This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.
AASHTO Design Studio
Transparent LRFD calculators
Cascading whole-bridge model
Full-Bridge Designer
One model from traffic loads to pile tip. Change the girder spacing, slab thickness or limit state and the deck strip moments, distribution factors, girder flexure and shear, bearing reactions, pier-cap strut-and-tie, column P-Δ interaction and the foundation all re-solve together — every check citing its AASHTO LRFD article with a utilization ratio.
Chapter 1
Bridge engineering fundamentals and design basis
Preliminary proportioning, life-cycle cost screening, and the LRFD reliability framework — load modifiers, factored demand versus factored resistance and the target reliability index.
Preliminary sizing, span-to-depth & life-cycle cost
Table 2.5.2.6.3-1 minimum depth, the L/800 live-load deflection limit, deck and girder quantities, and the present value of owner cost over the analysis period.
Span-to-depth screening from Table 2.5.2.6.3-1, the L/800 live-load deflection limit, deck quantities and a present-value comparison of owner cost.
Minimum overall depth
46.1 in
L/31
Girder spacing S
8.80 ft
Δ_allow = L/800
1.80 in
Deck concrete
138.5 yd³
Life-cycle PV
$1188073
Derivation — equation, substitution, result
Span-to-depth screening
Steel section depth
Girder spacing
Live-load deflection limit
Deck concrete quantity
Slab load per girder
Life-cycle present value
Detailing — plan, elevation and section
Constructability & detailing notes
- Keep the girder depth constant along the span where possible — haunched webs add fabrication cost that rarely pays back below 200 ft spans.
- Check shipping limits early: 12 ft depth and 150 ft length are practical highway limits for a single piece.
- Girder spacing between 8 and 12 ft usually minimises total cost; wider spacing thickens the deck and increases the distribution factor.
- Allow 2 in minimum haunch for construction tolerance and screed adjustment.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Girder spacing within the §4.6.2.2 approximate-equation range 3.5 – 16 ft | 8.80 ft | 3.5 – 16 ft | PASS |
| Deck thickness ≥ 7 in (§9.7.1.1) | 8.50 in | 7.0 in | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Depth ≈ 0.033L for a continuous composite steel girder | 47.5 in | VERIFIED |
Assumptions & basis of design
- Depth ratios from AASHTO LRFD Table 2.5.2.6.3-1 for constant-depth superstructures.
- Concrete unit weight 0.150 kcf; the deck quantity excludes haunches, barriers and the wearing surface.
- The present-value screening is a uniform-series discounting of owner cost — not an AASHTO provision.
Use the screening depth as the starting trial section, then confirm with the Chapter 8 flexure and Chapter 4 deflection modules.
LRFD design basis — η, factored demand and reliability
Ductility, redundancy and importance modifiers combined into η, the Strength I factored demand against φR_n, and the reliability index β = (μ_R − μ_Q)/√(σ_R² + σ_Q²).
Combines the ductility, redundancy and importance modifiers into η, applies the Strength I factors, and back-checks the reliability index.
η (load modifier)
1.050
Factored demand Q
5748.8
Factored resistance R_r
5400.0
Utilisation Q/R_r
1.065
Reliability index β
4.17
Derivation — equation, substitution, result
Load modifier
Factored demand
Factored resistance
Design inequality
Reliability index
Probability of failure
Detailing — plan, elevation and section
η-modified factored load Qu = 5749 vs. φRn = 5400 (nominal Rn = 6000). Reliability index β = 4.17 against the Strength I target β ≈ 3.50.
Constructability & detailing notes
- η is applied to the load side, never to the resistance — a common mark-up error in student calculations.
- Record the assumed operational classification on the cover sheet; it drives both η_I and the seismic R factor.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Strength limit state Σηγ Q ≤ φR_n | 5748.8 | 5400.0 | REVIEW |
| Target reliability β_T = 3.5 (§C1.3.2.1) | 4.17 | 3.50 | PASS |
| η ≥ 0.95 for maximum load factors | 1.050 | 0.95 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Target reliability index for Strength I | β ≈ 3.5 | 4.17 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD Eq. 1.3.2.1-1 with Strength I permanent factors from Table 3.4.1-2 (γ_DC 1.25/0.90, γ_DW 1.50/0.65).
- η_D, η_R and η_I each fall between 0.95 and 1.05; the minimum-load case inverts the product.
- The reliability index uses the lognormal-free first-order form; the AASHTO calibration target for girders is β_T = 3.5 at Strength I.
Demand exceeds resistance by 6.5 % — increase R_n by that margin, or reduce DW by specifying no future overlay allowance where the owner permits.
Chapter 3
Loads and load combinations
The HL-93 model, the position that maximises its effect, and the load factors that turn nominal effects into factored demands.
HL-93 live-load envelope (simply supported)
Envelope of design truck / tandem + lane load with IM and multiple-presence factors.
Computes the maximum midspan moment and end shear from the HL-93 envelope. AASHTO LRFD §3.6.1.2 / §3.6.2
Max midspan moment
kip-ft per design lane × factors
M = m · n · [(1+IM)·max(M_truck, M_tandem) + M_lane]
- M_truck (per lane)
- 1883.0 kip-ft
- M_tandem (per lane)
- 1450.3 kip-ft
- M_lane (per lane)
- 1152.0 kip-ft
- Governs
- Design truck
Max end shear
kip per design lane × factors
V = m · n · [(1+IM)·max(V_truck, V_tandem) + V_lane]
- V_truck (per lane)
- 60.80 kip
- V_tandem (per lane)
- 49.17 kip
- V_lane (per lane)
- 38.40 kip
- Governs
- Design truck
- w
- design lane load intensity [klf]
- L
- simply supported span length [ft]
- IM
- dynamic load allowance (33% typ.) [-]
- m
- multiple-presence factor [-]
Verification
Order-of-magnitude check: for L = 120 ft, the HL-93 envelope (per lane, per AASHTO tables) gives M ≈ 2,090 kip-ft (unfactored, no IM, no m). With IM = 1.33 and m = 1.00 the moment should approach ≈ 2,780 kip-ft plus lane contribution. Compare to the value returned above.
What can go wrong
This calculator idealizes a simply supported span. For continuous spans, use influence surfaces and apply the truck + lane combination for positive moment and two trucks (min. 50 ft between axles) × 0.90 + two lanes for negative moment AASHTO LRFD §3.6.1.3.1. Consult refined analysis for skew and curved bridges.
Governing vehicle: Design truck for moment (1883 vs 1450 k-ft truck/tandem), Design truck for shear. Design MLL+IM = 3656 k-ft, design VLL+IM = 119.3 kip on a 120 ft span.
Design-truck absolute maximum moment (Barré)
Locates the critical axle position by Barré's theorem, then computes truck, tandem and lane moments and the governing HL-93 moment and shear for one lane on a simple span.
Barré's theorem locates the absolute maximum moment under the axle nearest the resultant — not at midspan.
Maximum truck moment (no IM)
1164.9 k-ft
Maximum tandem moment (no IM)
950.0 k-ft
Lane moment
512.0 k-ft
Governing M_LL+IM per lane
2061.3 k-ft
Governing V_LL+IM per lane
110.19 kip
Governing live-load moment MLL+IM = 2061.30 k-ft per lane on a 80.0 ft span, lane load 0.64 klf.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Axle resultant location | x̄ = ΣPᵢxᵢ / ΣPᵢ | (8·0 + 32·14 + 32·28) / 72 | 18.67 ft from the front axle |
| Offset resultant-to-critical axle | e = |x̄ − x_crit| | |18.67 − 14| | 4.67 ft |
| Critical axle position (Barré) | a = L/2 − e/2 | 80.0/2 − 4.67/2 | 37.67 ft from the left support |
| Left reaction for that position | R = Σ Pᵢ(L − xᵢ)/L | 8(56.33) + 32(42.33) + 32(28.33) / 80.0 | 33.90 kip |
| Maximum truck moment | M = R·a − Σ P_left(a − xᵢ) | 33.90·37.67 − Σ… | 1164.9 k-ft |
| Design tandem moment | M = R·a₁ with axles at L/2 ± 2 ft | 25.00·38.00 | 950.0 k-ft |
| Design lane moment | M = wL²/8 | 0.64·80.0²/8 | 512.0 k-ft |
| Truck + IM | M_truck(1 + IM/100) | 1164.9 × 1.33 | 1549.3 k-ft |
| Governing HL-93 moment | M_LL+IM = max(M_truck, M_tandem)(1+IM) + M_lane | max(1549.3, 1263.5) + 512.0 | 2061.3 k-ft/lane |
| Governing HL-93 shear at support | V = max(V_truck, V_tandem)(1+IM) + V_lane | max(63.60, 48.75)·1.33 + 25.60 | 110.19 kip/lane |
The design truck governs moment on this 80 ft span (1549.3 k-ft vs 1263.5 k-ft for the tandem). The tandem typically governs below about 40 ft.
Assumptions & code basis
- HL-93 design truck 8-32-32 kip at 14 ft axle spacings (rear spacing at its 14 ft minimum for maximum simple-span moment), AASHTO LRFD §3.6.1.2.2.
- Design tandem: two 25 kip axles 4 ft apart, §3.6.1.2.3. Design lane load 0.64 klf over the full span, §3.6.1.2.4.
- Absolute maximum moment located by Barré's theorem: the span centreline bisects the distance between the resultant of the axles on the span and the axle nearest it.
- Dynamic load allowance IM applies to the truck or tandem only, never to the lane load (§3.6.2.1).
- Result is one lane of live load on a simple span before the distribution factor and multiple-presence factor are applied.
Influence-line explorer
Slide the HL-93 truck to locate the critical loading position for moment and shear at any section.
Drag the truck along the span and reposition the analysis section. AASHTO LRFD §3.6.1.2 — Design Vehicular Live Load
Moment at x = 60.0 ft
kip-ft (unfactored, per lane, IM not applied)
Shear at x = 60.0 ft
kip (unfactored, per lane, IM not applied)
How to use this
- Set the section (x/L) where you want the maximum effect.
- Slide the truck until the heaviest axles align under the peak ordinate.
- For shear at the end, sweep the truck toward the support; the lane load ordinate is largest just past the cut.
- Change the variable spacing (14 ft governs for most spans < 100 ft; 30 ft can govern for shear at far support on long spans).
Load-combination generator
Applies the Strength, Service, and Fatigue load factors to your DC, DW, and LL+IM effects, with maximum and minimum permanent-load cases.
Q = Σ η γᵢ Qᵢ. DC1 acts on the bare girder, DC2 on the composite section; both carry γ_DC. Maximum load factors govern where the effect adds; minimum factors govern where a permanent load relieves the effect (uplift, overturning, retaining walls).
M_DC = M_DC1 + M_DC2
900 k-ft
M_DW
140 k-ft
Factored M_u (Strength I)
3435 k-ft
MDC1 = 620 k-ft (girder + slab + haunch on the non-composite section) · MDC2 = 280 k-ft (barriers on the composite section) · MDW = 140 k-ft · MLL+IM = 1200 k-ft (distributed) · factored Mu = 3435 k-ft.
| Combination | γ_DC | γ_DW | γ_LL | Q (max) | Q (min) |
|---|---|---|---|---|---|
| Strength I | 1.25 | 1.50 | 1.75 | 3435 | 3001 |
| Strength II (permit) | 1.25 | 1.50 | 1.35 | 2955 | 2521 |
| Strength IV (dead governs) | 1.50 | 1.50 | 0.00 | 1560 | 901 |
| Service I | 1.00 | 1.00 | 1.00 | 2240 | 2240 |
| Service III (PS tension) | 1.00 | 1.00 | 0.80 | 2000 | 2000 |
| Fatigue I | 0.00 | 0.00 | 1.75 | 2100 | 2100 |
Design lanes, multiple presence & dynamic allowance
N_L = INT(w/12), the Table 3.6.1.1.2-1 multiple-presence factor m, and IM for decks, fatigue, buried components and all other components with the fill-depth reduction.
Number of design lanes, multiple-presence factor and the dynamic load allowance for the component you are designing.
Design lanes N_L
3
Multiple presence m
0.85
IM
33.0 %
Live-load effect
217.1 kip
Derivation — equation, substitution, result
Number of design lanes
Multiple presence
Dynamic load allowance
Applied to truck/tandem only
Factored one-component effect
Detailing — plan, elevation and section
Clear roadway 40.0 ft ⇒ NL = 3 design lane(s) at 200.00 ft each. Multiple-presence factor m = 0.85 governs when fewer than 3 lanes are loaded. IM = 33 % applied to the truck/tandem for the other case (not to the lane load).
Constructability & detailing notes
- The multiple-presence factor is already embedded in the approximate distribution-factor equations — never apply it twice.
- Fatigue design uses one truck in one lane with m = 1.0 and IM = 15 %.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Roadway wide enough for the assumed loaded lanes | 3 lanes | 3 lanes | PASS |
| m not applied with the approximate distribution equations (already embedded)Use m only with the lever rule, the rigid cross-section method or a refined analysis. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| N_L = INT(w/12) | 3 | 3 | VERIFIED |
Assumptions & basis of design
- Design lane width 12 ft with the 10-ft loaded strip placed to produce the extreme effect (§3.6.1.3.1).
- IM applies to the design truck and tandem only, and not to fatigue-limit centrifugal or braking forces.
- For 20 ft ≤ w < 24 ft, AASHTO requires two design lanes each equal to half the roadway width.
For the fatigue limit state use one lane with m = 1.00 (§3.6.1.4.3b) — the 1.20 single-lane factor is removed.
Braking (BR) and centrifugal (CE) forces
The governing of 25 % of axle weights and 5 % of truck-plus-lane, the centrifugal factor C = f v²/(gR), the 6 ft application height, and the overturning couple delivered to the substructure.
BR is the larger of 25 % of the axle weights or 5 % of truck plus lane; CE uses the f = 4/3 factor for the truck only.
Braking force BR
36.00 kip
Centrifugal force CE
32.35 kip
Governing horizontal
36.00 kip
braking governs
Substructure moment
468.0 kip·ft
Derivation — equation, substitution, result
Braking — 25 % of the axles
Braking — 5 % of truck + lane
Governing braking force
Centrifugal coefficient
Centrifugal force
Overturning couple
Detailing — plan, elevation and section
BR = 36.0 kip acts 6.0 ft above the deck, transferred through 7.0 ft to the bearings. CE = 32.4 kip from a curve radius R = 1200 ft adds a lateral, overturning couple at the same elevation.
Constructability & detailing notes
- Braking force acts 6 ft above the deck in both directions — check the bearings and the anchor bolts for the reversal.
- Centrifugal force adds an overturning couple that can unload the inside girder; verify uplift at the bearings.
- Detail fixed and expansion bearings so the horizontal load path into the substructure is explicit on the plans.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Braking applied in both directions on all lanes headed the same wayLanes carrying traffic in one direction only — use m for the number of loaded lanes. | — | — | PASS |
| Centrifugal force acts 6 ft above the roadway (§3.6.3) | 6.0 ft | 6.0 ft | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| BR ≥ 0.25 × axle weights | 18.0 kip per lane | VERIFIED |
Assumptions & basis of design
- BR per §3.6.4 with the dynamic load allowance intentionally omitted; the force acts 6 ft above the roadway surface.
- CE per §3.6.3 with f = 4/3 for all limit states except fatigue, where f = 1.0.
- Both forces are transmitted through the bearings into the substructure — check the anchor bolts and the bearing shear capacity.
Braking governs: detail the fixed bearing and its anchorage for this force, and check the pier for the resulting base moment.
Chapter 4
Section properties and composite action
Neutral axis, transformed sections, effective flange width, and the permanent loads each stage of the section must carry.
Transformed composite section properties
Modular ratio, §4.6.2.6 effective flange width, the composite neutral axis and inertia at n and 3n, and the stage-by-stage section moduli that DC1, DC2/DW and LL+IM act on.
Enter the bare-steel (or precast) girder properties; the module transforms the deck at n and 3n and reports the stage-by-stage section moduli.
Modular ratio n
7.96
Effective flange width b_eff
108.0 in
Non-composite I / S_b
20000 / 833 in⁴ / in³
Short-term composite I (n)
50535 in⁴
Long-term composite I (3n)
38763 in⁴
S_b short term / long term
1128 / 1051 in³
Effective flange width beff = 108.00 in; short-term composite I = 50535 in⁴.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Deck modulus | E_c = 33,000 w_c^1.5 √f′_c | 33,000 (0.145)^1.5 √4.00 | 3644 ksi |
| Modular ratio | n = E_s / E_c | 29000 / 3644 | 7.96 |
| Effective flange width | b_eff = min(S, L_eff/4) | min(108.0, 300.0) | 108.0 in |
| Transformed deck area (short term) | A_tr = b_eff·t_s / n | 108.0·8.00 / 7.96 | 108.57 in² |
| Composite neutral axis (n) | ȳ_b = Σ A_i y_i / Σ A_i | (48.00·24.00 + 108.57·54.00) / 156.57 | 44.80 in above the bottom flange |
| Composite inertia (n) | I = ΣI_i + ΣA_i d_i² | 20000 + … | 50535 in⁴ |
| Section moduli (n) | S_b = I/ȳ_b, S_t = I/y_t | 50535/44.80, 50535/3.20 | S_b = 1128 in³, S_t = 15806 in³ |
| Composite inertia (3n, long term) | Repeat with n′ = 3n | n′ = 23.87 | I = 38763 in⁴, ȳ_b = 36.90 in |
| Deck top-fibre modulus | S_deck = n·I / y_deck | 7.96·50535 / 13.20 | 30473 in³ |
Composite action increases the bottom-fibre section modulus from 833 in³ (steel alone, carrying DC1) to 1128 in³ (n, live load) — a factor of 1.35. Stack the stresses stage by stage: DC1 on the steel section, DC2 and DW on the 3n section, LL+IM on the n section.
Assumptions & code basis
- Modular ratio n = E_s/E_c with E_c = 33,000 w_c^1.5 √f′_c (AASHTO LRFD Eq. 5.4.2.4-1), w_c = 0.145 kcf.
- Effective flange width per §4.6.2.6.1: the tributary width, limited by L_eff/4 for interior girders (one-quarter effective span; L/8 each side for exterior).
- Short-term (n) properties govern live load; long-term (3n) properties govern superimposed dead load DC2/DW to account for creep (§6.10.1.1.1b).
- Concrete deck is assumed uncracked and fully composite in positive-moment regions; in negative-moment regions only the longitudinal deck reinforcement is normally considered effective.
- Haunch depth is included in the geometry but its concrete area is conservatively neglected.
Girder dead loads — DC1, DC2 & DW
Non-composite DC1 (slab, haunch, girder, diaphragms, forms), composite DC2 (barriers/sidewalk) and DW (future wearing surface), with midspan moments, support shears and factored permanent effects.
DC1 = slab + haunch + girder + diaphragms + SIP forms (non-composite) · DC2 = barriers / sidewalk ÷ Nb (composite) · DW = FWS × roadway width ÷ Nb
w_DC1 (non-composite)
0.9883 kip/ft
slab 0.8000 + haunch 0.0333
w_DC2 (composite)
0.1800 kip/ft
barriers shared by all girders
w_DW
0.2100 kip/ft
future wearing surface
M_DC1
790.7 kip-ft
M_DC2
144.0 kip-ft
M_DW
168.0 kip-ft
V_DC1
39.5 kip
V_DC2
7.2 kip
V_DW
8.4 kip
Strength I permanent moment (max: 1.25DC + 1.50DW)
1420.3 kip-ft
min case 0.90DC + 0.65DW = 950.4 kip-ft
Service I permanent moment (1.0DC + 1.0DW)
1102.7 kip-ft
factored permanent shear = 71.0 kip
MDC1 = 791 k-ft (girder + slab + haunch on the non-composite section) · MDC2 = 144 k-ft (barriers on the composite section) · MDW = 168 k-ft · MLL+IM = 0 k-ft (distributed) · factored Mu = 1420 k-ft.
Live load (HL-93) is added separately in Module 2, then distributed to the girder with the factors from Module 4. Only DC1 acts on the bare girder section; DC2 and DW act on the composite section, so their stresses use the composite section moduli.
Steel I-section stability & compression design
Cross-section proportion limits, web/flange classification, flange local buckling and lateral–torsional buckling with L_p / L_r, plus a compression-member slenderness check.
I-section
Compression member
λ_f = b_fc/2t_fc · L_p = 1.0 r_t √(E/F_yc) · L_r = π r_t √(E/F_yr) · F_nc = min(FLB, LTB) · P_n = 0.658^(P_o/P_e) P_o
D / t_w
108.0
limit 150 (§6.10.2.1.1)
b_fc / 2t_fc
8.00
λ_pf = 9.15, λ_rf = 16.97
Web class
non-compact
2D_c/t_w = 119.1
R_b (load shedding)
1.000
L_p
7.4 ft
bracing for full yield
L_r
27.8 ft
L_b = 20.0 ft → inelastic
F_nc (FLB)
50.00 ksi
F_nc (LTB)
40.76 ksi
F_nc governing
40.76 ksi
Lateral–torsional buckling (§6.10.8.2.3)
φM_n vs M_u
3900 ≥ 4200 k-ft
S_xc = 1148 in³ · utilization 1.08
Design verdict & redesign guidance
- • LTB governs at L_b = 240.0 ft: brace at or below L_p = 89.0 in (7.4 ft) to develop the full yield moment.
- • φM_n = 3900 k-ft < M_u = 4200 k-ft — increase S_xc by about 8%: try t_fc = 1.077 in or D = 56 in.
KL/r
86.1
limit 120 (§6.9.3)
P_e (Euler)
568 kip
inelastic buckling
φ_c P_n vs P_u
406 ≥ 300 kip
Compression-member verdict
- • Column adequate: KL/r = 86, utilization 0.74.
F_nc = 40.76 ksi · φM_n = 3900 k-ft vs M_u = 4200 k-ft
Chapter 4
Live-load distribution
How much of a lane a single girder carries — the approximate equations plus the stiffness, skew, lever-rule and rigid cross-section checks that surround them.
Live-load distribution factors
Approximate distribution equations for concrete decks on steel or prestressed I-girders, interior and exterior.
Cross-section type (k): concrete deck on steel or prestressed-concrete I-girders. Valid for 3.5 ≤ S ≤ 16 ft, 20 ≤ L ≤ 240 ft, 4.5 ≤ tₛ ≤ 12 in.
Kg / (12·L·tₛ³) = 5.0863 · gM,int = 0.075 + (S/9.5)0.6(S/L)0.2(Kg/12Ltₛ³)0.1
Interior moment — one lane
0.531 lanes/girder
Interior moment — two+ lanes
0.745 lanes/girder
Interior shear — one lane
0.680 lanes/girder
Interior shear — two+ lanes
0.814 lanes/girder
Exterior moment (e = 0.77 + dₑ/9.1)
0.737
e = 0.990
Exterior shear (e = 0.6 + dₑ/10)
0.652
e = 0.800
Governing interior moment factor is 0.745. Exterior girders must also be checked by the lever rule and the rigid cross-section (special analysis) equation for beam-slab bridges with diaphragms.
6 girders at S = 8.00 ft spacing, deck thickness ts = 8.00 in, overhang de = 2.00 ft. Interior moment DF ≈ 0.745 lanes/girder; exterior moment DF ≈ 0.737 lanes/girder.
K_g, skew corrections, lever rule & rigid cross-section
The longitudinal stiffness parameter K_g = n(I + Ae_g²), the §4.6.2.2.2e moment reduction and §4.6.2.2.3c shear increase for skew, and the two exterior-girder checks — lever rule and the rigid cross-section special analysis — with multiple-presence factors.
Wheel offsets are the distances from the exterior girder to each wheel of the loaded lanes, measured along the deck.
K_g
502964 in⁴
Skew factor — moment
1.0000
Skew factor — shear (obtuse corner)
1.1087
Lever-rule exterior DF
0.4444 lanes/girder
Rigid cross-section DF
1.0222 lanes/girder
Governing exterior DF
1.0222 lanes/girder
Governing exterior distribution factor = 1.022 lanes/girder for 5 girders at S = 9.00 ft, skew θ = 30°.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Modular ratio | n = E_B/E_D | 29000/3644 | 7.958 |
| Longitudinal stiffness parameter | K_g = n(I + A e_g²) | 7.958(20000 + 48.00·30.00²) | 502964 in⁴ |
| Stiffness term | K_g/(12 L t_s³) | 502964/(12·100.0·8.00³) | 0.8186 |
| Skew correction — moment | 1 − c₁(tan θ)^1.5 ; c₁ = 0.25(K_g/12Lt_s³)^0.25 (S/L)^0.5 | c₁ = 0.0713, θ = 30.0° | 1.0000 |
| Skew correction — shear | 1.0 + 0.20 (K_g/12Lt_s³)^0.3 tan θ | 1 + 0.20(0.8186)^0.3 tan 30.0° | 1.1087 |
| Lever rule reaction | R = Σ P_i x_i / S (P = 0.5 axle) | Σ(7.00, 1.00)/9.00 | 0.4444 lanes |
| Lever rule DF with m | g = m·R | 1.00 × 0.4444 | 0.4444 lanes/girder |
| Rigid cross-section reaction | R = N_L/N_b + X_ext ΣE / Σx² | 2/5 + 18.00·2·14.00/810.0 | 1.0222 |
| Rigid cross-section DF with m | g = m·R | 1.00 × 1.0222 | 1.0222 lanes/girder |
Exterior-girder design must use the largest of the approximate e·g equation, the lever rule (0.4444) and the rigid cross-section value (1.0222). Multiply moment DFs by 1.0000 and the support shear of the exterior girder at the obtuse corner by 1.1087.
Assumptions & code basis
- K_g = n(I + A e_g²) per AASHTO LRFD Eq. 4.6.2.2.1-1, with e_g the distance between the girder and deck centroids.
- Skew correction for moment applies only for 30° < θ ≤ 60° (§4.6.2.2.2e); for θ ≤ 30° no reduction is taken and for θ > 60° a refined analysis is required.
- Skew correction for support shear at the obtuse corner of the exterior girder, Table 4.6.2.2.3c-1, always ≥ 1.0 — the shear correction is an increase.
- Lever rule assumes the deck is hinged over the interior girder; wheel loads are placed 2 ft from the barrier face and 6 ft apart (§3.6.1.3.1).
- The rigid cross-section (special analysis) equation §C4.6.2.2.2d applies to beam-slab bridges with sufficiently stiff diaphragms or cross-frames acting as a unit.
- Multiple-presence factors m (1.20 / 1.00 / 0.85 / 0.65) are included in the lever-rule and rigid-section results but are already embedded in the approximate DF equations.
Cracked negative-moment composite section
Stage-dependent section properties neglecting concrete in tension, with the longitudinal deck steel acting compositely and the fibre stresses for DC1, DC2/DW and LL+IM at the pier.
Negative-moment region: the deck concrete is neglected and only the longitudinal deck steel acts with the girder.
Cracked ȳ
32.26 in
I_cr
45203 in⁴
S_b,cr
1401 in³
f_bottom
-32.49 ksi
f_top
-27.40 ksi
Deck reinforcement stress
-16.20 ksi
Derivation — equation, substitution, result
Cracked-section area
Neutral axis
Cracked inertia
Section moduli
Bottom-flange stress
Top-flange stress
Deck-steel stress
Detailing — plan, elevation and section
Constructability & detailing notes
- Two-thirds of the longitudinal deck steel goes in the top mat; place it before the negative-moment pour.
- Stagger deck-steel splices and extend the steel past the dead-load inflection point plus the development length.
- Shear studs are required through the negative-moment region even though the concrete is neglected for strength.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Bottom flange ≤ F_y | 32.49 ksi | 50 ksi | PASS |
| Top flange ≤ F_y | 27.40 ksi | 50 ksi | PASS |
| Deck longitudinal steel ≥ 1 % of the slab area (§6.10.1.7)Two-thirds in the top mat; #6 bars or smaller at ≤ 12 in. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Cracked inertia is smaller than the short-term composite value | I_cr < I_composite | in⁴ | VERIFIED |
Assumptions & basis of design
- Negative-moment region: concrete in tension is neglected and only the longitudinal deck reinforcement within the effective flange width acts compositely (§6.10.1.1.1c).
- DC1 acts on the bare steel section; DC2 and LL+IM act on the cracked composite section.
- Stresses are elastic first-order values — compare against the §6.10.8 lateral–torsional buckling resistance, not simply F_y, when the bottom flange is in compression.
Elastic stresses are within yield; continue with the §6.10.8 stability checks and the §6.10.1.7 minimum deck steel.
Chapter 5
Deck design
Equivalent strips, the three overhang design cases with yield-line barrier analysis, and the empirical (isotropic) design method.
Deck equivalent strip & Strength I demand
Equivalent strip widths for positive, negative, and overhang design, with factored slab moments and both reinforcement mats.
+M strip (26.0 + 6.6S)
78.8 in
−M strip (48.0 + 3.0S)
72.0 in
Overhang strip (45.0 + 10.0X)
75.0 in
M_DC
0.64 k-ft/ft
M_DW
0.16 k-ft/ft
M_LL+IM (approx.)
6.48 k-ft/ft
Strength I M_u
12.38 k-ft/ft
Bottom mat (+M)
#4 @ 5.5 in
A_s,req 0.432 → A_s,prov 0.436 in²/ft
Top mat (−M)
#6 @ 10.0 in
A_s,req 0.515 → A_s,prov 0.528 in²/ft
Deck bottom mat (positive moment) — AASHTO LRFD §5.6.3 / §5.10
| A_s required (strength) | 0.43 in²/ft |
| A_s minimum (§5.6.3.3 / §5.10.6) | 0.19 in²/ft |
| A_s design (governing) | 0.43 in²/ft |
| Bar selection | #4 @ 5.5 in c/c |
| Bar size / area | #4 — A_b = 0.20 in² |
| Spacing (c/c) | 5.5 in |
| A_s provided | 0.44 in²/ft |
| A_s,prov / A_s,req | 1.01 |
| Stress-block depth a | 0.64 in |
| Net tensile strain ε_t | 0.0236 |
| φ | 0.900 |
| φM_n (as detailed) | 12.5 k-ft/ft |
| M_cr (§5.6.3.3) | 5.5 k-ft/ft |
| Minimum-resistance demand min(M_cr, 1.33M_u) | 5.5 k-ft/ft |
| Reinforcement ratio ρ | 0.0054 |
PASS — Adequate — detail as scheduled
A_s,prov / A_s,req = 1.01; ε_t = 0.0236 (tension-controlled, φ = 0.90).
Deck top mat (negative moment) — AASHTO LRFD §5.6.3 / §5.10
| A_s required (strength) | 0.51 in²/ft |
| A_s minimum (§5.6.3.3 / §5.10.6) | 0.24 in²/ft |
| A_s design (governing) | 0.51 in²/ft |
| Bar selection | #6 @ 10.0 in c/c |
| Bar size / area | #6 — A_b = 0.44 in² |
| Spacing (c/c) | 10.0 in |
| A_s provided | 0.53 in²/ft |
| A_s,prov / A_s,req | 1.03 |
| Stress-block depth a | 0.78 in |
| Net tensile strain ε_t | 0.0140 |
| φ | 0.900 |
| φM_n (as detailed) | 11.4 k-ft/ft |
| M_cr (§5.6.3.3) | 5.5 k-ft/ft |
| Minimum-resistance demand min(M_cr, 1.33M_u) | 5.5 k-ft/ft |
| Reinforcement ratio ρ | 0.0085 |
PASS — Adequate — detail as scheduled
A_s,prov / A_s,req = 1.03; ε_t = 0.0140 (tension-controlled, φ = 0.90).
Top mat #4 @ 5.5 in (As = 0.436 in²/ft) for the negative strip moment over the girders; bottom mat #4 @ 7.0 in for the positive strip moment between girders. Required As = 0.432 in²/ft at Mu = 12.38 k-ft/ft. Distribution steel and 2 in clear top / 1 in clear bottom cover per AASHTO 5.10.1 and 9.7.3.
Dead-load moments use the continuous-slab approximation wS²/10. For final design use the Appendix A4 live-load moment table, which already includes multiple presence and dynamic load allowance.
Deck overhang — collision & wheel-load design
Yield-line barrier resistance R_w and critical length L_c, the collision moment delivered into the deck at Extreme Event II, the Strength I wheel-load case on the 45 + 10X strip, and the governing overhang steel.
M_c, M_w and M_b are the barrier's yield-line resistances about a horizontal axis (wall cantilever), a vertical axis (wall bending) and the beam at the top of the parapet.
Barrier resistance R_w
82.7 kip
Critical length L_c
6.98 ft
Strength I overhang moment
12.39 k-ft/ft
Extreme Event II overhang moment
8.81 k-ft/ft
Governing overhang moment
12.39 k-ft/ft
Required top steel A_s
0.173 in²/ft
Overhang L = 3.50 ft; governing overhang moment Mu = 12.39 k-ft/ft requires As = 0.173 in²/ft.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Yield-line critical length | L_c = L_t/2 + √[(L_t/2)² + 8H(M_b + M_w)/M_c] | 1.75 + √[3.06 + 8·2.70(0.0+18.0)/16.00] | 6.98 ft |
| Barrier resistance | R_w = 2/(2L_c − L_t) · [8M_b + 8M_w + M_c L_c²/H] | 2/(2·6.98 − 3.5)·[8·0.0 + 8·18.0 + 16.00·6.98²/2.70] | 82.7 kip |
| Collision moment into the deck | M = R_w/(L_c + 2H) | 82.7/(6.98 + 2·2.70) | 6.68 k-ft/ft |
| Overhang dead load | M_DC = w t_s L²/2 + W_barrier·arm | 0.1000·3.50²/2 + barrier | 2.07 k-ft/ft |
| Overhang strip | E = 45 + 10X | 45 + 10·1.25 | 57.5 in |
| Wheel-load moment | M_LL+IM = P(1+IM)X / (E/12) | 16·1.33·1.25/(57.5/12) | 5.55 k-ft/ft |
| Case 2 — Strength I | 1.25DC + 1.50DW + 1.75(LL+IM) | 1.25·2.07 + 1.50·0.06 + 1.75·5.55 | 12.39 k-ft/ft |
| Case 1 — Extreme Event II | 1.00DC + 1.00DW + M_collision | 2.07 + 0.06 + 6.68 | 8.81 k-ft/ft |
| Required overhang steel | A_s = 0.85f′_c b d/f_y [1 − √(1 − 2M_u/(0.85φ f′_c b d²))] | M_u = 12.39 k-ft/ft, d = 5.19 in | 0.173 in²/ft |
- OKBarrier resistance ≥ test level force F_tdemand 54.0 kipcapacity 82.7 kipratio 0.65
- OKGoverning caseStrength I vertical wheel load governs.
Provide at least 0.173 in²/ft of top transverse steel in the overhang, developed fully into the first bay. Strength I governs.
Assumptions & code basis
- Three design cases per AASHTO LRFD §A13.4.1: (1) transverse collision at Extreme Event II, (2) vertical wheel load at Strength I, (3) the deck design case checked at the design section.
- Yield-line barrier analysis §A13.3.1 gives R_w and the critical length L_c of the failure pattern for an interior wall segment.
- The barrier must fail before the deck: the deck overhang is designed for the barrier resistance R_w, not for the nominal test force F_t.
- Wheel load placed 1 ft from the barrier face; overhang strip width 45 + 10X in (Table 4.6.2.1.3-1).
- Extreme Event II uses γ_p = 1.00 on permanent loads and φ = 1.00 for flexure.
Empirical (isotropic) deck design method
Screens all eleven §9.7.2.4 applicability conditions and returns the prescribed 0.27 / 0.18 in²/ft isotropic mat with spacing and end-zone rules when the method applies.
The empirical method replaces flexural analysis with a prescribed isotropic mat — but only when every §9.7.2.4 condition is satisfied.
Method applicable
No
S / t_core
21.60
Bottom steel each way
0.27 in²/ft
Top steel each way
0.18 in²/ft
Suggested bars
#5 @ 12 in bottom, #4 @ 12 in top
≤ 18 in spacing
S/t_core = 21.60; bottom steel 0.27 in²/ft each way, top 0.18 in²/ft each way.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Effective length | S (face-to-face for monolithic, distance between flange tips + flange overhang for steel) | 9.00 ft | 108.0 in |
| Core depth | t_core = t_s − top cover − bottom cover | 8.00 − covers | 5.00 in |
| Span-to-depth ratio | S/t_core (must be 6 – 18) | 108.0/5.00 | 21.60 |
| Bottom mat, each direction | A_s = 0.27 in²/ft | — | 0.27 in²/ft |
| Top mat, each direction | A_s = 0.18 in²/ft | f_y = 60 ksi ≥ 60 ksi | 0.18 in²/ft |
- OKSupporting components are steel and/or concrete beams
- OKDeck is fully cast-in-place and water cured
- OKDeck is of uniform depth (haunches excepted)
- NGEffective length-to-depth ratio 6.0 ≤ S/t_core ≤ 18.0
- OKCore depth ≥ 4.0 in
- OKEffective length S ≤ 13.5 ft
- OKTotal slab depth ≥ 7.0 in
- OKOverhang ≥ 5.0 times slab depth (or 3.0 t_s with a composite barrier)
- OKDeck is made composite with the supporting components
- OKAt least three girder lines (N_b ≥ 3)
- OKSkew ≤ 25° for the standard reinforcement layout (otherwise double the end-zone steel)
Conditions failed: Effective length-to-depth ratio 6.0 ≤ S/t_core ≤ 18.0. Use the traditional equivalent-strip design (§4.6.2.1) instead, or adjust the geometry until the conditions are met.
Assumptions & code basis
- Empirical (isotropic) deck design per AASHTO LRFD §9.7.2 — applicable only when every design condition of §9.7.2.4 is met.
- Prescribed reinforcement §9.7.2.5: 0.27 in²/ft in each bottom layer and 0.18 in²/ft in each top layer, placed in both directions, f_y ≥ 60 ksi.
- Maximum bar spacing 18 in; the reinforcement is placed as close to the outside surfaces as cover allows.
- The overhang and the barrier are NOT covered by the empirical method — design them by the strip method with the three §A13.4.1 cases.
- For skews above 25° the end-zone transverse reinforcement in the two end panels is doubled.
Deck secondary steel, crack control & rebar fatigue
Distribution steel as a percentage of the main mat, shrinkage-and-temperature steel, the §5.6.7 crack-control spacing with γ_e, and the Δf ≤ 24 − 20 f_min/f_y fatigue check on straight bars.
Distribution steel, shrinkage and temperature steel, the Class 1/2 crack-control spacing and the rebar fatigue stress range.
Distribution steel
0.415 in²/ft
67.0 % of the main steel
Shrinkage & temp steel
0.110 in²/ft per face
Service stress f_ss
27.44 ksi
Max bar spacing
9.29 in
Fatigue Δf
16.46 ksi
Derivation — equation, substitution, result
Distribution steel percentage
Bottom distribution steel
Shrinkage & temperature steel
Cracked elastic lever arm
Service steel stress
Crack-control spacing
Fatigue stress range
Detailing — plan, elevation and section
Constructability & detailing notes
- Distribution steel goes in the bottom mat, tied to the main bars — it is not a substitute for temperature steel in the top mat.
- Use epoxy-coated or stainless bars in the top mat where deicing salts are used; repair coating damage before the pour.
- Maintain 2.5 in top cover (2 in with an integral wearing surface) using chairs at 4 ft o.c. maximum.
- Screed rails must bear on the girders, never on the reinforcing steel.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| f_ss ≤ 0.60 f_y | 27.44 ksi | 36.0 ksi | PASS |
| Crack-control spacing achievable | bar spacing used | 9.29 in | PASS |
| Rebar fatigue Δf ≤ (ΔF)_TH | 16.46 ksi | 27.34 ksi | PASS |
| Deck deflection Δ ≤ S/800 (optional, §2.5.2.6.2)Only mandatory for the owner-invoked deflection criterion. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Distribution steel = 220/√S ≤ 67 % of the main steel | 67.0 % | VERIFIED |
Assumptions & basis of design
- Straight, non-skewed deck with the primary reinforcement perpendicular to traffic; §9.7.3.2 bottom distribution steel.
- Class 1 exposure γ_e = 1.00; use 0.75 for decks exposed to de-icing salts (§5.6.7).
- Fatigue I with the fatigue truck at a 30 ft rear axle spacing and IM = 15 %.
Distribution, crack-control and fatigue requirements are all satisfied with the given mat.
Orthotropic steel deck — three-system fatigue
Superposition of the local rib-wall, rib-as-beam and global girder stress systems, the resulting stress range at the rib-to-deck weld, and the infinite / finite life prediction for the governing detail category.
Superimposes the local plate, rib and global girder stress ranges, then checks infinite and finite life for the governing detail category.
f₁ deck plate
38.71 ksi
f₂ rib
29.08 ksi
Total Δf
71.78 ksi
(ΔF)_n
5.00 ksi
Predicted life
0 yr
Derivation — equation, substitution, result
Contact pressure
System 1 — deck-plate local bending
System 2 — rib bending between floorbeams
System 3 — global girder action
Superimposed stress range
Cycles
Fatigue resistance
Predicted life
Detailing — plan, elevation and section
Deck plate tp = 0.625 in over ribs at 12.0 in spacing. Wheel load 21.0 kip on a 10.0 in tyre patch produces local Δf = 67.8 ksi; combined with the global girder range 4.0 ksi gives total Δf = 71.8 ksi against the threshold (ΔF)TH = 10.0 ksi.
Constructability & detailing notes
- Rib-to-deck welds must achieve 80 % penetration with tight fit-up — the fatigue performance of the whole deck depends on it.
- Use continuous ribs passing through slotted floorbeam webs and grind the cut-out radius smooth.
- Specify a wearing surface (epoxy asphalt or polymer) that bonds and shares load with the deck plate.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Infinite life Δf ≤ (ΔF)_TH (Category C) | 71.78 ksi | 10.0 ksi | REVIEW |
| Finite life Δf ≤ (ΔF)_n | 71.78 ksi | 5.00 ksi | REVIEW |
| Deck plate ≥ 5/8 in (§9.8.3.7.2) | 0.625 in | 0.625 in | PASS |
| Rib-to-deck weld ≥ 80 % penetrationDetail per §9.8.3.7.3 to keep the rib-to-deck joint in Category C. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Combined stress range below the constant-amplitude threshold | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §9.8.3 orthotropic deck design by the three-system superposition (local plate, rib/panel, global girder).
- Deck-plate strip idealised as fixed–fixed between ribs; ribs idealised as continuous beams over the floorbeams with M ≈ 0.20 P L.
- Fatigue I load factor 1.75 with the fatigue truck; single-lane ADTT_SL entered directly.
Thicken the deck plate (f₁ ∝ 1/t_p²) or close the rib spacing before enlarging the ribs — local plate bending dominates the rib-to-deck detail.
Chapter 6
Reinforced concrete — flexure, shear, torsion and interfaces
Strength design of concrete sections including the general (MCFT) shear procedure, torsion reinforcement, and shear transfer across cold joints.
Reinforced-concrete flexural capacity
Stress-block depth, net tensile strain, resistance factor, and the φM_n ≥ M_u check with bar selection.
a = A_s f_y / (0.85 f′_c b) · M_n = A_s f_y (d − a/2) · ε_t = 0.003 (d − c)/c
β₁
0.850
Stress-block depth a
5.88 in
Neutral axis c
6.92 in
Net tensile strain ε_t
0.0100
Tension-controlled
φ
0.900
M_n
541 k-ft
φM_n vs M_u
487 ≥ 400 k-ft
Section adequate for flexure.
Flexural reinforcement design — AASHTO LRFD §5.6.3 / §5.10
| A_s required (strength) | 3.22 in² |
| A_s minimum (§5.6.3.3 / §5.10.6) | 0.70 in² |
| A_s design (governing) | 3.22 in² |
| Bar selection | 2 – #14 |
| Bar size / area | #14 — A_b = 2.25 in² |
| Bars / layers | 2 bars in 1 layer (clear spacing 5.1 in) |
| A_s provided | 4.50 in² |
| A_s,prov / A_s,req | 1.40 |
| Stress-block depth a | 6.62 in |
| Net tensile strain ε_t | 0.0086 |
| φ | 0.900 |
| φM_n (as detailed) | 540.5 k-ft |
| M_cr (§5.6.3.3) | 93.4 k-ft |
| Minimum-resistance demand min(M_cr, 1.33M_u) | 93.4 k-ft |
| Reinforcement ratio ρ | 0.0125 |
PASS — Adequate — detail as scheduled
A_s,prov / A_s,req = 1.40; ε_t = 0.0086 (tension-controlled, φ = 0.90).
Transverse reinforcement — AASHTO LRFD §5.7.2.5 / §5.7.3.3
| Concrete contribution V_c | 41.0 kip |
| Steel required V_s = V_u/φ − V_c | 92.4 kip |
| Stirrup schedule | #4 2-leg @ 7.0 in c/c (A_v = 0.40 in²) |
| Maximum spacing s_max | 21.6 in |
| φV_n = φ(V_c + V_s) | 120.2 kip |
| Web-crushing limit 0.25 f′_c b_v d_v | 324.0 kip |
PASS — φV_n = 120.2 kip ≥ V_u = 120.0 kip.
5 #9 bars (5.00 in² provided against As = 4.50 in² assumed), 2 rows, 2 in clear cover, #4 stirrups. Whitney block a = 6.62 in, c = 7.79 in, fy = 60 ksi. φMn = 540 k-ft vs Mu = 400 k-ft (AASHTO 5.6.3.2).
Sectional shear — general (MCFT) procedure
Longitudinal strain ε_s, β and θ from Eqs. 5.7.3.4.2-1..-3, V_c and V_s with cot θ, the web-crushing ceiling, minimum transverse steel and the required stirrup spacing with the §5.7.3.4.1 maximum.
The general procedure iterates on ε_s: β falls and θ rises as the section strains, so a heavily loaded web needs both more stirrups and a flatter truss angle.
ε_s
-4.000e-4
β
6.857
θ
27.60 deg
V_c
294.2 kip
V_s
229.5 kip
φV_n
507.3 kip
Design spacing
24.0 in
θ = 27.60° and β = 6.857 at ε_s = -4.000e-4.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Longitudinal strain | ε_s = [|M_u|/d_v + 0.5N_u + |V_u − V_p| − A_ps f_po] / (E_s A_s + E_p A_ps) | [18000/60.00 + 0.5·0.0 + 260.0 − 869.4] / (29000·2.00 + 28500·4.60) | -4.000e-4 |
| Minimum transverse steel | A_v,min = 0.0316 √f′_c b_v s / f_y | 0.0316√8.00·8.00·12.00/60 | 0.143 in² (provided 0.400 in²) |
| β | β = 4.8/(1 + 750ε_s) | 4.8/(1 + 750·-4.000e-4) | 6.857 |
| θ | θ = 29 + 3500 ε_s | 29 + 3500·-4.000e-4 | 27.60° |
| Concrete contribution | V_c = 0.0316 β √f′_c b_v d_v | 0.0316·6.857·√8.00·8.00·60.00 | 294.2 kip |
| Stirrup contribution | V_s = A_v f_y d_v cot θ / s | 0.400·60·60.00·1.913/12.00 | 229.5 kip |
| Nominal shear | V_n = min(V_c + V_s + V_p, 0.25f′_c b_v d_v + V_p) | min(563.7, 1000.0) | 563.7 kip |
| Factored resistance | φV_n ≥ V_u | 0.90·563.7 vs 300.0 | 507.3 kip |
| Required stirrup spacing | s = A_v f_y d_v cot θ / (V_u/φ − V_c − V_p) | 0.400·60·60.00·1.913/(333.3 − 294.2) | stirrups not required by strength |
| Maximum spacing | v_u < 0.125f′_c → s ≤ min(0.8d_v, 24 in); else min(0.4d_v, 12 in) | v_u = 0.625 ksi | 24.00 in |
- OKShear strength φV_n ≥ V_udemand 300.0 kipcapacity 507.3 kipratio 0.59
- OKWeb crushing V_n ≤ 0.25f′_c b_v d_v + V_pdemand 563.7 kipcapacity 1000.0 kip
- OKMinimum transverse steeldemand 0.143 in²capacity 0.400 in²
Use 24.0 in stirrup spacing (governed by the maximum-spacing rule); φV_n = 507.3 kip ≥ V_u = 300.0 kip with θ = 27.6°.
Assumptions & code basis
- General (MCFT) sectional procedure, AASHTO LRFD §5.7.3.4.2, with β and θ from Eqs. 5.7.3.4.2-1..-3.
- Longitudinal strain ε_s taken at mid-depth of the tension reinforcement; negative values would require the concrete-tension refinement of Eq. 5.7.3.4.2-4 and are floored here.
- d_v = max(0.9d_e, 0.72h, moment arm) must be supplied consistently with the flexural design.
- Nominal shear capped at 0.25 f′_c b_v d_v + V_p (Eq. 5.7.3.3-2) to prevent web crushing.
- Longitudinal reinforcement must also satisfy §5.7.3.5 — the tension-tie demand from shear.
Torsion — closed ties & longitudinal A_ℓ
Threshold and cracking torsion, A_oh / p_h / A_o geometry, the combined shear-plus-torsion crushing check, the (A_v + 2A_t)/s tie schedule and the distributed longitudinal torsion steel.
φT_th = φλ√f′_c A_cp²/p_cp · A_t/s = T_u/(φ2A_o f_yt cot θ) · A_ℓ = (A_t/s)p_h cot²θ · s ≤ p_h/8 ≤ 12″
φT_th
13.4 k-ft
torsion designed
T_cr
71.5 k-ft
A_oh / p_h
384 / 82.0 in², in
A_t/s (one leg)
0.0184 in²/in
(A_v+2A_t)/s req
0.0950 in²/in
Tie spacing
4.0 in
s_max = 10.3 in
A_ℓ required
1.673 in²
A_ℓ,min = 1.673
A_ℓ provided
1.760 in²
Crushing check
0.307 / 0.530 ksi
Torsion reinforcement schedule — ACI 318-19 §22.7 / §9.7.5 / §9.7.6.3
| Closed ties | #4 closed ties @ 4.0 in c/c (2 legs) |
| Tie legs / hooks | 2 legs, 135° hooks (§25.7.1.6) |
| Longitudinal torsion steel | 4 – #6 distributed @ ≈ 20.5 in around the perimeter |
| Perimeter bar spacing | 20.5 in (≤ 12 in required) |
| A_o = 0.85A_oh | 327 in² |
| cot θ | 1.000 |
| V_c | 67.4 kip |
PASS — Provide closed #4 ties @ 4.0 in c/c (135° hooks, §25.7.1.6) plus 4 – #6 longitudinal bars distributed around the perimeter at ≤ 12 in (§9.7.5.1).
4 #6 bars (1.76 in² provided against As = 1.76 in² assumed), 1 row, 2 in clear cover, #4 stirrups. Whitney block a = 0.00 in, c = 0.00 in, fy = 60 ksi. φMn = 0 k-ft vs Mu = 0 k-ft (AASHTO 5.6.3.2).
Interface (cold-joint) shear transfer
v_ui = V_u/(b_vi d_v), the c + μ(A_vf f_y + P_c) shear-friction resistance with the K₁f′_c and K₂ ceilings for each surface condition, minimum interface steel and the extended-stirrup spacing across the girder-to-deck joint.
Interface shear governs the extended-stirrup spacing at the top of a precast girder far more often than the web shear does.
v_ui
0.2500 ksi
V_ui
60.00 kip/ft
φV_ni
82.08 kip/ft
A_vf required
0.200 in²/ft
Max spacing of extended stirrups
24.0 in
Interface shear vui = 0.2500 ksi; required Avf = 0.200 in²/ft at 12.00 in spacing (roughened surface).
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Interface shear stress | v_ui = V_u/(b_vi d_v) | 300.0/(20.00·60.00) | 0.2500 ksi |
| Interface shear per foot | V_ui = v_ui b_vi (12 in) | 0.2500·20.00·12 | 60.00 kip/ft |
| Interface steel provided | A_vf/ft = A_vf(12)/s | 0.400·12/12.00 | 0.400 in²/ft |
| Nominal interface resistance | V_ni = c A_cv + μ(A_vf f_y + P_c) | 0.28·240.0 + 1(0.400·60 + 0.0) | 91.20 kip/ft |
| Upper limits | V_ni ≤ K₁ f′_c A_cv and ≤ K₂ A_cv | 0.3·4.00·240.0 = 288.0; 1.8·240.0 = 432.0 | 288.00 kip/ft |
| Factored resistance | φV_ni ≥ V_ui | 0.9·91.20 vs 60.00 | 82.08 kip/ft |
| Required interface steel | A_vf = (V_ui/φ − cA_cv)/(μ f_y) ≥ 0.05A_cv/f_y | (66.67 − 67.20)/(1·60) | 0.200 in²/ft |
| Required stirrup spacing across the joint | s = A_vf(12)/A_vf,req | 0.400·12/0.200 | 24.00 in |
- OKInterface shear φV_ni ≥ V_uidemand 60.00 kip/ftcapacity 82.08 kip/ftratio 0.73
- OKMinimum interface reinforcement 0.05A_cv/f_ydemand 0.200 in²/ftcapacity 0.400 in²/ft
Extend the girder stirrups into the deck at 24.0 in or closer and roughen the top flange to a 0.25 in amplitude; φV_ni = 82.08 kip/ft ≥ V_ui = 60.00 kip/ft.
Assumptions & code basis
- Interface shear transfer (shear friction) per AASHTO LRFD §5.7.4 — the cold joint between a precast girder and a cast-in-place deck.
- Surface condition: roughened; c = 0.28 ksi, μ = 1, K₁ = 0.3, K₂ = 1.8 ksi (§5.7.4.4).
- Interface shear per unit length v_ui = V_u/(b_vi d_v); the check is performed on a 12 in length of interface.
- Permanent net compressive force P_c across the interface may be taken as zero unless it is reliably present.
- Minimum interface steel 0.05 A_cv/f_y may be waived when v_ui < 0.210 ksi and the surface is roughened to 0.25 in amplitude (§5.7.4.2).
Shrinkage & temperature steel
The ACI ratio equation and the AASHTO per-face equation side by side, governing A_s, bar size and spacing against the 5h ≤ 18 in cap, provided ρ and the bar count for the strip.
ρ = max(0.0018·60/f_y, 0.0014) · A_s = ρbh · A_s(AASHTO) = 1.30bh/[2(b+h)f_y] · s ≤ min(5h, 18″)
A_s (ACI)
0.194 in²
ρ = 0.00180
A_s (AASHTO/face)
0.110 in²/ft
A_s governing
0.194 in²
Spacing
18.0 in
s_max = 18 in
A_s provided
0.267 in²
ρ provided
0.00247
Shrinkage & temperature reinforcement schedule — ACI 318-19 §24.4 · AASHTO LRFD §5.10.6
| Call-out | #4 @ 18.0 in c/c each face |
| Faces | Each face (top and bottom) |
| Bars over strip length | 9 bars |
| Steel weight | 72 lb per 12 ft strip |
| Max spacing | 18 in |
PASS — Provide #4 @ 18.0 in c/c each way, each face (max 18 in, §24.4.3.3). ρ_prov = 0.00247.
Strip 12 in wide × 9.0 in thick, #4 @ 18.0 in c/c each way, top and bottom.
Chapter 7
Prestressed concrete
Stress limits at every stage, immediate and time-dependent losses, service fibre stresses, and flexural resistance with bonded strand.
Prestressing stress limits — steel & concrete
Table 5.9.2.2-1 strand limits at jacking, transfer and service, with the §5.9.2.3 concrete compression and tension limits at release and in Service I / Service III, each screened against your fibre stresses.
Enter fibre stresses with compression negative and tension positive; the module screens every steel and concrete limit at transfer and at service.
f_py
243.0 ksi
Jacking limit
202.5 ksi
Transfer compression limit
3.600 ksi
Service III tension limit
0.5374 ksi
All limits satisfied
Yes
All limits satisfied: Yes.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Assumed yield strength | f_py = 0.90 f_pu (low relaxation) | 0.90·270 | 243.0 ksi |
| Jacking limit | 0.75 f_pu | 0.75·270 | 202.5 ksi |
| Transfer limit | 0.70 f_pu | 0.70·270 | 189.0 ksi |
| Service steel limit | 0.80 f_py | 0.80·243.0 | 194.4 ksi |
| Transfer compression limit | 0.60 f′_ci | 0.60·6.00 | 3.600 ksi |
| Transfer tension limit | 0.24 √f′_ci (bonded) / min(0.0948√f′_ci, 0.2) otherwise | 0.24√6.00 = 0.5879 | 0.5879 ksi (unbonded 0.2000) |
| Service compression limits | 0.45f′_c permanent / 0.60f′_c all loads | 0.45·8.00, 0.60·8.00 | 3.600 / 4.800 ksi |
| Service III tension limit | 0.19 √f′_c | 0.19√8.00 | 0.5374 ksi |
- OKJacking stress f_pj ≤ 0.75f_pudemand 202.5 ksicapacity 202.5 ksi
- OKStress immediately after transfer f_pt ≤ 0.70f_pudemand 185.0 ksicapacity 189.0 ksi
- OKEffective stress at service f_pe ≤ 0.80f_pydemand 155.0 ksicapacity 194.4 ksi
- OKConcrete compression at transfer ≤ 0.60f′_cidemand 2.900 ksicapacity 3.600 ksi
- OKConcrete tension at transfer (bonded reinf.) ≤ 0.24√f′_cidemand 0.3500 ksicapacity 0.5879 ksi
- OKService III tension ≤ 0.19√f′_cdemand 0.0000 ksicapacity 0.5374 ksi
- OKService I compression (all loads) ≤ 0.60f′_cdemand 0.000 ksicapacity 4.800 ksi
All strand and concrete stress limits are satisfied at both transfer and service.
Assumptions & code basis
- Steel stress limits from AASHTO LRFD Table 5.9.2.2-1 for low-relaxation strand: 0.75f_pu at jacking, 0.70f_pu immediately after transfer, 0.80f_py at service after all losses.
- Concrete stress limits from §5.9.2.3: 0.60f′_ci compression at transfer, 0.24√f′_ci tension where bonded reinforcement is provided (0.0948√f′_ci ≤ 0.2 ksi otherwise).
- Service limits §5.9.2.3.2: 0.45f′_c under permanent loads, 0.60φ_w f′_c under all loads, and 0.19√f′_c tension in Service III (0.0948√f′_c for corrosive exposure).
- Fibre stresses must be entered with compression negative and tension positive.
Prestress losses — immediate & time-dependent
Friction and anchorage set for post-tensioning, elastic shortening from f_cgp, and the approximate long-term loss with γ_h and γ_st — totalled to f_pe with P_i and P_e.
Friction and anchorage-set terms apply to post-tensioning only; they are reported for reference when pretensioning is selected.
Elastic shortening Δf_pES
19.32 ksi
Friction Δf_pF
11.32 ksi
not applicable to pretensioning
Anchorage set Δf_pA
2.23 ksi
not applicable
Long-term Δf_pLT
21.41 ksi
Total loss
40.73 (20.1 %) ksi
f_pe after all losses
161.8 ksi
P_i at transfer / P_e at service
1121 / 990 kip
fpe after all losses = 161.8 ksi.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Concrete modulus at transfer | E_ci = 33,000 w^1.5 √f′_ci | 33,000(0.145)^1.5 √6.00 | 4463 ksi |
| Concrete stress at strand centroid | f_cgp = P/A_g + P e²/I_g − M_g e/I_g | 1.6158 + 2.2383 − 0.8283 | 3.0258 ksi |
| Elastic shortening | Δf_pES = (E_p/E_ci) f_cgp | (28500/4463)·3.0258 | 19.32 ksi |
| Friction loss (post-tensioned) | Δf_pF = f_pj[1 − e^−(Kx + μα)] | 202.5[1 − e^−(0.0002·100.0 + 0.25·0.150)] | 11.32 ksi |
| Anchorage set loss | L_set = √(ΔE_p/p), Δf_pA = 2p·L_set | L_set = √(0.375/12·28500/0.11644) = 9.6 ft | 2.23 ksi |
| Humidity factor | γ_h = 1.7 − 0.01H | 1.7 − 0.01·70 | 1.000 |
| Strength factor | γ_st = 5/(1 + f′_ci) | 5/(1 + 6.00) | 0.714 |
| Long-term loss | Δf_pLT = 10(f_pi A_ps/A_g)γ_h γ_st + 12γ_h γ_st + 2.4 | 10·1.462·1.000·0.714 + 12·1.000·0.714 + 2.4 | 21.41 ksi |
| Total loss | Δf_pT = Δf_pES + Δf_pLT | 19.32 + 21.41 | 40.73 ksi (20.1 %) |
| Effective strand stress | f_pe = f_pj − Δf_pT | 202.5 − 40.73 | 161.8 ksi |
| Prestress force | P_i = (f_pj − Δf_pES)A_ps ; P_e = f_pe A_ps | 183.2·6.12 ; 161.8·6.12 | P_i = 1121 kip, P_e = 990 kip |
- OKTotal loss within the usual 20–30 % bandratio 20.1 %
- OKf_pe ≤ 0.80 f_py (= 0.72 f_pu)demand 161.8 ksicapacity 194.4 ksi
Design with P_e = 990 kip at service (f_pe = 161.8 ksi, 20.1 % total loss) and P_i = 1121 kip at transfer. Losses are in the normal range for a pretensioned girder.
Assumptions & code basis
- Immediate losses: friction Δf_pF = f_pj[1 − e^−(Kx + μα)] and anchorage set (post-tensioned only), and elastic shortening Δf_pES = (E_p/E_ci) f_cgp (§5.9.3.2).
- For pretensioned members the full (E_p/E_ci)f_cgp is used; for post-tensioned members with sequential stressing the average is taken as one-half.
- Time-dependent losses by the approximate estimate of §5.9.3.3: Δf_pLT = 10 (f_pi A_ps/A_g) γ_h γ_st + 12 γ_h γ_st + Δf_pR, with γ_h = 1.7 − 0.01H, γ_st = 5/(1+f′_ci) and Δf_pR = 2.4 ksi for low-relaxation strand.
- f_cgp is the concrete stress at the centroid of the prestressing force at transfer, including the girder self-weight moment relief.
- The approximate method requires standard precast, pretensioned members with normal-weight concrete, average conditions, and a specified concrete strength at transfer; use the refined method of §5.9.3.4 for unusual members.
Prestress-loss estimator (approximate method)
Elastic shortening plus the approximate long-term loss with humidity and strength correction factors — the quick screening version.
γ_h = 1.7 − 0.01H · γ_st = 5 / (1 + f′_ci) · Δf_pLT = 10 γ_h γ_st + 12 γ_h γ_st + Δf_pR
Jacking stress f_pj = 0.75 f_pu
202.5 ksi
γ_h
1.000
γ_st
0.769
Elastic shortening Δf_pES
18.2 ksi
Long-term Δf_pLT
19.3 ksi
Total loss
37.5 ksi
18.5 % of jacking stress
Effective prestress f_pe
165.0 ksi
Use with Service III tension and flexural checks.
Jacking stress fpj = 202.5 ksi, elastic shortening ΔfpES = 18.2 ksi, long-term ΔfpLT = 19.3 ksi, effective prestress fpe = 165.0 ksi.
Prestressed-girder service stresses & flexure
Transfer and Service III fibre stresses, cracking moment, and the minimum-reinforcement check for a prestressed I-girder.
f = P/A ± Pe/S ∓ M/S · Mcr = Sb(fr + fcpe) − Md(Sb/Snc − 1) · fr = 0.24√f′c
Effective prestress Pe
1210 kip
Top stress at transfer
-0.735 ksi
Bottom stress at transfer
3.868 ksi
Bottom stress, Service III
2.341 ksi
Top stress, Service I
0.664 ksi
Cracking moment Mcr
5784 k-ft
Transfer compression
0.735 ≤ 3.000 ksi
Transfer tension
3.868 ≤ 0.200 ksi
Service III tension
2.341 ≤ 0.484 ksi
Service I compression
0.664 ≤ 2.925 ksi
Minimum reinforcement requires φMn ≥ min(1.33Mu, Mcr) = 4256 k-ft; verify against the section's computed φMn.
Strand centroid eccentricity e = 30.6 in below the section centroid. Top fiber ft = 0.664 ksi (limit 2.925 ksi), bottom fiber fb = 2.341 ksi (tension limit 0.484 ksi).
Flexural resistance with prestressing steel — f_ps and φM_n
Strand stress at nominal resistance f_ps = f_pu(1 − kc/d_p) with automatic rectangular / flanged equilibrium, φ from the net tensile strain, and the §5.6.3.3 minimum-reinforcement check against M_cr and 1.33M_u.
Rectangular behaviour is assumed first; the module switches to flanged equilibrium automatically when a = β₁c exceeds the flange.
c
5.184 in
f_ps
264.4 ksi
M_n
9142.0 k-ft
φ
1.000
φM_n
9142.0 k-ft
Behaviour
Rectangular
φM_n = 9142.0 k-ft vs M_u = 7500.0 k-ft; f_ps = 264.4 ksi.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Strand k factor | k = 2(1.04 − f_py/f_pu) | 2(1.04 − 243.0/270) | 0.280 |
| β₁ | 0.85 − 0.05(f′_c − 4) within 0.65–0.85 | f′_c = 4.00 ksi | 0.850 |
| Neutral axis | c = [A_ps f_pu + A_s f_y − A′_s f′_y] / [0.85f′_c β₁ b + k A_ps f_pu/d_p] | A_ps = 6.120 in², f_pu = 270 ksi, d_p = 70.00 in | 5.184 in (rectangular behaviour) |
| Stress block depth | a = β₁ c | 0.850·5.184 | 4.407 in |
| Strand stress at nominal resistance | f_ps = f_pu(1 − k c/d_p) | 270(1 − 0.280·5.184/70.00) | 264.4 ksi |
| Nominal moment | M_n = A_ps f_ps(d_p − a/2) + A_s f_y(d_s − a/2) | 6.120·264.4(70.00 − 2.203) + … | 9142.0 k-ft |
| Net tensile strain and φ | ε_t = 0.003(d_t − c)/c ; φ = 0.75 + 0.25(ε_t − ε_cl)/(ε_tl − ε_cl) | ε_t = 0.03751 | φ = 1.000 |
| Factored resistance | φM_n | 1.000·9142.0 | 9142.0 k-ft |
| Cracking moment | M_cr = γ₃[(γ₁ f_r + γ₂ f_cpe)S_c − M_dnc(S_c/S_nc − 1)] | f_r = 0.4800 ksi, S_c = 26000 in³ | 11232.6 k-ft |
| Minimum reinforcement | φM_n ≥ min(M_cr, 1.33M_u) | min(11232.6, 9975.0) | 9975.0 k-ft |
- OKStrength φM_n ≥ M_udemand 7500.0 k-ftcapacity 9142.0 k-ftratio 0.82
- NGMinimum reinforcement §5.6.3.3demand 9975.0 k-ftcapacity 9142.0 k-ft
- OKDuctility ε_t ≥ 0.005 (tension controlled)demand 0.03751capacity 0.00500
Strength is adequate but the §5.6.3.3 minimum-reinforcement check fails — add mild steel or strand so φM_n ≥ 9975.0 k-ft.
Assumptions & code basis
- Bonded strand: f_ps = f_pu(1 − k c/d_p) with k = 2(1.04 − f_py/f_pu) = 0.28 for low-relaxation strand (AASHTO LRFD Eq. 5.6.3.1.1-1).
- Equilibrium of the rectangular stress block gives c; flanged behaviour is triggered automatically when a = β₁c exceeds the flange thickness.
- Flexural resistance φM_n with φ from §5.5.4.2 varying between 0.75 (compression controlled) and 1.00 (tension controlled) for prestressed concrete.
- Minimum reinforcement §5.6.3.3: φM_n ≥ min(M_cr, 1.33M_u) with M_cr = γ₃(γ₁ f_r + γ₂ f_cpe)S_c − M_dnc(S_c/S_nc − 1).
- Compression steel A′_s is included in equilibrium but conservatively assumed to yield.
Prestress camber & deflection — PCI multipliers
Camber at release from the strand profile, self-weight deflection, and the PCI time-dependent multipliers at erection and final service with the net camber for screed setting.
Time-dependent camber with PCI multipliers at release, erection and final — the numbers the fabricator and the screed crew actually need.
Camber at release
1.559 in
Camber at erection
2.806 in
Final net camber
-3.030 in
Live-load deflection
0.929 in
Δ_allow = L/800
1.650 in
Haunch build-up
3.53 in
Derivation — equation, substitution, result
Moduli at release and in service
Camber from prestress
Self-weight deflection
Net camber at release
Camber at erection
Deck and superimposed dead load
Long-term net
Live-load deflection
Haunch build-up
Detailing — plan, elevation and section
Predicted camber at erection = 2.81 in, long-term final = -3.03 in over a span of 110 ft. Strand profile: harped, midspan eccentricity ec = 22.0 in, end eccentricity ee = 12.0 in.
Constructability & detailing notes
- Publish the predicted camber at 28, 60 and 120 days — the haunch detail must absorb the difference between predicted and measured.
- Girders stored longer than expected keep growing in camber; measure before setting the screed elevations.
- Differential camber between adjacent girders is the usual cause of deck thickness problems; specify a maximum of 3/4 in.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Live-load deflection ≤ L/800 (§2.5.2.6.2) | 0.929 in | 1.650 in | PASS |
| Residual camber positive after all dead load | -3.030 in | ≥ 0 | REVIEW |
| Camber at erection within ±0.5 in of the assumed screed elevationsLarge cambers complicate deck screeding — consider debonding rather than harping. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Net camber positive (upward) at erection | > 0 in | 2.806 | VERIFIED |
Assumptions & basis of design
- PCI Design Handbook multipliers: 1.80 at erection, 2.20/2.70/2.40/3.00 for the long-term components.
- Prestress camber uses the gross section; the composite section resists SDL and live load.
- Live-load deflection uses the distribution factor already embedded in w_LL, with all girders deflecting equally (§2.5.2.6.2).
The girder sags under full dead load — increase the drape or the strand count, or specify additional haunch build-up so the deck profile is preserved.
Chapters 8 – 11
Steel girders, splices, cross-frames and connections
Classification, plastic and yield moments, lateral–torsional buckling, web shear, splices and bearing stiffeners.
Steel girder flexural resistance & LTB
Web and flange classification, M_y and M_p, r_t with L_p and L_r, the three LTB zones with C_b, flange local buckling, φM_n and every §6.10.2 proportion limit — with the bracing or flange size needed when a check fails.
Cross-frame spacing L_b is the single most powerful lever on a plate girder's flexural resistance — compare the result at L_p.
M_y
4784 k-ft
M_p
5867 k-ft
L_p / L_r
8.19 / 30.75 ft
LTB zone
Plastic / no LTB (L_b ≤ L_p)
φM_n
4784 k-ft
Utilization
1.25
Plastic / no LTB (L_b ≤ L_p); φM_n = 4784 k-ft vs M_u = 6000 k-ft at L_b = 22.00 ft.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Web slenderness | 2D_c/t_w vs λ_pw = 3.76√(E/F_y), λ_rw = 5.7√(E/F_y) | 2·27.00/0.500 = 108.00; λ_pw = 90.55, λ_rw = 137.27 | Non-compact web |
| Compression-flange slenderness | λ_f = b_fc/2t_fc vs λ_pf = 0.38√(E/F_y) | 16.00/(2·1.000) = 8.00; λ_pf = 9.15 | Compact flange |
| Elastic section properties | I, S_xc = I/c_t, S_xt = I/c_b | I = 35333 in⁴, c_t = 30.77 in | S_xc = 1148 in³, S_xt = 1387 in³ |
| Yield moment | M_y = F_y S | 50·1148/12 | 4784 k-ft |
| Plastic moment | M_p = F_y Z_x | 50·1408/12 | 5867 k-ft |
| Effective radius of gyration | r_t = b_fc/√[12(1 + D_c t_w/(3 b_fc t_fc))] | 16.00/√[12(1 + 27.00·0.500/(3·16.00·1.000))] | 4.080 in |
| Bracing limits | L_p = 1.0 r_t √(E/F_y) ; L_r = π r_t √(E/F_yr) | r_t = 4.080 in, F_yr = 35.0 ksi | L_p = 8.19 ft, L_r = 30.75 ft |
| LTB resistance | Plastic / no LTB (L_b ≤ L_p) | L_b = 22.00 ft, C_b = 1.00 | F_nc(LTB) = 50.00 ksi |
| Flange local buckling resistance | F_nc = R_b R_h F_yc | λ_f = 8.00 | 50.00 ksi |
| Nominal flexural resistance | M_n = min(F_nc,LTB, F_nc,FLB)·S_xc (or M_p when compact and braced) | F_n = 50.00 ksi | 4784 k-ft |
| Factored resistance | φ_f M_n ≥ M_u | 1.00·4784 vs 6000 | 4784 k-ft |
- NGFlexural strength φM_n ≥ M_udemand 6000 k-ftcapacity 4784 k-ftratio 1.25
- OKWeb proportion D/t_w ≤ 150demand 108.0capacity 150
- OKFlange proportion b_f/2t_f ≤ 12demand 8.00capacity 12
- OKFlange width b_f ≥ D/6demand 16.00capacity 9.00
- OKFlange thickness t_f ≥ 1.1 t_wdemand 1.000capacity 0.550
Deficient by 1.25×. Either brace tighter — reducing L_b to L_p = 8.19 ft recovers the full F_y — thicken the compression flange to lower λ_f, or increase S_xc by about 25 %.
Assumptions & code basis
- I-section flexural resistance per AASHTO LRFD §6.10.6 – §6.10.8 (LRFD, φ_f = 1.00).
- Cross-section proportion limits of §6.10.2 must also be satisfied: D/t_w ≤ 150 (unstiffened), b_f/2t_f ≤ 12, b_f ≥ D/6, t_f ≥ 1.1t_w.
- Web classification uses 2D_c/t_w against 3.76√(E/F_y) (compact) and 5.7√(E/F_y) (slender, load-shedding factor R_b applies).
- Lateral–torsional buckling uses r_t = b_fc/√[12(1 + D_c t_w/(3 b_fc t_fc))] with L_p = 1.0 r_t √(E/F_y) and L_r = π r_t √(E/F_yr), F_yr = 0.7F_y.
- Hybrid factor R_h and web load-shedding factor R_b are taken as 1.0; apply them explicitly for hybrid or slender-web girders.
- Composite sections in positive flexure with a compact web may be governed instead by the §6.10.7.1 plastic-moment provisions and the D_p/D_t ductility limit.
Steel girder web shear resistance
Shear-buckling coefficient, ratio C, and the nominal shear resistance of a stiffened or unstiffened web.
V_p = 0.58 F_yw D t_w · k = 5 + 5/(d_o/D)² · V_n = C V_p (unstiffened / stiffened web)
D / t_w
120.0
Shear-buckling coefficient k
6.250
Ratio C
0.395
Plastic shear V_p
870 kip
V_n
344 kip
φ_v V_n (φ_v = 1.0)
344 kip
Shear check
344 ≥ 300 kip
Web adequate in shear.
Web 60.0 in deep × 0.500 in thick, D/tw = 120, transverse stiffeners at do = 120.0 in (do/D = 2.00). Vu = 300 kip vs φVn = 344 kip (AASHTO 6.10.9).
Bolted field splice design
Shear, bearing, and slip resistance of a high-strength bolted splice against a factored demand.
Rn,shear = 0.38 Ab Fub Ns · Rn,bearing = min(2.4dtFu, 1.2LctFu) · Rn,slip = Kh Ks Ns Pt
Bolt area Ab
0.601 in²
Shear resistance (splice)
702 kip
Bearing resistance (splice)
1310 kip
Slip resistance (splice)
412 kip
Governing capacity vs demand
702 ≥ 650 kip
Splice adequate for Strength I shear/bearing.
16 × 0.875 in Ø A325 bolts in 2 rows of 8, 3 in pitch, 1.75 in edge distance (AASHTO 6.13.2.6). Demand per bolt 650.0 kip vs Rn = 702.0 kip.
Slip resistance governs serviceability (Service II) checks and is not combined additively with the bearing-type strength resistance.
Web concentrated forces & bearing stiffeners
Web local yielding, crippling and compression buckling at reactions and point loads, then a full bearing-stiffener design — plate size, the 25t_w effective column, KL/r, F_cr, φP_n and the fillet weld.
R_n = F_ywt_w(5k+ℓ_b) · R_n = 0.80t_w²[1+3(ℓ_b/d)(t_w/t_f)^1.5]√(EF_ywt_f/t_w) · R_n = 24t_w³√(EF_yw)/h
φR_n yielding
205.7 kip
φR_n crippling
123.1 kip
φR_n web buckling
52.0 kip
Governing
52.0 kip
Web compression buckling (§J10.5)
Stiffener plates
2 – PL 3.78″ × 0.500″
φP_n stiffener
385.0 kip
Concentrated-force limit states & bearing stiffener design — AISC 360-22 §J10 / §J7 / §E3
| Clear web depth h | 21.32 in |
| Governing limit state | Web compression buckling (§J10.5) |
| Stiffener call-out | 2 – PL 3.78″ × 0.500″ bearing stiffeners, 3/16″ fillet both sides |
| Effective area A_eff | 8.62 in² |
| KL / r | 16.0 in / 1.576 in → 10.1 |
| F_e / F_cr | 2780.6 / 49.6 ksi |
| Weld | 3/16 in fillet, both sides, full web depth |
PASS — Provide a pair of bearing stiffeners 3.78 in × 0.500 in, fitted to the loaded flange, with 3/16 in fillet welds each side to the web (§J10.8).
End reaction Ru = 180 kip. Stiffener pair PL 3.78 × 0.500 in, fillet welds 3/16 in each side, full web depth.
Plate-girder trial sizing & proportion limits
Web depth from span-to-depth guidance, D/t_w and b_f/2t_f screening, the §6.10.2 proportion limits and the flange plate sizes needed to satisfy each one.
First-pass plate girder dimensions that satisfy the §6.10.2 proportion limits before any analysis is run.
Web D × t_w
60 × 0.4375 in
Top flange
15.0 × 0.7500 in
Bottom flange
15.0 × 1.0000 in
Total depth
61.75 in
Area
52.5 in²
Self weight
0.1786 klf
Derivation — equation, substitution, result
Web depth
Web thickness
Flange width
Flange thickness
Trial section
Self weight
Compactness screening
Deck fit
Detailing — plan, elevation and section
Constructability & detailing notes
- Keep the web thickness constant for the whole girder line; changing it saves less steel than it costs in fabrication.
- Flange transitions should occur at field splices or at least 10 ft from them, and the width change should be a 1:2.5 taper.
- Minimum flange width of 12 in keeps the girder stable during shipping and erection.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| D/t_w ≤ 150 without longitudinal stiffeners | 137.1 | 150 | PASS |
| b_f ≥ D/6 (§6.10.2.2-2) | 15.0 in | 10.0 in | PASS |
| t_f ≥ 1.1 t_w (§6.10.2.2-3) | 0.7500 in | 0.4813 in | PASS |
| b_f/(2t_f) ≤ 12 (§6.10.2.2-1) | 10.00 | 12.0 | PASS |
| Girder spacing 3.5 – 16 ft | 10.00 ft | 3.5 – 16 ft | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Web slenderness within the non-longitudinally-stiffened limit | D/t_w ≤ 150 | VERIFIED |
Assumptions & basis of design
- Depth ratios from AASHTO LRFD Table 2.5.2.6.3-1 with plate sizes rounded to commercial increments (web depth to 3 in, plate thickness to 1/8 in).
- Bottom flange is proportioned 25 % thicker than the top flange to reflect composite action in positive-moment regions.
- Steel unit weight 490 pcf; the estimate excludes stiffeners, cross-frames and connection material (add roughly 12 – 18 %).
Take this section into the composite section-property, flexure and shear modules; iterate the flange plates until the utilisation lands near 0.90 – 0.98.
Composite plastic moment M_p and PNA location
Slab, flange and web plastic forces, Appendix D6.1 case selection (I, II, III) for the plastic neutral axis, M_p, and the D_p ≤ 0.42 D_t ductility screen.
Locates the plastic neutral axis by Appendix D6.1 case selection and screens ductility with D_p ≤ 0.42 D_t.
PNA case
II
D_p
10.95 in
0.42 D_t
30.66 in
M_p
12952 kip·ft
φ_f M_n
12952 kip·ft
Utilisation
0.695
Derivation — equation, substitution, result
Plastic forces
PNA case
PNA location
Plastic moment
Total depth
Ductility requirement
Nominal flexural resistance
Detailing — plan, elevation and section
Constructability & detailing notes
- M_p is only available if the section is compact and adequately braced during the deck pour — check the non-composite stage separately.
- Ductility (D_p ≤ 0.42 D_t) is what allows the section to reach M_p; a deep slab with a shallow girder often fails it.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Ductility D_p ≤ 0.42 D_t (§6.10.7.3) | 10.95 in | 30.66 in | PASS |
| Flexure φ_f M_n ≥ M_u | 9000 kip·ft | 12952 kip·ft | PASS |
| Compact web 2D_cp/t_w ≤ 3.76√(E/F_yc) | 0.0 | 90.6 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Ductility requirement D_p ≤ 0.42 D_t | ≤ 0.42 D_t | 10.95 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD Appendix D6.1 plastic-moment cases for a composite section in positive flexure; concrete in tension neglected.
- Longitudinal deck reinforcement is conservatively neglected in the positive-moment plastic force sum.
- φ_f = 1.00 for flexure (§6.5.4.2); compact composite sections in positive flexure may reach M_p.
Section is compact and ductile — proceed to the §6.10.9 shear check and the §6.10.10 shear-connector design.
Shear connectors — strength and fatigue pitch
Stud resistance Q_r, the number of studs for the strength limit state between points of maximum moment and zero moment, and the Fatigue I / II pitch from Z_r and the range of horizontal shear flow.
Strength count from the plastic horizontal force and fatigue pitch from Z_r and the horizontal shear range.
Q_n per stud
36.08 kip
Q_r per stud
30.67 kip
Studs required (strength)
79
Z_r fatigue
2.105 kip
Governing pitch
3.5 in
Callout
3 — 0.875 in ø × 6.0 in studs @ 3.5 in
Derivation — equation, substitution, result
Stud area
Nominal stud strength
Factored strength
Strength-limit stud count
Design cycles
Fatigue shear resistance
Fatigue pitch
Detailing — plan, elevation and section
Constructability & detailing notes
- Studs are welded in the shop through clean, dry flange surfaces; bend-test the first two of each shift and 1 % thereafter.
- Keep 2 in clear cover over the stud head and 1 in clear between the stud and the deck bottom mat.
- Vary the pitch in bands rather than continuously — the fabricator lays out from a table, not a curve.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Pitch 6d ≤ p ≤ 24 in (§6.10.10.1.2) | 3.5 in | 5.3 – 24 in | REVIEW |
| Stud height H ≥ 4d (§6.10.10.1.1) | 6.0 in | 3.5 in | PASS |
| Stud diameter ≤ 2.5 t_fc (§6.10.10.1.4) | 0.875 in | 2.500 in | PASS |
| Penetration ≥ 2 in into the deck with ≥ 2 in top covertop cover ≈ 2.5 in | 6.0 in in a 8.5 in slab | 5.5 – 6.5 in | PASS |
| Transverse spacing ≥ 4d and ≤ 8 t_sCheck the flange width can accommodate the row. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Stud height-to-diameter ratio ≥ 4 | ≥ 4.0 | 6.86 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §6.10.10; φ_sc = 0.85; normal-weight concrete with E_c = 1,820√f′_c.
- Fatigue pitch computed from the Fatigue I horizontal shear range V_sr = V_f Q/I at the section considered.
- The strength check governs the total number of connectors; the fatigue check governs their spacing.
The required fatigue pitch is tighter than the 6d minimum — add a third or fourth stud per row rather than closing the pitch further.
Fatigue detail categories & remaining life
Category A–E′ constants, the Fatigue I and II load combinations, the single-lane ADTT_SL with cycles per truck passage, the (ΔF)_TH infinite-life screen and N = A/(Δf)³ finite life.
Fatigue I (infinite life) and Fatigue II (finite life) checks for AASHTO detail categories A through E′.
ADTT_SL
2550 trucks/day
Δf
10.50 ksi
(ΔF)_n
10.00 ksi
Utilisation
1.050
Estimated life
4 yr
Derivation — equation, substitution, result
Single-lane truck traffic
Fatigue load factor
Factored stress range
Design cycles
Nominal fatigue resistance
Estimated life
Detailing — plan, elevation and section
Category C: γ(Δf) = 10.50 ksi plotted at N = 69806250 cycles against the finite-life resistance (ΔF)n = 10.00 ksi and the constant-amplitude threshold (ΔF)TH = 10.00 ksi. Point falls above the resistance curve — review the detail.
Constructability & detailing notes
- Category E′ details (long cover plates on thick flanges) should be designed out, not checked — weld the plate away entirely if you can.
- Distortion-induced fatigue is not covered by these categories: weld connection plates to both flanges (§6.6.1.3).
- Grind weld toes and specify a peened or ground transition where a category improvement is needed.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| γ(Δf) ≤ (ΔF)_n — Category C | 10.50 ksi | 10.00 ksi | REVIEW |
| Infinite-life screening Δf ≤ (ΔF)_TH | 10.50 ksi | 10.0 ksi | REVIEW |
| Fracture-critical member? apply CVN and redundancy provisions§6.6.2 requires refined analysis and enhanced inspection for FCMs. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Stress range below the resistance | 10.00 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §6.6.1.2 detail categories with the fatigue truck (constant 30 ft rear axle spacing) and IM = 15 %.
- Fatigue I gives infinite life when Δf ≤ (ΔF)_TH; Fatigue II gives the finite-life resistance from the S-N curve.
- Cycles per truck passage n from Table 6.6.1.2.5-2 (typically 1.0 for spans > 40 ft, 2.0 for shorter spans and cantilevers).
Upgrade the detail — moving from Category C to the next better category raises the threshold; grinding cover-plate ends, removing backing bars and using full-penetration welds are the usual fixes.
Cross-frames and diaphragms — force and sizing
Wind and stability bracing forces into the cross-frame, the diagonal and strut member demands, the slenderness limits for bracing members, and the connection force to detail.
Compares the V-load (curvature), wind and 2 % stability bracing demands and picks the governing cross-frame force.
V-load H
4.17 kip
Diagonal force
4.56 kip
Wind force
2.40 kip
Stability force
18.00 kip
Design force
18.00 kip
Suggested member
L4×4×3/8
Derivation — equation, substitution, result
V-load (curved girder)
Diagonal geometry
Diagonal axial force
Wind on the exposed superstructure
Stability bracing
Governing design force
Detailing — plan, elevation and section
Constructability & detailing notes
- Weld the connection plate to both flanges — a gap at the tension flange is a distortion-induced fatigue crack waiting to happen.
- Cross-frames control the girder geometry during erection; specify whether they are detailed for no-load, steel-dead-load or full-dead-load fit.
- Provide slotted or oversized holes only where the erection tolerance genuinely requires them, and note them on the plans.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Cross-frame spacing ≤ 25 ft (§6.7.4.2) | 20.0 ft | 25 ft | PASS |
| Cross-frame depth ≥ 0.5 girder depth (straight) / 0.75 (curved)Connect near the flanges so the frame engages the full girder depth. | — | — | PASS |
| Members are primary in curved bridges (§6.7.4.1)Design curved-bridge cross-frames as primary members with fatigue checks on the connection plates. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Governing design force identified | max(V-load, wind, stability) | 18.00 | VERIFIED |
Assumptions & basis of design
- V-load method approximates curvature effects by a self-equilibrating couple between adjacent girders.
- Wind is distributed to the deck-level bracing over half the cross-frame spacing each side.
- Connection plates must be welded (not bolted) to both flanges to avoid a Category C′ distortion-induced fatigue detail.
On a curved bridge the cross-frames carry real load in every stage — check the erection condition, when they are often most heavily loaded.
Eccentric bolt group — instantaneous centre / elastic
Direct and torsional bolt force components for an eccentrically loaded group, the governing extreme bolt resultant, the elastic and IC-method comparison, and the bolt count needed to keep the resultant below φr_n.
Elastic vector analysis of an eccentric bolt group plus the flange-splice bolt count from the flange couple.
Bolt capacity
39.00 kip
Direct shear R_v
18.00 kip
Resultant R_max
31.62 kip
Group utilisation
0.811
Flange force F_fl
869.0 kip
Flange bolts per side
23
Derivation — equation, substitution, result
Bolt shear
Bearing on the connected material
Slip resistance
Governing bolt capacity
Group geometry
Direct shear per bolt
Torsional components
Resultant bolt force
Flange splice force
Detailing — plan, elevation and section
Constructability & detailing notes
- Slip-critical faying surfaces must be blast-cleaned Class B and left unpainted — mask them before shop priming.
- Use a minimum of two bolts per line and fill every hole; open holes in a splice are a fatigue and corrosion detail.
- Erection bolts and drift pins go in first; final pretensioning proceeds from the stiffest point outward.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Eccentric group R_max ≤ φR_n | 31.62 kip | 39.00 kip | PASS |
| Bolt pitch ≥ 3d (§6.13.2.6.1) | 3.00 in | 2.63 in | PASS |
| Edge distance ≥ 1.25 in for 7/8 in bolts (Table 6.13.2.6.6-1)Confirm the plate geometry provides the sheared/rolled edge distance. | — | — | PASS |
| Slip-critical check at Service II | 31.62 kip | 39.00 kip | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Resultant bolt force within capacity | 39.00 | 31.62 | VERIFIED |
Assumptions & basis of design
- Elastic (vector) analysis of the bolt group — conservative relative to the instantaneous-centre method.
- ASTM F3125 Grade A325 bolts (F_ub = 120 ksi) unless otherwise entered; φ_s = 0.80 for bolts in shear.
- Flange splice bolts sized for the flange couple M_u/h_eff; AASHTO also requires design for the smaller of the yield or 75 % of the flange resistance.
Detail 10 bolts in the web group and 23 per side in each flange splice plate.
Splice plate tension — yielding, rupture & block shear
Gross yielding, net-section rupture with hole deduction, block shear on the tearout path, and the plate thickness and width that satisfies the governing limit state at a flange or web splice.
Gross yielding, net-section rupture with shear lag, and both block-shear paths for a bolted tension splice plate.
A_n/A_g
0.750
Shear-lag U
1.000
Gross yielding
570.0 kip
Net rupture
468.0 kip
Block shear
328.8 kip
Governing capacity
328.8 kip
block shear
Derivation — equation, substitution, result
Gross and net areas
Shear lag
Gross-section yielding
Net-section rupture
Block shear — path 1
Block shear — path 2
Factored block shear
Governing limit state
Detailing — plan, elevation and section
Constructability & detailing notes
- Punch-and-ream or drill full size — punched holes in thick plate leave a work-hardened edge that reduces the rupture capacity.
- Splice plates on both faces halve the shear-lag penalty and keep the load path concentric.
- Mark the plates for orientation; asymmetric hole patterns get installed backwards more often than anyone admits.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| φR_n ≥ P_u | 420.0 kip | 328.8 kip | REVIEW |
| A_n ≤ 0.85 A_g for splice plates (§6.13.5.2)AASHTO caps the effective net area of splice plates at 0.85 A_g. | 0.750 | 0.850 | PASS |
| Rupture is not the governing failure mode (ductility preference)Yielding should precede rupture — widen the plate or reduce hole loss. | — | — | REVIEW |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Governing limit-state capacity exceeds demand | 328.8 | P_u applied | CHECK |
Assumptions & basis of design
- AASHTO LRFD §6.8.2, §6.13.4 and §6.13.5 with hole diameter taken as the bolt diameter + 1/8 in for standard holes.
- U_bs = 1.0 for uniform tensile stress and 0.5 where the stress is non-uniform (coped beams).
- Splice plates are proportioned so the effective net area does not exceed 0.85 A_g.
Increase the plate thickness or width — the block shear limit state controls, so target that path first (block shear responds best to longer end distances).
Chapter 10
Bearings, joints and movement
Thermal, shrinkage and creep movement, the joint gap through the temperature range, and the elastomeric pad that accommodates it.
Elastomeric bearing design
Shape factor, service compressive stress limit, and the shear-deformation requirement for a steel-reinforced pad.
S = LW / [2 h_ri (L + W)] · σ_s ≤ 1.25 G S ≤ 1.75 ksi · h_rt ≥ 2 Δ_s
Shape factor S
6.00
Total elastomer h_rt
2.00 in
Service stress σ_s
1.111 ksi
Compressive stress check
1.111 ≤ 0.975 ksi
Enlarge the pad or increase the shape factor.
Shear-deformation check
h_rt = 2.00 ≥ 2Δ_s = 1.50 in
Satisfies §14.7.6.3.4.
18 × 9 in pad, 5 elastomer layers with steel shims. Service reaction 180 kip gives σs = 1.111 ksi against the 0.98 ksi limit (AASHTO 14.7.6.3.2) — increase the plan area.
Thermal movement, joint sizing & bearing shear
Rise and fall movement with γ_TU = 1.20, shrinkage and creep shortening, the joint gap at T_max and T_min against the joint's movement rating, the skewed-joint component, and the elastomer thickness needed for h_rt ≥ 2Δ_s.
α = 6.0×10⁻⁶ /°F for concrete, 6.5×10⁻⁶ /°F for steel. Movement length is measured from the point of fixity.
Total movement range
3.110 in
Factored design movement
3.732 in
Gap at T_max (closing)
1.057 in
Gap at T_min (opening)
4.789 in
Bearing shear strain Δ_s/h_rt
0.697
Required elastomer thickness
5.58 in
Gap ranges from 1.057 in (hot) to 4.789 in (cold); factored design movement = 3.732 in.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Temperature rise / fall | ΔT_rise = T_max − T_install ; ΔT_fall = T_install − T_min | 110 − 68 ; 68 − -10 | 42 / 78 °F |
| Thermal expansion | Δ = α ΔT L | 6.50e-6·42·2880 | 0.786 in |
| Thermal contraction | Δ = α ΔT L | 6.50e-6·78·2880 | 1.460 in |
| Shrinkage + creep shortening | Δ = (ε_sh + ε_cr) L | (2.0e-4 + 1.0e-4)·2880 | 0.864 in |
| Total movement range | Δ_total = Δ_rise + Δ_fall + Δ_sh+cr | 0.786 + 1.460 + 0.864 | 3.110 in |
| Factored design movement | γ_TU Δ | 1.20 × 3.110 | 3.732 in |
| Joint gap at maximum temperature | G_min = G_install − γ_TU Δ_rise | 2.000 − 1.20·0.786 | 1.057 in |
| Joint gap at minimum temperature | G_max = G_install + γ_TU(Δ_fall + Δ_sh) | 2.000 + 1.20(1.460 + 0.864) | 4.789 in |
| Bearing shear strain | γ = Δ_s/h_rt ≤ 0.5 | 2.789/4.00 | 0.697 |
| Movement normal to a skewed joint | Δ_n = Δ cos θ | 3.732·cos 0° | 3.732 in |
- OKJoint movement rating ≥ design movementdemand 3.732 incapacity 4.00 in
- OKMinimum open gap 0.25 in at maximum temperaturedemand 1.057 incapacity 0.25 in
- NGBearing shear h_rt ≥ 2Δ_sdemand 0.697capacity 0.500
Adjust the detail — required elastomer thickness h_rt ≥ 5.58 in and joint movement capacity ≥ 3.73 in. If the gap closes below 0.25 in, increase the installation gap or reset the joint at a measured temperature.
Assumptions & code basis
- Uniform temperature range from AASHTO LRFD Table 3.12.2.1-1 (Procedure A) or the contour maps of Procedure B; entered here directly as T_max / T_min.
- Coefficient of thermal expansion: 6.0×10⁻⁶ /°F for normal-weight concrete, 6.5×10⁻⁶ /°F for steel (§5.4.2.2, §6.4.1).
- Load factor γ_TU = 1.20 applied to the movement when sizing joints and bearings (Table 3.4.1-1, deformation calculations).
- Shrinkage plus creep shortening is applied only for concrete superstructures and only in the shortening direction.
- Elastomeric bearing shear deformation limited to h_rt ≥ 2Δ_s, i.e. an engineering shear strain of 0.5 (§14.7.5.3.2 / §14.7.6.3.4).
- For skewed joints the movement normal to the joint is the longitudinal movement times cos θ; the transverse component must also be accommodated.
Bearing rotation, stability & anchorage
Total design rotation with the 0.005 rad construction allowance, the §14.7.6.3.5 combined compression-plus-rotation check, the aspect-ratio stability limit, uplift screening and the anchor-bolt demand.
Full steel-reinforced elastomeric bearing check — stress, shear deformation, rotation, stability and anchorage.
Shape factor S
8.84
σ_s
0.536 ksi
Stress limit
1.250 ksi
h_rt
2.000 in
Shear strain γ_s
0.375
Anchor capacity
102.5 kip
Derivation — equation, substitution, result
Plan area and shape factor
Service compressive stress
Stress limit
Shear deformation
Rotation criterion
Stability
Instantaneous deflection
Anchorage
Detailing — plan, elevation and section
Constructability & detailing notes
- Set the bearing at the mean design temperature and record the installation temperature on the as-builts.
- Provide a level, grouted seat within 1/16 in — a sloped seat walks the pad out over time.
- Detail jacking points and 6 in of clearance so the bearing can be replaced without removing the girder.
- Bevel the sole plate to remove the built-in grade rotation instead of asking the elastomer to absorb it.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Compressive stress limit | 0.536 ksi | 1.250 ksi | PASS |
| h_rt ≥ 2Δ_s | 1.500 in | 2.000 in | PASS |
| Rotation / uplift criterion | 1.352 ksi | 0.536 ksi | REVIEW |
| Stability h_rt ≤ L/3 | 2.000 in | 4.667 in | PASS |
| Anchor bolts φR_n ≥ H_u | 12.0 kip | 102.5 kip | PASS |
| Shape factor 3 ≤ S ≤ 12 practical range | 8.84 | 3 – 12 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Compressive stress within the method limit | 1.250 | 0.536 | VERIFIED |
| Total elastomer thickness ≥ 2Δ_s | h_rt ≥ 2Δ_s | 2.000 | VERIFIED |
Assumptions & basis of design
- Steel-reinforced elastomeric bearing, 50-durometer neoprene, G taken at the low-temperature design value.
- Method A (§14.7.6) is the simplified route; Method B (§14.7.5) permits higher stresses with additional checks.
- Anchor bolts assumed ASTM F1554 Grade 36 in single shear with threads in the shear plane.
The pad rotates more than the compressive stress can hold down — increase the pad plan area, reduce the number of layers, or use a tapered sole plate to remove the built-in rotation.
Chapters 9 · 12 – 13
Substructure — piers, abutments, walls and foundations
Earth pressure and stability, pier-cap and column interaction, single piles and pile groups under axial load and biaxial moment.
Pier-cap flexure & column axial–moment interaction
Cap flexural and shear resistance alongside a column P-M interaction screening ratio with slenderness magnification.
Mn = As fy(d − a/2) · Vc = 0.0316β√f′c bv dv · Po = 0.85f′c(Ag−Ast)+fyAst
Cap φMn
1477 k-ft
Cap φVc
158 kip
Column φPn,max
3145 kip
Column φMn (approx.)
659 k-ft
Cap flexure check
1477 ≥ 2200 k-ft
Cap shear check
158 ≥ 400 kip
Column P-M interaction
1.939
Pu/φPn + Mu/φMn ≤ 1.0 (simplified — verify with a full interaction diagram).
Pier cap longitudinal reinforcement — AASHTO LRFD §5.6.3 / §5.10
| A_s required (strength) | 12.22 in² |
| A_s minimum (§5.6.3.3 / §5.10.6) | 3.12 in² |
| A_s design (governing) | 12.22 in² |
| Bar selection | 8 – #11 |
| Bar size / area | #11 — A_b = 1.56 in² |
| Bars / layers | 8 bars in 1 layer (clear spacing 4.2 in) |
| A_s provided | 12.48 in² |
| A_s,prov / A_s,req | 1.02 |
| Stress-block depth a | 6.12 in |
| Net tensile strain ε_t | 0.0149 |
| φ | 0.900 |
| φM_n (as detailed) | 2243.1 k-ft |
| M_cr (§5.6.3.3) | 592.8 k-ft |
| Minimum-resistance demand min(M_cr, 1.33M_u) | 592.8 k-ft |
| Reinforcement ratio ρ | 0.0081 |
PASS — Adequate — detail as scheduled
A_s,prov / A_s,req = 1.02; ε_t = 0.0149 (tension-controlled, φ = 0.90).
Transverse reinforcement — AASHTO LRFD §5.7.2.5 / §5.7.3.3
| Concrete contribution V_c | 176.1 kip |
| Steel required V_s = V_u/φ − V_c | 268.3 kip |
| Stirrup schedule | #5 2-leg @ 5.0 in c/c (A_v = 0.62 in²) |
| Maximum spacing s_max | 24.0 in |
| φV_n = φ(V_c + V_s) | 417.6 kip |
| Web-crushing limit 0.25 f′_c b_v d_v | 1393.2 kip |
PASS — φV_n = 417.6 kip ≥ V_u = 400.0 kip.
Column longitudinal steel
18 – #14
A_st,req 40.45 → A_st,prov 40.50 in²
Column ties / spiral
#4 ties @ 12 in c/c (§5.10.4.3)
ρ = 2.92 % (limits 1 %–8 %) — 18 – #14 bars, clear spacing 4.76 in.
8 #11 continuous top bars (As = 12.48 in²) with skin and bottom steel; #5 double-leg stirrups @ 6 in through the cap. Cap 36 in wide × 48 in deep, 4.00 ft cantilever each end, 2 columns at 20.00 ft centres.
32 #10 longitudinal bars (Ast = 40.64 in², ρ = 2.93 %) against the required Ast = 40.50 in² at ρ = 2.92 %. #4 spiral at 3 in pitch, 2 in clear cover. Design actions Pu = 1800 kip, Mu = 900 k-ft (AASHTO 5.6.4, 5.10.4.2).
Abutment / retaining-wall stability screening
Rankine active thrust with overturning, sliding, and eccentricity screening ratios.
K_a = tan²(45° − φ′/2) · P_a = ½ K_a γ H² · e ≤ B/4 for soil foundations
K_a (Rankine)
0.283
Active thrust P_a
6.79 kip/ft
Overturning moment
45.2 k-ft/ft
Overturning ratio M_r/M_o
59.69
Target ≥ 2.0
Sliding ratio
44.73
Target ≥ 1.5
Eccentricity e
0.10 ft
B/4 = 3.00 ft
Stem 20.0 ft tall on a 12.0 ft footing. Active thrust Pa = 6.8 kip acting at H/3, resisting weight W = 450.0 kip, resultant eccentricity e = 0.10 ft. qmax = 39.38 ksf, qmin = 35.62 ksf (AASHTO 11.6.3).
Screening tool only: the LRFD check uses factored loads with the Strength I and Extreme Event combinations and resistance factors from §11.5.7, not global factors of safety.
Pile axial resistance
Skin friction and tip resistance for driven piles, with static and dynamically-verified factored resistances.
Rs = fs·perimeter·L · Rp = qp·Ap · Rn = Rs + Rp · φRn = φ·Rn
Side resistance Rs
166 kip
Tip resistance Rp
15 kip
Nominal resistance Rn
181 kip
φRn (static)
81 kip
φRn (dynamic)
118 kip
Piles required (static design)
23
Dynamic-verified: 16 piles
23 piles at 3.0D centres, 16 in diameter, 60 ft embedded with the top 0 ft inside the scour prism neglected. Demand 78 kip/pile against φQn = 81 kip (AASHTO 10.7.3.8).
Pile group — efficiency, block failure & cap distribution
Group efficiency η in clay, the equivalent-pier block failure check, factored group resistance, and the rigid-cap elastic distribution P_u/N ± M_x y/Σy² ± M_y x/Σx² with the corner-pile and uplift checks.
Corner piles govern: the elastic cap formula adds the moment terms about both axes.
Group efficiency η
0.775
Group size B × L
12.50 × 8.75 ft
Factored group resistance
1813 kip
Max pile load
240.7 kip
Min pile load
159.3 kip
Group size 12.50 × 8.75 ft; max pile load 240.7 kip vs φQ_p.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Pile count | N = rows × columns | 3 × 4 | 12 piles |
| Group efficiency | η = 0.7 at s = 2.5b, 1.0 at s = 6b (linear) | s/b = 3.00 | 0.775 |
| Sum of individual capacities | Q_g = η N Q_p | 0.775·12·300.0 | 2790 kip |
| Block failure (clay) | Q_block = 2(B + L)Z c_u + 9 c_u B L | 2(12.50 + 8.75)·45.0·1.20 + 9·1.20·12.50·8.75 | 3476 kip |
| Factored group resistance | φQ = φ·min(Q_g, Q_block) | 0.65·2790 | 1813 kip |
| Maximum pile load | P = P_u/N + M_x y_max/Σy² + M_y x_max/Σx² | 2400/12 + 900·3.75/112.5 + 400·5.63/210.9 | 240.7 kip |
| Minimum pile load | P = P_u/N − M_x y_max/Σy² − M_y x_max/Σx² | 2400/12 − … | 159.3 kip |
- NGGroup resistance φQ ≥ P_udemand 2400 kipcapacity 1813 kipratio 1.32
- NGIndividual pile P_max ≤ φQ_pdemand 240.7 kipcapacity 195.0 kip
- OKNo net upliftdemand 159.3 kip
- OKSpacing s ≥ 2.5b (§10.7.1.2)demand 3.75 ftcapacity 3.13 ft
Add piles or spread the group: about 16 piles are needed, or lengthen the piles to raise Q_p to 370.3 kip each.
Assumptions & code basis
- Group efficiency η applies to pile groups in cohesive soils; in cohesionless soils driven piles at s ≥ 2.5b are taken as η = 1.0 (AASHTO LRFD §10.7.3.9).
- Block failure of a group in clay checked as a single equivalent pier: perimeter adhesion plus 9c_u end bearing (§10.7.3.9).
- Individual pile loads from the rigid-cap elastic formula P = P_u/N ± M_x y/Σy² ± M_y x/Σx²; the cap is assumed infinitely rigid and the piles axially elastic.
- Resistance factors: φ = 0.65 (clay, static analysis with driving criteria) or 0.50 (sand, static analysis) — increase with dynamic testing per Table 10.5.5.2.3-1.
- Tension (uplift) piles must additionally be checked with φ_up ≤ 0.35–0.45.
Pier column slenderness & moment magnification
Effective length KL/r screening against the 22 / 34 − 12(M1/M2) thresholds, EI_eff with β_d, the critical load P_c, and the δ_ns magnified design moment with the minimum-eccentricity floor.
Screens the column for slenderness, then magnifies the moment with the §5.6.4.3 approximate procedure.
Kℓ_u/r
33.6
P_e
14396 kip
δ_b
1.200
M_c design
1080.1 kip·ft
ρ_g
0.0155
φP_n,max
4643 kip
Derivation — equation, substitution, result
Radius of gyration
Slenderness ratio
Slenderness limit
Flexural stiffness
Euler load
Moment gradient factor
Magnifier
Minimum eccentricity
Magnified design moment
Pure axial capacity
Detailing — plan, elevation and section
Constructability & detailing notes
- Column bars are spliced above the footing with a mechanical coupler or a lap outside the plastic-hinge zone.
- Provide a 2 in chamfer or a formliner detail — plain circular columns show every form seam.
- Check the free-standing (erection) condition before the cap is cast: K is effectively 2.1 for a cantilever pier.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| P_u < 0.75 P_e (stability) | 1800 kip | 10797 kip | PASS |
| δ_b ≤ 1.40 (practical limit — otherwise stiffen) | 1.200 | 1.40 | PASS |
| Steel ratio 1 % ≤ ρ_g ≤ 8 % (§5.6.4.2) | 0.0155 | 0.010 – 0.080 | PASS |
| Axial capacity φP_n,max ≥ P_u | 1800 kip | 4643 kip | PASS |
| Kℓ_u/r ≤ 100 (refined analysis required above) | 33.6 | 100 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Magnifier within the practical 1.0 – 1.4 band | 1.00 – 1.40 | 1.200 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §5.6.4.3 approximate moment magnification for a single-curvature or double-curvature column.
- β_d = ratio of factored permanent axial load to total factored axial load; 0.6 is typical for bridge piers.
- K = 1.0 for pinned–pinned, 2.1 for a free-standing cantilever pier, 0.65 – 0.80 for a fixed-base column in a braced frame.
Design the column for P_u = 1800 kip with M_c = 1080.1 kip·ft on the P–M interaction diagram.
Biaxial column bending — Bresler reciprocal
Uniaxial capacities about each axis, the Bresler reciprocal-load check 1/P_n = 1/P_nx + 1/P_ny − 1/P_o, and the load-contour comparison with the bar layout that satisfies both axes.
Bresler reciprocal-load check at moderate to high axial load, with the moment-contour alternative below 0.10 φP_o.
φP_ni (biaxial)
1942 kip
Reciprocal-load ratio
0.824
Moment-contour ratio
1.057
Governing utilisation
0.824
Derivation — equation, substitution, result
Screening
Reciprocal load
Axial utilisation
Moment contour
Governing ratio
Detailing — plan, elevation and section
Constructability & detailing notes
- Distribute the longitudinal bars around the full perimeter — corner-only layouts have poor biaxial capacity.
- Cross-ties on alternate bars are required when the clear spacing exceeds 6 in (§5.10.4.3).
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Biaxial interaction ≤ 1.0 | 0.824 | 1.000 | PASS |
| φP_nx and φP_ny each exceed P_u | 1600 kip | 2600 kip | PASS |
| Bresler validity P_u ≥ 0.10 φP_o | 1600 kip | 520 kip | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Governing interaction ≤ 1.0 | ≤ 1.000 | 0.824 | VERIFIED |
Assumptions & basis of design
- φP_nx and φP_ny are read from the uniaxial interaction diagrams at the respective eccentricities e_x = M_uy/P_u and e_y = M_ux/P_u.
- φP_o = φ[0.85f′_c(A_g − A_st) + f_y A_st] is the concentric capacity without the 0.80 cap.
- Bresler's reciprocal-load equation is accurate within about 10 % for symmetric sections at moderate to high axial load.
Biaxial capacity is adequate; confirm the tie or spiral detailing and the bar development into the cap and footing.
Column confinement, ties and plastic hinge detailing
Spiral ratio ρ_s and rectangular hoop A_sh from the two governing expressions, the hoop spacing and plastic-hinge length ℓ_o, tie size and the cross-tie layout for a seismic pier column.
Spiral or tie confinement, pitch, longitudinal bar layout and the seismic floor of 0.12 f′_c/f_yh.
ρ_s required
0.00800
Spiral pitch
3.50 in
ρ_s provided
0.00805
Tie spacing
12.00 in
ρ_g longitudinal
0.0111
Callout
20 — #9 vert. w/ #5 spiral @ 3.50 in
Derivation — equation, substitution, result
Gross and core areas
Confinement ratio (gravity)
Confinement ratio (seismic)
Governing ratio
Spiral pitch
Provided ratio
Tie spacing (tied column)
Longitudinal bar layout
Detailing — plan, elevation and section
Constructability & detailing notes
- Spirals are shipped compressed and stretched on site — specify spacer bars so the pitch survives concrete placement.
- Extend the confinement one full column dimension into the cap and the footing.
- Keep the clear pitch at 1 in minimum so a vibrator head and the aggregate can pass.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| ρ_s,prov ≥ ρ_s,req | 0.00800 | 0.00805 | PASS |
| Clear pitch 1 – 3 in (§5.10.4.3) | 2.88 in clear | 1.0 – 3.0 in | PASS |
| Longitudinal steel 1 – 8 % | 0.0111 | 0.010 – 0.080 | PASS |
| Bar clear spacing adequate for concrete placement | 5.61 in | 1.69 in | PASS |
| Spiral ≥ #3 (or #4 in seismic zones) | #5 | #4 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Provided confinement ratio ≥ required | 0.00800 | 0.00805 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §5.6.4.6 and §5.10.4 for gravity columns; §5.10.11 adds the seismic confinement floor.
- Spiral pitch is rounded down to the nearest 1/4 in and capped at 6 in.
- The core dimension D_c is measured out-to-out of the spiral.
Confinement satisfies the code; extend the spiral into the cap and footing for the full development length of the longitudinal bars.
Retaining wall — full stability and stem design
Coulomb / Rankine thrust with surcharge, the overturning, sliding and bearing-eccentricity checks, the factored bearing pressure diagram, and stem, heel and toe flexural steel with bar schedules.
External stability (overturning, sliding, eccentricity, bearing) and internal stem design in one pass.
K used
0.307
active (free to translate)
ΣH
10.55 kip/ft
ΣV
40.62 kip/ft
FS overturning
4.83
FS sliding
2.12
Eccentricity e
-0.850 ft
q_max
1.845 ksf
Stem steel
#3 @ 1 in
A_s,req = 0.994 in²/ft
Derivation — equation, substitution, result
Earth-pressure coefficients
Active thrust
Live-load surcharge
Vertical resultant
Overturning
Sliding
Resultant location
Bearing pressure
Meyerhof effective width
Stem moment and shear at the base
Factored stem demand
Stem reinforcement
Stem shear
Detailing — plan, elevation and section
Constructability & detailing notes
- Place free-draining backfill with a perforated underdrain — hydrostatic pressure is the most common cause of wall distress.
- Compact backfill in 8 in lifts with light equipment within 3 ft of the stem to avoid overstressing it.
- Provide contraction joints at 30 ft maximum and expansion joints at 90 ft with waterstops.
- Do not backfill until the stem concrete reaches its specified strength and the footing is fully cured.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Overturning FS ≥ 2.0 (soil) | 4.83 | 2.00 | PASS |
| Sliding FS ≥ 1.5 | 2.12 | 1.50 | PASS |
| Eccentricity within the middle third (e ≤ B/6) | 0.850 ft | 2.333 ft | PASS |
| Bearing q_max ≤ q_n | 1.845 ksf | 6.00 ksf | PASS |
| Stem shear without stirrups | 13.03 kip/ft | 26.42 kip/ft | PASS |
| No net uplift at the heel (q_min ≥ 0) | 3.958 ksf | 0 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Overturning factor of safety | ≥ 2.00 | 4.83 | VERIFIED |
| Sliding factor of safety | ≥ 1.50 | 2.12 | VERIFIED |
Assumptions & basis of design
- Rankine active pressure on a vertical virtual back face with a level backfill and no wall friction.
- Live-load surcharge as an equivalent height of soil h_eq from Table 3.11.6.4-1 (varies with wall height and distance from the traffic).
- Passive resistance in front of the toe is neglected — a conservative and customary assumption where scour or excavation is possible.
- Load factors: γ_EH = 1.50 max (active), γ_LS = 1.75, γ_EV = 1.35 max / 1.00 min.
Stability is satisfied. Detail the stem with #3 @ 1 in on the earth face, with the same area developed into the footing.
Spread footing — bearing, sliding, shear and steel
Factored bearing pressure with eccentricity and the middle-third rule, one-way and two-way shear at the critical sections, flexural steel each way, and the development length available from the column face.
Meyerhof bearing capacity on the effective width, elastic settlement, sliding and the scour-elevation check.
q_n
48.259 ksf
q_R factored
21.716 ksf
q applied
6.897 ksf
Eccentricity e
0.750 ft
Settlement
1.929 in
Sliding capacity
1056.0 kip
Derivation — equation, substitution, result
Bearing-capacity factors
Load eccentricity
Shape and depth factors
Nominal bearing resistance
Factored resistance
Applied pressure
Elastic pressure distribution
Elastic settlement
Sliding
Detailing — plan, elevation and section
Constructability & detailing notes
- Found on undisturbed material; if the excavation is over-dug, backfill with lean concrete, never compacted soil.
- A 3 in mud slab keeps the bottom mat clean and lets the crew work in wet conditions.
- Dowels must be templated to match the column cage before the pour — field bending of large bars is not permitted.
- Check the excavation slope or shoring separately; a footing failure during construction is a trench failure, not a bearing failure.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Bearing q ≤ q_R | 6.897 ksf | 21.716 ksf | PASS |
| Eccentricity e ≤ B/4 on soil (§10.6.3.3) | 0.750 ft | 4.000 ft | PASS |
| Settlement ≤ 1 in (typical service tolerance) | 1.929 in | 1.000 in | REVIEW |
| Sliding φR_n ≥ H | 180.0 kip | 1056.0 kip | PASS |
| Footing founded below the total scour depth | 4.00 ft of scour | 8.00 ft embedment | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Bearing pressure within the factored resistance | 21.716 | 6.897 | VERIFIED |
| Settlement within the 1 in service tolerance | ≤ 1.000 in | 1.929 | CHECK |
Assumptions & basis of design
- Meyerhof/Vesić bearing-capacity formulation per AASHTO §10.6.3.1.2a with an effective footing width B′ = B − 2e.
- Load inclination factors are omitted — acceptable when H/V < 0.1; include them for heavily loaded abutments.
- Elastic settlement uses a uniform half-space with rigidity factor I_f; for layered profiles use the Hough or Schmertmann method.
- Bearing resistance is computed on soil below the total scour elevation.
Bearing, eccentricity, settlement and sliding are all satisfied; design the footing for one-way and two-way shear and for the flexural cantilever.
Pile capacity — α, β and Nordlund methods
Side resistance in cohesive soil by the α-method and in granular soil by the β-method, tip resistance, the factored geotechnical resistance with resistance factors by verification method, and the required pile length.
α-method for clay, β-method for sand, and the rock-socket equation, with the Converse–Labarre group efficiency.
Unit side resistance f_s
0.989 ksf
R_s
372.8 kip
R_p
233.7 kip
R_r per pile
273.0 kip
Group efficiency η
0.727
Group capacity
1786 kip
Derivation — equation, substitution, result
Geometry
Mid-depth effective stress
β-method friction
Side resistance
Tip resistance
Nominal and factored single-pile resistance
Group efficiency
Group resistance
Detailing — plan, elevation and section
Constructability & detailing notes
- Specify the driving criterion (blow count and hammer energy) as well as the tip elevation — capacity is verified in the field, not on paper.
- Order piles 10 – 15 % longer than the estimated length; splicing in the field is slower than cutting off.
- For drilled shafts, keep the slurry head above the piezometric level and place concrete by tremie without interruption.
- Preserve a minimum 3D spacing so the group efficiency stays near unity and the driving does not heave adjacent piles.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Single pile R_r ≥ P_u/N | 444.4 kip | 273.0 kip | REVIEW |
| Group resistance ≥ P_u | 4000 kip | 1786 kip | REVIEW |
| Pile spacing ≥ 2.5 D (§10.7.1.2) | 6.00 ft | 5.00 ft | PASS |
| β within 0.25 – 1.20 for sands | 0.532 | 0.25 – 1.20 | PASS |
| Downdrag considered where fill is placed over compressible soil (§3.11.8)Add DD as a load, not a resistance reduction, and use the same φ as skin friction. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Group resistance exceeds the factored load | 1786 | demand applied | CHECK |
| Group efficiency at or above 0.70 | ≥ 0.700 | 0.727 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §10.7 for driven piles and §10.8 for drilled shafts; static analysis resistance factors from Table 10.5.5.2.3-1.
- α from the AASHTO/API correlation with s_u; β = K tan δ with a 3.0 ksf cap on unit side friction in sand.
- Group efficiency from Converse–Labarre; efficiency is taken as 1.0 at centre-to-centre spacings of 6D or more.
- Load test or dynamic verification would allow a higher φ (0.65 – 0.80) than the static value used here.
Lengthen the piles (R_s grows linearly with L), increase the diameter, or add piles at ≥ 3D spacing so the group efficiency stays near unity.
Abutment backwall, bridge seat and approach slab
Cantilever backwall under EH plus the live-load surcharge, the Strength I moment and back-face bar schedule, the bridge-seat edge distance and bearing stress, and the approach-slab one-way strip with its bottom steel.
Cantilever backwall under EH plus live-load surcharge, the bridge-seat geometry and bearing stress, and the approach-slab one-way strip — carried through to bar size and spacing on both elements.
Backwall M_u
8.07 kip·ft/ft
Service moment
5.01 kip·ft/ft
A_s required
0.324 in²/ft
Backwall bar
#4 @ 7.0 in
back face, vertical
A_s provided
0.343 in²/ft
φM_n backwall
23.05 kip·ft/ft
Seat edge distance
6.00 in
Seat bearing stress
1.481 ksi
Approach-slab bar
#9 @ 4.0 in
bottom, longitudinal
Derivation — equation, substitution, result
Active earth pressure at the backwall base
Earth-pressure resultant
Live-load surcharge (Table 3.11.6.4-1)
Strength I moment at the backwall base
Required flexural steel
Shrinkage and temperature minimum (§5.10.6)
Bar selection, back face
Provided flexural resistance
Bridge-seat geometry
Seat bearing stress (§5.6.5)
Approach-slab Strength I moment
Approach-slab bottom steel
Detailing — plan, elevation and section
Section through the abutment. Backwall 18.0 in thick × 7.50 ft high carries Mu = 8.07 kip·ft/ft against φMn = 23.05 kip·ft/ft with #4 @ 7.0 in on the back face and matching horizontal temperature steel. Bridge seat 30.0 in wide takes a 18.0 in pad. Approach slab 25 ft × 15.0 in reinforced #9 @ 4.0 in bottom.
Constructability & detailing notes
- Keep the backwall thick enough to house the deck-joint anchorage — 18 in is the practical minimum for a strip-seal joint.
- Provide a 1 in preformed filler between the backwall and the approach slab so thermal movement is not transferred into the wall.
- Detail a shear key or corbel at the base of the approach slab and drain the paving-notch area — trapped water is the single most common cause of backwall spalling.
- Lap the vertical backwall bars into the stem with a Class B splice and keep the bar spacing at 12 in maximum for crack control.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| φM_n ≥ M_u — backwall vertical steel | 8.07 kip·ft/ft | 23.05 kip·ft/ft | PASS |
| A_s ≥ shrinkage & temperature minimum (§5.10.6) | 0.324 in²/ft | 0.343 in²/ft | PASS |
| Bar spacing ≤ 12 in (crack control, §5.6.7) | 7.0 in | 12.0 in | PASS |
| Bearing-seat edge distance ≥ 3 in | 6.00 in | 3.0 in | PASS |
| Seat bearing stress ≤ 0.85φf′_c | 1.481 ksi | 2.380 ksi | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Hand check — EH resultant ½k_aγh² | 1.114 kip/ft | 5.01 kip·ft/ft (moment, not thrust) | VERIFIED |
Assumptions & basis of design
- Backwall analysed as a vertical cantilever spanning from the bridge seat, per §11.6.1.4 and §3.11.5.
- Live-load surcharge uses the equivalent-height table for the wall height; the surcharge is omitted behind an integral approach slab that is founded on the abutment.
- Approach slab treated as a simply supported one-way strip between the abutment corbel and the sleeper slab.
- Bearing-seat stress screened with A₂/A₁ = 1.0; a confined seat may take the √(A₂/A₁) increase up to 2.0.
Detail the backwall bars to lap into the stem with a Class B splice, and keep a 1 in preformed joint filler between the backwall and the approach slab so thermal movement is not transferred into the wall.
MSE wall / wingwall — internal stability
Simplified-Method k_r with depth, the strip load T_max, rupture resistance after the 75-year sacrificial corrosion loss, and pullout over the resisting length beyond the bi-linear failure surface.
Simplified-Method internal stability for a steel-strip MSE wall or wingwall: k_r with depth, the strip load T_max, rupture after 75-yr corrosion loss, and pullout over the resisting length beyond the bi-linear failure surface.
k_r at depth z
0.3746
σ_h
0.792 ksf
T_max per strip
4.952 kip
Rupture resistance T_r
9.994 kip
Effective length L_e
12.28 ft
Pullout resistance P_r
6.909 kip
Strips per ft of wall
1 ea/ft
S_h = 2.50 ft, S_v = 2.50 ft
L/H ratio
0.727
Derivation — equation, substitution, result
Active earth-pressure coefficient of the reinforced fill
Lateral stress ratio for inextensible steel strips
Vertical stress at the layer
Horizontal stress and maximum strip load
Rupture resistance after 75-yr corrosion loss
Effective (resisting) length beyond the failure surface
Pullout resistance
Demand-capacity ratios
Detailing — plan, elevation and section
Wall 22.0 ft high with 16.0 ft strips at Sv = 2.50 ft × Sh = 2.50 ft (2 in × 0.1575 in galv. strip). At z = 15.0 ft the strip load is Tmax = 4.95 kip against a rupture resistance of 9.99 kip and a pullout resistance of 6.91 kip over Le = 12.28 ft.
Constructability & detailing notes
- Keep the reinforcement length uniform for the full height unless a bench is provided — stepped lengths are a frequent source of field errors.
- Never let a strip conflict with an abutment pile or a drainage pipe; skew the strips around the obstruction and add a layer above and below.
- Compact the reinforced fill in 8 in lifts with light equipment within 3 ft of the face panels to prevent panel push-out.
- Wingwall corners need a corner element and shortened strips — check pullout with the reduced L_e at every corner layer.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Strip rupture — T_max ≤ φA_cF_y | 4.952 kip | 9.994 kip | PASS |
| Strip pullout — T_max ≤ P_r | 4.952 kip | 6.909 kip | PASS |
| Minimum reinforcement length L ≥ 0.7H (§11.10.2.1) | 15.40 ft | 16.00 ft | PASS |
| Minimum effective length L_e ≥ 3 ft | 3.0 ft | 12.28 ft | PASS |
| Vertical spacing S_v ≤ 2.5 ft | 2.50 ft | 2.50 ft | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Order-of-magnitude — σ_h ≈ k_a γ z at depth | 0.530 ksf | 0.792 ksf | VERIFIED |
Assumptions & basis of design
- Internal stability by the Simplified Method of §11.10.6 with inextensible galvanised steel strips.
- Bi-linear Coulomb failure surface; for extensible geosynthetics the surface is the single Rankine wedge and k_r = k_a throughout.
- Sacrificial steel thickness covers 75-yr design life in non-aggressive fill (§11.10.6.4.2a).
- External stability (sliding, eccentricity, bearing) and global stability are checked separately.
Both internal modes pass. Reduce S_v near the coping to control face-panel bulging, and detail the wingwall corner strips to skew around the abutment piles.
Laterally loaded piles — p-y and Broms screening
Relative stiffness factor T, the characteristic length, the head deflection and maximum moment from the non-dimensional coefficients, and the Broms ultimate lateral capacity for the fixed and free head cases.
Characteristic-length (T or R) solution for groundline deflection and maximum moment, with a Broms ultimate-capacity screen.
T (characteristic)
18.79 in
Groundline deflection
0.0042 in
M_max
699.2 kip·in
Depth to M_max
24.4 in
Broms H_u
3391.8 kip
Behaviour
long / flexible
Derivation — equation, substitution, result
Flexural stiffness
Characteristic length
Long-pile screening
Groundline deflection
Maximum moment
Broms ultimate lateral capacity
Section capacity
Detailing — plan, elevation and section
Constructability & detailing notes
- A fixed-head detail needs the pile embedded at least 12 in into the cap with the reinforcement fully developed — otherwise it is a pinned head.
- Battered piles pick up lateral load efficiently but attract large seismic forces; avoid them in high-seismic regions.
- Neglect the top 3 – 5 ft of soil around the pile: it is disturbed, may be scoured, and contributes little resistance.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Deflection ≤ 0.5 in at the groundline (typical service criterion) | 0.0042 in | 0.500 in | PASS |
| M_max ≤ φM_p of the pile section | 699.2 kip·in | 9000.0 kip·in | PASS |
| Pile long enough for the coefficient solution | 660 in | 75 in | PASS |
| Refined p-y analysis recommended for final design (§10.7.3.12)Use LPILE/COM624 p-y curves for production design; this module sizes the trial pile. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Maximum moment within the pile section capacity | ≤ φM_p | 699.2 | VERIFIED |
| Long-pile assumption valid | L ≥ 4T (sand) / 3.5R (clay) | long / flexible | VERIFIED |
Assumptions & basis of design
- Elastic subgrade-reaction (characteristic length) solution — Reese for sand with linearly increasing modulus, Matlock for clay with constant modulus.
- Free-head coefficients A_y = 2.43, A_m = 0.77; fixed-head A_y = 0.93, A_m = 0.93.
- Scour and liquefiable layers must be removed from the resisting profile before running the analysis.
The trial pile works; confirm with a p-y analysis using site-specific soil parameters and check the pile-to-cap connection for the same moment.
Chapters 15 – 16
Extreme events — seismic, scour and ice
Design response spectra and seismic demand, support lengths, scour depths, and ice forces on piers.
Seismic design spectrum & demand
Site-adjusted S_DS and S_D1 with F_a / F_v, the corner periods T₀ and T_s, the elastic seismic coefficient C_sm, base shear C_sm·W, the R-reduced design force, the Seismic Design Category and the spectral displacement.
Period T may be estimated from the single-mode method: T = 2π√(W/(g·k)) with k the lateral stiffness of the pier.
S_DS
1.200
S_D1
0.600
C_sm
1.0000
Elastic base shear V_e
2000.0 kip
Design shear V_e/R
666.7 kip
Seismic zone (SDC)
Zone 4
Spectral displacement
3.52 in
Zone 4 for site class D, T = 0.60 s.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Site-adjusted short-period acceleration | S_DS = F_a S_s | 1.6·0.750 | 1.200 |
| Site-adjusted 1-second acceleration | S_D1 = F_v S_1 | 2.4·0.250 | 0.600 |
| Corner periods | T_s = S_D1/S_DS ; T_0 = 0.2T_s | 0.600/1.200 | T_s = 0.500 s, T₀ = 0.100 s |
| Elastic seismic coefficient | C_sm = S_D1/T | T = 0.600 s | 1.0000 |
| Elastic base shear | V_e = C_sm W | 1.0000·2000 | 2000.0 kip |
| Design force | V = V_e / R | 2000.0/3.00 | 666.7 kip |
| Seismic design category | Table 3.10.6-1 on S_D1 | S_D1 = 0.600 | Zone 4 |
| Elastic spectral displacement | Δ = C_sm g T²/4π² | 1.0000·386.4·0.600²/4π² | 3.52 in |
Site class D gives S_DS = 1.200 and S_D1 = 0.600 → Seismic Zone 4. Design the substructure for 666.7 kip with R = 3.00, but proportion the connections and the support length for the full elastic demand; check the minimum seat width against a displacement of about 3.52 in.
Assumptions & code basis
- Design response spectrum per AASHTO LRFD §3.10.4.1 with site factors F_pga, F_a and F_v from Tables 3.10.3.2-1..-3 for the chosen site class.
- S_DS = F_a S_s and S_D1 = F_v S_1; the spectrum plateau extends to T_s = S_D1/S_DS and the ascending branch to T_0 = 0.2T_s.
- Seismic Design Category (Zone) from Table 3.10.6-1 keyed on S_D1.
- Response modification factor R applies to substructure elements (§3.10.7.1); connections use R = 0.8–1.0, and column forces from plastic hinging may govern in SDC C/D.
- The elastic force V_e = C_sm W assumes a single-mode (uniform load) analysis; multimode or time-history analysis is required for irregular bridges in SDC C and D.
Seismic support-length (seat) check
Empirical minimum support length with seismic-zone multipliers, compared against the provided seat width.
N = (8 + 0.02L + 0.08H)(1 + 0.000125S²) · Nreq = zone multiplier × N
Empirical N
13.37 in
Required seat Nreq
20.05 in
Seat width check
24.0 ≥ 20.05 in
Seat adequate.
Provided seat N = 24.0 in against the required N = 20.0 in (AASHTO 4.7.4.4) — adequate; the girder cannot unseat under the design displacement.
Scour design elevation
HEC-18 local pier scour, live-bed contraction scour, and the resulting design scour elevation and embedment check.
ys = 2.0 K1K2K3 a^0.65 y1^0.35 Fr1^0.43 · y2/y1 = (Q2/Q1)^(6/7)(W1/W2)^(6/7)
Froude number Fr1
0.407
Local pier scour
10.15 ft
Contraction scour
2.53 ft
Total scour depth
13.68 ft
Design scour elevation
86.32 ft
Foundation embedment check
88.00 vs 86.32 ft
Embedment margin 1.68 ft.
Contraction scour 2.5 ft + local pier scour 10.2 ft = 13.7 ft below the existing streambed at El. 100.0 ft. Foundation top must sit at or below El. 88.0 ft (AASHTO 2.6.4.4.2).
Ice force on piers
Crushing force p·t·w, the reduced bending failure force on an inclined nose, the narrow-pier w/t correction and the 15 % transverse component at Extreme Event II.
Effective ice crushing strength p: 8 ksf (break-up, disintegrated) to 32 ksf (solid sheet, well below freezing).
Crushing force F_c
64.0 kip
Bending force F_b
— kip
Design longitudinal ice force
53.3 kip
Design transverse ice force
9.6 kip
Pier width w = 4.00 ft, ice thickness t = 1.00 ft, nose angle α = 90°.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Width-to-thickness ratio | w/t | 4.00/1.00 | 4.00 |
| Crushing force | F_c = p·t·w | 16.0·1.00·4.00 | 64.0 kip |
| Bending failure on an inclined nose | F_b = p t² tan(α − 15°) | 16.0·1.00²·tan(90° − 15°) | not applicable (α ≥ 75°) |
| Narrow-pier reduction | w/t < 6 → F = (0.5 + w/12t)F_c | w/t = 4.00 | 53.3 kip |
| Governing longitudinal ice force | F = min(F_c, F_b) with the narrow-pier factor | min(64.0, —) | 53.3 kip |
| Transverse component | F_t = 0.15 F | 0.15·53.3 | 8.0 kip |
The vertical pier face crushes the ice at 64.0 kip. Sloping the nose to 60° would cut the force to about 16.0 kip.
Assumptions & code basis
- Ice loads per AASHTO LRFD §3.9 with an effective ice crushing strength p from §3.9.2.1 (8 to 32 ksf depending on break-up temperature and ice condition).
- Vertical-faced piers (α ≥ 75°) crush the ice: F = F_c = p·t·w. Inclined noses (α < 75°) allow the sheet to fail in bending at a lower force.
- For narrow piers with w/t < 6, the crushing force is reduced by (0.5 + w/12t).
- A transverse force of 15 % of the longitudinal force is applied simultaneously (§3.9.2.4).
- Ice force is combined at the Extreme Event II limit state with γ_IC = 1.00 and the reduced live load.
Wind on the structure, live load and substructure
Design pressure P_Z with K_z, G and C_d, the minimum-pressure floors, skew resolution into transverse and longitudinal components, wind on live load, vertical uplift and the pier base moment at Strength III and Strength V.
§3.8 design wind pressure on the superstructure and substructure, wind on live load, skew resolution into transverse and longitudinal components, and the resulting pier base moment at Strength III and Strength V.
P_Z superstructure
0.0440 ksf
WS total
48.63 kip
WS transverse
42.12 kip
WS longitudinal
24.32 kip
WL on live load
13.00 kip
Strength V / Service II
WS on pier
5.63 kip
Vertical wind
2.600 kip/ft width
Base moment, Strength III
1421.0 kip·ft
Base moment, Strength V
1781.3 kip·ft
Derivation — equation, substitution, result
Design wind pressure on the superstructure (§3.8.1.2.1)
Minimum windward pressure
Exposed superstructure area
Wind force on the structure
Skew resolution
Wind on live load (§3.8.1.3)
Wind on the substructure (§3.8.1.2.3)
Vertical wind uplift (§3.8.2)
Overturning moment at the pier base — Strength III
Overturning moment — Strength V (WS + WL)
Detailing — plan, elevation and section
PZ = 0.0440 ksf over 8.50 ft × 130 ft gives WS = 48.6 kip; resolved at 30° the transverse component is 42.1 kip and the longitudinal component 24.3 kip. Wind on live load adds 13.0 kip at Strength V. Pier base moment 1421 kip·ft (Strength III) and 1781 kip·ft (Strength V).
Constructability & detailing notes
- During erection the girders are far more wind-sensitive than in service — check the unbraced girder against the construction wind case of §3.4.2 before the cross-frames are bolted.
- Carry the transverse wind reaction into the bearing anchor bolts and the sole-plate weld, not just the pier.
- Open barrier rails reduce the exposed depth substantially; a solid parapet increases both the area and the drag coefficient.
- Screen bearing uplift with 0.90 DC plus vertical wind before finalising the anchorage.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Windward pressure ≥ 0.030 ksf minimumcomputed pressure governs | 0.0440 ksf computed | 0.030 ksf floor | PASS |
| Substructure pressure ≥ 0.040 ksf minimum | 0.0542 ksf | 0.040 ksf floor | PASS |
| Wind skew resolved into both orthogonal directions (Table 3.8.1.2.3-1) | θ = 30° | both components carried | PASS |
| Strength V governs over Strength III | 1421.0 kip·ft | 1781.3 kip·ft | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Minimum windward pressure × exposed area | 33.1 kip | 48.63 kip | VERIFIED |
Assumptions & basis of design
- Design wind speed V is the 3-second gust for the site from Figures 3.8.1.1.2-1 through -3 with the applicable MRI for the limit state.
- K_z uses the exposure category and the height of the superstructure centroid; G = 1.00 for typical rigid girder bridges.
- Wind on live load is only combined at Strength V and Service II; Strength III has no live load on the structure.
- Vertical wind is applied at the windward quarter point of the deck width and is only combined when it controls uplift at the bearings.
The skew produces a substantial longitudinal component — confirm the fixed-bearing line and the longitudinal restraint at the abutment can deliver it into the substructure.
Vessel collision — barge and ship impact
Kinetic energy of the design vessel, the barge bow damage depth a_B and impact force, the ship formula 8.15V√DWT, the empty-barge drifting minimum, the pier base moment and the Extreme Event II demand-capacity ratio.
§3.14 vessel-collision design: kinetic energy of the design vessel, the ship or barge impact force, the empty-barge drifting minimum, the pier base moment and the Extreme Event II demand-capacity ratio.
Kinetic energy
4676 kip·ft
Bow damage depth a_B
229.868 ft
Impact force P
26634.5 kip
Design force P_des
26634.5 kip
computed force governs
Base moment
372882 kip·ft
Pier shear demand
26634.5 kip
DCR on the pier
19.025
Pier width
6.00 ft
Derivation — equation, substitution, result
Impact velocity
Kinetic energy of the design vessel (§3.14.7)
Barge bow damage depth (§3.14.11)
Barge impact force (§3.14.11)
Design impact force with the drifting-barge floor
Overturning moment at the pier base
Pier demand-capacity ratio
Annual frequency of collapse target (§3.14.5)
Detailing — plan, elevation and section
Barge impact P = 26634.5 kip applied 14.0 ft above the pier base (KE = 4676 kip·ft, bow damage a_B = 229.868 ft). Pier lateral resistance 1400.0 kip gives DCR = 19.02 at Extreme Event II.
Constructability & detailing notes
- Protection systems — dolphins, fenders, islands — are almost always cheaper than sizing the pier for the full impact force.
- The impact acts at the design water level, which changes seasonally; check both the high and low water cases because the lever arm and the pier section both change.
- Detail the pier confinement steel continuously through the impact zone; a shear failure at the impact elevation is non-ductile.
- Coordinate the pier layout with the navigation channel — moving the pier out of the transit envelope reduces the annual frequency of collapse faster than any structural change.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Pier lateral resistance ≥ design impact force (Extreme Event II) | 26634.5 kip | 1400.0 kip | REVIEW |
| Design force ≥ empty-barge drifting minimum | 26634.5 kip | 600 kip | PASS |
| Impact applied at the design water level (§3.14.14) | 14.00 ft above the base | at the design water surface | PASS |
| Annual frequency of collapse ≤ target | 1.0e-4 | 0.0001 critical / 0.001 regular | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Ship-formula sanity — 8.15 V √DWT | 2939 kip | 26634.5 kip | VERIFIED |
Assumptions & basis of design
- Method II probability-based analysis; the design vessel is selected from the AF distribution of the waterway fleet.
- C_H is the hydrodynamic mass coefficient — 1.05 for an underkeel clearance greater than 0.5 draft, up to 1.25 in shallow water.
- Impact force is applied as a static equivalent load in Extreme Event II with γ_CV = 1.00 and all φ = 1.00.
- Pier lateral capacity should be the plastic-mechanism resistance, not the elastic strength, for Extreme Event II.
Provide a protection system — dolphins, a fender, or an island — rather than sizing the pier for the full impact; §3.14.15 explicitly allows the redirected or absorbed force to be used.
Open-channel hydraulics & waterway opening
Manning's equation for the design discharge, normal depth and velocity, the backwater from the constricted opening, freeboard to the low chord and the resulting design high-water elevation.
Solves Manning's equation for normal depth, then reports the Froude number, critical depth, freeboard and pier contraction.
Normal depth y_n
11.070 ft
Velocity V
7.076 ft/s
Froude number
0.413
subcritical
Critical depth y_c
6.404 ft
Freeboard
6.93 ft
Contracted velocity
7.504 ft/s
Derivation — equation, substitution, result
Channel geometry at trial depth
Manning's equation
Mean velocity
Froude number
Critical depth
Freeboard to the low chord
Pier contraction
Approximate backwater
Detailing — plan, elevation and section
Bottom width b = 120 ft, side slopes 3.0:1, normal depth y = 11.07 ft. Low chord 18.0 ft above invert provides 6.9 ft of freeboard over the design water surface; bridge opening = 140 ft.
Constructability & detailing notes
- Keep piers parallel to the flow; even 10° of skew measurably increases both scour and backwater.
- Coordinate the low-chord elevation with the debris and ice regime, not just the water surface.
- Temporary causeways and cofferdams contract the channel further — check the construction-stage hydraulics.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Freeboard ≥ required | 3.00 ft | 6.93 ft | PASS |
| Flow is not near critical (0.9 < Fr < 1.1 is unstable) | 0.413 | < 0.90 or > 1.10 | PASS |
| Velocity ≤ 12 ft/s (channel-stability screening) | 7.076 ft/s | 12.0 ft/s | PASS |
| Opening ratio ≥ 0.90 (limits backwater) | 0.943 | 0.900 | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Continuity check Q = V·A | 12000 cfs | matched by the normal-depth solution | VERIFIED |
Assumptions & basis of design
- Steady uniform flow in a prismatic trapezoidal channel; Manning's n from HDS-6 / FHWA channel tables.
- Backwater is the simple energy difference — a full HEC-RAS bridge routine is required for design submittals.
- Design discharge is normally the 100-yr event, checked against the 500-yr event for scour (HEC-18).
Hydraulics are acceptable; carry y_n and the contracted velocity into the scour module.
Total scour by HEC-18 — contraction, local & degradation
Live-bed or clear-water contraction scour, the CSU pier-scour equation with K₁–K₄, abutment scour, long-term degradation, and the total scour envelope with the required pile tip elevation.
Contraction, pier (CSU) and abutment (HIRE) scour combined into the total scour prism that sets the foundation elevation.
Bed condition
live bed
Contraction scour
2.564 ft
Pier scour
9.600 ft
Abutment scour
13.828 ft
Total at the pier
12.16 ft
Total at the abutment
16.39 ft
Derivation — equation, substitution, result
Critical velocity
Contraction scour (live bed)
Contraction scour (clear water)
Contraction scour depth
Pier-scour correction factors
CSU pier scour
Abutment scour
Total scour
Detailing — plan, elevation and section
Constructability & detailing notes
- Set the pile cut-off or footing bottom below the total scour line plus a 2 ft allowance for prediction uncertainty.
- Detail the pile cap so that exposure by scour does not create a debris catcher or increase the effective pier width.
- Record the as-built streambed elevation; every future scour evaluation is measured from it.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Pier scour ≤ 2.4a limit for Fr ≤ 0.8 (HEC-18) | 12.963 ft | 9.600 ft | REVIEW |
| Foundation extends below the total scour prismSet the footing or pile cut-off at least 14.2 ft below the streambed (total scour + 2 ft). | — | — | PASS |
| Check the 500-yr event as well (Extreme Event II)The check flood governs the foundation elevation on many sites. | — | — | PASS |
| Debris raft considered in the effective pier width aAdd the debris width to a where drift is likely — it often doubles the pier scour. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Pier scour within the 2.4a physical limit | ≤ 2.4 a | 9.600 | CHECK |
Assumptions & basis of design
- HEC-18 (5th ed.) equations: Laursen contraction scour, CSU pier scour, HIRE abutment scour.
- Scour is a load condition, not a load: foundations are checked at Strength and Extreme Event limit states with the scoured profile removed.
- K₃ = 1.1 for plane-bed and antidune flow; use 1.1 – 1.3 for larger dunes.
Found the pier below elevation −12.2 ft relative to the streambed, or provide countermeasures (riprap, articulated block) designed for the contracted velocity.
Riprap and countermeasure design
Isbash / HEC-23 stone sizing from the design velocity, the D₅₀ and gradation, apron thickness and extent, filter requirements and the placement detail around a pier.
HEC-23 pier riprap sizing with the gradation class, apron thickness, plan extent and filter requirement.
D₅₀ required
3.96 in
Riprap class
Class I (D₅₀ = 6 in)
Layer thickness
12.0 in
Plan extent
20.0 ft
Side slope
2.0H:1V
Derivation — equation, substitution, result
Pier riprap size
Gradation class
Layer thickness
Plan extent around the pier
Filter
Detailing — plan, elevation and section
Constructability & detailing notes
- Place riprap in the dry where the schedule allows; underwater placement requires a 50 % thickness increase.
- Never dump riprap from height onto a geotextile — it tears the fabric and the apron fails from below.
- Riprap is a monitored countermeasure, not a permanent fix; write the inspection trigger into the Plan of Action.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Side slope ≤ 2H:1V for stable riprap | 2.0H:1V | 2H:1V or flatter | PASS |
| Filter layer specifiedGeotextile with an apparent opening size compatible with the bed gradation. | — | — | PASS |
| Top of riprap at or below the streambedBurying the apron keeps it from becoming an obstruction and a debris catcher. | — | — | PASS |
| Riprap requires a monitoring plan (HEC-23)Riprap is not a permanent fix for a scour-critical bridge — pair it with inspection. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Selected class meets the computed D₅₀ | 3.96 | Class I (D₅₀ = 6 in) | VERIFIED |
Assumptions & basis of design
- HEC-23 pier riprap guidance; K = 1.5 for rectangular piers and 1.7 for round noses in the alternative Isbash form.
- Specific gravity S_s = 2.65 for typical quarried stone.
- Velocity is the local (contracted) velocity at the pier, not the average channel velocity.
Specify Class I (D₅₀ = 6 in) riprap, 12 in thick, over a geotextile filter, extending 20.0 ft beyond each pier face with the top set flush with the streambed.
Seismic demand, R factors and displacement compatibility
Site class coefficients through the design spectrum, elastic demand, the R-modified design forces for substructure and connections, and the displacement-compatibility and P-Δ checks.
Design spectrum, zone, elastic and inelastic demand, capacity-protection overstrength and the minimum support length.
S_a
0.5000 g
Seismic zone
3
Elastic V_e
2000.0 kip
Design V
666.7 kip
Column M demand
9333 kip·ft
Overstrength shear V_o
514.3 kip
Support length N req.
13.41 in
Derivation — equation, substitution, result
Design response spectrum
Seismic zone
Elastic force
Response modification
Column moment demand
Overstrength (capacity protection)
Minimum support length
Detailing — plan, elevation and section
Constructability & detailing notes
- The plastic-hinge zone needs tight spiral pitch and continuous confinement — do not allow the contractor to open it up for access.
- Cap, joint and foundation are capacity-protected: they are designed for 1.2 M_p, not for the elastic demand divided by R.
- Restrainers and shear keys must be detailed with a defined load path and a stated fuse capacity.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Column M_p ≥ demand | 9333 kip·ft | 6000 kip·ft | REVIEW |
| Seat length N provided ≥ required | 13.41 in | 24.00 in | PASS |
| Cap, joint and foundation designed for V_o / M_o, not for VCapacity protection: the plastic hinge must form in the column, never in the cap or footing. | — | — | PASS |
| Zone 3 – 4 requires full ductile detailing (§5.10.11.4)Provide plastic-hinge confinement, lap-splice exclusion zones and shear designed for V_o. | — | — | REVIEW |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Column capacity exceeds the reduced demand | M_p ≥ M demand | 9333 | CHECK |
| Support length adequate | 13.41 | provided seat | VERIFIED |
Assumptions & basis of design
- Uniform-load method of §4.7.4.3.2c — valid for regular bridges; irregular or long bridges require multimode analysis.
- R factors from Table 3.10.7.1-1 (single columns 3.0, multiple-column bents 5.0), reduced to 1.5 for operational bridges.
- Overstrength factor 1.2 for ASTM A706 reinforcement; use 1.4 for A615.
Increase the column size or longitudinal steel, or accept a lower R by adding redundancy to the bent.
Liquefaction screening & downdrag
Simplified cyclic stress ratio CSR from a_max and r_d, the cyclic resistance ratio from corrected blow counts, the factor of safety with depth, and the downdrag load added to the pile demand.
Simplified SPT-based triggering analysis: CSR from the ground motion, CRR from the corrected blow count, and the factor of safety.
σ′_v
1.566 ksf
CSR
0.3002
(N₁)₆₀cs
16.07
CRR (corrected)
0.2232
FS liquefaction
0.744
Verdict
liquefaction likely
Derivation — equation, substitution, result
Stresses
Stress-reduction coefficient
Cyclic stress ratio
Fines correction
Cyclic resistance ratio at M 7.5
Magnitude and overburden scaling
Factor of safety
Detailing — plan, elevation and section
Constructability & detailing notes
- Where liquefaction is predicted, ground improvement (stone columns, deep soil mixing) is often cheaper than lengthening every pile.
- Instrument the site with piezometers if staged fill is used — excess pore pressure during construction is a real hazard.
- Show the liquefiable layer on the foundation plan so the driving records can confirm it in the field.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| FS ≥ 1.2 (AASHTO screening) | 0.744 | 1.200 | REVIEW |
| (N₁)₆₀cs ≥ 30 — non-liquefiable regardless of CSR | 16.07 | 30 | REVIEW |
| Downdrag and loss of lateral support evaluated for liquefiable layersRemove the layer's p-y resistance and add post-liquefaction downdrag to the pile design. | — | — | REVIEW |
| Lateral spread evaluated where a free face existsUse the Youd–Hansen–Bartlett empirical model, then check the piles for the imposed soil displacement. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Triggering factor of safety | ≥ 1.20 | 0.744 | CHECK |
Assumptions & basis of design
- Simplified NCEER/Youd et al. (2001) SPT-based procedure as referenced by AASHTO §10.5.4.2.
- a_max is the peak ground surface acceleration = F_pga PGA from the design hazard.
- Clean-sand equivalence is applied for fines contents above 5 %; the correction is capped at 5.5 blows.
Design piles to punch through the liquefiable layer into competent material, neglect its side friction, add its post-liquefaction downdrag, and consider ground improvement (stone columns, deep soil mixing).
Chapters 18 – 20
Construction engineering, inspection and rating
Construction-stage combinations, LRFR rating factors and tonnage, deflection and span-depth serviceability, and remaining fatigue life.
Load rating (LRFR)
Inventory and Operating rating factors and rating tonnage for a rating vehicle under the LRFR methodology.
RF = (C − γDC·DC − γDW·DW ± γP·P) / (γLL·(LL+IM)) · RT = RF · W
Inventory RF
1.716
Operating RF
2.288
Inventory rating tonnage
68.6 ton
Operating rating tonnage
91.5 ton
Both Inventory and Operating rating factors exceed 1.0; the rating vehicle is adequately carried.
Inventory RF = 1.716, Operating RF = 2.288. Bars below the RF = 1.0 line indicate posting or restriction is required at that rating level (MBE §6A.4.2.1).
Construction stage, serviceability & remaining fatigue life
Strength I with construction loads, the LRFR inventory and operating rating factors and tonnages, the L/800 deflection and 0.033L depth guidance, and N = A/(Δf)³ fatigue life against the 75-year ADTT cycle count.
Fatigue constant A (×10⁸ ksi³): 250 for A, 120 B, 61 B′, 44 C, 22 D, 11 E, 3.9 E′.
Construction Strength I effect
2625.0
Inventory RF
1.508
Operating RF
1.955
Inventory / Operating rating
54.3 / 70.4 tons
Live-load deflection limit
1.500 in
Predicted fatigue life
55.8 years
Inventory / operating rating: 54.3 / 70.4 tons.
| Step | Equation | Substitution | Result |
|---|---|---|---|
| Construction combination | U = 1.25DC + 1.50DW + 1.50CE | 1.25·1500.0 + 1.50·300.0 + 1.50·200.0 | 2625.0 (k-ft or kip) |
| Rating dead load effect | γ_DC DC + γ_DW DW | 1.25(1500.0 + 300.0) | 2250.0 |
| Inventory rating factor | RF = (C − γ_D D)/(γ_L(LL+IM)) | (7000.0 − 2250.0)/(1.75·1800.0) | 1.508 |
| Operating rating factor | RF = (C − γ_D D)/(1.35(LL+IM)) | (7000.0 − 2250.0)/(1.35·1800.0) | 1.955 |
| Rating tonnage | RT = RF × W_vehicle | 1.508·36.0 ; 1.955·36.0 | Inventory 54.3 t, Operating 70.4 t |
| Live-load deflection limit | Δ ≤ L/800 (L/1000 with pedestrians) | 1200/800 | 1.500 in (provided 1.100 in) |
| Span-to-depth guidance | d ≥ 0.033L (composite) ; 0.027L (steel only) | 0.033·1200 | 39.60 in (provided 54.00 in) |
| Fatigue life | N = A/(Δf)³ | 44.00×10⁸/(6.00)³ | 20.37 million cycles |
| Design cycle count | N_75 = 365(75)n·ADTT_SL | 365·75·1.0·1000 | 27.38 million cycles |
- OKInventory rating factor ≥ 1.0demand 1.000capacity 1.508
- OKOperating rating factor ≥ 1.0demand 1.000capacity 1.955
- OKLive-load deflection ≤ L/800demand 1.100 incapacity 1.500 in
- OKDepth ≥ 0.033Ldemand 54.00 incapacity 39.60 in
- NGFatigue life ≥ 75 yearsdemand 75 yearscapacity 55.8 years
Inventory RF = 1.508 (54.3 tons) and Operating RF = 1.955 (70.4 tons) — the bridge carries legal loads without posting. Deflection 1.100 in vs the 1.500 in limit; minimum recommended depth 39.60 in (steel alone 32.40 in).
Assumptions & code basis
- Construction-stage combination: Strength I with construction loads per §3.4.2.1 — 1.25DC + 1.50DW + 1.50 of the construction load CE, with φ reduced for non-composite girders during deck placement.
- Load rating by LRFR (MBE §6A.4.2): RF = (C − γ_DC DC − γ_DW DW ∓ γ_P P)/(γ_LL (LL+IM)); Inventory γ_LL = 1.75, Operating γ_LL = 1.35.
- Live-load deflection limit L/800 for vehicular bridges and L/1000 where pedestrians are present (§2.5.2.6.2) — optional but almost always enforced by owners.
- Span-to-depth guidance §2.5.2.6.3: 0.033L for composite I-girder overall depth and 0.027L for the steel section alone.
- Fatigue life from the detail-category constant A: N = A/(Δf)³, compared with the 75-year cycle count 365·75·n·ADTT_SL (§6.6.1.2.5).
Falsework and temporary works design
Construction dead, live and equipment loads, the shoring post and stringer demands, the allowable stresses for temporary works, foundation bearing on mudsills and the lateral-stability bracing requirement.
ACI 347 formwork pressure, shore loads on the tributary grid, and the crane pick check for the erection plan.
Form pressure
793 psf
Post load
2.40 kip
Post DCR
0.400
Total pick weight
72.4 kip
Crane DCR
0.659
Picks required
8
Derivation — equation, substitution, result
Formwork lateral pressure
Bounds on pressure
Falsework vertical load
Post load
Post utilisation
Crane pick
Crane utilisation
Detailing — plan, elevation and section
Shore grid at 4.0 ft × 4.0 ft; governing post demand-capacity ratio = 0.40. Peak formwork pressure pmax = 793 psf over the 12.0 ft form height; crane pick at 66 % of chart capacity.
Constructability & detailing notes
- Falsework drawings must be sealed by a licensed engineer and independently checked — the FIU and Quebec collapses were both temporary-condition failures.
- Brace the shoring for 2 % of the vertical load in both directions, and check the wind case on the open frame.
- Survey the falsework before, during and after the pour; unexpected settlement is the first sign of a bearing problem.
- Do not release shoring until cylinder breaks confirm the specified release strength.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Post DCR ≤ 1.0 | 0.400 | 1.000 | PASS |
| Crane at ≤ 75 % of chart capacity | 0.659 | 0.750 | PASS |
| Falsework braced for 2 % of vertical load laterally (ACI 347)Provide diagonal bracing in both directions and check the wind case on the open frame. | — | — | PASS |
| Foundation / mudsill bearing checkedFalsework settlement is a leading cause of construction-stage cracking — survey during placement. | — | — | PASS |
| Independent falsework design check by a licensed engineerRequired by most owners after the FIU and Quebec lessons — never let the erector self-certify. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Shore utilisation | ≤ 1.000 | 0.400 | VERIFIED |
| Crane at or below 75 % of chart | ≤ 0.750 | 0.659 | VERIFIED |
Assumptions & basis of design
- ACI 347R-14 formwork pressures with C_w for unit weight and C_c for cement type/admixtures.
- Construction live load of 20 psf on horizontal surfaces plus 50 psf where motorised buggies operate.
- Crane charts are for level, fully outrigged, 360° operation — derate for on-rubber or partial outrigger picks.
Falsework and pick are within limits; require a pre-pour inspection and monitor deflection during placement.
Segmental erection — unbalanced moment and stability
Cantilever moments during balanced-cantilever erection, the unbalanced segment plus travelling-form case, wind uplift, the temporary post-tensioning bar demand and the pier stability check.
Balanced-cantilever erection: unbalanced segment, form traveler, construction live load and wind on the pier segment.
Cantilever length
128.0 ft
Unbalanced M (segment)
14400 kip·ft
Traveler M
11040 kip·ft
Wind M
1966 kip·ft
Factored M_u
34404 kip·ft
Pier DCR
0.860
Balanced baseline
0 kip·ft
perfectly balanced erection produces no net pier moment
Derivation — equation, substitution, result
Cantilever geometry
Unbalanced segment moment
Form traveler
Construction live load
Wind on the cantilever
Factored construction combination
Cantilever tendon couple
Pier utilisation
Detailing — plan, elevation and section
8 segments each side at 16.0 ft; form traveler cantilevers 10.0 ft beyond the tip. Pier moment demand-capacity ratio under the unbalanced case = 0.86.
Constructability & detailing notes
- The erection sequence is a contract document: casting order, maximum out-of-balance and tendon stressing stages must all be shown.
- Temporary PT bars or a falsework tower at the pier are normally required to carry the unbalanced case.
- Survey the cantilever tip elevation after every segment; geometry control errors accumulate and cannot be fixed at closure.
- Never stress a tendon before the concrete reaches the specified release strength — verify with match-cured cylinders.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Pier moment capacity ≥ M_u | 34404 kip·ft | 40000 kip·ft | PASS |
| Temporary supports or stressed bars provided at the pier segmentMost balanced-cantilever bridges need temporary towers or PT bars to resist the unbalanced case. | — | — | PASS |
| One-segment-out-of-balance assumption stated on the plansThe erection sequence must be a contract document, not a contractor option. | — | — | PASS |
| Wind-on-traveler case checked with the traveler at the tip | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Pier capacity exceeds the factored erection moment | DCR ≤ 1.000 | 0.860 | VERIFIED |
Assumptions & basis of design
- AASHTO LRFD §5.14.2 construction load cases: distributed CLL of 0.010 ksf and a concentrated CLL of 20 kip at the cantilever tip are typical.
- Load factors for construction: 1.1 on dead load and equipment, 1.5 on construction live load, 1.25 on construction wind.
- Segment weights include the wet concrete of the segment being cast plus the form traveler self-weight.
The pier can carry the erection case; publish the segment casting order and the maximum permitted out-of-balance condition on the plans.
Inspection, condition rating & deterioration modelling
NBI condition ratings converted to section-loss estimates, the reduced section properties, the remaining capacity ratio and the projected time to the intervention threshold.
Element-level condition states rolled into a health index, with NBI classification, inspection interval and the scour appraisal.
Deck HI
89.2
Superstructure HI
89.6
Substructure HI
82.5
Bridge health index
87.3
NBI classification
Fair
Inspection status
current
Annual detour cost
$23.65 M
Lanes carried
4
Derivation — equation, substitution, result
Element health index
Weighted bridge health index
NBI condition classification
Inspection interval
Scour appraisal
Detour user cost
Detailing — plan, elevation and section
Each bar shows the proportion of element quantity in condition states 1 (good) through 4 (severe) for the deck, superstructure and substructure. Composite health index = 87.3 / 100.
Constructability & detailing notes
- Photograph and station every CS3/CS4 quantity — the next inspector needs to know whether the defect grew.
- Element quantities must sum to the total element quantity in every inspection cycle; a mismatch invalidates the health index trend.
- Access equipment (snooper, rope, UAV) should be planned from the previous cycle's findings, not decided on site.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Routine inspection within the allowable interval | 20 months | 24 months | PASS |
| Fracture-critical members inspected hands-on at ≤ 24 months | — | — | PASS |
| Scour appraisal ≥ 4 | 5 | ≥ 4 | PASS |
| Health index ≥ 70 for a well-performing asset | 87.3 | 70.0 | PASS |
| Interval 24 months documented in the inspection program | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Inspection interval compliance | within the allowable interval | current | VERIFIED |
Assumptions & basis of design
- AASHTO Manual for Bridge Element Inspection condition states CS1 (good) through CS4 (severe).
- Health-index weights are the common FHWA/AASHTOWare convention; agencies may use their own weighting.
- NBI ratings 0–9 per the FHWA Recording and Coding Guide; item 113 codes the scour appraisal.
Condition is acceptable; continue routine inspection and use the health index to prioritise preservation funding.
LRFR rating — design, legal and permit vehicles
General rating equation with condition, system and φ factors, the Design (Inventory/Operating), Legal and Permit rating factors, posting load determination and rating tonnage.
LRFR rating factor with condition and system factors, the rating in tons, permit screening and the posting load.
φ_c φ_s
0.950
Adjusted capacity
5700 kip·ft
Rating factor RF
0.880
Rating (tons)
31.67 tons
Level
Inventory (γ = 1.75)
Posting
not required
Derivation — equation, substitution, result
Condition and system factors
Adjusted capacity
Rating factor
Rating in tons
Posting
Permit screening
Detailing — plan, elevation and section
Rating factor RF = 0.88 corresponds to a rating load of 31.7 tons. Posting required at 0.0 tons. Permit vehicle screening: does not pass — route or escort restriction required.
Constructability & detailing notes
- Field-measure the wearing surface thickness: γ_DW drops from 1.50 to 1.25 when the thickness is measured rather than assumed.
- Document the controlling member, section and limit state — the rating is only meaningful with that context.
- Re-rate after every rehabilitation, deck overlay or change in section loss.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| RF ≥ 1.0 | 0.880 | 1.000 | REVIEW |
| Permit vehicle within the operating rating | 80.0 tons | 31.67 tons | REVIEW |
| Posting required when the Operating RF < 1.0 | — | — | PASS |
| Consider a refined analysis or load test before postingRefined distribution factors and measured section properties often lift RF above 1.0. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Rating factor at or above 1.0 | ≥ 1.000 | 0.880 | CHECK |
Assumptions & basis of design
- AASHTO Manual for Bridge Evaluation, LRFR method, Strength I; γ_DC = 1.25, γ_DW = 1.50 (1.25 with a field-measured thickness).
- Live-load effect includes the appropriate distribution factor and dynamic allowance (IM = 33 %, or 10 % for fatigue).
- Legal-load ratings use γ_LL from Table 6A.4.4.2.3a-1 as a function of ADTT.
RF = 0.88 controls. Before posting, refine the analysis (measured deck thickness, actual distribution, composite action), then consider strengthening with FRP or external post-tensioning.
Strengthening and rehabilitation design
Capacity deficit from the rating, external post-tensioning force, FRP laminate area with the ACI 440 strain limit, added-plate composite action, and the restored rating factor after strengthening.
Closes a rating deficit with bonded FRP (ACI 440.2R) or external post-tensioning, including the unstrengthened-capacity safety net.
Deficit ΔM
500 kip·ft
Method
Bonded FRP (ACI 440.2R)
FRP area A_f
2.400 in²
f_fe
79.5 ksi
Capacity gain
549 kip·ft
φM_n upgraded
3194 kip·ft
Derivation — equation, substitution, result
Strength deficit
Environmental reduction
Existing substrate strain
Debonding strain
Effective FRP stress
FRP moment contribution
External PT contribution
Upgraded capacity
Service stress relief (PT)
Detailing — plan, elevation and section
3 plies of FRP laminate, 20.0 in wide, bonded to the soffit of a 24 in × 44 in section (d = 40 in) to close the rating deficit.
Constructability & detailing notes
- Surface preparation controls FRP performance: blast to a CSP 3 profile, round all corners to 1/2 in radius, and check the pull-off strength.
- Do not install FRP below 50 °F or on damp concrete; document ambient conditions during installation.
- External tendons need corrosion-protected anchorages, grouted HDPE ducts, and deviators designed for the tendon deviation force.
- Fire protection is required for FRP on structures where a vehicle fire is credible.
| Check | Demand | Capacity / limit | Status |
|---|---|---|---|
| Upgraded φM_n ≥ M_u | 3200 kip·ft | 3194 kip·ft | REVIEW |
| Unstrengthened section carries the unfactored DL + LL (ACI 440.2R §9.2)The member must survive loss of the FRP (fire, vandalism, impact). | 900 kip·ft | 2700 kip·ft | PASS |
| FRP strain governed by debonding, not ruptureAdd U-wrap anchorage at the ends if the debonding strain governs. | — | — | PASS |
| Corrosion and section loss addressed before strengtheningNever bond FRP over actively corroding steel — repair and passivate first. | — | — | PASS |
| External tendons protected and deviator blocks designedProvide HDPE ducts with grout and design the deviators for the tendon deviation force. | — | — | PASS |
| Independent verification | Expected | Computed | Status |
|---|---|---|---|
| Upgraded capacity meets the demand | φM_n ≥ M_u | 3194 | CHECK |
| Unstrengthened section carries the dead load alone | φM_n,existing ≥ M_DL | 549 | VERIFIED |
Assumptions & basis of design
- ACI 440.2R-17 for externally bonded FRP with ψ_f = 0.85 and an environmental reduction factor C_E for exposure.
- External post-tensioning losses of 15 – 20 % are typical for unbonded strand with anchorage set.
- Secondary (parasitic) moments from external PT in continuous spans must be included in the demand.
Specify 3 plies × 20.0 in wide FRP; add U-wrap anchors at both ends and verify the substrate tensile pull-off strength ≥ 200 psi.
Building design suite
Steel — AISC 360-22 (LRFD)
Element classification through connections and stability: every module carries the design all the way to a member size, plate thickness, bolt count or weld size, with the governing limit state named and explicit redesign guidance when a check fails.
Element slenderness & classification
Flange and web λ against λ_p and λ_r for flexure or axial compression, with the plate thicknesses needed to reach a compact section.
λ_f = b_f/2t_f · λ_w = h/t_w · compact if λ ≤ λ_p, slender if λ > λ_r
Flange bf/2tf element is noncompact; web h/tw element is compact. Governing section classification: noncompact. AISC 360-22 Table B4.1.
Flange λ
9.38
λ_p = 9.15, λ_r = 24.08
Web λ
50.63
λ_p = 90.55, λ_r = 137.27
Section
noncompact
Classification — AISC 360-22 §B4
| Flange | noncompact |
| Web | compact |
| Governing | noncompact |
PASS — Non-compact: interpolate between M_p and 0.7F_yS_x. To make it compact use t_f ≥ 0.656 in and t_w ≥ 0.221 in.
Tension members
Gross yielding, net-section rupture with shear lag, and block shear — the governing limit state and the area needed to satisfy the demand.
Block shear
φP_n = 0.90F_yA_g · φP_n = 0.75F_uA_e · φR_n = 0.75[min(0.6F_uA_nv, 0.6F_yA_gv) + U_bsF_uA_nt]
A_n
4.063 in²
A_e = U·A_n
3.453 in²
Yielding
225 kip
Rupture
168 kip
Block shear
190 kip
Design strength
168 kip
Net-section rupture (D2-2)
Ag = 5.00 in², 2 holes @ 0.9375 in in a 0.500 in ply → An = 4.063 in². Governing limit state: Net-section rupture (D2-2). φPn = 168.3 kip vs Pu = 180 kip.
Tension member design — AISC 360-22 §D2 / §D3 / §J4.3
| Demand P_u | 180 kip |
| Design strength φP_n | 168.3 kip |
| Governing limit state | Net-section rupture (D2-2) |
| Utilization | 1.07 |
REDESIGN — Increase A_e to ≥ 3.69 in² — add a connection length (raises U) or use fewer/smaller holes.
Compression members
Flexural buckling with the inelastic/elastic transition at 4.71√(E/F_y), slender-element Q factor, and the area or bracing needed if the column is short of capacity.
F_e = π²E/(KL/r)² · F_cr = 0.658^(F_y/F_e)·F_y if KL/r ≤ 4.71√(E/F_y), else 0.877F_e
KL/r
66.9
limit 113.4
F_e
63.89 ksi
F_cr
36.03 ksi
inelastic
φ_cP_n
477 kip
KL/r = 66.9 (inelastic buckling), Fcr = 36.03 ksi, φcPn = 477 kip vs Pu = 400 kip. K = 1.00, L = 14.0 ft.
Compression design — AISC 360-22 §E3
| P_u | 400 kip |
| φ_cP_n | 476.7 kip |
| Utilization | 0.84 |
PASS — Adequate — KL/r = 67 (inelastic buckling), utilization 0.84.
Flexural members — LTB zones
M_p, L_p and L_r, the three lateral–torsional-buckling zones, and the bracing spacing or Z_x required to develop the demand.
Zone 1: M_n = M_p · Zone 2: linear C_b interpolation · Zone 3: M_n = F_crS_x
M_p
608 k-ft
L_p
8.76 ft
L_r
25.36 ft
LTB zone
2 — inelastic LTB
M_n
608 k-ft
φ_bM_n
548 k-ft
Lp = 8.76 ft, Lr = 25.36 ft; design point at Lb = 12.0 ft falls in zone 2 — inelastic LTB. Mn = 608 k-ft, φMn = 548 k-ft vs Mu = 400 k-ft.
Flexural design — AISC 360-22 §F2
| M_u | 400 k-ft |
| φ_bM_n | 548 k-ft |
| Zone | 2 — inelastic LTB |
| Utilization | 0.73 |
PASS — Adequate in zone 2 — inelastic LTB — utilization 0.73.
Shear & web buckling
Web shear with k_v, the C_v1 buckling ratio, and the web thickness or stiffener spacing needed when the web governs.
V_n = 0.6F_yA_wC_v1 · C_v1 = 1.0 if h/t_w ≤ 1.10√(k_vE/F_y)
A_w
8.295 in²
k_v
5.340
h/t_w
46.3
limits 61.2 / 76.2
C_v1
1.000
web yielding (no buckling)
φ_v
1.00
φ_vV_n
249 kip
Web tw = 0.395 in, clear depth h = 18.30 in, kv = 5.340 (unstiffened). φvVn = 249 kip vs Vu = 120 kip.
Shear & web buckling — AISC 360-22 §G2.1
| V_u | 120 kip |
| φ_vV_n | 248.8 kip |
| Buckling mode | web yielding (no buckling) |
| Utilization | 0.48 |
PASS — Adequate — C_v1 = 1.000 (web yielding (no buckling)), utilization 0.48.
Combined forces — beam-columns
H1-1a / H1-1b interaction of axial force with biaxial bending, and the size increase implied by an over-unity ratio.
H1-1a (P_r/P_c ≥ 0.2): P_r/P_c + 8/9(M_rx/M_cx + M_ry/M_cy) ≤ 1.0 · H1-1b otherwise
P_r/P_c
0.357
Equation
H1-1a
Interaction
0.905
Governing equation H1-1a: interaction value = 0.905 (limit 1.0). Pr/Pc = 0.357, Mrx/Mcx = 0.450.
Beam-column interaction — AISC 360-22 §H1.1
| Axial term | 0.357 |
| Flexural terms | 0.450 + 0.167 |
| Total | 0.905 |
PASS — Interaction H1-1a = 0.905 ≤ 1.0 — beam-column adequate.
Bolted connections
Bolt shear, bearing and tearout, slip resistance and combined tension–shear, returning the bolt count, spacing and edge distances to detail.
φR_n = 0.75F_nvA_b (shear) · min(1.2l_ctF_u, 2.4d_btF_u) (bearing/tearout) · μD_uh_fT_bn_s (slip)
Bolt shear
146 kip
Bearing / tearout
197 kip
Design strength
146 kip
Bolt shear (J3-1)
Bolts required
8
provided 6
6 — 0.875 in bolts, ply t = 0.500 in, clear distance lc = 1.125 in. Governing limit state: Bolt shear (J3-1). φRn = 146.1 kip vs Pu = 180 kip. Min spacing 2.33 in (use 2.63 in), min edge 1.09 in.
Bolt group design — AISC 360-22 §J3
| Demand | 180 kip |
| Design strength | 146.1 kip |
| Governing | Bolt shear (J3-1) |
| Layout | s ≥ 2.33 in (use 2.63 in), L_e ≥ 1.09 in |
REDESIGN — Provide 8 bolts (currently 6) or increase the ply thickness to 0.616 in — bolt shear (j3-1) controls.
Fillet welds
Directional-strength weld metal capacity against base-metal rupture, with the minimum and maximum leg sizes and the length required per side.
φR_n = 0.75(0.60F_EXX)(0.707w)L(1.0 + 0.50sin^1.5θ)
t_e
0.1767 in
k_ds
1.000
Weld metal
89 kip
Base metal
234 kip
Design strength
89 kip
Weld metal shear (J2-4)
L required / side
8.08 in
Weld leg w = 0.2500 in, effective throat te = 0.1767 in, length L = 8.00 in per side × 2 side(s), load angle θ = 0°. Governing: Weld metal shear (J2-4). φRn = 89.1 kip vs Pu = 90 kip.
Fillet weld design — AISC 360-22 §J2.4
| Demand | 90 kip |
| Design strength | 89.1 kip |
| Governing | Weld metal shear (J2-4) |
| Size limits | 0.1875 – 0.4375 in |
REDESIGN — Increase the weld length to 8.1 in per side, or the leg to 0.253 in (≤ 0.438 in max for a 0.500 in ply).
Base plates & anchor rods
Concrete bearing with the √(A₂/A₁) confinement factor, the cantilever plate thickness, eccentricity classification, and anchor-rod steel and breakout strength.
φP_p = 0.65(0.85f′_cA₁)√(A₂/A₁) · t_req = l√(2P_u/0.9F_yBN)
A₁ provided
400 in²
required 113 in²
φP_p
1768 kip
l (cantilever)
4.20 in
m=3.35, n=4.20, λn′=3.56
t required
1.1875 in
φN_sa
58 kip
φV_sa
30 kip
Plate 20.0 × 20.0 × 1.1875 in with 4 — 0.750 in anchor rods. φPp = 1768 kip vs Pu = 500 kip.
Base plate & anchor rods — AISC §J8 + ACI 318-19 Ch.17
| Note 1 | Concrete bearing OK: φP_p = 1768 kip ≥ P_u (A₁ = 400 in², required 113 in²). |
| Note 2 | Use a plate thickness of 1.1875 in (t_req = 1.167 in from the cantilever l = 4.20 in). |
| Note 3 | e = 0.0 in ≤ N/6 — full bearing, anchor rods nominal. |
| Note 4 | Anchor rods: φN_sa = 58 kip, φV_sa = 30 kip, concrete breakout φN_cb ≈ 177 kip at h_ef = 12 in. |
REDESIGN — Specify a 20.0 × 20.0 × 1.1875 in plate with 4 – 0.750 in anchor rods, h_ef = 12.0 in.
Shear (simple) connection — shear tab
All six single-plate limit states — bolt shear, bearing/tearout, plate shear yield and rupture, block shear and the weld — with the governing one named.
Governing = min(bolt shear, bearing/tearout, plate shear yield, plate shear rupture, block shear, weld)
Bolt shear (J3-1)
72 kip
Plate bearing/tearout (J3-6)
117 kip
Plate shear yielding (J4-3)
97 kip
Plate shear rupture (J4-4)
86 kip
Block shear (J4-5)
82 kip
Weld to support (J2-4)
134 kip
4 bolts @ 3.00 in, edge distances Lev = 1.50 in, Leh = 1.50 in, plate tp = 0.375 in, weld leg 0.2500 in. Governing: Bolt shear (J3-1). φRn = 71.6 kip vs Vu = 70 kip.
Single-plate shear connection — AISC 360-22 §J3/J4 + Manual Part 10
| Plate | PL 0.3750 × 4.5 × 12.0 |
| Design strength | 71.6 kip |
| Governing | Bolt shear (J3-1) |
| Utilization | 0.98 |
PASS — Adequate — bolt shear (j3-1) governs at 0.98 utilization. Recommended weld: two-sided 0.234 in fillet (⅝ t_p rule).
Moment connection & column checks
Flange-couple force with the §J10 column-side checks that decide whether continuity plates and a web doubler are required.
P_uf = M_u/(d − t_f) · J10 checks decide whether continuity plates and a doubler plate are needed
P_uf
192 kip
Web local yielding
301 kip
Web crippling
397 kip
Flange local bending
276 kip
Flange rupture
321 kip
Panel zone
240 kip
Flange force Puf = Mu/(d − tf) = 192 kip. Governing column check: Column flange local bending (J10-1) = 276 kip. Continuity plates not required.
Moment connection & column checks — AISC 360-22 §J10
| Flange force P_uf | 192.0 kip |
| Governing column limit | Column flange local bending (J10-1) — 276 kip |
| Continuity plates | not required |
| Panel zone | Panel zone adequate (φR_v = 240 kip). |
PASS — No continuity plates required: all J10 column limit states exceed P_uf = 192 kip.
Composite beam with steel deck
Plastic composite flexure with the concrete, steel and stud forces, the degree of composite action, and the stud count for full composite behaviour.
C = min(0.85f′_cb_eff(t−h_r), A_sF_y, ΣQ_n) · a = C/0.85f′_cb_eff · φM_n = 0.90C(d/2 + Y₂)
C_concrete
1071 kip
T_steel
665 kip
ΣQ_n
688 kip
a
2.173 in
Composite action
100%
φM_n
662 k-ft
Effective width beff = 90 in, slab t = 5.50 in (rib hr = 2.0 in), degree of composite action = 100% with 40 studs. Stress-block depth a = 2.173 in, C = 665 kip. φMn = 662 k-ft vs Mu = 700 k-ft.
Composite beam with steel deck — AISC 360-22 §I3
| M_u | 700 k-ft |
| φM_n | 662 k-ft |
| Studs provided / required | 40 / 78 |
| Utilization | 1.06 |
REDESIGN — φM_n = 662 k-ft < M_u. Increase the stud count to 78 for full composite action, or use a heavier beam (A_s ≈ 14.1 in²).
Stability bracing — strength & stiffness
Nodal and relative bracing for columns and beams: both the required brace force and the required brace stiffness, plus the brace area that delivers it.
Strength AND stiffness both required — a strong but flexible brace does not stabilize the member.
Required brace strength P_br
3.00 kip
Required brace stiffness β_br
26.7 kip/in
Brace spacing Lbr = 10.0 ft. Required brace strength Pbr = 3.00 kip; required stiffness βbr = 26.7 kip/in. Nodal (point) bracing restrains a single cross-section.
Stability bracing — AISC 360-22 Appendix 6
| Case | Nodal column bracing, A-6-3/A-6-4 (conservative N_i = 4). |
| P_br | 3.00 kip |
| β_br | 26.7 kip/in |
Provide a brace with strength ≥ 3.0 kip AND stiffness ≥ 27 kip/in. A single-angle brace of length L and area A gives β = AE/L — required A ≈ 0.11 in² for a brace 10.0 ft long. Strength alone is not sufficient; both criteria must be met.
Stability — second-order B1 / B2
Amplified first-order analysis: the P-δ and P-Δ multipliers, the amplified moments and axial loads, and the drift limit that keeps B₂ acceptable.
B₁ = C_m/(1 − αP_r/P_e1) · B₂ = 1/(1 − αΣP/ΣP_e,story) · M_r = B₁M_nt + B₂M_lt
B₁
1.000
B₂
1.286
M_r
351 k-ft
P_r
264 kip
B1 = 1.000 amplifies the no-translation moment Mnt = 120 k-ft; B2 = 1.286 amplifies the lateral-translation moment Mlt = 180 k-ft. Combined required moment Mr = B1Mnt + B2Mlt = 351 k-ft.
Second-order amplification — AISC 360-22 Appendix 8
| B₁ | 1.000 |
| B₂ | 1.286 |
| Amplified M_r | 351 k-ft |
| Amplified P_r | 264 kip |
PASS — B₁ = 1.000, B₂ = 1.286 — amplified demands M_r = 351 k-ft, P_r = 264 kip.
Fatigue — stress range & life
Detail-category allowable stress range, threshold for infinite life, and the predicted number of cycles with the detail upgrade needed when the life is short.
F_SR = (C_f/n_SR)^(1/3) ≥ F_TH · life N = C_f/f_sr³
C_f
4.40e+9
F_TH
10.0 ksi
F_SR
10.00 ksi
Predicted life
5.13 M cycles
Infinite life?
yes
Constant-amplitude fatigue threshold FTH = 10.0 ksi; allowable range at nSR= 20.0M cycles is FSR = 10.00 ksi. Applied fsr = 9.50 ksi gives predicted life N = 5.13M cycles.
Fatigue — AISC 360-22 Appendix 3
| f_sr | 9.50 ksi |
| F_SR allowable | 10.00 ksi |
| Life | 5.13 M cycles |
PASS — f_sr = 9.50 ksi ≤ F_TH = 10 ksi — infinite life for Category C.
Deflection & serviceability
Live and total deflections against L/360 and L/240, camber, and the moment of inertia required when serviceability governs the beam size.
Δ = 5wL⁴/384EI
Δ_D
0.425 in
Δ_L
0.567 in
allow 1.000 in
Δ_total
0.992 in
allow 1.500 in
ΔD = 0.425 in, ΔL = 0.567 in (limit 1.000 in), Δtotal = 0.992 in (limit 1.500 in), camber = 0.00 in, span L = 30.0 ft.
Serviceability — AISC DG3 / IBC 1604.3
| Δ_live / limit | 0.567 / 1.000 in |
| Δ_total / limit | 0.992 / 1.500 in |
| I required | 880 in⁴ |
PASS — Δ_LL = 0.567 in ≤ L/360 = 1.000 in and Δ_total = 0.992 in ≤ L/240.
Building design suite
Concrete — ACI 318-19
Beams, columns, slabs and detailing — each module runs the full cycle: A_s,req → bar size, count and spacing → A_s,prov → capacity re-check → crack control, ductility and serviceability, with the redesign step spelled out when a limit is violated.
Beam flexure & crack control
Required and minimum steel, bar selection, φ from the net tensile strain, the re-checked φM_n, §24.3.2 bar spacing for crack control, skin steel, and a dimensioned section drawing.
a = A_sf_y/0.85f′_cb · ε_t = 0.003(d−c)/c · φM_n = φA_sf_y(d − a/2) · s ≤ 15(40/f_s) − 2.5c_c
A_s,req
2.793 in²
A_s,min
1.440 in²
A_s,prov
3.000 in²
3 – #9
a / c
3.31 / 3.89 in
ε_t
0.01781
φ = 0.900
φM_n
342.2 k-ft
Flexural reinforcement design & crack control — ACI 318-19 §9.5 / §9.6.1 / §24.3.2
| A_s design (governing) | 2.793 in² |
| Bar call-out | 3 – #9 |
| A_s provided | 3.000 in² |
| Bar spacing provided / max | 5.31 / 10.00 in |
| φM_n | 342.2 k-ft |
| ρ | 0.0069 |
PASS — Adequate: 3–#9, A_s,prov/A_s,req = 1.07, ε_t = 0.0178 (tension-controlled), spacing 5.3 in ≤ 10.0 in.
3 #9 bars (3.00 in² provided against As = 3.00 in² assumed), 1 row, 2 in clear cover, #4 stirrups. Whitney block a = 3.31 in, c = 3.89 in, fy = 60 ksi. φMn = 342 k-ft vs Mu = 320 k-ft (AASHTO 5.6.3.2).
Beam shear & stirrup design
V_c from Table 22.5.5.1, required V_s, the crushing limit, and a full stirrup schedule (size, legs, spacing, s_max) for every candidate bar.
V_c = 2λ√f′_c b_wd · V_s = A_vf_ytd/s · φ(V_c + V_s) ≥ V_u · V_s ≤ 8√f′_c b_wd
V_c
50.0 kip
φV_c/2
18.8 kip
stirrups required
V_s required
70.0 kip
Schedule
#3 2-leg stirrups @ 5.0 in c/c
s_max
13.5 in
φV_n
91.0 kip
Stirrup design schedule — ACI 318-19 §22.5 / §9.6.3 / §9.7.6
| #3 2-leg (A_v = 0.22 in²) | s = 5.0 in (strength 5.1, min-A_v 264.0, max 13.5) → φV_n = 91 kip |
| #4 2-leg (A_v = 0.40 in²) | s = 9.0 in (strength 9.3, min-A_v 480.0, max 13.5) → φV_n = 92 kip |
| #5 2-leg (A_v = 0.62 in²) | s = 13.5 in (strength 14.4, min-A_v 744.0, max 13.5) → φV_n = 93 kip |
| #6 2-leg (A_v = 0.88 in²) | s = 13.5 in (strength 20.4, min-A_v 1056.0, max 13.5) → φV_n = 117 kip |
PASS — #3 2-leg stirrups @ 5.0 in gives φV_n = 91 kip ≥ V_u = 90 kip (s_max = 13.5 in, minimum-A_v spacing 264.0 in).
2-leg #3 stirrups @ 5.0 in near the supports (Vc = 50.0 kip, φVn = 91.0 kip vs Vu = 90 kip), opening to the code maximum smax = 13.5 in toward midspan per ACI 318-19 §9.7.6.2.2.
Column axial capacity
P_o with the 0.80/0.85 cap, ρ limits of 1–8 %, the required A_st, and a bar-and-tie (or spiral) schedule.
P_o = 0.85f′_c(A_g − A_st) + f_yA_st · φP_n,max = φ·0.80·P_o
A_g
400 in²
ρ
2.00%
P_o
2146 kip
φP_n(max)
1116 kip
A_st required
10.90 in²
Column reinforcement & confinement — ACI 318-19 §22.4 / §10.6 / §25.7
| A_st required | 10.90 in² |
| Bar schedule | 14 – #8 vertical bars with #4 ties @ 16 in c/c (§25.7.2) |
| φP_n(max) | 1116 kip |
| Utilization | 1.08 |
REDESIGN — φP_n = 1116 kip < P_u — required A_st ≈ 10.90 in², or enlarge A_g to 430 in².
14 — #8 longitudinal bars around a 20 × 20 in section, #4 ties @ 16.0 in o.c. per ACI 318-19 §25.7.2 (tie spacing ≤ min(16db, 48dtie, least dimension)). φPn = 1116 kip vs Pu = 1200 kip.
Slender column moment magnification
Slenderness screening, EI_eff, the critical load P_c, the δ_ns magnifier and the design moment M_c with the minimum-eccentricity check.
δ_ns = C_m/(1 − P_u/0.75P_c) · P_c = π²EI/(kl_u)² · M_c = δ_nsM₂
kl_u/r
35.6
limit 28.0
P_c
2386 kip
C_m
0.800
δ_ns
1.110
M_c
133.2 k-ft
M₂,min
47.5 k-ft
Slenderness & moment magnification — ACI 318-19 §6.6.4
| Slender? | yes — magnify |
| δ_ns | 1.110 |
| Design moment M_c | 133.2 k-ft |
PASS — Slender: δ_ns = 1.110 → design moment M_c = 133 k-ft (min. eccentricity moment 48 k-ft).
k·lu = 1.00 × 16.0 ft. Primary end moments M₁ = 60 k-ft, M₂ = 120 k-ft magnified by δns = 1.110 to the design moment Mc = 133.2 k-ft — the member is slender and moments must be magnified (ACI 318-19 §6.6.4).
Column P–M interaction diagram
Strain-compatibility sweep of the neutral axis producing the nominal and φ-reduced interaction curves, with the demand point plotted and the available φM_n at that axial load.
Strain compatibility sweep of the neutral axis c → (P_n, M_n) → φ(ε_t)-reduced design curve
P_o
2392 kip
φP_n,max
1244 kip
φM_n at P_u
504 k-ft
P–M interaction — ACI 318-19 §22.2 / Table 21.2.2
| Demand | (600 kip, 400 k-ft) |
| φM_n at that axial load | 504 k-ft |
| Utilization | 0.79 |
PASS — At P_u = 600 kip the φ-curve allows φM_n = 504 k-ft ≥ M_u = 400 k-ft (utilization 0.79).
Nominal (Pn, Mn) curve and φ-reduced design curve from the ACI 318-19 §22.2 strain-compatibility sweep. Demand point (Mu = 400 k-ft, Pu = 600 kip) plots inside the design envelope — φMn at this Pu = 504 k-ft.
Development length & lap splices
Straight, hooked and compression development lengths with the confinement term, plus Class A / Class B lap lengths and staggering guidance.
ℓ_d = (3/40)(f_y/λ√f′_c)·(ψ_tψ_eψ_s)/[(c_b+K_tr)/d_b]·d_b
(c_b+K_tr)/d_b
2.000
capped at 2.5
ℓ_d tension
35.58 in
ℓ_dh hook
17.25 in
ℓ_dc compression
18.97 in
Lap splice
46.25 in
Development & splice schedule — ACI 318-19 §25.4 / §25.5
| Straight tension ℓ_d | 35.58 in (36 d_b) |
| Standard hook ℓ_dh | 17.25 in |
| Compression ℓ_dc | 18.97 in |
| Class B lap | 46.25 in |
Straight tension development ℓ_d = 35.6 in (confinement term (c_b+K_tr)/d_b = 2.00, capped at 2.5). Standard hook ℓ_dh = 17.2 in. Compression ℓ_dc = 19.0 in. Class B lap splice = 46.2 in — stagger splices out of the maximum-moment region (§25.5).
#8 (db = 1.000 in): straight tension development ℓd = 35.6 in, standard 90° hook ℓdh = 17.2 in, Class B lap splice ℓst = 46.2 in (ACI 318-19 §25.4 / §25.5).
Deflection — immediate & long term
Cracked and effective moments of inertia, immediate dead and live deflections, and the λ_Δ long-term multiplier against L/360 and L/240.
I_e (§24.2.3.5) · Δ = 5wL⁴/384E_cI_e · λ_Δ = ξ/(1 + 50ρ′)
E_c
3644 ksi
M_cr
96.0 k-ft
M_a = 205.8 k-ft
I_e
31331 in⁴
I_g = 36000, I_cr = 14169
Δ_live
0.109 in
allow 0.933 in
λ_Δ
2.000
Δ_LT + live
0.465 in
allow 1.400 in
Immediate & long-term deflection — ACI 318-19 §24.2
| Δ dead (immediate) | 0.145 in |
| Δ live (immediate) | 0.109 in |
| Δ long-term | 0.356 in |
| Δ total | 0.610 in |
PASS — Δ_LL = 0.109 in ≤ L/360 = 0.933 in; long-term + live = 0.465 in ≤ L/240 = 1.400 in.
Span L = 28.0 ft. Immediate live deflection Δlive = 0.109 in (limit L/360 = 0.933 in); long-term + live Δ = 0.465 in (limit L/240 = 1.400 in). Shape exaggerated for clarity.
One-way slab
Minimum thickness, factored strip moments, bottom and top bar selection at spacing, shrinkage-and-temperature steel and the one-way shear check.
w_u = 1.2D + 1.6L · M = w_uL²/coef · A_s,min = 0.0018A_g · s ≤ min(3h, 18 in)
h_min
6.00 in
w_u
0.301 kip/ft/ft
M⁺
4.21 k-ft/ft
Bottom steel
#4@15.5"
Top steel
#4@15.5"
S&T steel
#4@15.5"
One-way slab reinforcement — ACI 318-19 §7 / §24.4
| Note 1 | h = 7 in ≥ h_min = 6.00 in (Table 7.3.1.1) — deflection check by computation not required. |
| Note 2 | Main steel: #4 @ 15.5 in c/c bottom, #4 @ 15.5 in c/c top at supports. |
| Note 3 | Shrinkage & temperature steel: #4 @ 15.5 in c/c (A_s = 0.0018A_g = 0.151 in²/ft, §24.4.3.2). |
| Note 4 | One-way shear OK: φV_c = 6.8 kip/ft ≥ V_u = 2.0 kip/ft. |
REDESIGN — Design strip 12 in wide, d = 6.00 in.
7.00 in slab, both-ends span L = 14.0 ft. Bottom steel #4 @ 15.5 in, top steel at supports #4 @ 15.5 in. Shrinkage & temperature steel #4 @ 15.5 in transverse (ACI 318-19 §7.6.1 / §24.4).
Two-way slab (DDM) & punching shear
Total static moment M_o, column- and middle-strip distribution with bar schedules for each strip, and the two-way punching-shear check with β and α_s terms.
M_o = q_u l₂ l_n²/8 · v_c = min(4, 2 + 4/β, 2 + α_sd/b_o)λ√f′_c · φV_c = 0.75v_cb_od
q_u
0.310 ksf
M_o
238.7 k-ft
M⁻ / M⁺
155 / 84 k-ft
b_o
99.0 in
d = 6.75 in
v_c
253 psi
φV_c / V_u
127 / 110 kip
Two-way slab reinforcement (DDM) — ACI 318-19 §8.10 / §22.6
| Column strip (top) | #7 @ 16.0 in — φM_n = 13.00 vs 12.93 k-ft/ft |
| Column strip (bottom) | #3 @ 7.0 in |
| Middle strip (top) | #3 @ 7.5 in |
| Middle strip (bottom) | #3 @ 7.5 in |
| Punching shear | φV_c = 127 kip vs V_u = 110 kip |
PASS — M_o = q_u l₂ l_n²/8 = 238.7 k-ft; distributed 65 % negative / 35 % positive (§8.10.4). Column strip (9.0 ft wide): top #7 @ 16.0 in, bottom #3 @ 7.0 in. Middle strip (9.0 ft wide): top #3 @ 7.5 in, bottom #3 @ 7.5 in. Two-way (punching) shear OK: φv_cb_od = 127 kip ≥ V_u = 110 kip at d/2 from the column (b_o = 99 in).
Panel l₁ × l₂ = 20.0 × 18.0 ft, column c₁ × c₂ = 18.0 × 18.0 in. Critical shear perimeter bo = 99.0 in at d/2 = 3.38 in from the column face (ACI 318-19 §22.6.4.1), φVc = 126.8 kip vs Vu = 110.3 kip. Column strip: top #7@16.0", bottom #3@7.0". Middle strip: top #3@7.5", bottom #3@7.5".
Building design suite
Masonry — TMS 402/602-22
Strength design of reinforced concrete masonry: slender out-of-plane walls with the P-δ moment, in-plane shear walls, and bond-beam lintels.
Reinforced masonry wall — axial, flexure & P-δ
Slenderness-reduced axial capacity, the second-order P-δ moment, vertical bar size and grout-cell spacing, the maximum-reinforcement ductility limit and out-of-plane shear.
φM_n = 0.90(A_sf_y + P_u)(d − a/2) · a = (A_sf_y + P_u)/0.80f′_mb · M_u,total = M_u + P_uδ_u
h/r
109.0
(70r/h)²
φP_n
43.45 kip/ft
δ_u
0.160 in
M_u total
4.25 k-ft/ft
Reinforcement
#7@32"
φV_n
8.07 kip/ft
Reinforced masonry wall design — TMS 402-22 §9.3
| Note 1 | h/r = 109 > 99 — the slender (70r/h)² form governs; φP_n = 43.4 kip/ft. |
| Note 2 | Second-order: δ_u = 0.160 in gives M_u,total = M_u + P_uδ_u = 4.25 k-ft/ft (§9.3.5.4.3). |
| Note 3 | Provide #7 @ 32 in o.c. — φM_n = 4.30 k-ft/ft ≥ 4.25 k-ft/ft; A_s = 0.225 in²/ft ≤ A_s,max = 0.722 in²/ft. |
| Note 4 | Shear OK: φV_n = 8.1 kip/ft ≥ V_u = 1.1 kip/ft (M/(V d_v) = 1.00). |
| Note 5 | Detailing: minimum prescriptive steel 0.0007bt = 0.064 in²/ft each direction (0.002 total); bond beams at ≤ 48 in o.c.; lap splices per §9.3.3.4. |
PASS — #7 @ 32 in o.c. vertical (A_s = 0.225 in²/ft) in grouted cells
8 in CMU, fully grouted, #7 vertical bars @ 32 in o.c. centered in the grouted cells (TMS 402-22 §9.3). Wall height h = 20.0 ft. φPn = 43.45 kip/ft vs Pu = 3.50 kip/ft; φMn = 4.30 k-ft/ft vs magnified Mu = 4.25 k-ft/ft.
Masonry shear wall — in-plane
M/(Vd_v)-dependent masonry shear, the crushing ceiling, bond-beam horizontal steel spacing and the boundary flexural steel at each end cell.
V_nm = [4.0 − 1.75(M/Vd_v)]A_nv√f′_m + 0.25P_u · V_ns = 0.5(A_v/s)f_yd_v
M/(Vd_v)
0.781
V_nm
187.4 kip
V_n,max
261.9 kip
V_s required
0.0 kip
Horizontal steel
#4@48"
Boundary steel
4–#5
Masonry shear wall design — TMS 402-22 §9.3.4 / §7.3.2
| Note 1 | M/(V d_v) = 0.78 → V_nm = 187 kip, upper limit V_n,max = 262 kip (§9.3.4.1.2). |
| Note 2 | Section adequate against masonry crushing in shear. |
| Note 3 | Horizontal shear steel: #4 bond-beam bars @ 48 in o.c. (φV_n = 181 kip). |
| Note 4 | Boundary flexural steel: A_s = 1.23 in² each end → 4 – #5 in the end cells (A_s,prov = 1.24 in²), fully grouted and lapped per §9.3.3.4. |
| Note 5 | Aspect ratio h_w/l_w = 1.25 — flexure-dominated behaviour. |
PASS —
Wall lw × t × hw = 16.0 ft × 7.625 in × 20.0 ft. Horizontal (shear) reinforcement #4@48"; boundary flexural steel 4 – #5 in grouted end cells. φVn = 180.6 kip vs Vu = 90 kip (TMS 402-22 §9.3.4 / §7.3.2).
Reinforced masonry lintel
Effective span and demands, bottom bond-beam steel, the §9.3.3.5 maximum-reinforcement limit, M/(Vd)-dependent masonry shear with stirrups when needed, bearing stress and the ℓ/600 deflection limit.
M_u = w_uℓ²/8 · a = A_sf_y/0.80f′_mb · φM_n = φA_sf_y(d − a/2) · V_nm = [4 − 1.75(M/Vd)]A_nv√f′_m
M_u / V_u
15.0 / 6.9 k-ft, kip
A_s required
0.170 in²
A_s provided
0.310 in²
1 – #5 bottom bond beam
φM_n
26.8 k-ft
φV_n
12.3 kip
Bearing
0.114 ksi
limit 0.300 ksi
Lintel bond-beam schedule — TMS 402-22 §9.3 / §5.2.1 / §8.1.6.2
| Grouted width b | 7.625 in |
| Effective depth d | 20.0 in |
| Bottom steel | 1 – #5 |
| Stirrups | not required by analysis |
| A_s,max | 1.451 in² |
| Deflection limit ℓ/600 | 0.160 in |
PASS — Provide 1 – #5 in the bottom bond beam, 8 in bearing each end; φM_n = 26.8 k-ft ≥ M_u = 15.0 k-ft.
Clear span = 8.0 ft, lintel depth h = 24 in over a 8.00 in wall, bearing 8 in each end. Bottom steel 1 — #5 in the grouted bond-beam course: φMn = 26.8 k-ft ≥ Mu = 15.0 k-ft; φVn = 12.3 kip vs Vu = 6.9 kip (TMS 402-22 §9.3).
Advanced detailing suite
Discontinuity regions, punching, torsional stability & stiffened webs
Four deep-dive modules that carry the awkward regions all the way to a drawing: strut-and-tie for deep beams and corbels, complete punching-shear design with stud rails and cap/column layout, combined torsion-and-stability for open and closed steel shapes, and plate-girder stiffener and weld design.
Deep beams & corbels — strut-and-tie
Full STM: deep-member screening, truss geometry and strut angle, strut and CCC/CCT nodal-zone strengths, tie steel with bar selection, distributed crack-control steel or corbel hoops, and tie anchorage.
θ = atan(0.9d/a_v) ≥ 25° · F_ns = f_ce A_cs, f_ce = 0.85β_cβ_s f′_c · A_st = F_ut/φf_y · A_v, A_vh ≥ 0.0025 b s
Strut angle θ
52.2 deg
Strut force F_us
405 kip
φF_ns = 517 kip
Tie force F_ut
312 kip
Strut width w_s
13.52 in
A_cs = 216 in²
A_s tie required
6.93 in²
A_s,min = 2.43 in²
A_s provided
7.20 in²
Bearing node
714 kip
CCT node
163 kip
φV_n,max
365 kip
Strut-and-tie model — ACI 318-19 Ch. 23 · §9.9 · §16.5
| Classification | Deep member (ℓ_n/h = 2.00, a_v/d = 0.70) |
| Truss lever arm jd | 38.7 in |
| Strut efficiency β_s | 0.75 → f_ce = 3.19 ksi |
| Node f_ce (CCC / CCT) | 4.25 / 3.40 ksi |
| Tie width w_t | 4.00 in |
Reinforcement schedule — §23.7 · §23.5 · §9.9.3 / §16.5.5
| Primary tie | 12 – #7 primary tie bars |
| Vertical web steel | #4 @ 8.5 in c/c each face (s_max = 8.6 in) |
| Horizontal web steel | #4 @ 8.5 in c/c each face (s_max = 8.6 in) |
| Tie anchorage | ℓ_dh = 12.6 in — straight development adequate |
| Bearing plate | 14.0 × 16.0 in, A_nz = 224 in² |
REDESIGN — CCT node behind the tie overstressed — spread the tie over a greater height (increase the number of layers so w_t ≥ 7.6 in) or enlarge the bearing.
Single-panel truss: θ = 52.2° from the load node to the support node. Strut force Fus = 405 kip (width ws = 13.52 in), tie force Fut = 312 kip carried by 12 – #7 primary tie bars. Vu = 320 kip. #4 vertical stirrups @ 8.5 in c/c each face + #4 horizontal bars @ 8.5 in c/c each face
Punching shear — complete design
All three v_c expressions at the d/2 section, unbalanced-moment transfer by eccentric shear, headed stud rails or closed stirrups with s₀/s and rail length to the outer critical section, plus the cap/column bar and tie layout.
v_u = V_u/b_od + γ_v M_u c/J_c · v_c = min[4, 2+4/β, 2+α_sd/b_o]λ√f′_c · A_v/s = v_s b_o/f_yt · s ≤ 0.75d
b_o at d/2
112.0 in
d = 8.00 in
v_u total
235 psi
direct 201 + moment 34
φv_c
212 psi
4λ√f′_c
γ_v / γ_f
0.400 / 0.600
v_s required
101 psi
φv_n with reinforcement
247 psi
Stud spacing s
6.0 in
s₀ = 3.0 in, s_max = 6.0 in
Lines per rail
4
rail 21.0 in ≥ 16.5 in
Crushing ceiling
424 psi
Punching shear reinforcement layout — ACI 318-19 §22.6.6 / §8.7.6–8.7.7
| System | #3 headed studs — 3 rails per face (12 lines), s₀ = 3.0 in, s = 6.0 in, 4 lines each rail |
| First line s₀ | 3.0 in from the column face (≤ d/2 = 4.00 in) |
| Peripheral spacing | 6.0 in (s_max = 6.00 in) |
| Outer critical section | b_o,out required 212 in → extend 16.5 in beyond the column |
| A_v per peripheral line | 1.32 in² (12 legs) |
Cap / column reinforcement layout — ACI §8.7.4.2 · §10.6 · §25.7.2
| Column vertical bars | 12 – #6 vertical bars (ρ = 1.32 %) with #4 ties @ 12 in, tightened to 6 in through the joint |
| Tie spacing through joint | 6.0 in (#4) |
| Top band steel over column | #9 @ 6.5 in top over the column band |
| Structural-integrity bottom bars | 6 – #5 continuous bottom bars through the column core (§8.7.4.2) |
| A_st required / provided | 4.00 / 5.28 in² |
PASS — Shear reinforcement required: headed shear studs #3, 12 lines, first line at 3.0 in then @ 6.0 in for 4 peripheral lines (21.0 in from the column face) — φv_n = 247 psi ≥ v_u = 235 psi, and the outer section at 16.5 in needs b_o ≥ 212 in.
Column 20.0 × 20.0 in, interior condition. Critical section at d/2 (d = 8.00 in), perimeter bo = 112.0 in. Headed stud rails: 3 rails/face, s₀ = 3.0 in, s = 6.0 in, 4 lines, rail length 21.0 in (extend ≥ 16.5 in).
Torsion & stability — open sections and HSS
St. Venant plus warping torsion, plate slenderness classification, flexural and flexural-torsional buckling, lateral-torsional buckling, the §H3.2 combined interaction, twist serviceability and the torsional restraint detailing.
T_n = F_cr C · a = √(EC_w/GJ) · F_e,T = [π²EC_w/(K_zL)² + GJ]/(I_x+I_y) · (P_r/P_c + M_r/M_c) + (V_r/V_c + T_r/T_c)² ≤ 1
φT_n
2316 kip-in
T_u/φT_n = 0.13
Twist θ
1.36 deg
Section class
compact
flange compact, web compact
KL/r
91.4
F_cr = 27.13 ksi
φP_n
437 kip
φM_n
241 k-ft
closed section — LTB does not govern (§F7)
φV_n
324 kip
L_p / L_r
11.1 / — ft
Interaction
0.589
§H1.1 (torsion ≤ 20 % — may be neglected)
Torsion mechanics — AISC 360-22 §H3 · Design Guide 9
| Torsional model | Rectangular HSS, §H3.1: C = 85.8 in³, h/t = 21.0, F_cr = 30.0 ksi |
| Torsional bending constant a | n/a (closed section) |
| St. Venant shear stress | 0.46 ksi |
| Warping constant C_w | 0 in⁶ |
| Torsion utilization | 0.130 |
Torsional restraint & detailing — AISC §H3.2 · DG9 Ch. 6
| Detailing | Torsion is a secondary effect (T_u/φT_n = 0.13) — provide 0.500 in end connection plates able to develop the end torque, with 0.250 in fillet welds. |
| Internal diaphragms | Not required |
| End plate thickness | 0.500 in |
| Fillet weld to transfer torque | 0.250 in, E70XX |
| Governing interaction | §H1.1 (torsion ≤ 20 % — may be neglected) = 0.589 |
PASS — All limit states satisfied: torsion 0.13, axial 0.18, flexure 0.50, shear 0.12; §H1.1 (torsion ≤ 20 % — may be neglected) = 0.59 ≤ 1.0; compact section, closed section — LTB does not govern (§F7).
Rectangular HSS, Tu = 300 kip-in vs φTn = 2316 kip-in (Tu/φTn = 0.13). Twist over L = 24.0 ft is θ = 1.36°. Combined interaction satisfied.
Plate-girder transverse & longitudinal stiffeners
Web and flange proportion limits and plate classification, tension-field shear, transverse stiffener size and rigidity, longitudinal stiffener location and inertia, bearing stiffener bearing/column checks, and final fillet-weld legs and lengths.
k = 5 + 5/(d_o/D)² · V_n = V_p[C + 0.87(1−C)/√(1+(d_o/D)²)] · I_t ≥ d_o t_w³ J · R_sb = 1.4A_pn F_ys
D/t_w
120.0
limit 150
Web / flange class
noncompact / compact
k / C
7.22 / 0.457
V_p
870 kip
φV_n
625 kip
tension field used
Required d_o
60 in
current spacing adequate
Transverse PL
4.5 × 0.375 in
I 26.8 ≥ 23.2 in⁴
Bearing PL
7.3 × 0.688 in
R_sb = 650 kip
Weld legs
0.250 / 0.250 in
intermediate / bearing
Shear panel & plate classification — AASHTO §6.10.2 / §6.10.9 · AISC §G2.3
| Web slenderness | D/t_w = 120.0 (limit 150); 2D_c/t_w classification: noncompact |
| Flange slenderness | b_f/2t_f = 8.00 → compact; proportions OK |
| Panel aspect d_o/D | 1.500 |
| Tension field | permitted and used |
| V_n (TF / no TF) | 625 / 397 kip |
Stiffener & weld schedule — AASHTO §6.10.11 · §6.13.3
| Transverse stiffeners | Pairs of PL 4.5 × 0.375 transverse stiffeners @ 90 in c/c, 0.250 in fillet welds each side over 58 in, cut back 4t_w–6t_w from the tension flange |
| Rigidity check | I_t,prov 26.8 in⁴ vs I_t,req 23.2 in⁴ (J = 0.50) |
| Longitudinal stiffener | No longitudinal stiffener required at this web slenderness |
| Bearing stiffeners | Bearing stiffeners: pair of PL 7.3 × 0.688, milled to bear, 0.250 in fillet welds full depth (effective column 14.5 in², KL/r = 12) |
| Bearing stiffener column | A_eff = 14.47 in², KL/r = 12.3, φP_n = 680 kip |
| Welds | Intermediate 0.250 in fillet each side; bearing stiffener 0.250 in full depth (min leg 0.2500 in) |
PASS — Panel verified: tension-field action permitted, C = 0.457, φV_n/V_u = 1.49. Stiffeners 2 × 4.5 × 0.375 in @ 90 in with 0.250 in fillet welds; bearing stiffeners 0.688 in with 0.250 in welds.
Web 60.0 in deep × 0.500 in thick, D/tw = 120, transverse stiffeners at do = 90.0 in (do/D = 1.50). Vu = 420 kip vs φVn = 625 kip (AASHTO 6.10.9).
Calculation reports
Every module is print-ready
Each of the calculators above exports a full calculation report — governing equations, substituted values, engineering assumptions, and pass/fail limit-state checks — ready to print or save as a PDF for your project files.
