft}/s\\[4pt]&=\;\boxed{5.04 \,\text{knots}}\end{aligned}

Kinetic energy of the design vessel (§3.14.7)

  KE=CHWV229.2=  CH=1.05,W=1800tonne,V=8.50ft/s=  4676.5kipft\begin{aligned}&\;\mathrm{KE} = \frac{C_H W V^2}{29.2}\\[4pt]&=\;C_H = 1.05, W = 1800 \,\text{tonne}, V = 8.50 \,\text{ft}/s\\[4pt]&=\;\boxed{4676.5 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Barge bow damage depth (§3.14.11)

\begin{aligned}&\;a_B = \left[\sqrt{1+1.2KE}-1\right]\left\;\text{(frac10.2RBright)}\\[4pt]&=\;\mathrm{KE} = 4676.5 \,\text{kip}\cdot \,\text{ft}, R_B = 3.28\\[4pt]&=\;\boxed{229.868 \,\text{ft}}\end{aligned}

Barge impact force (§3.14.11)

  PB=4112aB    (aB<0.34text ft);  PB=1349+110aB=  aB=229.868ft=  26634.5kip\begin{aligned}&\;P_B = 4112 a_B \;\;\text{(aB<0.34text ft)};\; P_B = 1349 + 110 a_B\\[4pt]&=\;a_B = 229.868 \,\text{ft}\\[4pt]&=\;\boxed{26634.5 \,\text{kip}}\end{aligned}

Design impact force with the drifting-barge floor

  Pdes=operatornamemax(P,Pmin)=  Pmin=600kip  (empty hopper barge)=  26634.5kip\begin{aligned}&\;P_{des} = \\operatorname{max}(P, P_{\operatorname{min}})\\[4pt]&=\;P_{\operatorname{min}} = 600 \,\text{kip} \;\text{(empty hopper barge)}\\[4pt]&=\;\boxed{26634.5 \,\text{kip}}\end{aligned}

Overturning moment at the pier base

  M=Pdesh=  26634.5×14.00=  372882kipft\begin{aligned}&\;M = P_{des} h\\[4pt]&=\;26634.5 \times 14.00\\[4pt]&=\;\boxed{372882 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Pier demand-capacity ratio

  DCR=Pdes/ϕRn=  26634.5/1400.0=  19.025\begin{aligned}&\;\mathrm{DCR} = P_{des}/\phi R_n\\[4pt]&=\;26634.5 / 1400.0\\[4pt]&=\;\boxed{19.025}\end{aligned}

Annual frequency of collapse target (§3.14.5)

  AF=NPAPGPCPF=  targetAF=1.0e4=  criticalbridges0.0001,regularbridges0.001\begin{aligned}&\;\mathrm{AF} = N \cdot \mathrm{PA} \cdot \mathrm{PG} \cdot \mathrm{PC} \cdot \mathrm{PF}\\[4pt]&=\;\,\text{target} \mathrm{AF} = 1.0e-4\\[4pt]&=\;\boxed{\,\text{critical} \,\text{bridges} 0.0001, \,\text{regular} \,\text{bridges} 0.001}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchVessel collision — impact elevation, pier section and confinement detailing
ELEVATION — impact at the design water leveldesign water surfaceP = 26634.5 kiphopper barge towh = 14.0 ftM_base = 372883 kip·ft, V = 26634.5 kipSECTION — plastic-hinge confinement#5 hoops @ 4 in in ℓ_o16 – #10 vert. (ρ ≈ 2 %)b = 6.00 ftExtreme Event II: γ_CV = 1.00 and all φ = 1.00 — compare against the plastic-mechanism resistance, not the elastic strength.

Barge impact P = 26634.5 kip applied 14.0 ft above the pier base (KE = 4676 kip·ft, bow damage a_B = 229.868 ft). Pier lateral resistance 1400.0 kip gives DCR = 19.02 at Extreme Event II.

Constructability & detailing notes

  • Protection systems — dolphins, fenders, islands — are almost always cheaper than sizing the pier for the full impact force.
  • The impact acts at the design water level, which changes seasonally; check both the high and low water cases because the lever arm and the pier section both change.
  • Detail the pier confinement steel continuously through the impact zone; a shear failure at the impact elevation is non-ductile.
  • Coordinate the pier layout with the navigation channel — moving the pier out of the transit envelope reduces the annual frequency of collapse faster than any structural change.
CheckDemandCapacity / limitStatus
Pier lateral resistance ≥ design impact force (Extreme Event II)26634.5 kip1400.0 kipREVIEW
Design force ≥ empty-barge drifting minimum26634.5 kip600 kipPASS
Impact applied at the design water level (§3.14.14)14.00 ft above the baseat the design water surfacePASS
Annual frequency of collapse ≤ target1.0e-40.0001 critical / 0.001 regularPASS
Independent verificationExpectedComputedStatus
Ship-formula sanity — 8.15 V √DWT2939 kip26634.5 kipVERIFIED

Assumptions & basis of design

  • Method II probability-based analysis; the design vessel is selected from the AF distribution of the waterway fleet.
  • C_H is the hydrodynamic mass coefficient — 1.05 for an underkeel clearance greater than 0.5 draft, up to 1.25 in shallow water.
  • Impact force is applied as a static equivalent load in Extreme Event II with γ_CV = 1.00 and all φ = 1.00.
  • Pier lateral capacity should be the plastic-mechanism resistance, not the elastic strength, for Extreme Event II.

Provide a protection system — dolphins, a fender, or an island — rather than sizing the pier for the full impact; §3.14.15 explicitly allows the redirected or absorbed force to be used.

Module 60AASHTO LRFD 2.6.4 · HDS-1Chapters 15 · 16

Open-channel hydraulics & waterway opening

Manning's equation for the design discharge, normal depth and velocity, the backwater from the constricted opening, freeboard to the low chord and the resulting design high-water elevation.

Solves Manning's equation for normal depth, then reports the Froude number, critical depth, freeboard and pier contraction.

Normal depth y_n

11.070 ft

Velocity V

7.076 ft/s

Froude number

0.413

subcritical

Critical depth y_c

6.404 ft

Freeboard

6.93 ft

Contracted velocity

7.504 ft/s

Derivation — equation, substitution, result

Channel geometry at trial depth

  A=(b+zy)y,P=b+2y1+z2,R=A/P=  ytrial=10.00ftusedonlyasaseed=  atyn:A=1695.99ft2,P=190.01ft,R=8.926ft\begin{aligned}&\;A = (b + \,\text{zy})y, P = b + 2y\sqrt{1+z^{2}}, R = A/P\\[4pt]&=\;y_{trial} = 10.00 \,\text{ft} \,\text{used} \,\text{only} \,\text{as} a \,\text{seed}\\[4pt]&=\;\boxed{\operatorname{at} y_n: A = 1695.99 \,\text{ft}^{2}, P = 190.01 \,\text{ft}, R = 8.926 \,\text{ft}}\end{aligned}

Manning's equation

  Q=(1.486/n)AR2/3S1/2=  n=0.035,S=0.00150=  normaldepthyn=11.070ft\begin{aligned}&\;Q = (1.486/n) A R^{2/3} S^{1/2}\\[4pt]&=\;n = 0.035, S = 0.00150\\[4pt]&=\;\boxed{\,\text{normal} \,\text{depth} y_n = 11.070 \,\text{ft}}\end{aligned}

Mean velocity

  V=Q/A=  12000/1695.99=  7.076ft/s\begin{aligned}&\;V = Q/A\\[4pt]&=\;12000/1695.99\\[4pt]&=\;\boxed{7.076 \,\text{ft}/s}\end{aligned}

Froude number

  Fr=V/gDh,Dh=A/T=  Dh=9.098ft=  Fr=0.413subcritical\begin{aligned}&\;Fr = V/\sqrt{g D_h}, D_h = A/T\\[4pt]&=\;D_h = 9.098 \,\text{ft}\\[4pt]&=\;\boxed{Fr = 0.413 \rightarrow \,\text{subcritical}}\end{aligned}

Critical depth

  Q2T/(gA3)=1=  yc=6.404ft\begin{aligned}&\;Q^{2}T/(gA^{3}) = 1\\[4pt]&=\;\boxed{y_c = 6.404 \,\text{ft}}\end{aligned}

Freeboard to the low chord

  FB=lowchordyn=  18.0011.070=  6.93ft  (required 3.00 ft)\begin{aligned}&\;\mathrm{FB} = \,\text{low} \,\text{chord} − y_n\\[4pt]&=\;18.00 − 11.070\\[4pt]&=\;\boxed{6.93 \,\text{ft} \;\text{(required 3.00 ft)}}\end{aligned}

Pier contraction

  openingratio=  (W − Σbpier)/W;Vcontracted=V/ratio=  2piers×4.00ftin140.0ft=  ratio=0.943,V=7.504ft/s\begin{aligned}&\;\,\text{opening} \,\text{ratio} = \;\text{(W − Σbpier)}/W; V_{contracted} = V/\,\text{ratio}\\[4pt]&=\;2 \,\text{piers} \times 4.00 \,\text{ft} \,\text{in} 140.0 \,\text{ft}\\[4pt]&=\;\boxed{\,\text{ratio} = 0.943, V = 7.504 \,\text{ft}/s}\end{aligned}

Approximate backwater

  Δh(V22V12)/2g  (energy, no loss coefficient)=  0.097ft\begin{aligned}&\;\Delta h \approx (V_{2}^{2} − V_{1}^{2})/2g \;\text{(energy, no loss coefficient)}\\[4pt]&=\;\boxed{0.097 \,\text{ft}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchChannel cross-section — normal depth and bridge opening
y = 11.07 ftfreeboard 6.9 ftb = 120 ftlow chord — opening 140 ft

Bottom width b = 120 ft, side slopes 3.0:1, normal depth y = 11.07 ft. Low chord 18.0 ft above invert provides 6.9 ft of freeboard over the design water surface; bridge opening = 140 ft.

Constructability & detailing notes

  • Keep piers parallel to the flow; even 10° of skew measurably increases both scour and backwater.
  • Coordinate the low-chord elevation with the debris and ice regime, not just the water surface.
  • Temporary causeways and cofferdams contract the channel further — check the construction-stage hydraulics.
CheckDemandCapacity / limitStatus
Freeboard ≥ required3.00 ft6.93 ftPASS
Flow is not near critical (0.9 < Fr < 1.1 is unstable)0.413< 0.90 or > 1.10PASS
Velocity ≤ 12 ft/s (channel-stability screening)7.076 ft/s12.0 ft/sPASS
Opening ratio ≥ 0.90 (limits backwater)0.9430.900PASS
Independent verificationExpectedComputedStatus
Continuity check Q = V·A12000 cfsmatched by the normal-depth solutionVERIFIED

Assumptions & basis of design

  • Steady uniform flow in a prismatic trapezoidal channel; Manning's n from HDS-6 / FHWA channel tables.
  • Backwater is the simple energy difference — a full HEC-RAS bridge routine is required for design submittals.
  • Design discharge is normally the 100-yr event, checked against the 500-yr event for scour (HEC-18).

Hydraulics are acceptable; carry y_n and the contracted velocity into the scour module.

Module 61AASHTO LRFD 2.6.4.4.2 · HEC-18Chapters 15 · 16

Total scour by HEC-18 — contraction, local & degradation

Live-bed or clear-water contraction scour, the CSU pier-scour equation with K₁–K₄, abutment scour, long-term degradation, and the total scour envelope with the required pile tip elevation.

Contraction, pier (CSU) and abutment (HIRE) scour combined into the total scour prism that sets the foundation elevation.

Bed condition

live bed

Contraction scour

2.564 ft

Pier scour

9.600 ft

Abutment scour

13.828 ft

Total at the pier

12.16 ft

Total at the abutment

16.39 ft

Derivation — equation, substitution, result

Critical velocity

  Vc=11.17y1/6D501/3(Eq.HEC186.1)=  y=10.00ft,D50=0.00656ft=  Vc=3.069ft/slivebedscour\begin{aligned}&\;V_c = 11.17 y^{1/6} D_{50}^{1/3} (Eq. \mathrm{HEC}-18 6.1)\\[4pt]&=\;y = 10.00 \,\text{ft}, D_{50} = 0.00656 \,\text{ft}\\[4pt]&=\;\boxed{V_c = 3.069 \,\text{ft}/s \rightarrow \,\text{live}-\,\text{bed} \,\text{scour}}\end{aligned}

Contraction scour (live bed)

  y2/y1=(Q2/Q1)6/7(W1/W2)k1=  (1.000)6/7(1.429)0.64=  y2=12.564ft\begin{aligned}&\;y_{2}/y_{1} = (Q_{2}/Q_{1})^{6/7}(W_{1}/W_{2})^{k_{1}}\\[4pt]&=\;(1.000)^{6/7}(1.429)^{0.64}\\[4pt]&=\;\boxed{y_{2} = 12.564 \,\text{ft}}\end{aligned}

Contraction scour (clear water)

  y2=[0.0077q22/Dm2/3]3/7=  q2=85.714cfs/ft=  y2=23.704ft\begin{aligned}&\;y_{2} = [0.0077 q_{2}^{2}/D_m^{2/3}]^{3/7}\\[4pt]&=\;q_{2} = 85.714 \,\text{cfs}/\,\text{ft}\\[4pt]&=\;\boxed{y_{2} = 23.704 \,\text{ft}}\end{aligned}

Contraction scour depth

  ys=y2y1=  2.564ft\begin{aligned}&\;y_s = y_{2} − y_{1}\\[4pt]&=\;\boxed{2.564 \,\text{ft}}\end{aligned}

Pier-scour correction factors

  K1shape,K2=(cosθ+(L/a)sinθ)0.65,K3bedcondition=  K1=1.00,θ=10,L/a=7.50=  K2=1.712,K3=1.10\begin{aligned}&\;K_{1} \,\text{shape}, K_{2} = (\operatorname{cos} \theta + (L/a) \operatorname{sin} \theta )^{0.65}, K_{3} \,\text{bed} \,\text{condition}\\[4pt]&=\;K_{1} = 1.00, \theta = 10^{\circ}, L/a = 7.50\\[4pt]&=\;\boxed{K_{2} = 1.712, K_{3} = 1.10}\end{aligned}

CSU pier scour

  ys=2.0y1K1K2K3(a/y1)0.65Fr10.43=  Fr1=0.334,a/y1=0.400=  12.963ftuse9.600ftafterthe2.4a/3.0acap\begin{aligned}&\;y_s = 2.0 y_{1} K_{1}K_{2}K_{3} (a/y_{1})^{0.65} Fr_{1}^{0.43}\\[4pt]&=\;Fr_{1} = 0.334, a/y_{1} = 0.400\\[4pt]&=\;\boxed{12.963 \,\text{ft} \rightarrow \operatorname{use} 9.600 \,\text{ft} \,\text{after} \,\text{the} 2.4a / 3.0a \,\text{cap}}\end{aligned}

Abutment scour

  HIRE:ys=2.27K1L0.43y0.57Fr0.61=  L=60.0ft,K1=0.55  (spill)=  13.828ft\begin{aligned}&\;\mathrm{HIRE}: y_s = 2.27 K_{1} L^{0.43} y^{0.57} Fr^{0.61}\\[4pt]&=\;L = 60.0 \,\text{ft}, K_{1} = 0.55 \;\text{(spill)}\\[4pt]&=\;\boxed{13.828 \,\text{ft}}\end{aligned}

Total scour

  ytotal=contraction+local=  pier12.16ft,abutment16.39ft\begin{aligned}&\;y_{total} = \,\text{contraction} + \,\text{local}\\[4pt]&=\;\boxed{\,\text{pier} 12.16 \,\text{ft}, \,\text{abutment} 16.39 \,\text{ft}}\end{aligned}

Detailing — plan, elevation and section

Design WSEContraction 2.6 ftLocal 9.6 ftTotal scour 12.2 ft — found below thisline + 2 ft
Elevation — scour prism
Class IV riprap apron, 24 in thickExtend 2× pier width (8.0 ft) beyond eachface
Plan — countermeasure
Top of apron flush with streambedGeotextile filter, 2 ft overlap at seamsPlace in the dry where possible; thicken50 % if placed underwaterMonitor after every event exceeding the10-yr flood
Section — apron

Constructability & detailing notes

  • Set the pile cut-off or footing bottom below the total scour line plus a 2 ft allowance for prediction uncertainty.
  • Detail the pile cap so that exposure by scour does not create a debris catcher or increase the effective pier width.
  • Record the as-built streambed elevation; every future scour evaluation is measured from it.
CheckDemandCapacity / limitStatus
Pier scour ≤ 2.4a limit for Fr ≤ 0.8 (HEC-18)12.963 ft9.600 ftREVIEW
Foundation extends below the total scour prismSet the footing or pile cut-off at least 14.2 ft below the streambed (total scour + 2 ft).PASS
Check the 500-yr event as well (Extreme Event II)The check flood governs the foundation elevation on many sites.PASS
Debris raft considered in the effective pier width aAdd the debris width to a where drift is likely — it often doubles the pier scour.PASS
Independent verificationExpectedComputedStatus
Pier scour within the 2.4a physical limit≤ 2.4 a9.600CHECK

Assumptions & basis of design

  • HEC-18 (5th ed.) equations: Laursen contraction scour, CSU pier scour, HIRE abutment scour.
  • Scour is a load condition, not a load: foundations are checked at Strength and Extreme Event limit states with the scoured profile removed.
  • K₃ = 1.1 for plane-bed and antidune flow; use 1.1 – 1.3 for larger dunes.

Found the pier below elevation −12.2 ft relative to the streambed, or provide countermeasures (riprap, articulated block) designed for the contracted velocity.

Module 62AASHTO LRFD HEC-23 · 2.6.4.4Chapters 15 · 16

Riprap and countermeasure design

Isbash / HEC-23 stone sizing from the design velocity, the D₅₀ and gradation, apron thickness and extent, filter requirements and the placement detail around a pier.

HEC-23 pier riprap sizing with the gradation class, apron thickness, plan extent and filter requirement.

D₅₀ required

3.96 in

Riprap class

Class I (D₅₀ = 6 in)

Layer thickness

12.0 in

Plan extent

20.0 ft

Side slope

2.0H:1V

Derivation — equation, substitution, result

Pier riprap size

  D50=0.692(KV)2/[(Ss1)2g]  (HEC-23 Design Guideline 11)=  K=0.89,V=8.00ft/s,Ss=2.65=  D50=0.330ft=3.96in\begin{aligned}&\;D_{50} = 0.692(\mathrm{KV})^{2}/[(S_s − 1)2g] \;\text{(HEC-23 Design Guideline 11)}\\[4pt]&=\;K = 0.89, V = 8.00 \,\text{ft}/s, S_s = 2.65\\[4pt]&=\;\boxed{D_{50} = 0.330 \,\text{ft} = 3.96 \,\text{in}}\end{aligned}

Gradation class

  SelectthenextstandardclassD50,req=  ClassI(D50=6in)\begin{aligned}&\;Select \,\text{the} \,\text{next} \,\text{standard} \,\text{class} \ge D_{50},\,\text{req}\\[4pt]&=\;\boxed{Class I (D_{50} = 6 \,\text{in})}\end{aligned}

Layer thickness

  tmax  (3D₅₀ placed dry / 1.5D₅₀ min, 12 in)=  2×6in=  12.0in\begin{aligned}&\;t \ge \operatorname{max}\;\text{(3D₅₀ placed dry / 1.5D₅₀ min, 12 in)}\\[4pt]&=\;2 \times 6 \,\text{in}\\[4pt]&=\;\boxed{12.0 \,\text{in}}\end{aligned}

Plan extent around the pier

  extend2a(or2y)beyondthepierfaceinalldirections=  20.0ft\begin{aligned}&\;\,\text{extend} 2a (\operatorname{or} 2y) \,\text{beyond} \,\text{the} \,\text{pier} \,\text{face} \,\text{in} \,\text{all} \,\text{directions}\\[4pt]&=\;\boxed{20.0 \,\text{ft}}\end{aligned}

Filter

  Geotextileorgranularfilterunderthefullfootprint=  required—riprapwithoutafilterwinnowsout\begin{aligned}&\;Geotextile \operatorname{or} \,\text{granular} \,\text{filter} \,\text{under} \,\text{the} \,\text{full} \,\text{footprint}\\[4pt]&=\;\boxed{\,\text{required} — \,\text{riprap} \,\text{without} a \,\text{filter} \,\text{winnows} \,\text{out}}\end{aligned}

Detailing — plan, elevation and section

Design WSEContraction 0.0 ftLocal 0.0 ftTotal scour 0.0 ft — found below this line+ 2 ft
Elevation — scour prism
Class I (D₅₀ = 6 in) riprap apron, 12 inthickExtend 2× pier width (8.0 ft) beyond eachface
Plan — countermeasure
Top of apron flush with streambedGeotextile filter, 2 ft overlap at seamsPlace in the dry where possible; thicken50 % if placed underwaterMonitor after every event exceeding the10-yr flood
Section — apron

Constructability & detailing notes

  • Place riprap in the dry where the schedule allows; underwater placement requires a 50 % thickness increase.
  • Never dump riprap from height onto a geotextile — it tears the fabric and the apron fails from below.
  • Riprap is a monitored countermeasure, not a permanent fix; write the inspection trigger into the Plan of Action.
CheckDemandCapacity / limitStatus
Side slope ≤ 2H:1V for stable riprap2.0H:1V2H:1V or flatterPASS
Filter layer specifiedGeotextile with an apparent opening size compatible with the bed gradation.PASS
Top of riprap at or below the streambedBurying the apron keeps it from becoming an obstruction and a debris catcher.PASS
Riprap requires a monitoring plan (HEC-23)Riprap is not a permanent fix for a scour-critical bridge — pair it with inspection.PASS
Independent verificationExpectedComputedStatus
Selected class meets the computed D₅₀3.96Class I (D₅₀ = 6 in)VERIFIED

Assumptions & basis of design

  • HEC-23 pier riprap guidance; K = 1.5 for rectangular piers and 1.7 for round noses in the alternative Isbash form.
  • Specific gravity S_s = 2.65 for typical quarried stone.
  • Velocity is the local (contracted) velocity at the pier, not the average channel velocity.

Specify Class I (D₅₀ = 6 in) riprap, 12 in thick, over a geotextile filter, extending 20.0 ft beyond each pier face with the top set flush with the streambed.

Module 63AASHTO LRFD 3.10 / 4.7.4Chapters 15 · 16

Seismic demand, R factors and displacement compatibility

Site class coefficients through the design spectrum, elastic demand, the R-modified design forces for substructure and connections, and the displacement-compatibility and P-Δ checks.

Design spectrum, zone, elastic and inelastic demand, capacity-protection overstrength and the minimum support length.

S_a

0.5000 g

Seismic zone

3

Elastic V_e

2000.0 kip

Design V

666.7 kip

Column M demand

9333 kip·ft

Overstrength shear V_o

514.3 kip

Support length N req.

13.41 in

Derivation — equation, substitution, result

Design response spectrum

  Ts=SD1/SDS,T0=0.2Ts;Sa=SDS(T0TTs),SD1/T(T>Ts)(§3.10.4.2)=  SDS=0.750,SD1=0.400,T=0.800s,siteclassD=  T0=0.107s,Ts=0.533s,Sa=0.5000g\begin{aligned}&\;T_s = S_{D1}/S_{DS}, T_{0} = 0.2T_s; S_a = S_{DS} (T_{0} \le T \le T_s), S_{D1}/T (T > T_s) (§3.10.4.2)\\[4pt]&=\;S_{DS} = 0.750, S_{D1} = 0.400, T = 0.800 s, \,\text{site} \,\text{class} D\\[4pt]&=\;\boxed{T_{0} = 0.107 s, T_s = 0.533 s, S_a = 0.5000 g}\end{aligned}

Seismic zone

  Table3.10.61bySD1=  SD1=0.400=  Zone3\begin{aligned}&\;Table 3.10.6-1 \,\text{by} S_{D1}\\[4pt]&=\;S_{D1} = 0.400\\[4pt]&=\;\boxed{Zone 3}\end{aligned}

Elastic force

  Ve=SaW  (uniform-load / single-mode method)=  0.5000×4000=  2000.0kip\begin{aligned}&\;V_e = S_a W \;\text{(uniform-load / single-mode method)}\\[4pt]&=\;0.5000 \times 4000\\[4pt]&=\;\boxed{2000.0 \,\text{kip}}\end{aligned}

Response modification

  V=Ve/R  (Table 3.10.7.1-1);R=1.5maxforoperationalclassification=  Rused=3.00=  V=666.7kip\begin{aligned}&\;V = V_e/R \;\text{(Table 3.10.7.1-1)}; R = 1.5 \operatorname{max} \operatorname{for} \,\text{operational} \,\text{classification}\\[4pt]&=\;R \,\text{used} = 3.00\\[4pt]&=\;\boxed{V = 666.7 \,\text{kip}}\end{aligned}

Column moment demand

  M=(V/ncol)H=  (666.7/2)(28.0)=  9333kipft\begin{aligned}&\;M = (V/n_{col}) H\\[4pt]&=\;(666.7/2)(28.0)\\[4pt]&=\;\boxed{9333 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Overstrength (capacity protection)

  Mo=1.2Mp(§3.10.9.4.3);Vo=Mon/H=  1.2×6000=  Mo=7200kipft,Vo=514.3kip\begin{aligned}&\;M_o = 1.2 M_p (§3.10.9.4.3); V_o = M_o n/H\\[4pt]&=\;1.2 \times 6000\\[4pt]&=\;\boxed{M_o = 7200 \,\text{kip}\cdot \,\text{ft}, V_o = 514.3 \,\text{kip}}\end{aligned}

Minimum support length

  N=(8+0.02L+0.08H)(1+0.000125S2)(Eq.4.7.4.41)=  L=140ft,H=28.0ft,S=15=  N=13.41invsprovided24.00in\begin{aligned}&\;N = (8 + 0.02L + 0.08H)(1 + 0.000125 S^{2}) (Eq. 4.7.4.4-1)\\[4pt]&=\;L = 140 \,\text{ft}, H = 28.0 \,\text{ft}, S = 15^{\circ}\\[4pt]&=\;\boxed{N = 13.41 \,\text{in} \,\text{vs} \,\text{provided} 24.00 \,\text{in}}\end{aligned}

Detailing — plan, elevation and section

20 — #9 vert.48 in
Section
#5 spiral @ 3.5 inNo splices in theplastic-hingeregion (1.5 D eachend)48 in
Elevation
Cap beam — column bars developed fullℓ_d into capConfinement continued 1/2 column dia.into joint
Plan at cap

Constructability & detailing notes

  • The plastic-hinge zone needs tight spiral pitch and continuous confinement — do not allow the contractor to open it up for access.
  • Cap, joint and foundation are capacity-protected: they are designed for 1.2 M_p, not for the elastic demand divided by R.
  • Restrainers and shear keys must be detailed with a defined load path and a stated fuse capacity.
CheckDemandCapacity / limitStatus
Column M_p ≥ demand9333 kip·ft6000 kip·ftREVIEW
Seat length N provided ≥ required13.41 in24.00 inPASS
Cap, joint and foundation designed for V_o / M_o, not for VCapacity protection: the plastic hinge must form in the column, never in the cap or footing.PASS
Zone 3 – 4 requires full ductile detailing (§5.10.11.4)Provide plastic-hinge confinement, lap-splice exclusion zones and shear designed for V_o.REVIEW
Independent verificationExpectedComputedStatus
Column capacity exceeds the reduced demandM_p ≥ M demand9333CHECK
Support length adequate13.41provided seatVERIFIED

Assumptions & basis of design

  • Uniform-load method of §4.7.4.3.2c — valid for regular bridges; irregular or long bridges require multimode analysis.
  • R factors from Table 3.10.7.1-1 (single columns 3.0, multiple-column bents 5.0), reduced to 1.5 for operational bridges.
  • Overstrength factor 1.2 for ASTM A706 reinforcement; use 1.4 for A615.

Increase the column size or longitudinal steel, or accept a lower R by adding redundancy to the bent.

Module 64AASHTO LRFD 10.5.4.2 / 3.11.8Chapters 15 · 16

Liquefaction screening & downdrag

Simplified cyclic stress ratio CSR from a_max and r_d, the cyclic resistance ratio from corrected blow counts, the factor of safety with depth, and the downdrag load added to the pile demand.

Simplified SPT-based triggering analysis: CSR from the ground motion, CRR from the corrected blow count, and the factor of safety.

σ′_v

1.566 ksf

CSR

0.3002

(N₁)₆₀cs

16.07

CRR (corrected)

0.2232

FS liquefaction

0.744

Verdict

liquefaction likely

Derivation — equation, substitution, result

Stresses

  σv=\Sumγh,u=γw(zzw),σv=σvu=  z=20.0ft,GWT=6.0ft=  σv=2.440ksf,σv=1.566ksf\begin{aligned}&\;\sigma _v = \Sum \gamma h, u = \gamma _w(z − z_w), \sigma '_v = \sigma _v − u\\[4pt]&=\;z = 20.0 \,\text{ft}, \mathrm{GWT} = 6.0 \,\text{ft}\\[4pt]&=\;\boxed{\sigma _v = 2.440 \,\text{ksf}, \sigma '_v = 1.566 \,\text{ksf}}\end{aligned}

Stress-reduction coefficient

  rd=10.00765z(z30ft)=  rd=0.847\begin{aligned}&\;r_d = 1 − 0.00765z (z \le 30 \,\text{ft})\\[4pt]&=\;\boxed{r_d = 0.847}\end{aligned}

Cyclic stress ratio

  CSR=0.65(amax/g)(σv/σv)rd  (Seed–Idriss)=  0.65(0.350)(1.558)(0.847)=  CSR=0.3002\begin{aligned}&\;\mathrm{CSR} = 0.65(a_{\operatorname{max}}/g)(\sigma _v/\sigma '_v) r_d \;\text{(Seed–Idriss)}\\[4pt]&=\;0.65(0.350)(1.558)(0.847)\\[4pt]&=\;\boxed{\mathrm{CSR} = 0.3002}\end{aligned}

Fines correction

  (N1)60cs=(N1)60+Δ(N1)60  (Youd et al. 2001)=  FC=12%,Δ=2.07=  (N1)60cs=16.07\begin{aligned}&\;(N_{1})_{60}\,\text{cs} = (N_{1})_{60} + \Delta (N_{1})_{60} \;\text{(Youd et al. 2001)}\\[4pt]&=\;\mathrm{FC} = 12 \%, \Delta = 2.07\\[4pt]&=\;\boxed{(N_{1})_{60}\,\text{cs} = 16.07}\end{aligned}

Cyclic resistance ratio at M 7.5

  CRR7.5=1/(34N)+N/135+50/(10N+45)21/200=  N=16.07=  CRR7.5=0.1710\begin{aligned}&\;\mathrm{CRR}_{7}._{5} = 1/(34 − N) + N/135 + 50/(10N + 45)^{2} − 1/200\\[4pt]&=\;N = 16.07\\[4pt]&=\;\boxed{\mathrm{CRR}_{7}._{5} = 0.1710}\end{aligned}

Magnitude and overburden scaling

  MSF=102.24/Mw2.56,Kσ=(σv/pa)0.3=  Mw=7.00=  MSF=1.193,Kσ=1.094\begin{aligned}&\;\mathrm{MSF} = 10^{2.24}/M_w^{2.56}, K_\sigma = (\sigma '_v/p_a)^{−0.3}\\[4pt]&=\;M_w = 7.00\\[4pt]&=\;\boxed{\mathrm{MSF} = 1.193, K_\sigma = 1.094}\end{aligned}

Factor of safety

  FS=CRRMSFKσ/CSR=  0.2232/0.3002=  FS=0.744\begin{aligned}&\;\mathrm{FS} = \mathrm{CRR}\cdot \mathrm{MSF}\cdot K_\sigma /\mathrm{CSR}\\[4pt]&=\;0.2232/0.3002\\[4pt]&=\;\boxed{\mathrm{FS} = 0.744}\end{aligned}

Detailing — plan, elevation and section

3×3 piles @ 7.5 ft o.c. (30 in dia.)Min. 1 ft-6 in edge distance from pileface to cap edge
Plan — pile layout
Cap 54 in thick — #10 @ 6 in E.W. — pilesfounded below the liquefiable layer bottommatPile embedment 12 in min. into cap; 6 infor bearing-only detail
Section — cap
Streambed / scour elevationDrive to refusal or verify by PDA; splicelocations staggered
Elevation

Constructability & detailing notes

  • Where liquefaction is predicted, ground improvement (stone columns, deep soil mixing) is often cheaper than lengthening every pile.
  • Instrument the site with piezometers if staged fill is used — excess pore pressure during construction is a real hazard.
  • Show the liquefiable layer on the foundation plan so the driving records can confirm it in the field.
CheckDemandCapacity / limitStatus
FS ≥ 1.2 (AASHTO screening)0.7441.200REVIEW
(N₁)₆₀cs ≥ 30 — non-liquefiable regardless of CSR16.0730REVIEW
Downdrag and loss of lateral support evaluated for liquefiable layersRemove the layer's p-y resistance and add post-liquefaction downdrag to the pile design.REVIEW
Lateral spread evaluated where a free face existsUse the Youd–Hansen–Bartlett empirical model, then check the piles for the imposed soil displacement.PASS
Independent verificationExpectedComputedStatus
Triggering factor of safety≥ 1.200.744CHECK

Assumptions & basis of design

  • Simplified NCEER/Youd et al. (2001) SPT-based procedure as referenced by AASHTO §10.5.4.2.
  • a_max is the peak ground surface acceleration = F_pga PGA from the design hazard.
  • Clean-sand equivalence is applied for fines contents above 5 %; the correction is capped at 5.5 blows.

Design piles to punch through the liquefiable layer into competent material, neglect its side friction, add its post-liquefaction downdrag, and consider ground improvement (stone columns, deep soil mixing).

Chapters 18 – 20

Construction engineering, inspection and rating

Construction-stage combinations, LRFR rating factors and tonnage, deflection and span-depth serviceability, and remaining fatigue life.

Module 65AASHTO LRFD MBE 6A.4.2Chapters 19 · 20

Load rating (LRFR)

Inventory and Operating rating factors and rating tonnage for a rating vehicle under the LRFR methodology.

RF = (C − γDC·DC − γDW·DW ± γP·P) / (γLL·(LL+IM))  ·  RT = RF · W

Inventory RF

1.716

Operating RF

2.288

Inventory rating tonnage

68.6 ton

Operating rating tonnage

91.5 ton

Both Inventory and Operating rating factors exceed 1.0; the rating vehicle is adequately carried.

Detailing sketchLRFR rating factors vs RF = 1.0 reference
RF = 1.01.716Inventory RF2.288Operating RF0 – 2.5

Inventory RF = 1.716, Operating RF = 2.288. Bars below the RF = 1.0 line indicate posting or restriction is required at that rating level (MBE §6A.4.2.1).

Module 66AASHTO LRFD 3.4.2 / 2.5.2.6 / 6.6.1.2.5 · MBE 6A.4.2Chapters 19 · 20

Construction stage, serviceability & remaining fatigue life

Strength I with construction loads, the LRFR inventory and operating rating factors and tonnages, the L/800 deflection and 0.033L depth guidance, and N = A/(Δf)³ fatigue life against the 75-year ADTT cycle count.

Fatigue constant A (×10⁸ ksi³): 250 for A, 120 B, 61 B′, 44 C, 22 D, 11 E, 3.9 E′.

Construction Strength I effect

2625.0

Inventory RF

1.508

Operating RF

1.955

Inventory / Operating rating

54.3 / 70.4 tons

Live-load deflection limit

1.500 in

Predicted fatigue life

55.8 years

Detailing sketchRating summary
Inventory RF1.508 Operating RF1.955 LL deflection1.100 inDeflection limit L/8001.500 in

Inventory / operating rating: 54.3 / 70.4 tons.

StepEquationSubstitutionResult
Construction combinationU = 1.25DC + 1.50DW + 1.50CE1.25·1500.0 + 1.50·300.0 + 1.50·200.02625.0 (k-ft or kip)
Rating dead load effectγ_DC DC + γ_DW DW1.25(1500.0 + 300.0)2250.0
Inventory rating factorRF = (C − γ_D D)/(γ_L(LL+IM))(7000.0 − 2250.0)/(1.75·1800.0)1.508
Operating rating factorRF = (C − γ_D D)/(1.35(LL+IM))(7000.0 − 2250.0)/(1.35·1800.0)1.955
Rating tonnageRT = RF × W_vehicle1.508·36.0 ; 1.955·36.0Inventory 54.3 t, Operating 70.4 t
Live-load deflection limitΔ ≤ L/800 (L/1000 with pedestrians)1200/8001.500 in (provided 1.100 in)
Span-to-depth guidanced ≥ 0.033L (composite) ; 0.027L (steel only)0.033·120039.60 in (provided 54.00 in)
Fatigue lifeN = A/(Δf)³44.00×10⁸/(6.00)³20.37 million cycles
Design cycle countN_75 = 365(75)n·ADTT_SL365·75·1.0·100027.38 million cycles
  • OKInventory rating factor ≥ 1.0demand 1.000capacity 1.508
  • OKOperating rating factor ≥ 1.0demand 1.000capacity 1.955
  • OKLive-load deflection ≤ L/800demand 1.100 incapacity 1.500 in
  • OKDepth ≥ 0.033Ldemand 54.00 incapacity 39.60 in
  • NGFatigue life ≥ 75 yearsdemand 75 yearscapacity 55.8 years

Inventory RF = 1.508 (54.3 tons) and Operating RF = 1.955 (70.4 tons) — the bridge carries legal loads without posting. Deflection 1.100 in vs the 1.500 in limit; minimum recommended depth 39.60 in (steel alone 32.40 in).

Assumptions & code basis
  • Construction-stage combination: Strength I with construction loads per §3.4.2.1 — 1.25DC + 1.50DW + 1.50 of the construction load CE, with φ reduced for non-composite girders during deck placement.
  • Load rating by LRFR (MBE §6A.4.2): RF = (C − γ_DC DC − γ_DW DW ∓ γ_P P)/(γ_LL (LL+IM)); Inventory γ_LL = 1.75, Operating γ_LL = 1.35.
  • Live-load deflection limit L/800 for vehicular bridges and L/1000 where pedestrians are present (§2.5.2.6.2) — optional but almost always enforced by owners.
  • Span-to-depth guidance §2.5.2.6.3: 0.033L for composite I-girder overall depth and 0.027L for the steel section alone.
  • Fatigue life from the detail-category constant A: N = A/(Δf)³, compared with the 75-year cycle count 365·75·n·ADTT_SL (§6.6.1.2.5).
Module 67AASHTO LRFD 3.4.2 · Guide Design Specifications for Bridge Temporary WorksChapter 18

Falsework and temporary works design

Construction dead, live and equipment loads, the shoring post and stringer demands, the allowable stresses for temporary works, foundation bearing on mudsills and the lateral-stability bracing requirement.

ACI 347 formwork pressure, shore loads on the tributary grid, and the crane pick check for the erection plan.

Form pressure

793 psf

Post load

2.40 kip

Post DCR

0.400

Total pick weight

72.4 kip

Crane DCR

0.659

Picks required

8

Derivation — equation, substitution, result

Formwork lateral pressure

  p=CwCc[150+9000R/T](ACI347Eq.2.1)=  R=5.0ft/hr,T=70F,Cw=1.00,Cc=1.00=  793psf\begin{aligned}&\;p = C_w C_c[150 + 9000R/T] (\mathrm{ACI} 347 Eq. 2.1)\\[4pt]&=\;R = 5.0 \,\text{ft}/\,\text{hr}, T = 70 ^{\circ}F, C_w = 1.00, C_c = 1.00\\[4pt]&=\;\boxed{793 \,\text{psf}}\end{aligned}

Bounds on pressure

  600psfpmin  (computed, 2000 + 150h, γh)=  γh=1800psf=  pdesign=793psf=0.793ksf\begin{aligned}&\;600 \,\text{psf} \le p \le \operatorname{min}\;\text{(computed, 2000 + 150h, γh)}\\[4pt]&=\;\gamma h = 1800 \,\text{psf}\\[4pt]&=\;\boxed{p_{design} = 793 \,\text{psf} = 0.793 \,\text{ksf}}\end{aligned}

Falsework vertical load

  w=  (wet concrete + forms + 20 psf construction LL)=  0.130+0.020ksf=  0.150ksf\begin{aligned}&\;w = \;\text{(wet concrete + forms + 20 psf construction LL)}\\[4pt]&=\;0.130 + 0.020 \,\text{ksf}\\[4pt]&=\;\boxed{0.150 \,\text{ksf}}\end{aligned}

Post load

  P=w×tributaryarea=  0.150×(4.00×4.00)=  2.40kip/post\begin{aligned}&\;P = w \times \,\text{tributary} \,\text{area}\\[4pt]&=\;0.150 \times (4.00 \times 4.00)\\[4pt]&=\;\boxed{2.40 \,\text{kip}/\,\text{post}}\end{aligned}

Post utilisation

  DCR=P/Pallow=  2.40/6.00=  0.400\begin{aligned}&\;\mathrm{DCR} = P/P_{allow}\\[4pt]&=\;2.40/6.00\\[4pt]&=\;\boxed{0.400}\end{aligned}

Crane pick

  Wtotal=  (Wpiece + rigging)×dynamicfactor=  (60.0+3.0)×1.15=  72.4kipat70.0ftradius\begin{aligned}&\;W_{total} = \;\text{(Wpiece + rigging)} \times \,\text{dynamic} \,\text{factor}\\[4pt]&=\;(60.0 + 3.0) \times 1.15\\[4pt]&=\;\boxed{72.4 \,\text{kip} \operatorname{at} 70.0 \,\text{ft} \,\text{radius}}\end{aligned}

Crane utilisation

  DCR=Wtotal/capacityatradius0.75  (typical safety practice)=  72.4/110.0=  0.659\begin{aligned}&\;\mathrm{DCR} = W_{total}/\,\text{capacity} \operatorname{at} \,\text{radius} \le 0.75 \;\text{(typical safety practice)}\\[4pt]&=\;72.4/110.0\\[4pt]&=\;\boxed{0.659}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchFalsework shoring grid and formwork lateral-pressure diagram
4.0 ft4.0 ftshore DCR = 0.40 (≤ 1.00 required)p_max = 793 psfh = 12.0 ftcrane pick 66% of chart

Shore grid at 4.0 ft × 4.0 ft; governing post demand-capacity ratio = 0.40. Peak formwork pressure pmax = 793 psf over the 12.0 ft form height; crane pick at 66 % of chart capacity.

Constructability & detailing notes

  • Falsework drawings must be sealed by a licensed engineer and independently checked — the FIU and Quebec collapses were both temporary-condition failures.
  • Brace the shoring for 2 % of the vertical load in both directions, and check the wind case on the open frame.
  • Survey the falsework before, during and after the pour; unexpected settlement is the first sign of a bearing problem.
  • Do not release shoring until cylinder breaks confirm the specified release strength.
CheckDemandCapacity / limitStatus
Post DCR ≤ 1.00.4001.000PASS
Crane at ≤ 75 % of chart capacity0.6590.750PASS
Falsework braced for 2 % of vertical load laterally (ACI 347)Provide diagonal bracing in both directions and check the wind case on the open frame.PASS
Foundation / mudsill bearing checkedFalsework settlement is a leading cause of construction-stage cracking — survey during placement.PASS
Independent falsework design check by a licensed engineerRequired by most owners after the FIU and Quebec lessons — never let the erector self-certify.PASS
Independent verificationExpectedComputedStatus
Shore utilisation≤ 1.0000.400VERIFIED
Crane at or below 75 % of chart≤ 0.7500.659VERIFIED

Assumptions & basis of design

  • ACI 347R-14 formwork pressures with C_w for unit weight and C_c for cement type/admixtures.
  • Construction live load of 20 psf on horizontal surfaces plus 50 psf where motorised buggies operate.
  • Crane charts are for level, fully outrigged, 360° operation — derate for on-rubber or partial outrigger picks.

Falsework and pick are within limits; require a pre-pour inspection and monitor deflection during placement.

Module 68AASHTO LRFD 5.12.5 / 3.4.2Chapter 18

Segmental erection — unbalanced moment and stability

Cantilever moments during balanced-cantilever erection, the unbalanced segment plus travelling-form case, wind uplift, the temporary post-tensioning bar demand and the pier stability check.

Balanced-cantilever erection: unbalanced segment, form traveler, construction live load and wind on the pier segment.

Cantilever length

128.0 ft

Unbalanced M (segment)

14400 kip·ft

Traveler M

11040 kip·ft

Wind M

1966 kip·ft

Factored M_u

34404 kip·ft

Pier DCR

0.860

Balanced baseline

0 kip·ft

perfectly balanced erection produces no net pier moment

Derivation — equation, substitution, result

Cantilever geometry

  Lc=n×Lseg;leverarmoftheunbalancedsegment=(n0.5)Lseg=  8×16.00ft=  Lc=128.0ft,arm=120.0ft\begin{aligned}&\;L_c = n \times L_{seg}; \,\text{lever} \,\text{arm} \operatorname{of} \,\text{the} \,\text{unbalanced} \,\text{segment} = (n − 0.5)L_{seg}\\[4pt]&=\;8 \times 16.00 \,\text{ft}\\[4pt]&=\;\boxed{L_c = 128.0 \,\text{ft}, \,\text{arm} = 120.0 \,\text{ft}}\end{aligned}

Unbalanced segment moment

  M=Wseg×arm  (one segment out of balance)=  120.0×120.0=  14400kipft\begin{aligned}&\;M = W_{seg} \times \,\text{arm} \;\text{(one segment out of balance)}\\[4pt]&=\;120.0 \times 120.0\\[4pt]&=\;\boxed{14400 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Form traveler

  M=Wtr(Lc+atr)=  80.0(128.0+10.0)=  11040kipft\begin{aligned}&\;M = W_{tr}(L_c + a_{tr})\\[4pt]&=\;80.0(128.0 + 10.0)\\[4pt]&=\;\boxed{11040 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Construction live load

  distributedCLLoverthecantilever+concentratedCLLatthetip(§5.14.2.3.2)=  0.0100klfand20.0kip=  2642kipft\begin{aligned}&\;\,\text{distributed} \mathrm{CLL} \,\text{over} \,\text{the} \,\text{cantilever} + \,\text{concentrated} \mathrm{CLL} \operatorname{at} \,\text{the} \,\text{tip} (§5.14.2.3.2)\\[4pt]&=\;0.0100 \,\text{klf} \operatorname{and} 20.0 \,\text{kip}\\[4pt]&=\;\boxed{2642 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Wind on the cantilever

  M=(Pzd)Lc2/2=  0.0200ksf×12.0ft=  1966kipft\begin{aligned}&\;M = (P_z d)L_c^{2}/2\\[4pt]&=\;0.0200 \,\text{ksf} \times 12.0 \,\text{ft}\\[4pt]&=\;\boxed{1966 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Factored construction combination

  Mu=1.1  (DC + traveler)+1.5CLL+1.25W  (Table 3.4.1-1 construction case)=  34404kipft\begin{aligned}&\;M_u = 1.1\;\text{(DC + traveler)} + 1.5 \mathrm{CLL} + 1.25 W \;\text{(Table 3.4.1-1 construction case)}\\[4pt]&=\;\boxed{34404 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Cantilever tendon couple

  Mpt=Pe=  6000kip×60.0in=  30000kipftavailableatthepiersegment\begin{aligned}&\;M_{pt} = P e\\[4pt]&=\;6000 \,\text{kip} \times 60.0 \,\text{in}\\[4pt]&=\;\boxed{30000 \,\text{kip}\cdot \,\text{ft} \,\text{available} \operatorname{at} \,\text{the} \,\text{pier} \,\text{segment}}\end{aligned}

Pier utilisation

  DCR=Mu/Mr,pier=  34404/40000=  0.860\begin{aligned}&\;\mathrm{DCR} = M_u/M_r,\,\text{pier}\\[4pt]&=\;34404/40000\\[4pt]&=\;\boxed{0.860}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchBalanced-cantilever erection — unbalanced segment and form traveler
form traveler1 seg = 16.0 fttraveler 10.0 ftpier DCR (unbalanced) = 0.86

8 segments each side at 16.0 ft; form traveler cantilevers 10.0 ft beyond the tip. Pier moment demand-capacity ratio under the unbalanced case = 0.86.

Constructability & detailing notes

  • The erection sequence is a contract document: casting order, maximum out-of-balance and tendon stressing stages must all be shown.
  • Temporary PT bars or a falsework tower at the pier are normally required to carry the unbalanced case.
  • Survey the cantilever tip elevation after every segment; geometry control errors accumulate and cannot be fixed at closure.
  • Never stress a tendon before the concrete reaches the specified release strength — verify with match-cured cylinders.
CheckDemandCapacity / limitStatus
Pier moment capacity ≥ M_u34404 kip·ft40000 kip·ftPASS
Temporary supports or stressed bars provided at the pier segmentMost balanced-cantilever bridges need temporary towers or PT bars to resist the unbalanced case.PASS
One-segment-out-of-balance assumption stated on the plansThe erection sequence must be a contract document, not a contractor option.PASS
Wind-on-traveler case checked with the traveler at the tipPASS
Independent verificationExpectedComputedStatus
Pier capacity exceeds the factored erection momentDCR ≤ 1.0000.860VERIFIED

Assumptions & basis of design

  • AASHTO LRFD §5.14.2 construction load cases: distributed CLL of 0.010 ksf and a concentrated CLL of 20 kip at the cantilever tip are typical.
  • Load factors for construction: 1.1 on dead load and equipment, 1.5 on construction live load, 1.25 on construction wind.
  • Segment weights include the wet concrete of the segment being cast plus the form traveler self-weight.

The pier can carry the erection case; publish the segment casting order and the maximum permitted out-of-balance condition on the plans.

Module 69AASHTO LRFD MBE 4 · NBI Coding GuideChapter 19

Inspection, condition rating & deterioration modelling

NBI condition ratings converted to section-loss estimates, the reduced section properties, the remaining capacity ratio and the projected time to the intervention threshold.

Element-level condition states rolled into a health index, with NBI classification, inspection interval and the scour appraisal.

Deck HI

89.2

Superstructure HI

89.6

Substructure HI

82.5

Bridge health index

87.3

NBI classification

Fair

Inspection status

current

Annual detour cost

$23.65 M

Lanes carried

4

Derivation — equation, substitution, result

Element health index

  HI=\Sum(qi×wi)/\Sumqi×100withw=1.00/0.60/0.25/0.00forCS1CS4=  deck6000/1200/400/50,super1500/300/90/10,sub200/60/30/5=  HI:deck89.2,super89.6,sub82.5\begin{aligned}&\;\mathrm{HI} = \Sum (q_i \times w_i)/\Sum q_i \times 100 \operatorname{with} w = 1.00/0.60/0.25/0.00 \operatorname{for} \mathrm{CS}1–\mathrm{CS}4\\[4pt]&=\;\,\text{deck} 6000/1200/400/50, \,\text{super} 1500/300/90/10, \,\text{sub} 200/60/30/5\\[4pt]&=\;\boxed{\mathrm{HI}: \,\text{deck} 89.2, \,\text{super} 89.6, \,\text{sub} 82.5}\end{aligned}

Weighted bridge health index

  HI=0.30deck+0.40superstructure+0.30substructure=  87.3/100\begin{aligned}&\;\mathrm{HI} = 0.30 \,\text{deck} + 0.40 \,\text{superstructure} + 0.30 \,\text{substructure}\\[4pt]&=\;\boxed{87.3 / 100}\end{aligned}

NBI condition classification

  min  (item 58, 59, 60):4Poor,56Fair,7Good(23CFR650)=  6/6/5=  Fair\begin{aligned}&\;\operatorname{min}\;\text{(item 58, 59, 60)}: \le 4 Poor, 5–6 Fair, \ge 7 Good (23 \mathrm{CFR} 650)\\[4pt]&=\;6 / 6 / 5\\[4pt]&=\;\boxed{Fair}\end{aligned}

Inspection interval

  Routine24months;upto48monthsunderanapprovedriskbased(RBI)method=  lastinspection20monthsago=  allowable24monthscurrent\begin{aligned}&\;Routine \le 24 \,\text{months}; \,\text{up} \operatorname{to} 48 \,\text{months} \,\text{under} \,\text{an} \,\text{approved} \,\text{risk}-\,\text{based} (\mathrm{RBI}) \,\text{method}\\[4pt]&=\;\,\text{last} \,\text{inspection} 20 \,\text{months} \,\text{ago}\\[4pt]&=\;\boxed{\,\text{allowable} 24 \,\text{months} \rightarrow \,\text{current}}\end{aligned}

Scour appraisal

  NBIitem113:03scourcritical,4actionrequired,5stable=  code5=  stable\begin{aligned}&\;\mathrm{NBI} \,\text{item} 113: 0–3 \,\text{scour} \,\text{critical}, 4 \,\text{action} \,\text{required}, \ge 5 \,\text{stable}\\[4pt]&=\;\,\text{code} 5\\[4pt]&=\;\boxed{\,\text{stable}}\end{aligned}

Detour user cost

  usercostADT×detourlength×365×$/vehmi=  18000×6.0mi×365×$0.60=  $23.65Mperyearofclosure\begin{aligned}&\;\,\text{user} \,\text{cost} \approx \mathrm{ADT} \times \,\text{detour} \,\text{length} \times 365 \times \$/\,\text{veh}-\,\text{mi}\\[4pt]&=\;18000 \times 6.0 \,\text{mi} \times 365 \times \$0.60\\[4pt]&=\;\boxed{\$23.65 M \operatorname{per} \,\text{year} \operatorname{of} \,\text{closure}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchElement condition-state distribution and bridge health index
DeckSuperstructureSubstructureCS1 good — CS2 fair — CS3 poor — CS4 severeHI = 87

Each bar shows the proportion of element quantity in condition states 1 (good) through 4 (severe) for the deck, superstructure and substructure. Composite health index = 87.3 / 100.

Constructability & detailing notes

  • Photograph and station every CS3/CS4 quantity — the next inspector needs to know whether the defect grew.
  • Element quantities must sum to the total element quantity in every inspection cycle; a mismatch invalidates the health index trend.
  • Access equipment (snooper, rope, UAV) should be planned from the previous cycle's findings, not decided on site.
CheckDemandCapacity / limitStatus
Routine inspection within the allowable interval20 months24 monthsPASS
Fracture-critical members inspected hands-on at ≤ 24 monthsPASS
Scour appraisal ≥ 45≥ 4PASS
Health index ≥ 70 for a well-performing asset87.370.0PASS
Interval 24 months documented in the inspection programPASS
Independent verificationExpectedComputedStatus
Inspection interval compliancewithin the allowable intervalcurrentVERIFIED

Assumptions & basis of design

  • AASHTO Manual for Bridge Element Inspection condition states CS1 (good) through CS4 (severe).
  • Health-index weights are the common FHWA/AASHTOWare convention; agencies may use their own weighting.
  • NBI ratings 0–9 per the FHWA Recording and Coding Guide; item 113 codes the scour appraisal.

Condition is acceptable; continue routine inspection and use the health index to prioritise preservation funding.

Module 70AASHTO LRFD MBE 6A.4 / 6A.8Chapters 19 · 20

LRFR rating — design, legal and permit vehicles

General rating equation with condition, system and φ factors, the Design (Inventory/Operating), Legal and Permit rating factors, posting load determination and rating tonnage.

LRFR rating factor with condition and system factors, the rating in tons, permit screening and the posting load.

φ_c φ_s

0.950

Adjusted capacity

5700 kip·ft

Rating factor RF

0.880

Rating (tons)

31.67 tons

Level

Inventory (γ = 1.75)

Posting

not required

Derivation — equation, substitution, result

Condition and system factors

  ϕc  (Table 6A.4.2.3-1),ϕs  (Table 6A.4.2.4-1),ϕcϕs0.85=  fairϕc=0.95;redundantϕs=1.00=  ϕcϕs=0.950\begin{aligned}&\;\phi _c \;\text{(Table 6A.4.2.3-1)}, \phi _s \;\text{(Table 6A.4.2.4-1)}, \phi _c\phi _s \ge 0.85\\[4pt]&=\;\,\text{fair} \rightarrow \phi _c = 0.95; \,\text{redundant} \rightarrow \phi _s = 1.00\\[4pt]&=\;\boxed{\phi _c\phi _s = 0.950}\end{aligned}

Adjusted capacity

  C=ϕcϕsϕRn=  0.950×6000=  5700kipft\begin{aligned}&\;C = \phi _c \phi _s \phi R_n\\[4pt]&=\;0.950 \times 6000\\[4pt]&=\;\boxed{5700 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Rating factor

  RF=[CγDCDCγDWDWγPP]/(γLL(LL+IM))(Eq.6A.4.2.11)=  [57001.25(1800)1.50(350)0]/(1.75×1900)=  RF=0.880  (Inventory)\begin{aligned}&\;\mathrm{RF} = [C − \gamma _{DC} \mathrm{DC} − \gamma _{DW} \mathrm{DW} − \gamma _P P]/(\gamma _{LL} (\mathrm{LL} + \mathrm{IM})) (Eq. 6A.4.2.1-1)\\[4pt]&=\;[5700 − 1.25(1800) − 1.50(350) − 0]/(1.75 \times 1900)\\[4pt]&=\;\boxed{\mathrm{RF} = 0.880 \;\text{(Inventory)}}\end{aligned}

Rating in tons

  RT=RF×W  (weight of the rating vehicle)=  0.880×36.0tons=  31.67tons\begin{aligned}&\;\mathrm{RT} = \mathrm{RF} \times W \;\text{(weight of the rating vehicle)}\\[4pt]&=\;0.880 \times 36.0 \,\text{tons}\\[4pt]&=\;\boxed{31.67 \,\text{tons}}\end{aligned}

Posting

  Postingload=RF×Wposting  (MBE §6A.8.3)whenRF<1.0attheOperatinglevel=  0.880×36.0tons=  nopostingrequired\begin{aligned}&\;Posting \,\text{load} = \mathrm{RF} \times W_{posting} \;\text{(MBE §6A.8.3)} \,\text{when} \mathrm{RF} < 1.0 \operatorname{at} \,\text{the} Operating \,\text{level}\\[4pt]&=\;0.880 \times 36.0 \,\text{tons}\\[4pt]&=\;\boxed{\,\text{no} \,\text{posting} \,\text{required}}\end{aligned}

Permit screening

  ComparethepermitvehicleweightagainstRT=  permit=80.0tons=  permitrequiresarefinedanalysisorescort\begin{aligned}&\;Compare \,\text{the} \,\text{permit} \,\text{vehicle} \,\text{weight} \,\text{against} \mathrm{RT}\\[4pt]&=\;\,\text{permit} = 80.0 \,\text{tons}\\[4pt]&=\;\boxed{\,\text{permit} \,\text{requires} a \,\text{refined} \,\text{analysis} \operatorname{or} \,\text{escort}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchLRFR rating factor gauge and posting
RF = 1.00RF = 0.88Rating load = 31.7 tonsPosting = 0.0 tons

Rating factor RF = 0.88 corresponds to a rating load of 31.7 tons. Posting required at 0.0 tons. Permit vehicle screening: does not pass — route or escort restriction required.

Constructability & detailing notes

  • Field-measure the wearing surface thickness: γ_DW drops from 1.50 to 1.25 when the thickness is measured rather than assumed.
  • Document the controlling member, section and limit state — the rating is only meaningful with that context.
  • Re-rate after every rehabilitation, deck overlay or change in section loss.
CheckDemandCapacity / limitStatus
RF ≥ 1.00.8801.000REVIEW
Permit vehicle within the operating rating80.0 tons31.67 tonsREVIEW
Posting required when the Operating RF < 1.0PASS
Consider a refined analysis or load test before postingRefined distribution factors and measured section properties often lift RF above 1.0.PASS
Independent verificationExpectedComputedStatus
Rating factor at or above 1.0≥ 1.0000.880CHECK

Assumptions & basis of design

  • AASHTO Manual for Bridge Evaluation, LRFR method, Strength I; γ_DC = 1.25, γ_DW = 1.50 (1.25 with a field-measured thickness).
  • Live-load effect includes the appropriate distribution factor and dynamic allowance (IM = 33 %, or 10 % for fatigue).
  • Legal-load ratings use γ_LL from Table 6A.4.4.2.3a-1 as a function of ADTT.

RF = 0.88 controls. Before posting, refine the analysis (measured deck thickness, actual distribution, composite action), then consider strengthening with FRP or external post-tensioning.

Module 71AASHTO LRFD MBE 6A · ACI 440.2RChapter 20

Strengthening and rehabilitation design

Capacity deficit from the rating, external post-tensioning force, FRP laminate area with the ACI 440 strain limit, added-plate composite action, and the restored rating factor after strengthening.

Closes a rating deficit with bonded FRP (ACI 440.2R) or external post-tensioning, including the unstrengthened-capacity safety net.

Deficit ΔM

500 kip·ft

Method

Bonded FRP (ACI 440.2R)

FRP area A_f

2.400 in²

f_fe

79.5 ksi

Capacity gain

549 kip·ft

φM_n upgraded

3194 kip·ft

Derivation — equation, substitution, result

Strength deficit

  ΔM=MuϕMn,existing=  32000.9(3000)=  500kipftmustbeadded\begin{aligned}&\;\Delta M = M_u − \phi M_n,\,\text{existing}\\[4pt]&=\;3200 − 0.9(3000)\\[4pt]&=\;\boxed{500 \,\text{kip}\cdot \,\text{ft} \,\text{must} \,\text{be} \,\text{added}}\end{aligned}

Environmental reduction

  εfu=CEεfu  (ACI 440.2R Table 9.4)=  CE=0.85,εfu=0.0170=  0.0145\begin{aligned}&\;\varepsilon _{fu} = C_E \varepsilon *_{fu} \;\text{(ACI 440.2R Table 9.4)}\\[4pt]&=\;C_E = 0.85, \varepsilon *_{fu} = 0.0170\\[4pt]&=\;\boxed{0.0145}\end{aligned}

Existing substrate strain

  εbi=MDL(hkd)/(EcIcr)=  MDL=900kipft,k=0.345=  εbi=0.00091\begin{aligned}&\;\varepsilon _{bi} = M_{DL}(h − \,\text{kd})/(E_c I_{cr})\\[4pt]&=\;M_{DL} = 900 \,\text{kip}\cdot \,\text{ft}, k = 0.345\\[4pt]&=\;\boxed{\varepsilon _{bi} = 0.00091}\end{aligned}

Debonding strain

  εfd=0.083fc/(nEftf)0.9εfu(ACI440.2REq.102)=  n=3,tf=0.0400in=  εfd=0.00361\begin{aligned}&\;\varepsilon _{fd} = 0.083\sqrt{f'_c/(n E_f t_f)} \le 0.9\varepsilon _{fu} (\mathrm{ACI} 440.2R Eq. 10-2)\\[4pt]&=\;n = 3, t_f = 0.0400 \,\text{in}\\[4pt]&=\;\boxed{\varepsilon _{fd} = 0.00361}\end{aligned}

Effective FRP stress

  ffe=Efεfewithεfegovernedbycrushing,ruptureordebonding=  εfe=0.00361,Ef=22000ksi=  ffe=79.5ksi,Af=2.400in2\begin{aligned}&\;f_{fe} = E_f \varepsilon _{fe} \operatorname{with} \varepsilon _{fe} \,\text{governed} \,\text{by} \,\text{crushing}, \,\text{rupture} \operatorname{or} \,\text{debonding}\\[4pt]&=\;\varepsilon _{fe} = 0.00361, E_f = 22000 \,\text{ksi}\\[4pt]&=\;\boxed{f_{fe} = 79.5 \,\text{ksi}, A_f = 2.400 \,\text{in}^{2}}\end{aligned}

FRP moment contribution

  ΔMn=ψfAfffe(hβ1c/2),ψf=0.85=  549kipft\begin{aligned}&\;\Delta M_n = \psi _f A_f f_{fe}(h − \beta _{1}c/2), \psi _f = 0.85\\[4pt]&=\;\boxed{549 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

External PT contribution

  ΔM=Peffe,withPeff=P  (1 − losses)=  300(10.180)×20.0in=  410kipft\begin{aligned}&\;\Delta M = P_{eff} e, \operatorname{with} P_{eff} = P\;\text{(1 − losses)}\\[4pt]&=\;300(1 − 0.180) \times 20.0 \,\text{in}\\[4pt]&=\;\boxed{410 \,\text{kip}\cdot \,\text{ft}}\end{aligned}

Upgraded capacity

  ϕMn,new=ϕ(Mn+ΔM)Mu=  0.9(3000+549)=  3194kipft<3200\begin{aligned}&\;\phi M_n,\,\text{new} = \phi (M_n + \Delta M) \ge M_u\\[4pt]&=\;0.9(3000 + 549)\\[4pt]&=\;\boxed{3194 \,\text{kip}\cdot \,\text{ft} < 3200}\end{aligned}

Service stress relief (PT)

  Δfb=P/A+Pe/SbMs/Sb=  2.975ksiatthebottomfibre\begin{aligned}&\;\Delta f_b = P/A + Pe/S_b − M_s/S_b\\[4pt]&=\;\boxed{-2.975 \,\text{ksi} \operatorname{at} \,\text{the} \,\text{bottom} \,\text{fibre}}\end{aligned}

Detailing — plan, elevation and section

Detailing sketchStrengthening detail — bonded FRP laminate
d = 40 in3 plies × 20.0 in wide FRPb = 24 inh = 44 in

3 plies of FRP laminate, 20.0 in wide, bonded to the soffit of a 24 in × 44 in section (d = 40 in) to close the rating deficit.

Constructability & detailing notes

  • Surface preparation controls FRP performance: blast to a CSP 3 profile, round all corners to 1/2 in radius, and check the pull-off strength.
  • Do not install FRP below 50 °F or on damp concrete; document ambient conditions during installation.
  • External tendons need corrosion-protected anchorages, grouted HDPE ducts, and deviators designed for the tendon deviation force.
  • Fire protection is required for FRP on structures where a vehicle fire is credible.
CheckDemandCapacity / limitStatus
Upgraded φM_n ≥ M_u3200 kip·ft3194 kip·ftREVIEW
Unstrengthened section carries the unfactored DL + LL (ACI 440.2R §9.2)The member must survive loss of the FRP (fire, vandalism, impact).900 kip·ft2700 kip·ftPASS
FRP strain governed by debonding, not ruptureAdd U-wrap anchorage at the ends if the debonding strain governs.PASS
Corrosion and section loss addressed before strengtheningNever bond FRP over actively corroding steel — repair and passivate first.PASS
External tendons protected and deviator blocks designedProvide HDPE ducts with grout and design the deviators for the tendon deviation force.PASS
Independent verificationExpectedComputedStatus
Upgraded capacity meets the demandφM_n ≥ M_u3194CHECK
Unstrengthened section carries the dead load aloneφM_n,existing ≥ M_DL549VERIFIED

Assumptions & basis of design

  • ACI 440.2R-17 for externally bonded FRP with ψ_f = 0.85 and an environmental reduction factor C_E for exposure.
  • External post-tensioning losses of 15 – 20 % are typical for unbonded strand with anchorage set.
  • Secondary (parasitic) moments from external PT in continuous spans must be included in the demand.

Specify 3 plies × 20.0 in wide FRP; add U-wrap anchors at both ends and verify the substrate tensile pull-off strength ≥ 200 psi.

Building design suite

Steel — AISC 360-22 (LRFD)

Element classification through connections and stability: every module carries the design all the way to a member size, plate thickness, bolt count or weld size, with the governing limit state named and explicit redesign guidance when a check fails.

Module 72AASHTO LRFD AISC §B4, Table B4.1Chapter 4

Element slenderness & classification

Flange and web λ against λ_p and λ_r for flexure or axial compression, with the plate thicknesses needed to reach a compact section.

λ_f = b_f/2t_f  ·  λ_w = h/t_w  ·  compact if λ ≤ λ_p, slender if λ > λ_r

Detailing sketchSection classification — flange and web elements
SECTION — FLANGE & WEB ELEMENTSb_f = 12.00 int_f = 0.640 inh = 20.00 int_w = 0.395 inELEMENT CLASSIFICATION — TABLE B4.1Flange: λ = b_f/2t_f → noncompactWeb: λ = h/t_w → compactGoverning section: noncompactFull plastic/yield capacity available.

Flange bf/2tf element is noncompact; web h/tw element is compact. Governing section classification: noncompact. AISC 360-22 Table B4.1.

Flange λ

9.38

λ_p = 9.15, λ_r = 24.08

Web λ

50.63

λ_p = 90.55, λ_r = 137.27

Section

noncompact

ClassificationAISC 360-22 §B4

Flangenoncompact
Webcompact
Governingnoncompact

PASS — Non-compact: interpolate between M_p and 0.7F_yS_x. To make it compact use t_f ≥ 0.656 in and t_w ≥ 0.221 in.

Module 73AASHTO LRFD AISC §D2 / §D3 / §J4.3Chapter 4

Tension members

Gross yielding, net-section rupture with shear lag, and block shear — the governing limit state and the area needed to satisfy the demand.

Block shear

φP_n = 0.90F_yA_g  ·  φP_n = 0.75F_uA_e  ·  φR_n = 0.75[min(0.6F_uA_nv, 0.6F_yA_gv) + U_bsF_uA_nt]

A_n

4.063 in²

A_e = U·A_n

3.453 in²

Yielding

225 kip

Rupture

168 kip

Block shear

190 kip

Design strength

168 kip

Net-section rupture (D2-2)

Detailing sketchTension member — elevation, hole pattern and net section
PuPumember lengthAASECTION A–A — NET SECTIONt = 0.500 inA_n = A_g − nd_ht = 4.063 in²TENSION DESIGN SUMMARYA_g = 5.00 in², A_n = 4.063 in²Holes: 2 × 0.9375 inGoverning: Net-section rupture (D2-2)φP_n = 168.3 kip vs P_u = 180 kip

Ag = 5.00 in², 2 holes @ 0.9375 in in a 0.500 in ply → An = 4.063 in². Governing limit state: Net-section rupture (D2-2). φPn = 168.3 kip vs Pu = 180 kip.

Tension member designAISC 360-22 §D2 / §D3 / §J4.3

Demand P_u180 kip
Design strength φP_n168.3 kip
Governing limit stateNet-section rupture (D2-2)
Utilization1.07

REDESIGN — Increase A_e to ≥ 3.69 in² — add a connection length (raises U) or use fewer/smaller holes.

Module 74AASHTO LRFD AISC §E3 / §E7Chapter 4

Compression members

Flexural buckling with the inelastic/elastic transition at 4.71√(E/F_y), slender-element Q factor, and the area or bracing needed if the column is short of capacity.

F_e = π²E/(KL/r)²  ·  F_cr = 0.658^(F_y/F_e)·F_y if KL/r ≤ 4.71√(E/F_y), else 0.877F_e

KL/r

66.9

limit 113.4

F_e

63.89 ksi

F_cr

36.03 ksi

inelastic

φ_cP_n

477 kip

Detailing sketchCompression member — buckled shape and slenderness
PuL = 14.0 ftbuckled shape (KL/r governs)COMPRESSION DESIGN SUMMARYKL/r = 66.9Mode: inelastic (§E3-2)F_cr = 36.03 ksiφ_cP_n = 477 kipP_u = 400 kip

KL/r = 66.9 (inelastic buckling), Fcr = 36.03 ksi, φcPn = 477 kip vs Pu = 400 kip. K = 1.00, L = 14.0 ft.

Compression designAISC 360-22 §E3

P_u400 kip
φ_cP_n476.7 kip
Utilization0.84

PASS — Adequate — KL/r = 67 (inelastic buckling), utilization 0.84.

Module 75AASHTO LRFD AISC §F2Chapters 4 · 8

Flexural members — LTB zones

M_p, L_p and L_r, the three lateral–torsional-buckling zones, and the bracing spacing or Z_x required to develop the demand.

Zone 1: M_n = M_p  ·  Zone 2: linear C_b interpolation  ·  Zone 3: M_n = F_crS_x

M_p

608 k-ft

L_p

8.76 ft

L_r

25.36 ft

LTB zone

2 — inelastic LTB

M_n

608 k-ft

φ_bM_n

548 k-ft

Detailing sketchFlexural strength vs. unbraced length — LTB zones
Lp=8.8Lr=25.4Zone 1: plasticZone 2: inelastic LTBZone 3: elastic LTBLb=12.0 ft, Mn=608 k-ftUnbraced length Lb (ft)M

Lp = 8.76 ft, Lr = 25.36 ft; design point at Lb = 12.0 ft falls in zone 2 — inelastic LTB. Mn = 608 k-ft, φMn = 548 k-ft vs Mu = 400 k-ft.

Flexural designAISC 360-22 §F2

M_u400 k-ft
φ_bM_n548 k-ft
Zone2 — inelastic LTB
Utilization0.73

PASS — Adequate in zone 2 — inelastic LTB — utilization 0.73.

Module 76AASHTO LRFD AISC §G2.1Chapters 8 · 11

Shear & web buckling

Web shear with k_v, the C_v1 buckling ratio, and the web thickness or stiffener spacing needed when the web governs.

V_n = 0.6F_yA_wC_v1  ·  C_v1 = 1.0 if h/t_w ≤ 1.10√(k_vE/F_y)

A_w

8.295 in²

k_v

5.340

h/t_w

46.3

limits 61.2 / 76.2

C_v1

1.000

web yielding (no buckling)

φ_v

1.00

φ_vV_n

249 kip

Detailing sketchWeb panel — shear buckling and stiffener layout
h = 18.30 ind = 21.00 inELEVATION — girder web panelSHEAR & WEB BUCKLINGt_w = 0.395 in, k_v = 5.340No transverse stiffenersφ_vV_n = 249 kipV_u = 120 kip

Web tw = 0.395 in, clear depth h = 18.30 in, kv = 5.340 (unstiffened). φvVn = 249 kip vs Vu = 120 kip.

Shear & web bucklingAISC 360-22 §G2.1

V_u120 kip
φ_vV_n248.8 kip
Buckling modeweb yielding (no buckling)
Utilization0.48

PASS — Adequate — C_v1 = 1.000 (web yielding (no buckling)), utilization 0.48.

Module 77AASHTO LRFD AISC §H1.1Chapters 4 · 9

Combined forces — beam-columns

H1-1a / H1-1b interaction of axial force with biaxial bending, and the size increase implied by an over-unity ratio.

H1-1a (P_r/P_c ≥ 0.2): P_r/P_c + 8/9(M_rx/M_cx + M_ry/M_cy) ≤ 1.0  ·  H1-1b otherwise

P_r/P_c

0.357

Equation

H1-1a

Interaction

0.905

Detailing sketchBeam-column interaction — P-M envelope and demand point
P/Pc=0.2demand (0.36, 0.45)Mrx/McxPr/PcINTERACTION SUMMARYEquation: H1-1aP_r/P_c = 0.357Interaction = 0.905 (limit 1.0)

Governing equation H1-1a: interaction value = 0.905 (limit 1.0). Pr/Pc = 0.357, Mrx/Mcx = 0.450.

Beam-column interactionAISC 360-22 §H1.1

Axial term0.357
Flexural terms0.450 + 0.167
Total0.905

PASS — Interaction H1-1a = 0.905 ≤ 1.0 — beam-column adequate.

Module 78AASHTO LRFD AISC §J3Chapters 8 · 11

Bolted connections

Bolt shear, bearing and tearout, slip resistance and combined tension–shear, returning the bolt count, spacing and edge distances to detail.

φR_n = 0.75F_nvA_b (shear)  ·  min(1.2l_ctF_u, 2.4d_btF_u) (bearing/tearout)  ·  μD_uh_fT_bn_s (slip)

Bolt shear

146 kip

Bearing / tearout

197 kip

Design strength

146 kip

Bolt shear (J3-1)

Bolts required

8

provided 6

Detailing sketchBolted connection — bolt group elevation and plan
ELEVATION — PLIES AND BOLT LINEt = 0.500 inPu = 180 kipPLAN — BOLT PATTERN AND SPACINGs = 2.63 ins = 2.63 inLe = 1.09 inBOLT GROUP DESIGN6 × 0.875 in boltsGoverning: Bolt shear (J3-1)φR_n = 146.1 kip

60.875 in bolts, ply t = 0.500 in, clear distance lc = 1.125 in. Governing limit state: Bolt shear (J3-1). φRn = 146.1 kip vs Pu = 180 kip. Min spacing 2.33 in (use 2.63 in), min edge 1.09 in.

Bolt group designAISC 360-22 §J3

Demand180 kip
Design strength146.1 kip
GoverningBolt shear (J3-1)
Layouts ≥ 2.33 in (use 2.63 in), L_e ≥ 1.09 in

REDESIGN — Provide 8 bolts (currently 6) or increase the ply thickness to 0.616 in — bolt shear (j3-1) controls.

Module 79AASHTO LRFD AISC §J2.4Chapters 8 · 11

Fillet welds

Directional-strength weld metal capacity against base-metal rupture, with the minimum and maximum leg sizes and the length required per side.

φR_n = 0.75(0.60F_EXX)(0.707w)L(1.0 + 0.50sin^1.5θ)

t_e

0.1767 in

k_ds

1.000

Weld metal

89 kip

Base metal

234 kip

Design strength

89 kip

Weld metal shear (J2-4)

L required / side

8.08 in

Detailing sketchFillet weld — plan, leg size and throat section
PLAN — WELD RUNSL = 8.00 inθ = 0° load angleSECTION — THROATte=0.1767 inw=0.2500 inFILLET WELD DESIGNw = 0.2500 in, L = 8.00 in × 2 side(s)Governing: Weld metal shear (J2-4)φR_n = 89.1 kip

Weld leg w = 0.2500 in, effective throat te = 0.1767 in, length L = 8.00 in per side × 2 side(s), load angle θ = 0°. Governing: Weld metal shear (J2-4). φRn = 89.1 kip vs Pu = 90 kip.

Fillet weld designAISC 360-22 §J2.4

Demand90 kip
Design strength89.1 kip
GoverningWeld metal shear (J2-4)
Size limits0.1875 – 0.4375 in

REDESIGN — Increase the weld length to 8.1 in per side, or the leg to 0.253 in (≤ 0.438 in max for a 0.500 in ply).

Module 80AASHTO LRFD AISC §J8 + ACI 318-19 Ch.17Chapters 4 · 13

Base plates & anchor rods

Concrete bearing with the √(A₂/A₁) confinement factor, the cantilever plate thickness, eccentricity classification, and anchor-rod steel and breakout strength.

φP_p = 0.65(0.85f′_cA₁)√(A₂/A₁)  ·  t_req = l√(2P_u/0.9F_yBN)

A₁ provided

400 in²

required 113 in²

φP_p

1768 kip

l (cantilever)

4.20 in

m=3.35, n=4.20, λn′=3.56

t required

1.1875 in

φN_sa

58 kip

φV_sa

30 kip

Detailing sketchBase plate — plan (anchor layout) and elevation
PLAN — PLATE, COLUMN, ANCHORSB = 20.0 inN = 20.0 inELEVATION — PLATE & ANCHOR EMBEDMENTplate t=1.1875 inanchor h_ef embedmenthefBASE PLATE & ANCHOR DESIGNPlate 20.0 × 20.0 × 1.1875 inAnchors: 4 × 0.750 inφP_p = 1768 kip vs P_u = 500 kip

Plate 20.0 × 20.0 × 1.1875 in with 40.750 in anchor rods. φPp = 1768 kip vs Pu = 500 kip.

Base plate & anchor rodsAISC §J8 + ACI 318-19 Ch.17

Note 1Concrete bearing OK: φP_p = 1768 kip ≥ P_u (A₁ = 400 in², required 113 in²).
Note 2Use a plate thickness of 1.1875 in (t_req = 1.167 in from the cantilever l = 4.20 in).
Note 3e = 0.0 in ≤ N/6 — full bearing, anchor rods nominal.
Note 4Anchor rods: φN_sa = 58 kip, φV_sa = 30 kip, concrete breakout φN_cb ≈ 177 kip at h_ef = 12 in.

REDESIGN — Specify a 20.0 × 20.0 × 1.1875 in plate with 4 – 0.750 in anchor rods, h_ef = 12.0 in.

Module 81AASHTO LRFD AISC §J3/J4 + Manual Part 10Chapters 8 · 11

Shear (simple) connection — shear tab

All six single-plate limit states — bolt shear, bearing/tearout, plate shear yield and rupture, block shear and the weld — with the governing one named.

Governing = min(bolt shear, bearing/tearout, plate shear yield, plate shear rupture, block shear, weld)

Bolt shear (J3-1)

72 kip

Plate bearing/tearout (J3-6)

117 kip

Plate shear yielding (J4-3)

97 kip

Plate shear rupture (J4-4)

86 kip

Block shear (J4-5)

82 kip

Weld to support (J2-4)

134 kip

Detailing sketchShear tab (single-plate) connection — elevation and weld section
ELEVATION — PLATE, BOLTS, WELD TO SUPPORTweld w=0.2500 inLev=1.50 ins=3.00 inLeh=1.50 inPlate tp=0.375 inSHEAR TAB DESIGNPL 0.3750 × 4.5 × 12.0 in4 bolts × 0.750 in @ 3.00 inWeld leg 0.2500 inGoverning: Bolt shear (J3-1)φR_n = 71.6 kip

4 bolts @ 3.00 in, edge distances Lev = 1.50 in, Leh = 1.50 in, plate tp = 0.375 in, weld leg 0.2500 in. Governing: Bolt shear (J3-1). φRn = 71.6 kip vs Vu = 70 kip.

Single-plate shear connectionAISC 360-22 §J3/J4 + Manual Part 10

PlatePL 0.3750 × 4.5 × 12.0
Design strength71.6 kip
GoverningBolt shear (J3-1)
Utilization0.98

PASS — Adequate — bolt shear (j3-1) governs at 0.98 utilization. Recommended weld: two-sided 0.234 in fillet (⅝ t_p rule).

Module 82AASHTO LRFD AISC §J10Chapters 8 · 11

Moment connection & column checks

Flange-couple force with the §J10 column-side checks that decide whether continuity plates and a web doubler are required.

P_uf = M_u/(d − t_f)  ·  J10 checks decide whether continuity plates and a doubler plate are needed

P_uf

192 kip

Web local yielding

301 kip

Web crippling

397 kip

Flange local bending

276 kip

Flange rupture

321 kip

Panel zone

240 kip

Detailing sketchMoment connection — flange-force couple and column limit states
Puf = 192 kip (T)Puf = 192 kip (C)d = 20.80 incol: tw=0.605, tf=0.990, d=14.7beam bf=8.27, tf=0.795 inCOLUMN-SIDE CHECKSGoverning: Column flange local bending (J10-1)φR_n = 276 kipP_uf = 192 kipNo continuity plates required

Flange force Puf = Mu/(d − tf) = 192 kip. Governing column check: Column flange local bending (J10-1) = 276 kip. Continuity plates not required.

Moment connection & column checksAISC 360-22 §J10

Flange force P_uf192.0 kip
Governing column limitColumn flange local bending (J10-1) — 276 kip
Continuity platesnot required
Panel zonePanel zone adequate (φR_v = 240 kip).

PASS — No continuity plates required: all J10 column limit states exceed P_uf = 192 kip.

Module 83AASHTO LRFD AISC §I3 / §I8Chapters 4 · 8

Composite beam with steel deck

Plastic composite flexure with the concrete, steel and stud forces, the degree of composite action, and the stud count for full composite behaviour.

C = min(0.85f′_cb_eff(t−h_r), A_sF_y, ΣQ_n)  ·  a = C/0.85f′_cb_eff  ·  φM_n = 0.90C(d/2 + Y₂)

C_concrete

1071 kip

T_steel

665 kip

ΣQ_n

688 kip

a

2.173 in

Composite action

100%

φM_n

662 k-ft

Detailing sketchComposite beam — section, PNA and stud layout
SECTION — SLAB, PNA, STEEL BEAMPNAb_eff = 90 int=5.50 ind=17.7 inCOMPOSITE BEAM SUMMARYDegree of composite action: 100%Studs provided: 40a = 2.173 in, C = 665 kipφM_n = 662 k-ft vs M_u = 700 k-ft

Effective width beff = 90 in, slab t = 5.50 in (rib hr = 2.0 in), degree of composite action = 100% with 40 studs. Stress-block depth a = 2.173 in, C = 665 kip. φMn = 662 k-ft vs Mu = 700 k-ft.

Composite beam with steel deckAISC 360-22 §I3

M_u700 k-ft
φM_n662 k-ft
Studs provided / required40 / 78
Utilization1.06

REDESIGN — φM_n = 662 k-ft < M_u. Increase the stud count to 78 for full composite action, or use a heavier beam (A_s ≈ 14.1 in²).

Module 84AASHTO LRFD AISC Appendix 6Chapters 4 · 8

Stability bracing — strength & stiffness

Nodal and relative bracing for columns and beams: both the required brace force and the required brace stiffness, plus the brace area that delivers it.

Strength AND stiffness both required — a strong but flexible brace does not stabilize the member.

Required brace strength P_br

3.00 kip

Required brace stiffness β_br

26.7 kip/in

Detailing sketchStability bracing — column nodal
Lbr = 10.0 ftMember elevation — brace pointsBRACING REQUIREMENTS (APP. 6)Type: column-nodalRequired strength P_br = 3.00 kipRequired stiffness β_br = 26.7 kip/inBoth strength AND stiffness must be provided.

Brace spacing Lbr = 10.0 ft. Required brace strength Pbr = 3.00 kip; required stiffness βbr = 26.7 kip/in. Nodal (point) bracing restrains a single cross-section.

Stability bracingAISC 360-22 Appendix 6

CaseNodal column bracing, A-6-3/A-6-4 (conservative N_i = 4).
P_br3.00 kip
β_br26.7 kip/in

Provide a brace with strength ≥ 3.0 kip AND stiffness ≥ 27 kip/in. A single-angle brace of length L and area A gives β = AE/L — required A ≈ 0.11 in² for a brace 10.0 ft long. Strength alone is not sufficient; both criteria must be met.

Module 85AASHTO LRFD AISC Appendix 8Chapters 4 · 9

Stability — second-order B1 / B2

Amplified first-order analysis: the P-δ and P-Δ multipliers, the amplified moments and axial loads, and the drift limit that keeps B₂ acceptable.

B₁ = C_m/(1 − αP_r/P_e1)  ·  B₂ = 1/(1 − αΣP/ΣP_e,story)  ·  M_r = B₁M_nt + B₂M_lt

B₁

1.000

B₂

1.286

M_r

351 k-ft

P_r

264 kip

Detailing sketchSecond-order amplification — sway frame
H (lateral load)Δ (B2 = 1.286)AMPLIFIERSB1 = 1.000 (member, no translation)B2 = 1.286 (story, lateral translation)Mr = B1·Mnt + B2·MltMr = 351 k-ft

B1 = 1.000 amplifies the no-translation moment Mnt = 120 k-ft; B2 = 1.286 amplifies the lateral-translation moment Mlt = 180 k-ft. Combined required moment Mr = B1Mnt + B2Mlt = 351 k-ft.

Second-order amplificationAISC 360-22 Appendix 8

B₁1.000
B₂1.286
Amplified M_r351 k-ft
Amplified P_r264 kip

PASS — B₁ = 1.000, B₂ = 1.286 — amplified demands M_r = 351 k-ft, P_r = 264 kip.

Module 86AASHTO LRFD AISC Appendix 3 · AASHTO §6.6.1Chapters 8 · 18

Fatigue — stress range & life

Detail-category allowable stress range, threshold for infinite life, and the predicted number of cycles with the detail upgrade needed when the life is short.

F_SR = (C_f/n_SR)^(1/3) ≥ F_TH  ·  life N = C_f/f_sr³

C_f

4.40e+9

F_TH

10.0 ksi

F_SR

10.00 ksi

Predicted life

5.13 M cycles

Infinite life?

yes

Detailing sketchFatigue S-N curve — Category C
FTH=10.0fsr=9.50 ksi @ N=5.1MnSR=20.0Mlog Fsr (ksi)log N (cycles)CATEGORY C SUMMARYF_TH = 10.0 ksiF_SR (allow) = 10.00 ksif_sr (applied) = 9.50 ksiPredicted life = 5.13 M cycles

Constant-amplitude fatigue threshold FTH = 10.0 ksi; allowable range at nSR= 20.0M cycles is FSR = 10.00 ksi. Applied fsr = 9.50 ksi gives predicted life N = 5.13M cycles.

FatigueAISC 360-22 Appendix 3

f_sr9.50 ksi
F_SR allowable10.00 ksi
Life5.13 M cycles

PASS — f_sr = 9.50 ksi ≤ F_TH = 10 ksi — infinite life for Category C.

Module 87AASHTO LRFD AISC DG3 / IBC 1604.3Chapters 4 · 19

Deflection & serviceability

Live and total deflections against L/360 and L/240, camber, and the moment of inertia required when serviceability governs the beam size.

Δ = 5wL⁴/384EI

Δ_D

0.425 in

Δ_L

0.567 in

allow 1.000 in

Δ_total

0.992 in

allow 1.500 in

Detailing sketchDeflected shape and serviceability limits
L = 30.0 ftΔ_total = 0.992 inallowable Δ_total = L/240 = 1.500 inDEFLECTION SUMMARYΔ_D = 0.425 inΔ_L = 0.567 in (allow 1.000 in)Δ_total = 0.992 in (allow 1.500 in)Camber = 0.00 in

ΔD = 0.425 in, ΔL = 0.567 in (limit 1.000 in), Δtotal = 0.992 in (limit 1.500 in), camber = 0.00 in, span L = 30.0 ft.

ServiceabilityAISC DG3 / IBC 1604.3

Δ_live / limit0.567 / 1.000 in
Δ_total / limit0.992 / 1.500 in
I required880 in⁴

PASS — Δ_LL = 0.567 in ≤ L/360 = 1.000 in and Δ_total = 0.992 in ≤ L/240.

Building design suite

Concrete — ACI 318-19

Beams, columns, slabs and detailing — each module runs the full cycle: A_s,req → bar size, count and spacing → A_s,prov → capacity re-check → crack control, ductility and serviceability, with the redesign step spelled out when a limit is violated.

Module 88AASHTO LRFD ACI §9.5 / §9.6.1 / §24.3.2Chapters 5 · 6

Beam flexure & crack control

Required and minimum steel, bar selection, φ from the net tensile strain, the re-checked φM_n, §24.3.2 bar spacing for crack control, skin steel, and a dimensioned section drawing.

a = A_sf_y/0.85f′_cb  ·  ε_t = 0.003(d−c)/c  ·  φM_n = φA_sf_y(d − a/2)  ·  s ≤ 15(40/f_s) − 2.5c_c

A_s,req

2.793 in²

A_s,min

1.440 in²

A_s,prov

3.000 in²

3 – #9

a / c

3.31 / 3.89 in

ε_t

0.01781

φ = 0.900

φM_n

342.2 k-ft

Flexural reinforcement design & crack controlACI 318-19 §9.5 / §9.6.1 / §24.3.2

A_s design (governing)2.793 in²
Bar call-out3 – #9
A_s provided3.000 in²
Bar spacing provided / max5.31 / 10.00 in
φM_n342.2 k-ft
ρ0.0069

PASS — Adequate: 3–#9, A_s,prov/A_s,req = 1.07, ε_t = 0.0178 (tension-controlled), spacing 5.3 in ≤ 10.0 in.

Detailing sketchReinforced-concrete beam — section, elevation and bar plan
ε_c = 0.003c = 3.89 inε_t (tension steel)b = 16.0 ind = 27.0 ina = 3.31 in blockREINFORCEMENT CALL-OUTA_s provided = 3 — #9 = 3.00 in² (1 row)A_s used in analysis = 3.00 in², f_y = 60 ksiStirrups: #4 double leg, 2 in clear coverφM_n = 342 k-ft vs M_u = 320 k-ftSECTION A–A (at midspan)ELEVATION — SIDE VIEW, STIRRUP LAYOUT AND BAR CUT-OFFS#4 @ 4 in#4 @ 8 in3 — #9 bottom bars continuous into the supports, 90° hooks (5.10.8)Stirrups closely spaced over d from each face where V_u is largest, relaxed at midspan (5.7.2.6)AAPLAN — BOTTOM BAR LAYOUT (SOFFIT)b = 16.0 in3 bars per row × 1 row — clear bar spacing ≥ max(1.5 d_b, 1.5 in, 1.33 × max aggregate)

3 #9 bars (3.00 in² provided against As = 3.00 in² assumed), 1 row, 2 in clear cover, #4 stirrups. Whitney block a = 3.31 in, c = 3.89 in, fy = 60 ksi. φMn = 342 k-ft vs Mu = 320 k-ft (AASHTO 5.6.3.2).

Module 89AASHTO LRFD ACI §22.5 / §9.6.3 / §9.7.6Chapter 6

Beam shear & stirrup design

V_c from Table 22.5.5.1, required V_s, the crushing limit, and a full stirrup schedule (size, legs, spacing, s_max) for every candidate bar.

V_c = 2λ√f′_c b_wd  ·  V_s = A_vf_ytd/s  ·  φ(V_c + V_s) ≥ V_u  ·  V_s ≤ 8√f′_c b_wd

V_c

50.0 kip

φV_c/2

18.8 kip

stirrups required

V_s required

70.0 kip

Schedule

#3 2-leg stirrups @ 5.0 in c/c

s_max

13.5 in

φV_n

91.0 kip

Stirrup design scheduleACI 318-19 §22.5 / §9.6.3 / §9.7.6

#3 2-leg (A_v = 0.22 in²)s = 5.0 in (strength 5.1, min-A_v 264.0, max 13.5) → φV_n = 91 kip
#4 2-leg (A_v = 0.40 in²)s = 9.0 in (strength 9.3, min-A_v 480.0, max 13.5) → φV_n = 92 kip
#5 2-leg (A_v = 0.62 in²)s = 13.5 in (strength 14.4, min-A_v 744.0, max 13.5) → φV_n = 93 kip
#6 2-leg (A_v = 0.88 in²)s = 13.5 in (strength 20.4, min-A_v 1056.0, max 13.5) → φV_n = 117 kip

PASS — #3 2-leg stirrups @ 5.0 in gives φV_n = 91 kip ≥ V_u = 90 kip (s_max = 13.5 in, minimum-A_v spacing 264.0 in).

Detailing sketchBeam shear reinforcement — stirrup section and spacing elevation
b_w = 16.0 ind = 27.0 in2-leg #3 stirrupsSECTION — mid-support regionELEVATION — STIRRUP SPACING (SUPPORT ZONE TIGHTER, MIDSPAN OPENS OUT)2-#3 @ 5.0 in@ 13.5 in max2-#3 @ 5.0 inL ≈ 20 ft span shown schematicallySTIRRUP SCHEDULE2-leg #3 @ 5.0 in o.c. near supportss_max = 13.5 in (§9.7.6.2.2)V_c = 50.0 kipφV_n = 91.0 kip vs V_u = 90 kip

2-leg #3 stirrups @ 5.0 in near the supports (Vc = 50.0 kip, φVn = 91.0 kip vs Vu = 90 kip), opening to the code maximum smax = 13.5 in toward midspan per ACI 318-19 §9.7.6.2.2.

Module 90AASHTO LRFD ACI §22.4 / §10.6 / §25.7Chapters 9 · 12 · 13

Column axial capacity

P_o with the 0.80/0.85 cap, ρ limits of 1–8 %, the required A_st, and a bar-and-tie (or spiral) schedule.

P_o = 0.85f′_c(A_g − A_st) + f_yA_st  ·  φP_n,max = φ·0.80·P_o

A_g

400 in²

ρ

2.00%

P_o

2146 kip

φP_n(max)

1116 kip

A_st required

10.90 in²

Column reinforcement & confinementACI 318-19 §22.4 / §10.6 / §25.7

A_st required10.90 in²
Bar schedule14 – #8 vertical bars with #4 ties @ 16 in c/c (§25.7.2)
φP_n(max)1116 kip
Utilization1.08

REDESIGN — φP_n = 1116 kip < P_u — required A_st ≈ 10.90 in², or enlarge A_g to 430 in².

Detailing sketchTied column — section and reinforcement
b = 20 inh = 20 in14 — #8 longitudinal#4 ties @ 16.0 inCOLUMN REINFORCEMENT SCHEDULE14 — #8 longitudinal bars#4 ties @ 16.0 in o.c.φP_n = 1116 kipP_u = 1200 kip (utilization 1.08)SECTION A–A

14#8 longitudinal bars around a 20 × 20 in section, #4 ties @ 16.0 in o.c. per ACI 318-19 §25.7.2 (tie spacing ≤ min(16db, 48dtie, least dimension)). φPn = 1116 kip vs Pu = 1200 kip.

Module 91AASHTO LRFD ACI §6.6.4Chapters 9 · 12 · 13

Slender column moment magnification

Slenderness screening, EI_eff, the critical load P_c, the δ_ns magnifier and the design moment M_c with the minimum-eccentricity check.

δ_ns = C_m/(1 − P_u/0.75P_c)  ·  P_c = π²EI/(kl_u)²  ·  M_c = δ_nsM₂

kl_u/r

35.6

limit 28.0

P_c

2386 kip

C_m

0.800

δ_ns

1.110

M_c

133.2 k-ft

M₂,min

47.5 k-ft

Slenderness & moment magnificationACI 318-19 §6.6.4

Slender?yes — magnify
δ_ns1.110
Design moment M_c133.2 k-ft

PASS — Slender: δ_ns = 1.110 → design moment M_c = 133 k-ft (min. eccentricity moment 48 k-ft).

Detailing sketchSlender column — moment magnification and deflected shape
δ = magnified lateral deflectionk l_u = 16.0 ftM₁ = 60 k-ftM₂ = 120 k-ftM_c = δ_ns·M₂ = 133.2 k-ftPrimary (solid) vs magnified (dashed) moment diagram

k·lu = 1.00 × 16.0 ft. Primary end moments M₁ = 60 k-ft, M₂ = 120 k-ft magnified by δns = 1.110 to the design moment Mc = 133.2 k-ft — the member is slender and moments must be magnified (ACI 318-19 §6.6.4).

Module 92AASHTO LRFD ACI §22.2 / Table 21.2.2Chapters 9 · 12 · 13

Column P–M interaction diagram

Strain-compatibility sweep of the neutral axis producing the nominal and φ-reduced interaction curves, with the demand point plotted and the available φM_n at that axial load.

Strain compatibility sweep of the neutral axis c → (P_n, M_n) → φ(ε_t)-reduced design curve

P_o

2392 kip

φP_n,max

1244 kip

φM_n at P_u

504 k-ft

P–M interactionACI 318-19 §22.2 / Table 21.2.2

Demand(600 kip, 400 k-ft)
φM_n at that axial load504 k-ft
Utilization0.79

PASS — At P_u = 600 kip the φ-curve allows φM_n = 504 k-ft ≥ M_u = 400 k-ft (utilization 0.79).

Detailing sketchColumn P–M interaction diagram
M (k-ft)P (kip)(M_u, P_u) = (400, 600)Nominal Pₙ–MₙDesign φPₙ–φMₙ

Nominal (Pn, Mn) curve and φ-reduced design curve from the ACI 318-19 §22.2 strain-compatibility sweep. Demand point (Mu = 400 k-ft, Pu = 600 kip) plots inside the design envelope — φMn at this Pu = 504 k-ft.

Module 93AASHTO LRFD ACI §25.4 / §25.5 · AASHTO §5.10.8Chapters 5 · 6

Development length & lap splices

Straight, hooked and compression development lengths with the confinement term, plus Class A / Class B lap lengths and staggering guidance.

ℓ_d = (3/40)(f_y/λ√f′_c)·(ψ_tψ_eψ_s)/[(c_b+K_tr)/d_b]·d_b

(c_b+K_tr)/d_b

2.000

capped at 2.5

ℓ_d tension

35.58 in

ℓ_dh hook

17.25 in

ℓ_dc compression

18.97 in

Lap splice

46.25 in

Development & splice scheduleACI 318-19 §25.4 / §25.5

Straight tension ℓ_d35.58 in (36 d_b)
Standard hook ℓ_dh17.25 in
Compression ℓ_dc18.97 in
Class B lap46.25 in

Straight tension development ℓ_d = 35.6 in (confinement term (c_b+K_tr)/d_b = 2.00, capped at 2.5). Standard hook ℓ_dh = 17.2 in. Compression ℓ_dc = 19.0 in. Class B lap splice = 46.2 in — stagger splices out of the maximum-moment region (§25.5).

Detailing sketchDevelopment length, standard hook and lap splice
ℓ_d = 35.6 inStraight tension developmentℓ_dh = 17.2 inStandard 90° hook (§25.4.3)extension ≥ 12d_bℓ_st = 46.2 in (Class B)Tension lap splice — bars shown offset for clarity

#8 (db = 1.000 in): straight tension development ℓd = 35.6 in, standard 90° hook ℓdh = 17.2 in, Class B lap splice ℓst = 46.2 in (ACI 318-19 §25.4 / §25.5).

Module 94AASHTO LRFD ACI §24.2Chapters 6 · 19

Deflection — immediate & long term

Cracked and effective moments of inertia, immediate dead and live deflections, and the λ_Δ long-term multiplier against L/360 and L/240.

I_e (§24.2.3.5)  ·  Δ = 5wL⁴/384E_cI_e  ·  λ_Δ = ξ/(1 + 50ρ′)

E_c

3644 ksi

M_cr

96.0 k-ft

M_a = 205.8 k-ft

I_e

31331 in⁴

I_g = 36000, I_cr = 14169

Δ_live

0.109 in

allow 0.933 in

λ_Δ

2.000

Δ_LT + live

0.465 in

allow 1.400 in

Immediate & long-term deflectionACI 318-19 §24.2

Δ dead (immediate)0.145 in
Δ live (immediate)0.109 in
Δ long-term0.356 in
Δ total0.610 in

PASS — Δ_LL = 0.109 in ≤ L/360 = 0.933 in; long-term + live = 0.465 in ≤ L/240 = 1.400 in.

Detailing sketchBeam deflection — immediate, long-term and deflected shape
L = 28.0 ftΔ_long-term+live = 0.465 inΔ_live = 0.109 inDEFLECTION CHECKΔ_live = 0.109 in ≤ L/360 = 0.933 in OKΔ_long-term+live = 0.465 in ≤ L/240 = 1.400 in OK

Span L = 28.0 ft. Immediate live deflection Δlive = 0.109 in (limit L/360 = 0.933 in); long-term + live Δ = 0.465 in (limit L/240 = 1.400 in). Shape exaggerated for clarity.

Module 95AASHTO LRFD ACI §7 / §24.4Chapter 5

One-way slab

Minimum thickness, factored strip moments, bottom and top bar selection at spacing, shrinkage-and-temperature steel and the one-way shear check.

w_u = 1.2D + 1.6L  ·  M = w_uL²/coef  ·  A_s,min = 0.0018A_g  ·  s ≤ min(3h, 18 in)

h_min

6.00 in

w_u

0.301 kip/ft/ft

M⁺

4.21 k-ft/ft

Bottom steel

#4@15.5"

Top steel

#4@15.5"

S&T steel

#4@15.5"

One-way slab reinforcementACI 318-19 §7 / §24.4

Note 1h = 7 in ≥ h_min = 6.00 in (Table 7.3.1.1) — deflection check by computation not required.
Note 2Main steel: #4 @ 15.5 in c/c bottom, #4 @ 15.5 in c/c top at supports.
Note 3Shrinkage & temperature steel: #4 @ 15.5 in c/c (A_s = 0.0018A_g = 0.151 in²/ft, §24.4.3.2).
Note 4One-way shear OK: φV_c = 6.8 kip/ft ≥ V_u = 2.0 kip/ft.

REDESIGN — Design strip 12 in wide, d = 6.00 in.

Detailing sketchOne-way slab — section and plan of reinforcement
L = 14.0 fth = 7.00 inBottom: #4 @ 15.5 inTop: #4 @ 15.5 inSECTION — 12 in design stripPLAN — MAIN STEEL AND SHRINKAGE/TEMPERATURE STEELMain bars (#4 @ 15.5 in) span L; S&T steel #4 @ 15.5 in placed transverse

7.00 in slab, both-ends span L = 14.0 ft. Bottom steel #4 @ 15.5 in, top steel at supports #4 @ 15.5 in. Shrinkage & temperature steel #4 @ 15.5 in transverse (ACI 318-19 §7.6.1 / §24.4).

Module 96AASHTO LRFD ACI §8.10 / §22.6Chapter 5

Two-way slab (DDM) & punching shear

Total static moment M_o, column- and middle-strip distribution with bar schedules for each strip, and the two-way punching-shear check with β and α_s terms.

M_o = q_u l₂ l_n²/8  ·  v_c = min(4, 2 + 4/β, 2 + α_sd/b_o)λ√f′_c  ·  φV_c = 0.75v_cb_od

q_u

0.310 ksf

M_o

238.7 k-ft

M⁻ / M⁺

155 / 84 k-ft

b_o

99.0 in

d = 6.75 in

v_c

253 psi

φV_c / V_u

127 / 110 kip

Two-way slab reinforcement (DDM)ACI 318-19 §8.10 / §22.6

Column strip (top)#7 @ 16.0 in — φM_n = 13.00 vs 12.93 k-ft/ft
Column strip (bottom)#3 @ 7.0 in
Middle strip (top)#3 @ 7.5 in
Middle strip (bottom)#3 @ 7.5 in
Punching shearφV_c = 127 kip vs V_u = 110 kip

PASS — M_o = q_u l₂ l_n²/8 = 238.7 k-ft; distributed 65 % negative / 35 % positive (§8.10.4). Column strip (9.0 ft wide): top #7 @ 16.0 in, bottom #3 @ 7.0 in. Middle strip (9.0 ft wide): top #3 @ 7.5 in, bottom #3 @ 7.5 in. Two-way (punching) shear OK: φv_cb_od = 127 kip ≥ V_u = 110 kip at d/2 from the column (b_o = 99 in).

Detailing sketchTwo-way slab (DDM) — strip plan and punching-shear critical perimeter
PLAN — CRITICAL PERIMETER AT D/2b_o perimeter (d/2 = 3.38 in)column stripl₂ = 18.0 ftl₁ = 20.0 ftCOLUMN STRIP / MIDDLE STRIP MOMENTSColumn strip — top #7@16.0"bottom #3@7.0"Middle strip — top #3@7.5"bottom #3@7.5"PUNCHING SHEAR CHECKb_o = 99.0 in at d/2 = 3.38 in from the column faceφV_c = 126.8 kip vs V_u = 110.3 kip OK

Panel l₁ × l₂ = 20.0 × 18.0 ft, column c₁ × c₂ = 18.0 × 18.0 in. Critical shear perimeter bo = 99.0 in at d/2 = 3.38 in from the column face (ACI 318-19 §22.6.4.1), φVc = 126.8 kip vs Vu = 110.3 kip. Column strip: top #7@16.0", bottom #3@7.0". Middle strip: top #3@7.5", bottom #3@7.5".

Building design suite

Masonry — TMS 402/602-22

Strength design of reinforced concrete masonry: slender out-of-plane walls with the P-δ moment, in-plane shear walls, and bond-beam lintels.

Module 97AASHTO LRFD TMS 402-22 §9.3Chapters 9 · 12 · 13

Reinforced masonry wall — axial, flexure & P-δ

Slenderness-reduced axial capacity, the second-order P-δ moment, vertical bar size and grout-cell spacing, the maximum-reinforcement ductility limit and out-of-plane shear.

φM_n = 0.90(A_sf_y + P_u)(d − a/2)  ·  a = (A_sf_y + P_u)/0.80f′_mb  ·  M_u,total = M_u + P_uδ_u

h/r

109.0

(70r/h)²

φP_n

43.45 kip/ft

δ_u

0.160 in

M_u total

4.25 k-ft/ft

Reinforcement

#7@32"

φV_n

8.07 kip/ft

Reinforced masonry wall designTMS 402-22 §9.3

Note 1h/r = 109 > 99 — the slender (70r/h)² form governs; φP_n = 43.4 kip/ft.
Note 2Second-order: δ_u = 0.160 in gives M_u,total = M_u + P_uδ_u = 4.25 k-ft/ft (§9.3.5.4.3).
Note 3Provide #7 @ 32 in o.c. — φM_n = 4.30 k-ft/ft ≥ 4.25 k-ft/ft; A_s = 0.225 in²/ft ≤ A_s,max = 0.722 in²/ft.
Note 4Shear OK: φV_n = 8.1 kip/ft ≥ V_u = 1.1 kip/ft (M/(V d_v) = 1.00).
Note 5Detailing: minimum prescriptive steel 0.0007bt = 0.064 in²/ft each direction (0.002 total); bond beams at ≤ 48 in o.c.; lap splices per §9.3.3.4.

PASS — #7 @ 32 in o.c. vertical (A_s = 0.225 in²/ft) in grouted cells

Detailing sketchReinforced masonry wall — section, elevation and cell layout
32 in o.c.t = 7.625 in#7 centered in grouted cellPLAN SECTION — through wall thicknessELEVATION — VERTICAL BAR LAYOUT32 in o.c.h = 20.0 ftBond beam / horizontal joint reinforcement at 45 px intervals (schematic)

8 in CMU, fully grouted, #7 vertical bars @ 32 in o.c. centered in the grouted cells (TMS 402-22 §9.3). Wall height h = 20.0 ft. φPn = 43.45 kip/ft vs Pu = 3.50 kip/ft; φMn = 4.30 k-ft/ft vs magnified Mu = 4.25 k-ft/ft.

Module 98AASHTO LRFD TMS 402-22 §9.3.4 / §7.3.2Chapters 9 · 12 · 13

Masonry shear wall — in-plane

M/(Vd_v)-dependent masonry shear, the crushing ceiling, bond-beam horizontal steel spacing and the boundary flexural steel at each end cell.

V_nm = [4.0 − 1.75(M/Vd_v)]A_nv√f′_m + 0.25P_u  ·  V_ns = 0.5(A_v/s)f_yd_v

M/(Vd_v)

0.781

V_nm

187.4 kip

V_n,max

261.9 kip

V_s required

0.0 kip

Horizontal steel

#4@48"

Boundary steel

4–#5

Masonry shear wall designTMS 402-22 §9.3.4 / §7.3.2

Note 1M/(V d_v) = 0.78 → V_nm = 187 kip, upper limit V_n,max = 262 kip (§9.3.4.1.2).
Note 2Section adequate against masonry crushing in shear.
Note 3Horizontal shear steel: #4 bond-beam bars @ 48 in o.c. (φV_n = 181 kip).
Note 4Boundary flexural steel: A_s = 1.23 in² each end → 4 – #5 in the end cells (A_s,prov = 1.24 in²), fully grouted and lapped per §9.3.3.4.
Note 5Aspect ratio h_w/l_w = 1.25 — flexure-dominated behaviour.

PASS —

Detailing sketchMasonry shear wall — elevation with boundary and horizontal reinforcement
l_w = 16.0 fth_w = 20.0 ftBoundary: 4 – #5Horizontal: #4@48"SHEAR WALL REINFORCEMENT SCHEDULEBoundary (end-cell) steel: 4 – #5 each endHorizontal (shear) steel: #4@48"φV_n = 180.6 kip vs V_u = 90 kip

Wall lw × t × hw = 16.0 ft × 7.625 in × 20.0 ft. Horizontal (shear) reinforcement #4@48"; boundary flexural steel 4 – #5 in grouted end cells. φVn = 180.6 kip vs Vu = 90 kip (TMS 402-22 §9.3.4 / §7.3.2).

Module 99AASHTO LRFD TMS 402-22 §9.3 / §5.2.1 / §8.1.6.2Chapters 9 · 12 · 13

Reinforced masonry lintel

Effective span and demands, bottom bond-beam steel, the §9.3.3.5 maximum-reinforcement limit, M/(Vd)-dependent masonry shear with stirrups when needed, bearing stress and the ℓ/600 deflection limit.

M_u = w_uℓ²/8 · a = A_sf_y/0.80f′_mb · φM_n = φA_sf_y(d − a/2) · V_nm = [4 − 1.75(M/Vd)]A_nv√f′_m

M_u / V_u

15.0 / 6.9 k-ft, kip

A_s required

0.170 in²

A_s provided

0.310 in²

1 – #5 bottom bond beam

φM_n

26.8 k-ft

φV_n

12.3 kip

Bearing

0.114 ksi

limit 0.300 ksi

Lintel bond-beam scheduleTMS 402-22 §9.3 / §5.2.1 / §8.1.6.2

Grouted width b7.625 in
Effective depth d20.0 in
Bottom steel1 – #5
Stirrupsnot required by analysis
A_s,max1.451 in²
Deflection limit ℓ/6000.160 in

PASS — Provide 1 – #5 in the bottom bond beam, 8 in bearing each end; φM_n = 26.8 k-ft ≥ M_u = 15.0 k-ft.

Detailing sketchReinforced masonry lintel — elevation and bearing detail, with grouted section
ELEVATION — LINTEL OVER OPENINGclear span = 8.0 fth = 24 inbearing = 8 inELEVATIONSECTION — GROUTED BOND BEAMt = 8.00 in1 — #5LINTEL REINFORCEMENT SCHEDULEBottom steel: 1 — #5 in the bottom grouted bond-beam courseφM_n = 26.8 k-ft vs M_u = 15.0 k-ftφV_n = 12.3 kip vs V_u = 6.9 kipBearing 8 in each end on 8.00 in wall

Clear span = 8.0 ft, lintel depth h = 24 in over a 8.00 in wall, bearing 8 in each end. Bottom steel 1#5 in the grouted bond-beam course: φMn = 26.8 k-ft ≥ Mu = 15.0 k-ft; φVn = 12.3 kip vs Vu = 6.9 kip (TMS 402-22 §9.3).

Advanced detailing suite

Discontinuity regions, punching, torsional stability & stiffened webs

Four deep-dive modules that carry the awkward regions all the way to a drawing: strut-and-tie for deep beams and corbels, complete punching-shear design with stud rails and cap/column layout, combined torsion-and-stability for open and closed steel shapes, and plate-girder stiffener and weld design.

Module 100AASHTO LRFD ACI 318-19 Ch. 23 · §9.9 · §16.5Chapters 6 · 12 · 13

Deep beams & corbels — strut-and-tie

Full STM: deep-member screening, truss geometry and strut angle, strut and CCC/CCT nodal-zone strengths, tie steel with bar selection, distributed crack-control steel or corbel hoops, and tie anchorage.

θ = atan(0.9d/a_v) ≥ 25° · F_ns = f_ce A_cs, f_ce = 0.85β_cβ_s f′_c · A_st = F_ut/φf_y · A_v, A_vh ≥ 0.0025 b s

Strut angle θ

52.2 deg

Strut force F_us

405 kip

φF_ns = 517 kip

Tie force F_ut

312 kip

Strut width w_s

13.52 in

A_cs = 216 in²

A_s tie required

6.93 in²

A_s,min = 2.43 in²

A_s provided

7.20 in²

Bearing node

714 kip

CCT node

163 kip

φV_n,max

365 kip

Strut-and-tie modelACI 318-19 Ch. 23 · §9.9 · §16.5

ClassificationDeep member (ℓ_n/h = 2.00, a_v/d = 0.70)
Truss lever arm jd38.7 in
Strut efficiency β_s0.75 → f_ce = 3.19 ksi
Node f_ce (CCC / CCT)4.25 / 3.40 ksi
Tie width w_t4.00 in

Reinforcement schedule§23.7 · §23.5 · §9.9.3 / §16.5.5

Primary tie12 – #7 primary tie bars
Vertical web steel#4 @ 8.5 in c/c each face (s_max = 8.6 in)
Horizontal web steel#4 @ 8.5 in c/c each face (s_max = 8.6 in)
Tie anchorageℓ_dh = 12.6 in — straight development adequate
Bearing plate14.0 × 16.0 in, A_nz = 224 in²

REDESIGN — CCT node behind the tie overstressed — spread the tie over a greater height (increase the number of layers so w_t ≥ 7.6 in) or enlarge the bearing.

Detailing sketchDeep beam — strut-and-tie model
support node (CCT)V_u = 320 kipTie F_ut = 312 kipStrut F_us = 405 kip, w_s = 13.5 inCCC node (bearing)CCT nodea_v = 30.0 inh = 48.0 inθ = 52.2°STRUT-AND-TIE SUMMARYSection b × h = 16.0 × 48.0 in, d = 43.0 inAngle θ = 52.2° (≥ 25° req'd)Tie steel: 12 – #7 primary tie barsWeb crack-control: #4 vertical stirrups @ 8.5 in c/c each face + #4 horizontal bars @ 8.5 in c/c each face

Single-panel truss: θ = 52.2° from the load node to the support node. Strut force Fus = 405 kip (width ws = 13.52 in), tie force Fut = 312 kip carried by 12 – #7 primary tie bars. Vu = 320 kip. #4 vertical stirrups @ 8.5 in c/c each face + #4 horizontal bars @ 8.5 in c/c each face

Module 101AASHTO LRFD ACI 318-19 §22.6 · §8.4.4 · §8.7.7Chapters 5 · 12 · 13

Punching shear — complete design

All three v_c expressions at the d/2 section, unbalanced-moment transfer by eccentric shear, headed stud rails or closed stirrups with s₀/s and rail length to the outer critical section, plus the cap/column bar and tie layout.

v_u = V_u/b_od + γ_v M_u c/J_c · v_c = min[4, 2+4/β, 2+α_sd/b_o]λ√f′_c · A_v/s = v_s b_o/f_yt · s ≤ 0.75d

b_o at d/2

112.0 in

d = 8.00 in

v_u total

235 psi

direct 201 + moment 34

φv_c

212 psi

4λ√f′_c

γ_v / γ_f

0.400 / 0.600

v_s required

101 psi

φv_n with reinforcement

247 psi

Stud spacing s

6.0 in

s₀ = 3.0 in, s_max = 6.0 in

Lines per rail

4

rail 21.0 in ≥ 16.5 in

Crushing ceiling

424 psi

Punching shear reinforcement layoutACI 318-19 §22.6.6 / §8.7.6–8.7.7

System#3 headed studs — 3 rails per face (12 lines), s₀ = 3.0 in, s = 6.0 in, 4 lines each rail
First line s₀3.0 in from the column face (≤ d/2 = 4.00 in)
Peripheral spacing6.0 in (s_max = 6.00 in)
Outer critical sectionb_o,out required 212 in → extend 16.5 in beyond the column
A_v per peripheral line1.32 in² (12 legs)

Cap / column reinforcement layoutACI §8.7.4.2 · §10.6 · §25.7.2

Column vertical bars12 – #6 vertical bars (ρ = 1.32 %) with #4 ties @ 12 in, tightened to 6 in through the joint
Tie spacing through joint6.0 in (#4)
Top band steel over column#9 @ 6.5 in top over the column band
Structural-integrity bottom bars6 – #5 continuous bottom bars through the column core (§8.7.4.2)
A_st required / provided4.00 / 5.28 in²

PASS — Shear reinforcement required: headed shear studs #3, 12 lines, first line at 3.0 in then @ 6.0 in for 4 peripheral lines (21.0 in from the column face) — φv_n = 247 psi ≥ v_u = 235 psi, and the outer section at 16.5 in needs b_o ≥ 212 in.

Detailing sketchPunching shear — critical perimeter plan, stud-rail layout and section
PLAN — CRITICAL PERIMETER & STUD RAILScritical section at d/2c₁ = 20.0 inc₂ = 20.0 inSECTION THROUGH THE COLUMN — CRITICAL SECTION AT D/2h = 10.0 ind = 8.00 inStud rail spacing s₀ = 3.0 in from column face, s = 6.0 in peripheral

Column 20.0 × 20.0 in, interior condition. Critical section at d/2 (d = 8.00 in), perimeter bo = 112.0 in. Headed stud rails: 3 rails/face, s₀ = 3.0 in, s = 6.0 in, 4 lines, rail length 21.0 in (extend ≥ 16.5 in).

Module 102AASHTO LRFD AISC 360-22 §H3 · §E4 · §F2 · DG9Chapters 8 · 11

Torsion & stability — open sections and HSS

St. Venant plus warping torsion, plate slenderness classification, flexural and flexural-torsional buckling, lateral-torsional buckling, the §H3.2 combined interaction, twist serviceability and the torsional restraint detailing.

T_n = F_cr C · a = √(EC_w/GJ) · F_e,T = [π²EC_w/(K_zL)² + GJ]/(I_x+I_y) · (P_r/P_c + M_r/M_c) + (V_r/V_c + T_r/T_c)² ≤ 1

φT_n

2316 kip-in

T_u/φT_n = 0.13

Twist θ

1.36 deg

Section class

compact

flange compact, web compact

KL/r

91.4

F_cr = 27.13 ksi

φP_n

437 kip

φM_n

241 k-ft

closed section — LTB does not govern (§F7)

φV_n

324 kip

L_p / L_r

11.1 / — ft

Interaction

0.589

§H1.1 (torsion ≤ 20 % — may be neglected)

Torsion mechanicsAISC 360-22 §H3 · Design Guide 9

Torsional modelRectangular HSS, §H3.1: C = 85.8 in³, h/t = 21.0, F_cr = 30.0 ksi
Torsional bending constant an/a (closed section)
St. Venant shear stress0.46 ksi
Warping constant C_w0 in⁶
Torsion utilization0.130

Torsional restraint & detailingAISC §H3.2 · DG9 Ch. 6

DetailingTorsion is a secondary effect (T_u/φT_n = 0.13) — provide 0.500 in end connection plates able to develop the end torque, with 0.250 in fillet welds.
Internal diaphragmsNot required
End plate thickness0.500 in
Fillet weld to transfer torque0.250 in, E70XX
Governing interaction§H1.1 (torsion ≤ 20 % — may be neglected) = 0.589

PASS — All limit states satisfied: torsion 0.13, axial 0.18, flexure 0.50, shear 0.12; §H1.1 (torsion ≤ 20 % — may be neglected) = 0.59 ≤ 1.0; compact section, closed section — LTB does not govern (§F7).

Detailing sketchTorsion & stability — section, shear flow, twist and interaction
SECTION & SHEAR FLOWd = 12.0, b_f = 8.0 int_f = 0.500, t_w = 0.500 inTWIST ALONG THE LENGTHθ_max = 1.36° over L = 24.0 ftINTERACTION CHECKP_r / P_cM_r / M_cV_r=0.123, T_r=0.130

Rectangular HSS, Tu = 300 kip-in vs φTn = 2316 kip-in (Tu/φTn = 0.13). Twist over L = 24.0 ft is θ = 1.36°. Combined interaction satisfied.

Module 103AASHTO LRFD AASHTO §6.10.9 / §6.10.11 · AISC §G2.3 / §F13Chapters 8 · 11

Plate-girder transverse & longitudinal stiffeners

Web and flange proportion limits and plate classification, tension-field shear, transverse stiffener size and rigidity, longitudinal stiffener location and inertia, bearing stiffener bearing/column checks, and final fillet-weld legs and lengths.

k = 5 + 5/(d_o/D)² · V_n = V_p[C + 0.87(1−C)/√(1+(d_o/D)²)] · I_t ≥ d_o t_w³ J · R_sb = 1.4A_pn F_ys

D/t_w

120.0

limit 150

Web / flange class

noncompact / compact

k / C

7.22 / 0.457

V_p

870 kip

φV_n

625 kip

tension field used

Required d_o

60 in

current spacing adequate

Transverse PL

4.5 × 0.375 in

I 26.8 ≥ 23.2 in⁴

Bearing PL

7.3 × 0.688 in

R_sb = 650 kip

Weld legs

0.250 / 0.250 in

intermediate / bearing

Shear panel & plate classificationAASHTO §6.10.2 / §6.10.9 · AISC §G2.3

Web slendernessD/t_w = 120.0 (limit 150); 2D_c/t_w classification: noncompact
Flange slendernessb_f/2t_f = 8.00 → compact; proportions OK
Panel aspect d_o/D1.500
Tension fieldpermitted and used
V_n (TF / no TF)625 / 397 kip

Stiffener & weld scheduleAASHTO §6.10.11 · §6.13.3

Transverse stiffenersPairs of PL 4.5 × 0.375 transverse stiffeners @ 90 in c/c, 0.250 in fillet welds each side over 58 in, cut back 4t_w–6t_w from the tension flange
Rigidity checkI_t,prov 26.8 in⁴ vs I_t,req 23.2 in⁴ (J = 0.50)
Longitudinal stiffenerNo longitudinal stiffener required at this web slenderness
Bearing stiffenersBearing stiffeners: pair of PL 7.3 × 0.688, milled to bear, 0.250 in fillet welds full depth (effective column 14.5 in², KL/r = 12)
Bearing stiffener columnA_eff = 14.47 in², KL/r = 12.3, φP_n = 680 kip
WeldsIntermediate 0.250 in fillet each side; bearing stiffener 0.250 in full depth (min leg 0.2500 in)

PASS — Panel verified: tension-field action permitted, C = 0.457, φV_n/V_u = 1.49. Stiffeners 2 × 4.5 × 0.375 in @ 90 in with 0.250 in fillet welds; bearing stiffeners 0.688 in with 0.250 in welds.

Detailing sketchPlate-girder web panel — elevation and stiffener section
d_o = 90.0 inD = 60.0 inDiagonals indicate the tension field in each panelELEVATION — girder webAASECTION A–A — STIFFENER PLAN AT THE WEB (LOOKING DOWN)b_t ≈ 4.0 instiffener plate each side of the webWeb t_w = 0.500 in; fillet welds to the web, tight fit to the compression flange (6.10.11.1)b_t ≥ 2.0 + D/30 and 0.25 b_f; t_p ≥ b_t/16 · √(F_ys/E) limits (6.10.11.1.2–.3)

Web 60.0 in deep × 0.500 in thick, D/tw = 120, transverse stiffeners at do = 90.0 in (do/D = 1.50). Vu = 420 kip vs φVn = 625 kip (AASHTO 6.10.9).

Calculation reports

Every module is print-ready

Each of the calculators above exports a full calculation report — governing equations, substituted values, engineering assumptions, and pass/fail limit-state checks — ready to print or save as a PDF for your project files.

Bridge Engineering and Design Using AASHTO LRFD

Graduate interactive textbook for civil engineering students. Aligned to AASHTO LRFD Bridge Design Specifications, 10th Edition (2024).

Regional focus

Maryland & Mid-Atlantic — MDOT SHA, VDOT, PennDOT, FHWA.

Educational notice

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

© 2026 Dr. Steve Efe, Ph.D. All Rights Reserved.

Developed for engineering education. Unauthorized reproduction, distribution, or commercial use is prohibited.

v1.0 · Reference edition · Aligned to AASHTO LRFD, 10th Edition (2024)