SE

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

Chapter 03

Bridge Loads and Load Combinations

Permanent and transient loads, HL-93 live loading, dynamic load allowance, multiple-presence factors, braking and centrifugal effects, and Strength / Service / Fatigue / Extreme-Event combinations. Includes a full three-span Mid-Atlantic bridge worked example.

Estimated Time

10 Hours

Difficulty

Intermediate

AASHTO Refs

6 sections

Focus Area

Loads

Bookmark

Chapter

Engineering story

The Woodrow Wilson Bridge — a Mid-Atlantic loading lesson

The original Woodrow Wilson Bridge, carrying I-95/I-495 across the Potomac between Alexandria, Virginia and Prince George's County, Maryland, opened in 1961 for a projected 75,000 vehicles per day. By 2000 it carried more than 200,000 vehicles per day — a live-load environment far in excess of the loading assumptions used in its original 1950s design. A landmark FHWA and NCHRP investigation of the crossing (a driver behind the development of the HL-93 notional load model) documented growing fatigue damage, deck deterioration, and a rising fraction of permit trucks. It was demolished after the replacement twin bascule bridges opened in 2006–2008.

Heavy semi-truck crossing a steel plate-girder bridge, viewed from below
Figure 3.0Every truck crossing is a live-load event the AASHTO HL-93 model must envelope. A single fully-loaded semi delivers axle forces comparable to two-thirds of the HL-93 design truck.

The Woodrow Wilson replacement was designed to AASHTO LRFD and rated for HL-93 plus MDOT SHA / VDOT permit envelopes. That project — plus MDOT SHA's ongoing evaluation of the Chesapeake Bay Bridge and the recovery of the Francis Scott Key Bridge site — illustrates why loads (not resistance) drive most modern bridge decisions in the Mid-Atlantic.

Heavily trafficked urban

American Legion Bridge (I-495 over the Potomac). ~230,000 vehicles/day; ongoing MDOT-Virginia joint replacement project driven by capacity and deck condition.

Rural interstate

I-70 over the South Branch, Washington County, MD. Governed by fatigue truck loading and future overlay assumptions rather than peak demand.

Permit-vehicle bridge

US 40 crossings routing MDOT SHA permit vehicles (superloads for wind-turbine components). Strength II combinations control the load rating.

Vessel-collision case

Francis Scott Key Bridge (I-695, 1977–2024). Container-vessel strike on a non-redundant pier caused progressive collapse — an extreme-event limit state failure.

Fatigue-governed detail

Girder-web welded stiffener terminations along US-50; MDOT SHA fatigue retrofits under §6.6.1 Category C details.

Chapter objectives

What you will be able to do

Learning objectives

By the end of this chapter you will be able to:

  1. 1Identify all permanent and transient loads that act on a highway bridge.
  2. 2Compute HL-93 live-load force effects for simple and continuous spans.
  3. 3Apply the correct dynamic load allowance IM and multiple-presence factor m.
  4. 4Select and compute Strength I, Service I, Fatigue I, and Extreme Event II combinations.
  5. 5Position design truck, tandem, and lane loads for maximum moment and shear using influence lines.
  6. 6Distinguish DC, DW, LL, IM, BR, WA, WS, WL, TU, EQ, CT, CV, CR, SH loads.
  7. 7Verify computed demands with independent hand checks and code-based envelopes.
  8. 8Interpret the permit-vehicle envelope adopted by MDOT SHA and neighboring DOTs.

Pre-lecture — Section properties & load computation

Before you compute demands: how a bridge cross-section actually resists load

Every demand you will compute in §3.1 – §3.8 is only meaningful when you also know the section that resists it. In a composite steel–concrete bridge the resisting section is not one section — it is three or four, depending on the age of the concrete, the direction of bending, and whether the deck is cracked. This pre-lecture builds the vocabulary and the arithmetic you need to turn a plate girder + deck sketch into a set of design section properties (A, I, Stop, Sbot) and then apply the correct permanent-load pieces (self-weight, deck, SIP formwork, haunch, barriers, wearing surface, cross-frames) at the correct sequence in construction.

Why the sequence matters

The wet concrete deck is resisted by the steel girder alone. The barrier and future wearing surface, poured months later, are resisted by the long-term composite section. HL-93 truck traffic is resisted by the short-term composite section. Using the wrong section under a given load is the single most common student error in bridge design.

PL.1 — Terminology

Naming every piece of a composite bridge cross-section

Section properties are fundamental to load and stress computations, structural analysis, and resistance/capacity checks. In this course they include cross-sectional area A, centroid location ȳ, moment of inertia I, section modulus S, and slenderness ratios. Before we compute any of them, we need agreement on names.

Composite bridge cross-section with labeled effective flange width, IWS, structural and total slab thickness, haunch, top flange, web, bottom flange, shear studs
Figure PL.1Anatomy of a composite steel-concrete bridge girder. The concrete deck is connected to the steel plate girder through welded shear studs; a small haunch fills the gap between the top of the web and the underside of the deck.
TermDefinitionTypical value
Total slab thicknessFull deck depth as poured (IWS + structural).8 in – 9½ in
Integral Wearing Surface (IWS)Sacrificial top layer of the deck assumed to wear off over the design life.¼ in – ½ in
Structural slab thicknessDeck depth remaining after IWS is deducted. Used for capacity.7½ in – 9 in
HaunchGap between top of steel web and underside of the deck. Accommodates screed elevation and formwork tolerance.2 in – 4 in
Effective flange width, b_effPortion of the deck that acts compositely with a given girder.See §4.6.2.6 (AASHTO)
Top flangeCompression flange of a positive-moment section. Sized against local buckling.b_tf × t_tf
WebVertical plate resisting shear. Slenderness limited by D/t_w.D × t_w
Bottom flangeTension flange in positive-moment regions; typically 1.5× top flange area.b_bf × t_bf

IWS split-use rule

For loads use the total slab thickness (all the concrete you actually pour weighs on the girder). For resistance use the structural slab thickness (the IWS is assumed gone at end of life).

PL.2 — Effective flange width

Why only part of the deck acts as a girder flange

AASHTO LRFD §4.6.2.6

Concrete compression stress in a wide deck is highest directly above the girder web and drops off toward mid-span between girders — this is shear lag. Rather than integrate a curved stress block, AASHTO defines an effective flange width bE over which the peak stress fc is assumed uniform, delivering the same total compressive force.

Left: curved compressive stress distribution over an actual wide flange. Right: equivalent uniform stress over the effective flange width b_E.
Figure PL.2Effective flange width replaces the real (non-uniform) compressive stress field over the deck with a uniform stress block of width b_E and depth h, preserving the total compressive force.

AASHTO LRFD Reference

§4.6.2.6.1 — General. Unless specified otherwise, the effective flange width of a concrete deck slab in composite or monolithic construction may be taken as the tributary width perpendicular to the axis of the member for determining cross-section stiffnesses for analysis and for determining flexural resistances.

Tributary width means: for an interior girder, half the spacing to each adjacent girder — i.e. the full girder spacing S. For an exterior girder, half the spacing to the adjacent interior girder plus the deck overhang. That's why the same bridge often has two sets of composite section properties — one interior, one exterior. Always label your section with which one you are computing.

Typical bridge deck cross-section showing 36 ft out-to-out width, 34 ft roadway, 10.5 ft girder spacing, SIP metal deck, Jersey barriers
Figure PL.3A typical 4-girder composite steel bridge cross-section (MDOT SHA style). Out-to-out width 36'-0, clear roadway 34'-0, girder spacing 10'-6, overhang 1'-3¼. Stay-in-place (SIP) metal deck forms span between girders. Interior and exterior girders have different tributary widths and therefore different b_eff.

PL.3 — Materials & modular ratio

Transforming concrete into equivalent steel

AASHTO LRFD §5.4.2.4 / §6.4.1

The girder is steel and the deck is concrete — two materials with very different stiffnesses. To perform a single beam-bending analysis, we transform the concrete into an equivalent area of steel using the modular ratio n.

(PL.3-1)
  1. Modular ratio

    n  =  EsEcn \;=\; \frac{E_{s}}{E_{c}}
EsE_{s}
Modulus of elasticity of structural steel [ksi]
EcE_{c}
Modulus of elasticity of concrete [ksi]
nn
Modular ratio, rounded to nearest whole number

For all grades of structural steel AASHTO AASHTO LRFD §6.4.1 sets Es = 29,000 ksi. For normal-weight concrete AASHTO AASHTO LRFD §C5.4.2.4 gives the practical form:

(PL.3-2)
  1. Concrete modulus

    Ec  =  1,820fcE_{c} \;=\; 1{,}820\sqrt{f'_{c}}
fcf'_{c}
Specified 28-day compressive strength [ksi]
f′_c (ksi)E_c (ksi)n = 29,000 / E_cRounded n3n (long-term)
3.031529.20927
3.534058.50824
4.036407.97824
4.538617.51824
5.040707.13721
6.044586.51721
8.051485.63618

PL.4 — Positive-bending section family

Noncomposite, short-term composite, long-term composite

AASHTO LRFD §6.10.1.1

The class of section that resists a given load depends on when that load arrives on the bridge and how long it acts.

  1. Noncomposite (steel only). The bare steel girder — before the deck has cured — resists every load applied during construction: girder self-weight, wet concrete deck, haunch, SIP formwork, and cross-frames.
  2. Short-term composite (steel + b_eff / n). After the deck cures, transient loads (traffic, wind on live load) are applied for seconds to minutes. The concrete is transformed by dividing the effective width by n.
  3. Long-term composite (steel + b_eff / 3n). Permanent loads added after the deck cures — barriers, sidewalks, future wearing surface, utility conduits, sign structures — act for decades. Concrete creeps under sustained stress; using 3n instead of n reduces the transformed area so the steel picks up the extra strain the creeping concrete cannot sustain.
Four side-by-side girder cross-sections: noncomposite steel only, short-term composite (b_eff/n), long-term composite (b_eff/3n), and steel + longitudinal reinforcement
Figure PL.4The family of sections that a composite bridge girder is analyzed under. As you move left → right, the neutral axis rises and the girder becomes more efficient in positive bending. Section (4) is used only in negative-bending (over-pier) regions.

Why 3n and not 2n or 4n

The 3× factor traces to the AASHTO calibration of long-term creep coefficient for normal-weight concrete under sustained stress. It is a code-mandated approximation — do not derive it from first principles for design; simply apply it whenever a load is sustained (DC applied to composite, DW, utilities, etc.).

PL.5 — Negative-bending sections

What happens over the pier

Over interior supports of continuous girders the top of the deck is in tension. Concrete has essentially no tensile strength for design purposes, so we assume the deck concrete cracks and take steel + longitudinal deck reinforcement as the resisting section. Two methods are permitted:

  • Count every longitudinal deck bar within beff and include its area and centroid — tedious but exact.
  • Use the conservative shortcut of AASHTO LRFD §6.10.1.1.1c: assume 1% longitudinal reinforcement in the effective flange width (two-thirds in the top mat, one-third in the bottom mat).
Two-span continuous bridge elevation with negative-moment region highlighted, plus cross-sections showing cracked deck concrete and longitudinal rebar in tension
Figure PL.5Continuous-girder negative-moment region. Because the top of the deck is in tension, deck concrete is assumed cracked and only the longitudinal reinforcement (plus the bare steel girder) is used to compute negative-bending section properties.

Design cover requirements (AASHTO §5.10.1)

Locate top-mat longitudinal reinforcement using cover: 2.5 in for deck surfaces exposed to deicing salts (typical for MDOT SHA), 1.0 in bottom cover for the bottom-mat bars up to No. 11. Cover directly drives the effective depth of the cracked-section analysis.

PL.6 — The arithmetic

Parallel-axis theorem, applied to every section in the family

For each section variant (noncomposite, short-term, long-term, steel + rebar) you follow the same 5-step recipe:

  1. Choose a datum (usually bottom of bottom flange).
  2. List each component: area Ai and centroid height yi above the datum.
  3. Compute the section centroid ȳ = ΣAiyi / ΣAi.
  4. Compute each component's di = yiȳ, then sum I = Σ(Io,i + Aidi2).
  5. Get section moduli: Stop = I / ctop and Sbot = I / cbot.
  1. Parallel-axis theorem

    I  =  (Io+Ad2)I \;=\; \sum\left(I_{o} + A\,d^{2}\right)

    (PL.6-1)

  2. Rectangle self-inertia

    Io  =  bh312(for a rectangle)I_{o} \;=\; \frac{b\,h^{3}}{12}\quad\text{(for a rectangle)}

    (PL.6-2)

  3. Section modulus and bending stress

    S  =  Icσmax  =  MSS \;=\; \frac{I}{c} \quad\Rightarrow\quad \sigma_{max} \;=\; \frac{M}{S}

    (PL.6-3)

PL.6b — Preliminary sizing

How to select a trial section for a plate girder

AASHTO LRFD §6.10

Before you can compute section properties you need a starting cross-section. The following rules come from AASHTO slenderness limits, plate-availability tables from the AASHTO/NSBA Steel Bridge Collaboration, and decades of fabricator practice. They give an economical trial girder — you will iterate once demands are known.

#DimensionCode limitDesign rule (backed off)Trial equation
1Girder depth DL/D ≤ 30 (Table 2.5.2.6.3-1)L/D = 27.5D = L / 27.5
2Web thickness twD/t_w ≤ 150 (unstiffened)D/t_w = 120t_w = D / 120
3Compression flange width bfcb_f/D ≤ 1/6b_fc/D = 1/4 (stockier)b_fc = D / 4
4Compression flange thickness tfcb_fc/(2 t_fc) ≤ 0.38 √(E/F_yc)Fy = 50 ksi → t_fc = b_fc/18.3
Fy = 70 ksi → t_fc = b_fc/15.5
t_fc ≥ b_fc / (0.76 √(E/F_yc))
5Tension flange thickness tftTypically 1.5× top flangeAssume b_ft = b_fct_ft = 1.5 t_fc

Why these rules of thumb?

Rule 1 sets a stiffness that keeps live-load deflection manageable. Rule 2 keeps the web from bend-buckling before we've done any real analysis. Rule 3 keeps the flange stocky enough that we don't spend the whole design budget on lateral-torsional buckling. Rule 4 is the AASHTO local-buckling limit rearranged for tfc. Rule 5 reflects that in positive-moment regions the bottom flange (tension) usually needs more area than the top (compression) because the compression flange gets help from the composite deck.

Worked trial — span L = 150 ft (1,800 in):

PL.6b

Trial section — span L = 150 ft (1,800 in)

  1. Girder depth

    D  =  L27.5  =  1,80027.5  =  65.45 in  D66 inD \;=\; \tfrac{L}{27.5} \;=\; \tfrac{1{,}800}{27.5} \;=\; 65.45\ \text{in}\ \Rightarrow\ D \approx 66\ \text{in}
  2. Web thickness

    tw  =  D120  =  66120  =  0.55 in  tw=58 int_{w} \;=\; \tfrac{D}{120} \;=\; \tfrac{66}{120} \;=\; 0.55\ \text{in}\ \Rightarrow\ t_{w} = \tfrac{5}{8}\ \text{in}
  3. Flange width

    bf  =  D4  =  664  =  16.5 in  bf18 inb_{f} \;=\; \tfrac{D}{4} \;=\; \tfrac{66}{4} \;=\; 16.5\ \text{in}\ \Rightarrow\ b_{f} \approx 18\ \text{in}
  4. Flange thicknesses

    tfc  =  bfc18.31.0 in,tft  =  1.5tfc  =  112 int_{fc} \;=\; \tfrac{b_{fc}}{18.3} \approx 1.0\ \text{in},\quad t_{ft} \;=\; 1.5\,t_{fc} \;=\; 1\tfrac{1}{2}\ \text{in}
  5. Trial girder

    18×1 top flange,  66×58 web,  18×112 bottom flange18{\times}1\ \text{top flange},\ \ 66{\times}\tfrac{5}{8}\ \text{web},\ \ 18{\times}1\tfrac{1}{2}\ \text{bottom flange}
Blueprint-style trial welded plate girder cross-section: 18x1 top flange, 66x5/8 web, 18x1.5 bottom flange
Figure PL.6bPreliminary trial girder from the L = 150 ft example. This is a starting point only — flange plates will change thickness (not width) along the span once analysis demands are known.

Layout considerations before you draw plates

  • Girder spacing. Wider is generally more economical (fewer girders, cross-frames, bearings). For L < 140 ft use S = 10–11 ft; for L > 140 ft use S = 11–14 ft. Wider spacing → thicker deck.
  • Minimum plate thicknesses. Stiffeners & connection plates 7/16 in min (½ in preferred). Webs 7/16 in min (½ in preferred), 1/16-in increments. Flanges ¾ in min, 1/8-in increments up to 2½ in then ¼-in increments.
  • Never change flange width along the girder — change thickness. Butt-weld thicker flange plates with CJP welds, torch-cut a 60-in min transition length. Constant flange width simplifies fabrication.
  • Plate availability. Use AASHTO/NSBA plate-length tables (e.g. ½-in × 72-in plate available up to ~972 in long, 3-in × 96-in only ~734 in) so you don't specify a plate the mill can't roll.

PL.7 — Worked example

Noncomposite section properties of a 42-in plate girder

Compute ȳ, I, and both section moduli for the steel-only cross-section below. This is the section that resists deck-pour loading — before composite action develops.

Welded steel plate girder with dimensions and tabulated area-moment properties
Figure PL.6Steel plate girder used in the worked example. Top flange 14 × ¾ in; web 40 × 7/16 in; bottom flange 16 × 1¼ in. Total depth ¾ + 40 + 1¼ = 42 in. Datum is placed at the bottom of the bottom flange.
ComponentA (in²)y (in)Ay (in³)I_o (in⁴)d = y − ȳ (in)Ad² (in⁴)
Top flange (14 × ¾)10.50041.625437.060.492+24.5126,308.5
Web (40 × 7/16)17.50021.250371.882,333.33+4.137299.5
Bottom flange (16 × 1¼)20.0000.62512.502.60−16.4885,437.0
Σ48.000821.442,336.4312,045.0

PL.7

Steel-only section properties (bare plate girder)

  1. Centroid

    yˉ  =  AiyiAi  =  821.4448.000\bar{y} \;=\; \frac{\sum A_i y_i}{\sum A_i} \;=\; \frac{821.44}{48.000}
  2. Moment of inertia

    I  =  Io,i+Aidi2  =  2,336.43+12,045.0I \;=\; \sum I_{o,i} + \sum A_i d_i^{2} \;=\; 2{,}336.43 + 12{,}045.0
  3. Section modulus — top

    Stop  =  Ictop  =  14,38142.0017.11  =  14,38124.89S_{top} \;=\; \frac{I}{c_{top}} \;=\; \frac{14{,}381}{42.00-17.11} \;=\; \frac{14{,}381}{24.89}
  4. Section modulus — bottom

    Sbot  =  Icbot  =  14,38117.11S_{bot} \;=\; \frac{I}{c_{bot}} \;=\; \frac{14{,}381}{17.11}
  5. Bare-steel properties

    yˉ=17.11 in,  I=14,381 in4,  Stop=577.8 in3,  Sbot=840.5 in3\bar{y}=17.11\ \text{in},\ \ I=14{,}381\ \text{in}^{4},\ \ S_{top}=577.8\ \text{in}^{3},\ \ S_{bot}=840.5\ \text{in}^{3}
yˉ\bar{y}
centroid above the datum [in]
II
second moment of area about the neutral axis [in^4]
cc
distance from neutral axis to extreme fibre [in]

Short-term composite — same recipe, one extra row

Add the transformed deck (beff / n × ts) centered at the mid-depth of the slab, above the top flange by (haunch + ts/2). For beff = 120 in, ts = 8 in, n = 8, the transformed slab area = 120 in². The composite centroid rises to ≈39.2 in above datum and IST ≈ 47,700 in4 — more than 3× the bare-steel I.

PL.8 — Permanent loads

What weighs on the bridge, and which section catches it

AASHTO LRFD §3.5.1 / §3.3.2

Permanent loads are grouped by which section resists them, because that drives the modular ratio used in analysis. AASHTO breaks the components into two design codes — DC (structural components and non-structural attachments) and DW (wearing surfaces and utilities) — because they carry different load factors (γp = 1.25/0.90 for DC vs. 1.50/0.65 for DW).

Permanent loadCodeApplied toTypical valueFormula per girder
Steel plate girder self-weightDC1Noncomposite (steel only)ρ_s = 490 pcf ≈ 0.490 kcfw_g = A_s × ρ_s
Wet concrete deck (total thickness)DC1Noncomposite (steel only)ρ_c = 150 pcf; add 5 pcf for reinforcement → 155 pcfw_deck = t_total × S × ρ_c
Concrete haunchDC1Noncomposite (steel only)0.150 kcf × haunch height × top-flange widthw_h = t_haunch × b_tf × ρ_c
SIP metal deck formwork + ponded concrete in flutesDC1Noncomposite (steel only)≈15 psf of deck area (form) + concrete fill (add ¼ in equivalent)w_SIP = 15 psf × (S − b_tf)
Cross-frames / diaphragmsDC1Noncomposite (steel only)Point loads at brace lines; ~200 – 500 lb each end reactionDistribute to nearest node
Stiffeners, splice plates, boltsDC1Noncomposite (steel only)5 – 10% uplift on girder self-weightw_misc = 0.08 × w_g
Concrete parapets / Jersey barriersDC2Long-term composite (3n)MDOT SHA F-shape ≈ 470 plf per barrierw_b = (Σ barriers) / N_g (or distribute to exterior only)
Sidewalks / raised medians (if cast after deck)DC2Long-term composite (3n)0.150 kcf × sidewalk cross-sectionw_sw = A_sw × ρ_c / N_g
Bituminous wearing surface / future overlayDWLong-term composite (3n)MDOT SHA: 25 – 30 psf (2-in asphalt)w_ws = t_ws × ρ_asp × (roadway width) / N_g
Utilities (waterline, gas, conduit)DWLong-term composite (3n)Project-specific; get value from utility drawingsw_u = (weight per foot) / N_g
Bridge deck being poured on stay-in-place metal deck forms between steel girders
Figure PL.7Deck-pour day: wet concrete (DC1) rests on SIP formwork spanning between the top flanges. The steel girder alone resists this load — this is why noncomposite section properties matter.
Concrete Jersey barrier on top of a bridge deck with steel cross-frames visible below
Figure PL.8After the deck has cured, cast-in-place Jersey barriers (DC2) and any future wearing surface (DW) are added — these load the long-term composite section. Cross-frames (visible below deck) contribute a small DC1 load applied during erection.

Distribution to girders

Deck weight distributes to each girder by tributary width. Barriers are typically divided equally among all girders or assigned entirely to the exterior girder (MDOT SHA allows either — the exterior-girder-only method governs for exterior-girder design). Future wearing surface is distributed by tributary width of the roadway carried.

PL.8b — Worked example

Computing every permanent load on an interior girder

Given the bridge cross-section of Figure PL.4 (out-to-out width 36 ft, four girders at S = 10 ft 6 in, deck total ttotal = 8½ in with ½-in IWS, haunch = 2 in, top flange btf = 14 in, two F-shape barriers) and the trial girder from §PL.6b (As = 48.875 in²), compute the DC1, DC2, and DW loads carried by one interior girder. Use ρc = 0.150 kcf and ρs = 0.490 kcf.

Step 1 — DC1: steel girder self-weight

  1. Formula

    wg  =  Asρsw_{g} \;=\; A_{s}\cdot \rho_{s}
  2. Substitute

    wg  =  48.875 in21440.490 kcfw_{g} \;=\; \frac{48.875\ \text{in}^{2}}{144}\cdot 0.490\ \text{kcf}
  3. Result

    wg=0.166 klfw_{g} = 0.166\ \text{klf}

Add ~8% for stiffeners, splices, connection plates:

  1. Formula

    wg,misc  =  1.080.166w_{g,misc} \;=\; 1.08 \cdot 0.166
  2. Result

    wg,misc=0.180 klfw_{g,misc} = 0.180\ \text{klf}

Step 2 — DC1: wet concrete deck

  1. Formula

    wdeck  =  ttotalSρcw_{deck} \;=\; t_{total}\cdot S \cdot \rho_{c}
  2. Substitute

    wdeck  =  8.51210.50.150w_{deck} \;=\; \tfrac{8.5}{12}\cdot 10.5 \cdot 0.150
  3. Result

    wdeck=1.116 klfw_{deck} = 1.116\ \text{klf}

Step 3 — DC1: haunch

  1. Formula

    wh  =  thaunchbtfρcw_{h} \;=\; t_{haunch}\cdot b_{tf} \cdot \rho_{c}
  2. Substitute

    wh  =  21214120.150w_{h} \;=\; \tfrac{2}{12}\cdot \tfrac{14}{12}\cdot 0.150
  3. Result

    wh=0.029 klfw_{h} = 0.029\ \text{klf}

Step 4 — DC1: SIP formwork + concrete in flutes

Take 15 psf of the tributary form area (girder spacing minus top flange width):

  1. Formula

    wSIP  =  0.015 ksf(Sbtf)w_{SIP} \;=\; 0.015\ \text{ksf}\cdot (S - b_{tf})
  2. Substitute

    wSIP  =  0.015(10.51412)w_{SIP} \;=\; 0.015 \cdot \left(10.5 - \tfrac{14}{12}\right)
  3. Result

    wSIP=0.140 klfw_{SIP} = 0.140\ \text{klf}

Step 5 — DC1: cross-frames (as an equivalent UDL)

Assume K-frames at 25-ft spacing, each weighing ~350 lb; end reaction on one girder ~175 lb. Smeared over 25 ft:

  1. Substitute

    wxf    0.175 kip25 ftw_{xf} \;\approx\; \frac{0.175\ \text{kip}}{25\ \text{ft}}
  2. Result

    wxf=0.007 klfw_{xf} = 0.007\ \text{klf}
DC1 componentw (klf)
Steel girder + details0.180
Wet concrete deck1.116
Haunch0.029
SIP formwork + fill0.140
Cross-frames (smeared)0.007
Σ wDC11.472 klf

Applied to the noncomposite steel section.

Step 6 — DC2: barriers

Two F-shape barriers at 0.470 klf each, distributed equally to the four girders:

  1. Substitute

    wb  =  20.4704w_{b} \;=\; \frac{2 \cdot 0.470}{4}
  2. Result

    wb=0.235 klfw_{b} = 0.235\ \text{klf}

Step 7 — DW: future wearing surface

Assume 25 psf over the 34-ft clear roadway, distributed to all four girders:

  1. Substitute

    wws  =  0.025 ksf34 ft4w_{ws} \;=\; \frac{0.025\ \text{ksf}\cdot 34\ \text{ft}}{4}
  2. Result

    wws=0.213 klfw_{ws} = 0.213\ \text{klf}
Applied laterCodew (klf)Resisting section
BarriersDC20.235Long-term composite (3n)
Future wearing surfaceDW0.213Long-term composite (3n)

Sanity check the numbers

For an interior girder on a typical 4-girder composite highway bridge, DC1 usually lands between 1.2 and 1.7 klf — dominated by the wet deck. DC2 (barriers) is typically 0.15 – 0.30 klf per girder, and DW (2-in future overlay) is 0.15 – 0.25 klf. If your totals are far outside these ranges, check your tributary width, unit weights, and whether you accidentally distributed barrier weight only to the exterior girder.

PL.9 — Live loads, at a glance

What §3.1 – §3.4 will compute for you

AASHTO LRFD §3.6

The three live-load streams you will meet in §3.2 are all resisted by the short-term composite section:

  • HL-93 design truck (8 + 32 + 32 kip axles) — see §3.2.
  • HL-93 design tandem (25 + 25 kip axles, 4 ft apart) — governs short spans.
  • Design lane load (0.64 klf uniform) — the "traffic queue" component, always superimposed on truck or tandem.

Each is amplified by the dynamic load allowance IM (33% for strength, 15% for fatigue) and factored for how many lanes are simultaneously loaded via the multiple-presence factor m. Finally, an approximate live-load distribution factor DF (AASHTO Table 4.6.2.2.2b-1) assigns a fraction of the axle line to each girder — because you almost never do a full 3D analysis for routine composite steel bridges.

(PL.9-1)
  1. Live-load moment

    MLL+IM  =  DF(1+IM)mMlane-lineM_{LL+IM} \;=\; DF \cdot (1 + IM) \cdot m \cdot M_{lane\text{-}line}

With MLL+IM in hand and SST from §PL.7 you can already compute the live-load bending stress at any fiber:

  1. Bending stress

    σLL+IM, bottom  =  MLL+IMSST, bot\sigma_{LL+IM,\ bottom} \;=\; \frac{M_{LL+IM}}{S_{ST,\ bot}}

…which you'll then combine with the DC1 stress (on noncomposite S) and DC2 + DW stresses (on long-term S) in the Strength I equation from §3.4.

PL.10 — Design workflow

Putting section properties + loads together

  1. Sketch the cross-section with dimensions. Note interior vs exterior girder, spacing, overhang, deck thickness, IWS, haunch.
  2. Compute the noncomposite section properties (§PL.7 recipe).
  3. Compute beff (§PL.2), then the short-term composite (÷n) and long-term composite (÷3n) properties.
  4. For continuous spans, also compute the steel + longitudinal reinforcement properties for negative-moment regions (§PL.5).
  5. List every permanent load (§PL.8) and tag it DC1 / DC2 / DW. Compute its unfactored moment/shear per girder using structural analysis (Chapter 4 tools).
  6. Compute the live-load force effects (§3.2 – §3.3) and apply the distribution factor.
  7. Combine with the AASHTO load factors from Table 3.4.1-1 (§3.4). Check stresses on the correct section for each load type.

Common mistakes to avoid

  • Using short-term S for the barrier or the future wearing surface.
  • Forgetting the haunch weight (it can be 20 – 40 plf per girder).
  • Forgetting SIP formwork (~15 psf) — often 5 – 10% of the deck DC1.
  • Using total slab thickness for capacity or structural slab thickness for weight.
  • Using interior beff for both interior and exterior girders.
  • Dividing barrier weight by the number of girders when only the exterior girder should carry it.

With this pre-lecture complete you're ready for §3.1 Load Categories (below), where we formalize the AASHTO notation for every load type you just met, and then move into the HL-93 live-load model, dynamic allowance, and Strength/Service combinations.

3.1 — Load categories

Permanent, transient, extreme

AASHTO LRFD §3.3

Every highway bridge is subject to two broad classes of loads: permanent (present throughout the design life, essentially constant) and transient (variable in space, time, or occurrence). AASHTO LRFD subdivides these into notation each engineer must memorize, because every subsequent chapter references it.

Diagram of a highway bridge annotated with DC, DW, LL+IM, BR, WS, WA, TU, EQ, CT/CV loads
Figure 3.1The load environment of a typical highway bridge. Permanent loads (DC, DW) act every day of the design life; transient loads (LL, BR, WS, WA, TU) vary with traffic, weather, and season; extreme-event loads (EQ, CT, CV) are rare but govern non-redundant elements.
NotationNameTypical source
DCDead load of components + attachmentsGirders, deck, diaphragms, barriers
DWDead load of wearing surface + utilitiesAsphalt overlay, waterline, conduit
EH / EV / ESEarth pressure (horizontal / vertical / surcharge)Backfill on abutments and walls
LLVehicular live loadHL-93 truck, tandem, lane
IMDynamic load allowanceImpact factor applied to LL truck/tandem
BRVehicular braking forceDecelerating trucks
CEVehicular centrifugal forceCurved bridges
PLPedestrian loadSidewalks > 2 ft
WAWater load & stream pressurePiers in waterway
WS / WLWind on structure / wind on live loadGirder web, deck overhang
TU / TGUniform thermal / thermal gradientBearings, expansion joints, continuous frames
CR / SHCreep / shrinkageTime-dependent PC girder behavior
EQEarthquakeSeismic design
CT / CVVehicular / vessel collisionPiers exposed to traffic or navigation
ICIce loadNorthern rivers

Estimating dead load (DC, DW). Dead load of a structural component is its volume times its unit weight. AASHTO LRFD Table 3.5.1-1 tabulates the unit weights the designer must use so that every engineer computing DC and DW on the same girder arrives at the same number. The most-used values are reproduced below (kip/ft³):

MaterialUnit weight γ (kip/ft³)Where it appears
Normal-weight concrete (f′c ≤ 5 ksi, incl. reinforcement)0.145Deck, girder, pier, abutment (DC)
Normal-weight concrete (5 < f′c < 15 ksi)0.140 + 0.001·f′cHigh-strength PC girders (DC)
Lightweight concrete (incl. reinforcement)0.110Deck on long-span steel (DC)
Sand-lightweight concrete (incl. reinforcement)0.120Deck (DC)
Structural steel0.490Plate girders, rolled beams (DC)
Cast iron0.450Legacy bridges (DC)
Aluminum0.175Signs, luminaires (DC)
Bituminous wearing surface (asphalt)0.140Future overlay (DW)
Stone masonry0.170Historic arch spandrels, retaining (DC)
Hardwood / softwood0.060 / 0.050Timber decks, formwork
Water (fresh / salt)0.062 / 0.064Buoyancy on submerged piers (WA)
Compact sand, silt, or clay0.120Backfill above abutment footings (EV)
Loose sand, silt, or gravel0.100Backfill (EV)
Transit rails, ties & fastenings0.200 kip/ft (per track)Rail transit deck loads (DC)

Adapted from AASHTO LRFD §3.5.1 (Table 3.5.1-1), 10th Edition (2024). Verify current values against the specification for each new design; older editions used slightly different concrete-strength thresholds.

Why DC and DW carry different load factors

DC (structural components) can be estimated tightly — geometry is fixed and material unit weights are well controlled — so its Strength-I factor is γp,DC = 1.25 (max) or 0.90 (min). DW (wearing surface + utilities) is far less certain because the same deck may be re-overlaid several times over 75 years, adding thickness beyond the original design; hence DW carries the larger factor γp,DW = 1.50 (max) or 0.65 (min). The permanent-load categories are ordered in AASHTO §3.3.2 as: DC, DW, EV, EH, ES, EL, DD, PS, CR, SH — memorize these two-letter codes; every subsequent load-combination table uses them.

3.1.5 — Load-by-load lecture

How each highway-bridge load is quantified

AASHTO LRFD §3.5 – §3.14

The table above lists the notation; this lecture is what the notation actually means in a design calculation. For each load, you need to know (a) the physical mechanism, (b) the AASHTO-prescribed equation or table used to quantify it, and (c) the units and typical magnitude on a Mid-Atlantic bridge. Every worked example in this course draws from the equations below.

DC — Dead load of structural components AASHTO LRFD §3.5.1

The self-weight of everything that forms part of the structure: girders, deck slab, diaphragms, cross-frames, stiffeners, bearings, barriers, and end blocks. Computed by multiplying volume by unit weight from AASHTO Table 3.5.1-1 (γc = 150 pcf for normal-weight reinforced concrete, γs = 490 pcf for structural steel).

  1. wDC,deck=γctsS [klf per girder line]w_{DC,deck} = \gamma_{c} \cdot t_{s} \cdot S \ \text{[klf per girder line]}

Example: a 9-in cast-in-place deck at 10-ft girder spacing gives wDC,deck = 0.150 · 0.75 · 10 = 1.125 klf on each interior girder.

DW — Dead load of wearing surface and utilities AASHTO LRFD §3.5.1

Everything not part of the structural cross-section: asphalt overlay, waterproofing membrane, utilities (waterlines, conduits, gas lines). DW is separated from DC because it has a higher load factor (γDW = 1.50 vs. γDC = 1.25) — future overlays and utilities are far less certain than the structural steel weight.

  1. wDW=qFWSS+wutil [klf per girder line]w_{DW} = q_{FWS} \cdot S + w_{util} \ \text{[klf per girder line]}

MDOT SHA standard future-wearing-surface allowance: qFWS = 0.025 ksf (equivalent to a 2-in bituminous overlay at 150 pcf).

LL — Vehicular live load AASHTO LRFD §3.6.1

HL-93 as introduced in §3.2. The force effect from LL is obtained by positioning the design truck (or tandem) and design lane load on the influence line for the response of interest. A closed-form simple-span expression that every graduate should have memorized:

  1. Lane load moment

    Mlane=0.64L2/8 [kip-ft, simple span L in ft]M_{lane} = 0.64 \cdot L^{2} / 8 \ \text{[kip-ft, simple span } L \text{ in ft]}
  2. Truck moment (simple span)

    Mtruck,SSPL/4aPM_{truck,SS} \approx P \cdot L / 4 - a \cdot P

    Depends on rear-axle spacing

BR — Vehicular braking force AASHTO LRFD §3.6.4

Horizontal force at 6 ft above the deck, applied longitudinally to the superstructure to represent decelerating trucks. AASHTO requires the larger of:

  1. BR=0.25(design truck OR tandem, per lane)BR = 0.25 \cdot \text{(design truck OR tandem, per lane)}
  2. BR=0.05[design truck + lane load, per lane]BR = 0.05 \cdot \text{[design truck + lane load, per lane]}

    Multiple-presence factor m applies to BR.

WA — Water load and stream pressure AASHTO LRFD §3.7

Longitudinal pressure on a pier submerged in flowing water:

(3.7.3.1-1)
  1. p=CDV2/1000 [ksf, V in ft/s]p = C_{D} \cdot V^{2} / 1000 \ \text{[ksf, } V \text{ in ft/s]}

    C_D = drag coefficient (0.7 for semicircular nose, 1.4 for square).

WS — Wind on structure AASHTO LRFD §3.8

The 10th Edition adopts the same wind-hazard framework used by ASCE 7 (basic wind speed V, exposure category, gust factor, pressure coefficients). Design pressure on the exposed area of the girder web and barriers:

(3.8.1.2.1-1)
  1. PZ=2.56×106V2KzGCd [ksf]P_{Z} = 2.56 \times 10^{-6} \cdot V^{2} \cdot K_{z} \cdot G \cdot C_{d} \ \text{[ksf]}

TU — Uniform thermal expansion AASHTO LRFD §3.12.2

Change in bridge length due to uniform temperature change; drives bearing displacement and pier flexure. For Maryland (moderate climate zone, cold-climate steel bridges): ΔT = 150 °F design range for steel and ΔT = 80 °F for concrete.

  1. ΔT=αΔTL [in, α in /°F, L in in]\Delta_{T} = \alpha \cdot \Delta T \cdot L \ \text{[in, } \alpha \text{ in /°F, } L \text{ in in]}

    α_steel = 6.5 × 10⁻⁶ /°F; α_concrete = 6.0 × 10⁻⁶ /°F.

EQ — Earthquake AASHTO LRFD §3.10

Elastic seismic response coefficient Csm as a function of site class, SDS, SD1, and structural period T:

(3.10.4.2-1)
  1. Csm=SD1/T  SDSC_{sm} = S_{D1} / T \ \le \ S_{DS}

Maryland is a low-to-moderate seismic region; most MDOT SHA bridges fall in Seismic Zone 1 (SD1 ≤ 0.15) — minimum detailing requirements apply but explicit seismic analysis rarely governs member sizes.

CV / CT — Vessel or vehicle collision AASHTO LRFD §3.14

Extreme-event load on piers exposed to navigable waterways or highway traffic. Vessel impact force is a function of vessel dead-weight tonnage, transit speed, and pier geometry — the 2024 Francis Scott Key Bridge collapse is the reference case for the Mid-Atlantic and has driven MDOT SHA's revised vessel-collision risk assessments on the Bay and Patapsco crossings.

(3.14.8-1)
  1. Ps=8.15VDWT [kip, V in ft/s, DWT in short tons]P_{s} = 8.15 \cdot V \cdot \sqrt{DWT} \ \text{[kip, } V \text{ in ft/s, DWT in short tons]}

CR / SH — Creep and shrinkage AASHTO LRFD §5.4.2.3

Time-dependent volume changes in concrete. Critical for prestressed girders because they cause loss of prestress and long-term camber growth. Handled in detail in Chapter 9.

Concept checkpoint

For an interior girder of a straight 120-ft simple-span steel bridge in Baltimore County, rank the following demands from largest to smallest in Strength I:
(a) LL + IM    (b) DC    (c) DW    (d) BR    (e) WS.  Typical answer: LL+IM > DC > DW ≫ WS ~ BR. Strength I omits WS entirely.

3.2 — HL-93

The design vehicular live load

AASHTO LRFD §3.6.1.2

HL-93 is a notional loading — its combination of design truck and design lane load was calibrated by NCHRP Project 12-33 to envelope the force effects of a fleet of real heavy vehicles observed on U.S. bridges. The design engineer selects, for each response of interest:

  1. (design truck + design lane load), or
  2. (design tandem + design lane load),

whichever produces the larger force effect.

AASHTO HL-93 design vehicular live load: design truck (8+32+32 kip), design tandem (2x25 kip at 4 ft), and design lane load (0.64 klf over 10 ft)
Figure 3.2The three components of the AASHTO HL-93 notional live load. The engineer envelopes (truck + lane) vs. (tandem + lane) at each response point and selects the larger. Only the truck/tandem receive the dynamic load allowance IM — the lane load is applied without impact.

Design truck

3 axles: 8 kip + 32 kip + 32 kip. First spacing 14 ft. Variable rear spacing 14–30 ft — vary to maximize the effect.

Design tandem

2 axles of 25 kip at 4 ft. Controls short spans and short-loaded lengths.

Design lane load

0.64 klf uniformly distributed over a 10-ft-wide strip. No IM applied to the lane load.

AASHTO LRFD Bridge Design Specifications, 10th Edition, 2024

The governing document

All rules, factors, and combinations in this chapter derive from the AASHTO LRFD Bridge Design Specifications, 10th Edition (2024). Every equation cited with an AASHTO reference is verified against this edition. Older editions used different HL-93 load factors and IM values — always check the edition printed on the cover before using published examples.

AASHTO LRFD Reference

For NEGATIVE moment and reactions at interior supports of continuous spans, AASHTO LRFD §3.6.1.3.1 requires two design trucks × 0.90 + design lane load, with a minimum 50-ft clear between the rear axle of one truck and the lead axle of the next. Do not confuse this with the two-lane loading rule.

3.3 — Modifiers

Dynamic allowance and multiple-presence

AASHTO LRFD §3.6.1.1 / §3.6.2

The static HL-93 forces are amplified for dynamic vehicle–bridge interaction (bouncing, pothole strike, joint impact) using the dynamic load allowance IM, and reduced for the low likelihood that all traffic lanes are simultaneously loaded to maximum using the multiple-presence factor m.

(3.6.1.1-1)
  1. Formula

    LLdyn=(1+IM)LLstaticLL_{dyn} = (1 + IM) \cdot LL_{static}

    Applied to truck / tandem only

ComponentIMApplies to
Deck joints — all limit states75%Deck panel at expansion joint
Fatigue and fracture15%Truck only, fatigue limit state
All other components33%Truck / tandem, Strength & Service
Number of loaded lanesMultiple-presence factor mRationale
11.20Single lane loaded — one heavy truck likely to appear in its worst position
21.00Base case; HL-93 was calibrated at m = 1.00
30.85Low probability all three lanes simultaneously at maximum
≥40.65Very low probability all lanes simultaneously at maximum

A common student error

Multiple-presence m is not applied when fatigue is under consideration, and it is not applied when the empirical live-load distribution factor is used — those DFs already include m internally. Applying m twice is an easy way to overestimate demand by 20% on a single-lane bridge.

3.4 — Combinations

Which factors, in which state?

AASHTO LRFD §3.4.1 (Table 3.4.1-1)

AASHTO LRFD requires the engineer to check every relevant limit state — a boundary between acceptable and unacceptable performance. Each limit state is expressed as a linear combination of factored loads and compared to the corresponding factored resistance:

(1.3.2.1-1)
  1. ηiγiQiϕRn=Rr\sum \eta_{i} \gamma_{i} Q_{i} \le \phi R_{n} = R_{r}

    Total factored demand (left) must not exceed factored resistance (right).

Four limit states: Strength, Service, Fatigue, Extreme Event
Figure 3.3AASHTO LRFD divides bridge performance into four families of limit states. Each family answers a different question about the structure: Will it break? Will it work day to day? Will it accumulate damage? Will it survive a rare event?

The following table lists the most commonly used highway load factors from the AASHTO LRFD 10th Edition. Values shown are maximum load factors; minimum values (used when a load is favorable to the response) are noted where required.

ComboDCDWLL + IMBRWSTUPurpose
Strength I1.251.501.751.750.50Normal use, no wind
Strength II1.251.501.351.350.50Permit vehicles
Strength III1.251.501.000.50Bridge with wind > 55 mph, no live load
Strength V1.251.501.351.351.000.50Normal use with wind
Service I1.001.001.001.000.301.00 / 1.20Deflection, prestress compressive
Service II1.001.001.301.001.00 / 1.20Steel yield / bolt slip
Service III1.001.000.801.00 / 1.20PC tensile stresses
Fatigue I1.75Infinite-life fatigue
Fatigue II0.80Finite-life fatigue
Ext. Event I1.251.500.500.50Seismic
Ext. Event II1.251.500.500.50Ice, collision, vessel impact

Values are max factors; Service I TU shows force-effect / deformation split. Consult the current AASHTO LRFD table for the complete matrix including wave, ice, temperature-gradient, and vehicle-collision entries.

3.5 — Interactive activity

Position the HL-93 truck on an influence line

Manipulate the truck below to find the maximum moment and shear at any section on a 120-ft simply supported span. This is the same core operation the software performs when computing envelopes, and it should be routine before you trust any commercial output.

Influence line for moment at midspan of a simply supported beam with HL-93 truck positioned
Figure 3.4The influence line gives the moment (or shear, or reaction) at a fixed section due to a unit load at any position. To maximize moment, place the heaviest axles under the peak of the influence line; the total effect is Σ Pᵢ · yᵢ, where yᵢ is the ordinate under axle i.
Influence-Line Explorer — HL-93 Truck on a 120-ft Simply Supported Span

Drag the truck along the span and reposition the analysis section. AASHTO LRFD §3.6.1.2 — Design Vehicular Live Load

x = 60.0 ft8k32k32k0L = 120 ftη_max = 30.00 ft
30.00
14.00
0.50

Moment at x = 60.0 ft

2904.00

kip-ft (unfactored, per lane, IM not applied)

Truck axles1752.00
Design lane (0.64 klf)1152.00

Shear at x = 60.0 ft

-19.60

kip (unfactored, per lane, IM not applied)

Truck axles-29.20
Design lane (0.64 klf)9.60

How to use this

  1. Set the section (x/L) where you want the maximum effect.
  2. Slide the truck until the heaviest axles align under the peak ordinate.
  3. For shear at the end, sweep the truck toward the support; the lane load ordinate is largest just past the cut.
  4. Change the variable spacing (14 ft governs for most spans < 100 ft; 30 ft can govern for shear at far support on long spans).

3.6 — Calculator

HL-93 force-effect calculator

Use the interactive calculator to explore how span length, IM, number of loaded lanes, and multiple-presence factor combine into per-lane envelopes. The report at the bottom is exportable for your notes.

HL-93 Live-Load Effect — Simply Supported Span

Computes the maximum midspan moment and end shear from the HL-93 envelope. AASHTO LRFD §3.6.1.2 / §3.6.2

Max midspan moment

3656.4

kip-ft per design lane × factors

M = m · n · [(1+IM)·max(M_truck, M_tandem) + M_lane]
M_truck (per lane)
1883.0 kip-ft
M_tandem (per lane)
1450.3 kip-ft
M_lane (per lane)
1152.0 kip-ft
Governs
Design truck

Max end shear

119.3

kip per design lane × factors

V = m · n · [(1+IM)·max(V_truck, V_tandem) + V_lane]
V_truck (per lane)
60.80 kip
V_tandem (per lane)
49.17 kip
V_lane (per lane)
38.40 kip
Governs
Design truck
Mlane = w · L² / 8 Vlane = w · L / 2 w = 0.64 klf
(derived)
w
design lane load intensity [klf]
L
simply supported span length [ft]
IM
dynamic load allowance (33% typ.) [-]
m
multiple-presence factor [-]

Verification

Order-of-magnitude check: for L = 120 ft, the HL-93 envelope (per lane, per AASHTO tables) gives M ≈ 2,090 kip-ft (unfactored, no IM, no m). With IM = 1.33 and m = 1.00 the moment should approach ≈ 2,780 kip-ft plus lane contribution. Compare to the value returned above.

What can go wrong

This calculator idealizes a simply supported span. For continuous spans, use influence surfaces and apply the truck + lane combination for positive moment and two trucks (min. 50 ft between axles) × 0.90 + two lanes for negative moment AASHTO LRFD §3.6.1.3.1. Consult refined analysis for skew and curved bridges.

The calculator returns per-lane envelopes; you still need distribution factors (Chapter 4) to obtain girder-line demands.

3.7 — Worked example

Worked examples: from AASHTO tables to a designed girder line

Section 3.7 works two examples end-to-end. Example 1 is the classical AASHTO reinforced-concrete T-beam bridge — a short simple span where every step (section properties, HL-93 truck / tandem / lane loads, distribution factors, dead loads, Strength I combinations) can be done by hand. Example 2 scales the same workflow up to a three-span continuous steel plate-girder bridge used in Mid-Atlantic practice.

3.7 — Example 1

Reinforced-concrete T-beam bridge (L = 50 ft simple span)

Problem statement. A bridge is to be designed with a span length of L = 50 ft. The superstructure consists of five T-beams spaced at S = 10 ft with a cast-in-place reinforced-concrete deck slab of ts = 9 in. The overall width is 48 ft and the clear (roadway) width is 44 ft 6 in. Design the superstructure of the T-beam bridge using the specifications below. The three limit states considered are Strength I, Fatigue II, and Service I.

SymbolDescriptionValue
C&PCurb + parapet cross-section area3.37 ft²
EcModulus of elasticity of concrete4 × 10³ ksi
f′cSpecified compressive strength of concrete4.5 ksi
fyYield strength of epoxy-coated rebar60 ksi
wcUnit weight of concrete0.15 kcf
wFWSFuture wearing surface0.03 ksf
Cross-section of 5-girder T-beam bridge with 48 ft width and 10 ft spacing
Figure 3.7.1Elevation, section, and overhang geometry for the T-beam bridge example (5 beams @ 10 ft, 9-in deck, 48 ft out-to-out).

Roadmap for this example

We will (1) size the stem and deck, (2) compute section properties of the interior T-beam, (3) find the number of design lanes, (4) place the HS-20 truck and tandem for maximum moment and shear, (5) compute distribution factors, (6) compute dead loads, and (7) combine everything into Strength I demands for the interior and exterior girders.
1

Strength I factored load Q

The Strength I combination weights dead loads (DC, DW) and live loads (TL = truck, LN = lane) by AASHTO Tables 3.4.1-1 and 3.4.1-2. This is the equation every subsequent step feeds:

(Strength I)
  1. Q=1.25DC+1.50DW+1.75(TL+LN)Q = 1.25 \cdot DC + 1.50 \cdot DW + 1.75 \cdot (TL + LN)
2

Choose deck thickness and stem width

What we are doing: pick minimum trial dimensions that (a) satisfy AASHTO minimums for a T-beam serving as its own deck and (b) leave room for two layers of #11 bars in the stem.

  • Minimum deck thickness for a T-beam deck slab ≥ 7 in AASHTO LRFD §5.14.1.5.1a, §9.7.1.1. Try ts = 9 in.
  • Minimum web thickness = 8 in AASHTO LRFD Com. §5.14.1.5.1c.
  • Concrete cover for main epoxy-coated bars ≥ 1 in; use 1.5 in for main + stirrups AASHTO LRFD Tbl. 5.12.3-1.

Minimum stem width for four #11 bars in a single row with #4 stirrups and 2.0 in clear cover. Write the formula first, then substitute:

  1. Formula

    bmin=2(cover+dstirrup)+ndb+(n1)(1.5db)b_{min} = 2 \cdot (\text{cover} + d_{stirrup}) + n \cdot d_{b} + (n - 1) \cdot (1.5 \cdot d_{b})
  2. Substitute

    bmin=2(2.0+0.5)+4(1.41)+3(1.51.41)=5.0+5.64+6.34517 inb_{min} = 2 \cdot (2.0 + 0.5) + 4 \cdot (1.41) + 3 \cdot (1.5 \cdot 1.41) = 5.0 + 5.64 + 6.345 \approx 17\ \text{in}

    cover = 2.0 in, d_stirrup (#4) = 0.5 in, n = 4, d_b (#11) = 1.41 in

  3. Result

    bmin17 inb_{min} \approx 17\ \text{in}

Round up: try bw = 18 in.

T-beam stem cross-section showing 2.0 in cover, #4 stirrup, 4 #11 longitudinal bars with 1.5·d_b clear spacing
Figure 3.7.2aMinimum stem width — cover, #4 stirrup, 4 #11 bars in a single row, three 1.5·d_b clear spaces. All terms in the formula are labeled on the section.
3

Beam depth (including deck)

What we are doing: AASHTO Table 2.5.2.6.3-1 gives a minimum overall depth ratio for reinforced-concrete T-beams to control deflection without an explicit deflection check.

  1. hmin=0.070L=0.070(50 ft12 in/ft)=42 inh_{min} = 0.070 \cdot L = 0.070 \cdot (50\ \text{ft} \cdot 12\ \text{in/ft}) = 42\ \text{in}

Try h = 44 in (stem = 35 in + deck = 9 in).

4

Effective flange width

Why: shear-lag makes only a portion of the wide slab effective in compression at midspan. AASHTO gives simple limits AASHTO LRFD §4.6.2.6.1.

  • Interior beam: bi = S = 10 ft · 12 = 120 in
  • Exterior beam: be = ½·S + overhang = ½·(10 ft · 12) + (4 ft · 12) = 108 in
5

Interior T-beam section properties

Interior T-beam cross-section, 120 in flange x 9 in, 18 in x 35 in stem, centroid 31.4 in from bottom
Figure 3.7.2Interior T-beam section. Centroid measured 31.4 in from the extreme tension (bottom) fiber.

What we are doing: the moment demand from Strength I acts about the composite T-beam's centroid; we need ȳ, Ig, and S to size reinforcement in later chapters.

  1. Area

    A=(9)(120)+(35)(18)=1,710 in2A = (9)(120) + (35)(18) = 1{,}710\ \text{in}^2
  2. Centroid from bottom

    yˉt=(9120)(35+4.5)+(3518)(17.5)1,710=31.4 in\bar{y}_{t} = \frac{(9 \cdot 120)(35 + 4.5) + (35 \cdot 18)(17.5)}{1{,}710} = 31.4\ \text{in}

    Parallel-axis theorem numerator ÷ total area

  3. Moment of inertia about the centroid

    Ig=1209312+(1209)(12.54.5)2+1835312+(1835)(31.417.5)2=264,183.6 in4I_{g} = \frac{120 \cdot 9^{3}}{12} + (120 \cdot 9)(12.5 - 4.5)^{2} + \frac{18 \cdot 35^{3}}{12} + (18 \cdot 35)(31.4 - 17.5)^{2} = 264{,}183.6\ \text{in}^4
  4. Section modulus

    S=Ig/yˉt=264,183.6/31.4=8,413.5 in3S = I_{g} / \bar{y}_{t} = 264{,}183.6 / 31.4 = 8{,}413.5\ \text{in}^3
6

Number of design lanes

What we are doing: the number of loaded lanes controls the multiple-presence factor and how many trucks we must place side-by-side.

  1. NL=w/12=44.5/12=3.7=3 lanesN_{L} = \lfloor w / 12 \rfloor = \lfloor 44.5 / 12 \rfloor = \lfloor 3.7 \rfloor = 3\ \text{lanes}
7

Truck and tandem live-load effects per lane

What we are doing: maximum simple-span moment under HS-20 occurs with the center 32-kip axle at midspan (Barré's theorem gives the same result within rounding for the 14-14 spacing). We take moments about the right support to get the reaction, then compute midspan moment. Simple-beam influence-line ordinates at the load positions give shears.

Formula (midspan moment from statics). Sum axle contributions using the influence-line ordinate at midspan, ηi = min(xi, L − xi)·½:

  1. Formula

    MC=Piηi(xi) where ηi=ai(Lai)/LM_{C} = \sum P_{i} \cdot \eta_{i}(x_{i}) \ \text{where} \ \eta_{i} = a_{i} \cdot (L - a_{i}) / L
  2. Substitute HS-20 truck

    Mtr=32(12.5+5.5)+8(5.5)=576+44=620 k-ftM_{tr} = 32 \cdot (12.5 + 5.5) + 8 \cdot (5.5) = 576 + 44 = 620\ \text{k-ft}

    Center 32-k axle at midspan; arms a₁ = 5.5 ft (8-k), a₂ = 19.5 ft (center 32-k), a₃ = 33.5 ft (rear 32-k)

  3. Substitute HS-20 tandem

    Mtandem=25(12.5+10.5)=575 k-ftM_{tandem} = 25 \cdot (12.5 + 10.5) = 575\ \text{k-ft}

    Two 25-k axles at 4 ft, centered at midspan

Free-body diagram of 50 ft simple span with 8-32-32 kip axles at 14-14 ft spacing, center 32-kip axle at midspan, moment arms to right support labeled
Figure 3.7.3HS-20 truck positioned for maximum midspan moment on L = 50 ft. Distances a₁, a₂, a₃ are the moment arms of each axle about the right support B — read them straight off the FBD.

Formula (shear at left support). Using the shear influence line ηV(x) = (L − x)/L for loads to the right of the support:

  1. Formula

    VA=PiηV(xi)=Pi(Lxi)/LV_{A} = \sum P_{i} \cdot \eta_{V}(x_{i}) = \sum P_{i} \cdot (L - x_{i}) / L
  2. Substitute truck at support

    Vtr=32(1.00)+32(0.72)+8(0.44)=32+23.04+3.5258.6 kipsV_{tr} = 32 \cdot (1.00) + 32 \cdot (0.72) + 8 \cdot (0.44) = 32 + 23.04 + 3.52 \approx 58.6\ \text{kips}

    Lead 32-k axle at A, so η values are 1.00, 0.72, 0.44

  3. Substitute tandem straddling the support

    Vtandem=25(1.00+0.92)=48 kipsV_{tandem} = 25 \cdot (1.00 + 0.92) = 48\ \text{kips}

    η = 1.00, 0.92

Shear influence line for a simply supported beam showing triangular diagram with ordinate 1.0 at the support and 0 at the far end
Figure 3.7.3bShear influence line at the left support A for a simply supported span: η(x) = (L − x)/L. Ordinates at each axle position are read directly off the triangle.
8

Lane load effects per lane

What we are doing: AASHTO's 0.64 klf design lane load carries no IM; use standard uniformly-loaded simple-beam formulas.

  1. Mln=wL2/8=(0.64)(50)2/8=200 k-ftM_{ln} = w \cdot L^{2} / 8 = (0.64)(50)^{2} / 8 = 200\ \text{k-ft}
  2. Vln=wL/2=(0.64)(50)/2=16 kipsV_{ln} = w \cdot L / 2 = (0.64)(50) / 2 = 16\ \text{kips}
9

Distribution factors for moment (DFM)

Why: the truck sits on one lane, but its load spreads to several girders. AASHTO Table 4.6.2.2.2b-1 gives closed-form DFMs for cast-in-place T-beam decks (deck type "e"). Applicability checks: 3.5 ≤ S = 10 ≤ 16 ft, 4.5 ≤ ts = 9 ≤ 12 in, 20 ≤ L = 50 ≤ 240 ft, Nb = 5 ≥ 4. ✓

Longitudinal stiffness parameter (n = 1 for monolithic T-beam):

(4.6.2.2.1-1)
  1. Longitudinal stiffness parameter

    Istem=(18353)/12=64,312.5 in4, eg=17.5+4.5=22 inI_{stem} = (18 \cdot 35^{3})/12 = 64{,}312.5\ \text{in}^4, \ e_{g} = 17.5 + 4.5 = 22\ \text{in}
  2. Kg=n[I+Aeg2]=1[64,312.5+1,710222]=891,953 in4K_{g} = n \cdot [I + A \cdot e_{g}^{2}] = 1 \cdot [64{,}312.5 + 1{,}710 \cdot 22^{2}] = 891{,}953\ \text{in}^4
  3. [Kg/(12Lts3)]0.1=1.05[K_{g} / (12 \cdot L \cdot t_{s}^{3})]^{0.1} = 1.05
  4. Interior beam — one lane loaded

    DFMsi=0.06+(S/14)0.4(S/L)0.3[Kg/(12Lts3)]0.1=0.06+(10/14)0.4(10/50)0.3(1.05)=0.629 lane/girderDFM_{si} = 0.06 + (S/14)^{0.4} \cdot (S/L)^{0.3} \cdot [K_{g}/(12Lt_{s}^{3})]^{0.1} = 0.06 + (10/14)^{0.4} \cdot (10/50)^{0.3} \cdot (1.05) = 0.629\ \text{lane/girder}
  5. Interior beam — two or more lanes loaded

    DFMmi=0.075+(S/9.5)0.6(S/L)0.2[Kg/(12Lts3)]0.1=0.075+(10/9.5)0.6(10/50)0.2(1.05)=0.859 lane/girderDFM_{mi} = 0.075 + (S/9.5)^{0.6} \cdot (S/L)^{0.2} \cdot [K_{g}/(12Lt_{s}^{3})]^{0.1} = 0.075 + (10/9.5)^{0.6} \cdot (10/50)^{0.2} \cdot (1.05) = 0.859\ \text{lane/girder}

    Governs interior

Exterior beam — one lane loaded (lever rule). Treat the deck strip as simply supported between the exterior girder and the first interior girder. Multiple-presence m = 1.20 applies with the lever rule.

Formula. Sum moments about the interior girder support (ΣM = 0), then apply m:

  1. Formula

    Mint=0: RS+(P/2)a1+(P/2)a2=0  R=(P/2)(a1+a2)/S\sum M_{int} = 0: \ -R \cdot S + (P/2) \cdot a_{1} + (P/2) \cdot a_{2} = 0 \ \Rightarrow \ R = (P/2) \cdot (a_{1} + a_{2}) / S
  2. DFMse=m(R/P)DFM_{se} = m \cdot (R / P)
  3. Substitute

    R=(P/2)(10.25+4.25)/10=0.725PR = (P/2) \cdot (10.25 + 4.25) / 10 = 0.725 \cdot P

    S = 10 ft, a₁ = 10.25 ft, a₂ = 4.25 ft, m = 1.20

  4. DFMse=1.200.725=0.87 lane/girderDFM_{se} = 1.20 \cdot 0.725 = 0.87\ \text{lane/girder}

    Governs exterior

Free-body diagram of deck strip between exterior and first interior girder, with two P/2 wheel loads and reaction R at the exterior support
Figure 3.7.4Lever-rule FBD: the deck strip between the exterior and first interior girder is treated as a simply supported beam. Wheel loads P/2 act at their transverse positions; R at the exterior support is the fraction of one lane assigned to the exterior girder.

Exterior beam — two or more lanes (e-factor on interior DF):

  1. de=2.25 ft (within1.0de5.5)d_{e} = 2.25\ \text{ft} \ (\text{within} -1.0 \le d_{e} \le 5.5)
  2. e=0.77+de/9.1=0.77+2.25/9.1=1.017  use e=1.0e = 0.77 + d_{e}/9.1 = 0.77 + 2.25/9.1 = 1.017 \ \rightarrow \ \text{use}\ e = 1.0
  3. DFMme=meDFMmi=0.851.00.859=0.730 lane/girderDFM_{me} = m \cdot e \cdot DFM_{mi} = 0.85 \cdot 1.0 \cdot 0.859 = 0.730\ \text{lane/girder}
10

Distributed live-load moments per beam

What we are doing: multiply the per-lane truck/tandem/lane moment by the governing DFM. Apply IM = 33% to truck/tandem onlyAASHTO LRFD Tbl. 3.6.2.1-1.

BeamMTL (truck) [kip-ft]MLN (lane) [kip-ft]
Interior (DFM = 0.859)620·0.859·1.33 = 708.33200·0.859 = 171.8
Exterior (DFM = 0.87)620·0.87·1.33 = 717.40200·0.87 = 174.0
11

Distribution factors for shear (DFV) and shears per beam

What we are doing: shear DFs come from a different AASHTO table (AASHTO LRFD §4.6.2.2.3). Shear DFs do not include a Kgterm — the response is more local.

  1. DFVsi=0.36+S/25=0.36+10/25=0.76DFV_{si} = 0.36 + S/25 = 0.36 + 10/25 = 0.76
  2. DFVmi=0.2+S/12(S/35)2=0.2+10/12(10/35)2=0.95DFV_{mi} = 0.2 + S/12 - (S/35)^{2} = 0.2 + 10/12 - (10/35)^{2} = 0.95

    Governs interior

  3. DFVse=DFMse=0.87DFV_{se} = DFM_{se} = 0.87

    Governs exterior, lever

  4. DFVme=meDFVmi, e=0.6+de/10=0.825DFV_{me} = m \cdot e \cdot DFV_{mi}, \ e = 0.6 + d_{e}/10 = 0.825
  5. DFVme=1.00.8250.95=0.784DFV_{me} = 1.0 \cdot 0.825 \cdot 0.95 = 0.784
BeamVTL [kips]VLN [kips]
Interior (DFV = 0.95)58.6·0.95·1.33 = 74.0416·0.95 = 15.2
Exterior (DFV = 0.87)58.6·0.87·1.33 = 67.8016·0.87 = 13.92
12

Dead-load force effects

What we are doing: the T-beam stem, deck flange, and curb-and-parapet are part of the section → DC. The 2-in future overlay is not → DW. Distribute both as uniform loads and apply wL/2 and wL²/8.

Interior beam (self-weight includes full effective flange):

  1. DCT-beam=1,710 in2(1 ft2/144 in2)0.15 kcf=1.78 klfDC_{T\text{-}beam} = 1{,}710\ \text{in}^2 \cdot (1\ \text{ft}^2/144\ \text{in}^2) \cdot 0.15\ \text{kcf} = 1.78\ \text{klf}
  2. DCC&P=2(3.37 ft2)(0.15 kcf)(1/5 beams)=0.202 klfDC_{C\&P} = 2 \cdot (3.37\ \text{ft}^2) \cdot (0.15\ \text{kcf}) \cdot (1/5\ \text{beams}) = 0.202\ \text{klf}
  3. wDC=1.78+0.202=1.98 klfw_{DC} = 1.78 + 0.202 = 1.98\ \text{klf}
  4. wDW=0.03 ksf10 ft=0.30 klfw_{DW} = 0.03\ \text{ksf} \cdot 10\ \text{ft} = 0.30\ \text{klf}
  5. VDC=wL/2=1.9850/2=49.5 kipsV_{DC} = wL/2 = 1.98 \cdot 50/2 = 49.5\ \text{kips}
  6. MDC=wL2/8=1.98502/8=618.75 k-ftM_{DC} = wL^{2}/8 = 1.98 \cdot 50^{2}/8 = 618.75\ \text{k-ft}
  7. VDW=0.3050/2=7.5 kipsV_{DW} = 0.30 \cdot 50/2 = 7.5\ \text{kips}
  8. MDW=0.30502/8=93.75 k-ftM_{DW} = 0.30 \cdot 50^{2}/8 = 93.75\ \text{k-ft}

Exterior beam — deck slab + FWS reactions come from statics on the overhang. Deck-slab pressure: ws = (9/12)·0.15 = 0.113 ksf; FWS: 0.03 ksf; total 0.143 ksf. Taking moments about the first interior support gives RA = 1.31 klf (deck + FWS combined). Splitting proportionally:

  1. DCdeckext=1.31(0.113/0.143)=1.04 klfDC_{deck}|_{ext} = 1.31 \cdot (0.113/0.143) = 1.04\ \text{klf}
  2. DCC&P,ext=0.728 klfDC_{C\&P,ext} = 0.728\ \text{klf}

    From overhang statics on 0.51 klf line load

  3. DCstem,ext=630/1440.15=0.656 klfDC_{stem,ext} = 630/144 \cdot 0.15 = 0.656\ \text{klf}
  4. wDC,ext=1.04+0.728+0.656=2.42 klfw_{DC,ext} = 1.04 + 0.728 + 0.656 = 2.42\ \text{klf}
  5. wDW,ext=1.31(0.03/0.143)=0.27 klfw_{DW,ext} = 1.31 \cdot (0.03/0.143) = 0.27\ \text{klf}
  6. MDC,ext=2.42502/8=756.3 k-ft, VDC,ext=60.5 kipsM_{DC,ext} = 2.42 \cdot 50^{2}/8 = 756.3\ \text{k-ft}, \ V_{DC,ext} = 60.5\ \text{kips}
  7. MDW,ext=0.27502/8=84.4 k-ft, VDW,ext=6.75 kipsM_{DW,ext} = 0.27 \cdot 50^{2}/8 = 84.4\ \text{k-ft}, \ V_{DW,ext} = 6.75\ \text{kips}
13

Assemble Strength I demands and identify controls

What we are doing: plug the unfactored effects into Q = 1.25·DC + 1.50·DW + 1.75·(TL + LN) and compare interior vs. exterior girders to identify the governing case that Chapter 8 (flexure) and Chapter 6 (shear) must resist.

EffectInterior beamExterior beam
MDC618.75756.3
MDW93.7584.4
MTL708.33717.4
MLN171.8174.0
VDC49.560.5
VDW7.56.75
VTL74.0467.8
VLN15.213.92

All moments in kip-ft; shears in kips.

  1. Mu,int=1.25(618.75)+1.50(93.75)+1.75(708.33+171.8)=2,454.3 k-ftM_{u,int} = 1.25(618.75) + 1.50(93.75) + 1.75(708.33 + 171.8) = 2{,}454.3\ \text{k-ft}
  2. Vu,int=1.25(49.5)+1.50(7.5)+1.75(74.04+15.2)=229.2 kipsV_{u,int} = 1.25(49.5) + 1.50(7.5) + 1.75(74.04 + 15.2) = 229.2\ \text{kips}

    Controls shear

  3. Mu,ext=1.25(756.3)+1.50(84.4)+1.75(717.4+174.0)=2,631.9 k-ftM_{u,ext} = 1.25(756.3) + 1.50(84.4) + 1.75(717.4 + 174.0) = 2{,}631.9\ \text{k-ft}

    Controls moment

  4. Vu,ext=1.25(60.5)+1.50(6.75)+1.75(67.8+13.92)=228.8 kipsV_{u,ext} = 1.25(60.5) + 1.50(6.75) + 1.75(67.8 + 13.92) = 228.8\ \text{kips}

Governing demands hand off to design

Exterior girder moment (2,631.9 kip-ft) and interior girder shear (229.2 kips) control. These are the numbers you carry into flexural-reinforcement design (Chapter 8) and stirrup design (Chapter 6). Compression reinforcement is neglected in the flexural sizing.

3.7 — Example 2

Three-span Maryland highway bridge (90-120-90 ft): loads & combinations

This example uses a representative Mid-Atlantic bridge configured to reflect typical MDOT SHA practice. It follows the same 13-step calculation format used in Example 1.

1

Interpret the problem

Determine the unfactored and factored dead-load, live-load, and secondary force effects for an interior steel plate-girder line in the 120-ft center span of a three-span continuous highway bridge. Result feeds the Strength I, Service II, and Fatigue I combinations required for Chapter 8 girder design.

2

Draw the structural system

Plan, elevation, and cross-section of the three-span continuous steel plate-girder bridge
Figure 3.5Plan, elevation, and cross-section of the analyzed bridge. Six steel plate girders at 10-ft spacing carry a 9-in reinforced-concrete deck over spans of 90-120-90 ft with a 20° skew. All dimensions used in the calculations below are shown.
West Abut.Pier 1Pier 2East Abut.90'-0"Span 1120'-0" (CENTER — analyzed)Span 290'-0"Span 30.4·L (analyzed section)Cross-section: 6 girders @ 10'-0", 9" deck, 48'-0" roadway, 20° skewG1G2G3G4G5G6
Figure 3.6 — Schematic elevation with analyzed 0.4·L section marked (orange). See Figure 3.5 above for the full dimensioned plan, elevation, and cross-section.
3

Declare known information

Structure3 continuous steel plate girders, spans 90-120-90 ft
Deck width60 ft out-to-out; 48 ft roadway (4 lanes @ 12 ft)
Girders6 girder lines, spaced S = 10 ft, exterior overhang = 2.5 ft
Skew20°
Deck slab9-in cast-in-place reinforced concrete, γc = 150 pcf
Barrier36-in F-shape concrete, 0.42 klf per barrier
Future wearing surface2-in bituminous overlay, 0.025 ksf per MDOT SHA
Utilities3-in ductile-iron waterline on fascia, 0.08 klf on one exterior girder
Steel girder self-weight0.35 klf (est., interior girder)
Stay-in-place forms0.015 ksf between girders
Live loadHL-93 per AASHTO LRFD §3.6.1.2, IM = 33% (Strength/Service)
4

Declare required results

  • Unfactored DC and DW moments at the 0.4·L point of the 120-ft center span (interior girder).
  • Unfactored HL-93 LL + IM moment envelope in the center span (per lane).
  • Distribution factor for one design lane loaded (interior girder, moment).
  • Strength I, Service II, and Fatigue I demand moments at the 0.4·L point.
5

Identify governing provisions

  • AASHTO LRFD §3.3.2load notation
  • AASHTO LRFD §3.5.1permanent loads DC/DW
  • AASHTO LRFD §3.6.1.2HL-93
  • AASHTO LRFD §3.6.1.3.1continuous-span rules
  • AASHTO LRFD §3.6.2.1IM = 33% for Strength/Service, 15% for Fatigue
  • AASHTO LRFD §4.6.2.2.2blive-load distribution factor for moment
  • AASHTO LRFD §3.4.1 Table 3.4.1-1load combinations
6

State assumptions

  • Composite behavior in positive-moment regions after deck cures.
  • Beam-line analysis is adequate for preliminary demand estimation (§4.6.2.1).
  • Skew ≤ 20° — no distribution-factor skew correction required for interior girder moment (§4.6.2.2.2e-Table 1).
  • Utilities lumped on one exterior girder; other exterior carries none. Interior girders unaffected.
  • Stay-in-place forms treated as DC (non-composite steel-only stage) per MDOT SHA.
7

Write the governing equations

  1. wdeck=γctsSw_{deck} = \gamma_{c} \cdot t_{s} \cdot S

    Interior girder, per unit length

  2. wbarrier=0.42 klf/6 girdersw_{barrier} = 0.42\ \text{klf} / 6\ \text{girders}

    Evenly distributed, MDOT SHA

  3. wFWS=0.025 ksfSw_{FWS} = 0.025\ \text{ksf} \cdot S

    Interior girder DW

  4. wSIP=0.015 ksfSw_{SIP} = 0.015\ \text{ksf} \cdot S

    Stay-in-place forms, DC non-composite

  5. wgirder=0.35 klfw_{girder} = 0.35\ \text{klf}

    Self-weight

(AASHTO LRFD 4.6.2.2.2b-1)
  1. DFint=0.06+(S/14)0.4(S/L)0.3[Kg/(12Lts3)]0.1DF_{int} = 0.06 + (S/14)^{0.4} \cdot (S/L)^{0.3} \cdot [K_{g} / (12 \cdot L \cdot t_{s}^{3})]^{0.1}
S — girder spacing [ft]
L — span length, 120 [ft]
Kg — longitudinal stiffness parameter [in⁴]
ts — deck thickness [in]
8

Substitute values (dead loads)

w_deck(150 pcf) · (9/12 ft) · (10 ft) = 1.125 klf
w_barrier per girder(2 × 0.42) / 6 = 0.140 klf
w_FWS0.025 ksf · 10 ft = 0.250 klf
w_SIP0.015 ksf · 10 ft = 0.150 klf
w_girder0.35 klf
Σ DC (interior)w_deck + w_barrier + w_SIP + w_girder = 1.125 + 0.140 + 0.150 + 0.35 = 1.765 klf
DW0.250 klf
9

Calculate dead-load moments at 0.4·L (center span)

For a continuous three-span beam with uniform load and span ratio 90:120:90, the moment at the 0.4·L point in the center span from a uniform load w on all spans is well approximated (from three-moment analysis) by:

(approx.)
  1. M0.4L,unif0.083wL2M_{0.4L,unif} \approx 0.083 \cdot w \cdot L^{2}

    Interior span, all-spans loaded

M_DC0.083 · 1.765 · (120)² = 0.083 · 1.765 · 14,400 ≈ 2,110 kip-ft
M_DW0.083 · 0.250 · (120)² ≈ 299 kip-ft

What can go wrong

For final design, replace the 0.083 coefficient with the value from your continuous-beam influence-line integration or FE model — the coefficient depends on span-length ratios and support conditions. This step matches the accuracy needed for preliminary sizing.
10

Compute HL-93 LL + IM in the center span (per lane)

For positive moment in the center span, place one design truck in the center span with lane load also in the center span (§3.6.1.3.1). A direct calculation using the 120-ft simply supported equivalent (upper bound; refined continuous analysis is slightly lower) gives:

Truck M (unfactored, simply supported)≈ 1,861 kip-ft
Tandem M (unfactored, simply supported)≈ 1,462 kip-ft
Lane M = 0.64 · 120² / 8= 1,152 kip-ft
Envelope per lane (with IM = 33%)1.33 · 1861 + 1152 = 3,627 kip-ft

Design check

Verification: for a 120-ft simple span, AASHTO's tabulated per-lane HL-93 total moment is ≈ 3,620 kip-ft (rounded). Our envelope of 3,627 kip-ft matches within ~0.2% — a strong sanity check on the calculator behind this example.
11

Distribution factor for interior girder (moment)

Compute Kg (longitudinal stiffness parameter) from the composite section. For this example, using representative non-composite steel-girder properties (Isteel = 47,000 in⁴, A = 68 in², eg = 34 in from girder N.A. to deck centroid, deck n = 8):

  1. Formula

    Kg=n(I+Aeg2)K_{g} = n \cdot (I + A \cdot e_{g}^{2})
  2. Substitute

    Kg=8(47,000+68342)=8(47,000+78,608)1.00×106 in4K_{g} = 8 \cdot (47{,}000 + 68 \cdot 34^{2}) = 8 \cdot (47{,}000 + 78{,}608) \approx 1.00 \times 10^{6}\ \text{in}^4
(S/14)^0.4(10/14)^0.4 = 0.878
(S/L)^0.3(10/120)^0.3 = 0.469
[Kg / (12·L·ts³)]^0.1[1.0e6 / (12·120·9³)]^0.1 = [1.0e6 / 104,976]^0.1 = 9.526^0.1 = 1.253
DF (one lane)0.06 + 0.878 · 0.469 · 1.253 = 0.06 + 0.516 = 0.576

For two design lanes loaded, DF = 0.075 + (S/9.5)^0.6 · (S/L)^0.2 · [Kg/(12·L·ts³)]^0.1 ≈ 0.755. Two-lane DF typically governs interior girders — use the larger.

12

Assemble Strength I, Service II, Fatigue I demands (interior girder, 0.4·L)

  1. MLL+IM,girder=DF2-lanem[envelope per lane]M_{LL+IM,girder} = DF_{2\text{-}lane} \cdot m \cdot [\text{envelope per lane}]
  2. MLL+IM,girder=0.7551.003,6272,738 k-ftM_{LL+IM,girder} = 0.755 \cdot 1.00 \cdot 3{,}627 \approx 2{,}738\ \text{k-ft}
CombinationExpressionValue (kip-ft)
Strength I1.25·MDC + 1.50·MDW + 1.75·MLL+IM1.25·2110 + 1.50·299 + 1.75·2738 = 2637 + 448 + 4791 = 7,876
Service II (steel)1.00·MDC + 1.00·MDW + 1.30·MLL+IM2110 + 299 + 1.30·2738 = 2110 + 299 + 3559 = 5,968
Fatigue I (LL only)1.75 · (1.15 · truck at 30-ft rear spacing, DF for fatigue, per lane, m=1.0)1,470 (see Chapter 17 for full derivation)
13

Independent verification and final summary

  • Order-of-magnitude: A 120-ft continuous steel-girder span at typical demand ratios has M_Str-I ~ 6,500 – 9,000 kip-ft per interior girder — our 7,876 kip-ft sits mid-range. ✓
  • Unit check: All moments in kip-ft; distribution factor dimensionless. ✓
  • Envelope check: Strength I > Service II — as expected for a 1.75 vs. 1.30 LL factor combined with the same DC/DW. ✓
  • Sensitivity: Increasing S from 10 to 11 ft raises DF to ≈ 0.82 and M_LL+IM (girder) to ≈ 2,980 kip-ft, raising Strength I demand to ≈ 8,300 kip-ft (+5.4%). Girder spacing is a strong lever.

Final design summary — interior girder, 0.4·L, 120-ft center span

MDC
2,110 kip-ft
MDW
299 kip-ft
MLL+IM (per lane env.)
3,627 kip-ft
DF (2-lane)
0.755
MLL+IM (girder)
2,738 kip-ft
Strength I
7,876 kip-ft
Service II
5,968 kip-ft
Fatigue I (LL only)
≈ 1,470 kip-ft

Design status

These are demands only. Chapter 8 develops the composite steel-girder resistance model and completes the φ·R_n side of the LRFD inequality. Do not size a girder from demands alone.

3.8 — Design challenge

T-beam bridge — full load & section-property workup

Apply everything from Chapter 3 (and the pre-lecture on section properties) to the simply-supported reinforced-concrete T-beam bridge shown below. Produce a complete hand-calculation package and upload it at the bottom of this section.

T-beam bridge cross section (Figure 2.16) and T-beam section (Figure 2.17)
Fig. 3.CH-1Cross section and interior T-beam geometry. Roadway 44 ft 6 in, 5 stems @ 10 ft, 4 ft overhangs, ts = 9 in, stem 18 in × 35 in below deck, 12 #11 bars (As = 18.75 in²), #4 stirrups @ 6.5 in, 2 ft 8 in parapet.
Design data for the T-beam bridge challenge
Fig. 3.CH-2Design data: L = 50 ft, s = 10 ft, f'c = 4.5 ksi, fy = 60 ksi, DW = 0.030 ksf (future wearing surface), ADTT = 1900, skew = 0°, year built 1960.

Deliverables — compute and report for BOTH an interior and an exterior girder

  1. Section properties — for both the non-composite stem (bare RC T-beam before deck-slab hardens is not relevant here since this is cast-monolithic RC; still report the stem-only section as reference) and the composite T-section with effective flange width beff per AASHTO 4.6.2.6:
    • Positive-moment region (midspan): untransformed composite section — full deck in compression. Report beff, neutral-axis depth yb, gross moment of inertia Ig, and section moduli Stop and Sbot.
    • Negative-moment region: since the bridge is simply supported, there is no continuous negative-moment region. If instead the two 50-ft spans were made continuous, deck concrete cracks — the effective section is the stem plus the longitudinal deck reinforcement inside beff. Report the cracked-transformed Icr and ycr for that hypothetical continuous case (state your assumed As,deck).
    • For steel-composite thinking (short- vs. long-term), state the modular ratio n = Es/Ec and 3n for long-term (creep), and briefly explain why the RC T-beam here uses a single n (all concrete).
  2. Permanent loads — compute per linear foot of one girder:
    • DC1 — self-weight of the girder stem and the tributary deck slab (both cast monolithically, γc = 0.150 kcf). Show the tributary width you used for interior vs. exterior girders.
    • DC2 — barriers/parapets (γc·A_parapet, 2 ft 8 in tall). Distribute equally to all girders per AASHTO 4.6.2.2.1 and comment on the exterior-girder exception.
    • DW — future wearing surface (0.030 ksf) over the 44 ft 6 in roadway, distributed to the appropriate girders.
    • SIP formwork and steel cross-frames — state whether they apply here (cast-in-place RC deck, no steel diaphragms) and justify.

Note: live-load distribution factors, per-lane HL-93 moment/shear envelopes, and per-girder MLL+IM / VLL+IM are analysisoutputs and have been migrated to the Chapter 4 design challenge (§4.7). Complete the Ch 3 items here — section properties and permanent loads — and use them as inputs to the Ch 4 challenge.

What to hand in

A single PDF (or scanned neat handwriting) containing: (a) a cross-section sketch with your assumed tributary widths marked, (b) all section-property tables, (c) each load computed formula-first (symbolic → substitution → result), (d) a summary table with DC1, DC2, DW, MLL+IM, VLL+IM for the interior and exterior girders. Cite AASHTO section numbers for every equation you use. Upload below.

Submit your design challenge

Chapter 3 challenge — T-beam bridge: section properties, DC1, DC2, DW, distribution factors, live-load M & V

You must be signed in to upload a submission.

Sign in →

3.9 — Graded quiz

Chapter 3 assessment (20 questions)

Twenty questions covering load categories, HL-93, IM, m, combinations, influence-line placement, and the worked example. Your attempt is recorded to your student progress.

Start Chapter 3 quiz →

Chapter summary

Key takeaways

  • HL-93 = (design truck OR tandem) + design lane load. IM applies only to the truck/tandem.
  • Multiple-presence m = 1.20, 1.00, 0.85, 0.65 for 1, 2, 3, ≥4 loaded lanes.
  • Strength I governs most normal traffic; Strength II governs permit vehicles (MDOT SHA).
  • Negative moment at interior supports uses the two-truck × 0.90 rule.
  • Always identify governing combination BEFORE selecting member sizes.

Section 1

Concept Demonstrations

Instructor-led walkthroughs of core ideas. Read these first — every worked example that follows builds on them.

Demo 1

Estimating the dead load of a reinforced concrete deck

Convert a deck geometry + unit weight into a distributed DC load carried by each girder.

§3.5.1
Table 3.5.1-1

An 8-in normal-weight concrete deck spans between girders spaced at S = 8 ft. Using γc = 0.150 kcf (0.145 kcf plain + 0.005 kcf allowance for reinforcement per AASHTO Table 3.5.1-1):

wdeck = γc · t · S = 0.150 · (8/12) · 8 = 0.800 klf per interior girder.

This is the DC1 contribution (deck acting on the non-composite girder). Add a barrier of 0.320 klf split equally to the two fascia girders, and a haunch of 0.010 klf. Note we did not apply a load factor — DC and DW are computed as unfactored demands here; γDC = 1.25 (Strength I max) is applied at the combination step.

Demo 2

Reading the HL-93 truck: which axle governs shear vs. moment?

The 32-kip axle drives shear near supports; the 32-32 pair drives midspan moment.

§3.6.1.2.2

Place the HL-93 truck (8-32-32 kip, first spacing 14 ft, rear variable 14–30 ft) on a simple span. For maximum shear at the left support, the heaviest axle sits directly over the support; the influence-line ordinate is 1.0.

For maximum moment at midspan, position the truck so the load's resultant and the closest axle straddle midspan by equal amounts (Barré's theorem). On most simple spans of 40–90 ft, the two 32-kip axles at 14-ft spacing govern; on very short spans the design tandem (2 × 25 kip at 4 ft) usually controls instead.

Demo 3

Applying IM and multiple-presence — the correct order of operations

IM amplifies the truck/tandem only. m modifies the sum of live-load effects across loaded lanes.

§3.6.1.1.2
§3.6.2.1

Compute the raw static effect of truck (or tandem) and lane separately. Apply IM = 33% (Strength/Service) to the truck/tandem only. Combine the amplified truck with the lane load. Then, if two lanes are simultaneously loaded, multiply the two-lane result by m = 1.00; one-lane loading uses m = 1.20; three lanes m = 0.85.

LL+IM (per lane) = 1.33 · (truck or tandem) + 1.00 · (0.64 klf lane load)

IM is never applied to the lane load or to pedestrian, wind, or thermal loads.

Demo 4

Selecting the governing Strength combination

Strength I dominates highway girders; Strength III/V come in only when wind is significant.

Table 3.4.1-1

For a typical highway girder in the Mid-Atlantic, Strength I:

η · [1.25·DC + 1.50·DW + 1.75·(LL+IM) + 1.00·(WA + FR) + 0.50·TU]

controls positive and negative moment envelopes 95% of the time. Strength III (wind without LL) and Strength V (wind with LL at 55 mph reference) become relevant only for tall piers, long-span steel plate girders, or superstructures with high W/D. Extreme Event I (EQ) and Extreme Event II (CT/CV/IC) always accompany a Strength I check — never as the sole envelope.

Section 2

Fully Worked Examples

Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.

Worked Example 1

Dead load of a composite steel-girder deck section
Basic

Problem

Compute unfactored DC1 (deck + girder + haunch), DC2 (barriers), and DW (future 2 in. of asphalt overlay) in klf on the interior girder.

Step-by-Step

w = 0.150 · (8/12) · 8 = 0.800 klf

Result

0.800 klf

W36×150 = 0.150 klf.

Result

0.150 klf

Design Verification

Total unfactored dead load on the interior girder: 0.97 + 0.128 + 0.187 ≈ 1.29 klf. Compare against DC + DW ≈ 1.3 klf typical for this bridge type (spot check passes).

Discussion

DC and DW are separated because DW carries a larger max factor (1.50 vs 1.25). MDOT SHA also requires a minimum DW of 0.025 ksf even when no overlay is planned, to hedge against 75-year rehabilitation cycles.

Worked Example 2

HL-93 lane-load moment on a simple span
Basic

Problem

Compute M_L/2 and M_L/4 from a uniform 0.64 klf lane load, per lane.

Step-by-Step

M = wL²/8 = 0.64·90²/8 = 648 k·ft

Result

648 k·ft

M = wx(L−x)/2 = 0.64·22.5·67.5/2 = 486 k·ft

Result

486 k·ft

Design Verification

M_L/4 / M_L/2 = 486/648 = 0.75, matches parabolic UDL moment ratio (3/4). ✓

Discussion

The lane load contributes typically 30–45% of the total LL+IM moment on medium spans; the truck governs the rest.

Worked Example 3

HL-93 design truck: maximum midspan moment on a 90-ft simple span
Intermediate

Problem

Find the truck position for maximum M at midspan, compute M_truck (no IM), then apply IM = 33%.

Step-by-Step

R = 72 kip. Distance of R from lead 8-kip axle: x̄ = (32·14 + 32·28)/72 = 18.67 ft.

Result

R = 72 k at 18.67 ft aft of lead axle

Place the middle 32-k axle at midspan + (18.67 − 14)/2 = 2.33 ft toward the lead. Then M is maximum under that axle.

Result

Middle axle at x = 45 − 2.33 = 42.67 ft from left support

Design Verification

Combine with lane load (Ex. 2): 1788 + 648 = 2436 k·ft per lane, LL+IM. Rule-of-thumb approximate M_HL-93 ≈ 0.10·wL² using w ≈ 3 klf equivalent gives ≈ 2430 k·ft — matches within 1%. ✓

Discussion

The variable rear axle at 14 ft gives max moment; only for very long spans (L > 145 ft) does opening to 30 ft alter M appreciably.

Worked Example 4

Design tandem vs. design truck — short 30-ft simple span
Intermediate

Problem

Compute static midspan moment from (a) design truck, (b) design tandem, on L = 30 ft. Report the governing value with IM.

Step-by-Step

Full 28-ft truck length fits within 30 ft. Position for max M: place 32-k axle 2.0 ft right of midspan (Barré with front pair, resultant of 8+32=40 k at 11.2 ft aft of lead).

Result

Two axles engage; rear 32-k off span

Using R and geometry: M_truck ≈ 250 k·ft (verify via influence lines).

Result

≈ 250 k·ft

Design Verification

Tandem > truck for L < ≈ 40 ft — matches AASHTO commentary and NCHRP 12-33 calibration curves.

Discussion

Never assume the truck always governs — for approach slabs, short overpasses, and rating of legacy short-span bridges, the tandem controls.

Worked Example 5

Two-lane loaded interior girder with distribution factor
Intermediate

Problem

Compute DF for one lane loaded and two lanes loaded, take the governing DF, and multiply by the (LL+IM) per-lane moment 2436 k·ft (from Ex. 2+3).

Step-by-Step

DF₁ = 0.06 + (S/14)^0.4 · (S/L)^0.3 · [K_g/(12·L·t_s³)]^0.1
= 0.06 + (8/14)^0.4 · (8/90)^0.3 · [6.0e6/(12·90·8³)]^0.1
= 0.06 + 0.796·0.478·1.130 = 0.06 + 0.430 = 0.490

Result

DF₁ ≈ 0.490

DF₂ = 0.075 + (S/9.5)^0.6 · (S/L)^0.2 · [K_g/(12·L·t_s³)]^0.1
= 0.075 + (8/9.5)^0.6 · (8/90)^0.2 · 1.130
= 0.075 + 0.903·0.615·1.130 = 0.075 + 0.628 = 0.703

Result

DF₂ ≈ 0.703 (governs)

Design Verification

Two-lane DF exceeds one-lane (as expected for S < 12 ft). Multiple-presence m is already embedded in the AASHTO empirical DF equations — don't double-count.

Discussion

The 1.20 multi-presence factor is not applied on top of Table 4.6.2.2.2b DFs, but IS applied when using the lever rule or 3-D refined analysis.

Worked Example 6

Strength I moment envelope for the interior girder
Intermediate

Problem

Compute the factored M_u at midspan using Strength I with η = 1.00 and standard γ-factors.

Step-by-Step

= 0.97·90²/8 = 982 k·ft

Result

982 k·ft

= 0.128·90²/8 = 130 k·ft

Result

130 k·ft

Design Verification

Live-load contribution 2996/4670 = 64% — typical for medium-span steel bridges. If the ratio exceeded 75%, revisit DF and cross-section.

Discussion

Service II (0.80·LL) would be used for steel-yielding overload check; Fatigue I (1.75·LL fatigue truck) for detail category checks.

Worked Example 7

Negative moment at interior support of a 90-120-90 continuous bridge
Advanced

Problem

Compute the unfactored (LL+IM) negative moment envelope at Pier 2 per lane. Use QCONBRIDGE-style influence coefficients (given).

Step-by-Step

Approximate each truck effect on IL: M_1truck ≈ 72 kip · (avg ordinate over 28-ft footprint). Using ordinate ≈ −0.8·|min| at each truck: M_1truck ≈ 72·(−9.6) = −691 k·ft per truck. Two trucks give −1382 k·ft.

Result

−1382 k·ft

M_trucks = 0.90 · 1.33 · (−1382) = −1655 k·ft.

Result

−1655 k·ft

Design Verification

Compare with single-truck result: 0.90 · 2 trucks / 1 truck ≈ 1.8× — the two-truck rule adds roughly 65–90% over single-truck negative moment on this configuration, in line with published QCONBRIDGE output.

Discussion

The 0.90 multiplier accounts for the low probability of two heavy trucks arriving with the exact 50-ft separation. Never omit it for continuous negative moment.

Worked Example 8

Fatigue I limit-state moment range for a plate-girder detail
Advanced

Problem

Compute (LL+IM)_fatigue for one fatigue truck (fixed 30-ft rear spacing, IM = 15%) then apply γ = 1.75 and DF_fatigue = DF_two/1.20.

Step-by-Step

With 8-32-32 at 14 and 30 ft, on 90 ft, static midspan M ≈ 1155 k·ft (position resultant symmetrically). Apply IM = 15%: 1.15·1155 = 1328 k·ft.

Result

1328 k·ft

DF_fat = DF_two / 1.20 = 0.703 / 1.20 = 0.586 (removes multi-presence built into the two-lane DF).

Result

0.586

Design Verification

Compare ΔM against Category B constant-amplitude fatigue limit (F)_TH · S_x for the girder; if ΔF_computed < (ΔF)_TH, infinite life is achieved.

Discussion

Fatigue II (finite life) uses the single fatigue truck with γ = 0.80 and (ADTT)_SL to compute stress cycles; Fatigue I is the infinite-life screening check.

Worked Example 9

Braking force BR and its distribution
Advanced

Problem

Compute BR, apply at 6 ft above deck, distribute equally to substructure units if stiffness are equal.

Step-by-Step

Option A: 25% of truck = 0.25·72 = 18 kip. Option B: 5% (truck + lane) = 0.05·(72+160) = 11.6 kip. Governs: 18 kip.

Result

BR = 18 kip / lane

N_lanes = 2, m = 1.00. BR_total = 18·2·1.00 = 36 kip.

Result

36 kip total

Design Verification

Compare to WS + WL on live load: BR frequently controls longitudinal loading on interior piers of continuous multi-span girder bridges.

Discussion

BR is applied in ALL lanes carrying traffic in the same direction. On future capacity expansion (adding a lane), re-evaluate BR — a common rehab-era oversight.

Worked Example 10

Strength I vs. Strength II — MDOT SHA permit vehicle
Consulting

Problem

Determine (a) HL-93 Strength I moment (from Ex. 6, per interior girder), (b) permit vehicle Strength II moment, and (c) governing envelope.

Step-by-Step

Center the 6-axle group at midspan. R_A = 220/2 = 110 kip. Sum axle contributions to M under middle axles: ≈ 2450 k·ft (computed via superposition).

Result

M_static ≈ 2450 k·ft

M_perlane = 1.33 · 2450 = 3259; M_girder = 1.20 · 0.490 · 3259 = 1917 k·ft.

Result

M_LL+IM = 1917 k·ft

Design Verification

Confirm permit rating factor RF = (φR_n − γ_DC·DC − γ_DW·DW) / (γ_LL·LL+IM) > 1.0. If Strength II governed and RF < 1.0, escort restrictions or overweight route reroute is required.

Discussion

Strength II is critical for load-rating and superload permitting decisions. Never assume HL-93 always envelopes — 200-kip cranes and 12-axle transformer haulers routinely control on medium spans.

Section 3

Guided Practice

Complete the missing steps. Use Hints for AASHTO article pointers and setup logic before revealing the full step. Submit at the end to send your work to your instructor.

Guided Problem 1

Fill in the DC + DW build-up for a T-beam bridge

Interior girder of a cast-in-place T-beam bridge: web 14 in × 36 in, flange (deck) 8 in over S = 9 ft, barrier 0.310 klf each side (2 barriers ÷ 4 girders), no future overlay assumed initially, γc = 0.150 kcf.

Step 1Compute the deck slab DC contribution to one interior girder (klf).
Step 2Compute the T-beam web self-weight (klf).
Step 3Compute DC2 barrier contribution per interior girder (klf).
Step 4MDOT SHA requires a minimum DW = 0.025 ksf. Compute equivalent DW klf on this interior girder.

Guided Problem 2

HL-93 tandem — simple 50-ft span

Simple span L = 50 ft. Determine the maximum midspan static moment from the design tandem alone, then the (LL+IM) tandem-plus-lane per-lane moment.

Step 1Static tandem M at midspan (both 25-k axles symmetric about midspan, 2 ft either side).
Step 2Apply IM = 33% to the tandem.
Step 3Lane load M at midspan (0.64 klf).
Step 4Combined (LL+IM) per lane, tandem-plus-lane.

Guided Problem 3

Strength I combination for a girder-line envelope

Unfactored per-girder demands: DC = 1200 k·ft, DW = 250 k·ft, LL+IM = 1900 k·ft. Compute Strength I M_u.

Step 1γDC\gamma_{DC} contribution.
Step 2γDW\gamma_{DW} contribution.
Step 3γLL\gamma_{LL} contribution.
Step 4Strength I MuM_{u} total.

Guided Problem 4

Distribution factor by the lever rule (exterior girder)

Exterior girder, S = 8 ft. Barrier + curb extends 2.5 ft outboard of the girder centerline. First wheel of a design truck is 2 ft from the barrier (§3.6.1.3.1: min 2 ft from curb). Compute one-lane DF by the lever rule.

Step 1Distance from exterior girder centerline to the wheel line (ft, positive outboard).
Step 2Second wheel is 6 ft further inboard (2×3-ft half-track). Its distance inboard of exterior girder (ft).
Step 3Sum of reaction fractions (wheels transferred to exterior girder). Each wheel = 0.5·axle.
Step 4Apply multi-presence m for one lane loaded and report DF.

Section 4

Independent Practice

Every problem randomizes its inputs. Work each step, submit for immediate feedback, request new values to practice again.

Practice 1

Simple-span lane-load midspan moment
§3.6.1.2.4
Lane load w (klf)
w = 0.62
Span L (ft)
L = 60
Step 1Compute midspan lane-load moment (k·ft).
Randomized inputs, symbolic grading (±2%).

Practice 2

Deck slab distributed load per interior girder
§3.5.1
γ_c (kcf)
gc = 0.14
t (in)
t = 8
S (ft)
S = 9
Step 1Compute deck DC (klf).
Randomized inputs, symbolic grading (±2%).

Practice 3

Future overlay DW per girder
§3.5.1
γ_ws (kcf)
gw = 0.14
Overlay t (in)
tw = 2
S (ft)
S = 10.5
Step 1Compute DW klf.
Randomized inputs, symbolic grading (±2%).

Practice 4

Tandem centered on a simple span
§3.6.1.2.3
L (ft)
L = 52
Step 1Reaction under symmetric 2×25 tandem (kip).
Step 2Static midspan tandem moment (k·ft).
Randomized inputs, symbolic grading (±2%).

Practice 5

Apply IM to a static truck moment
§3.6.2.1
M static (k·ft)
Mstatic = 1200
IM (%)
IM = 33
Step 1Dynamic-amplified moment.
Randomized inputs, symbolic grading (±2%).

Practice 6

Strength I permanent-load contribution
Table 3.4.1-1
DC (k·ft)
DC = 580
DW (k·ft)
DW = 390
Step 11.25·DC + 1.50·DW.
Randomized inputs, symbolic grading (±2%).

Practice 7

Full Strength I envelope
Table 3.4.1-1
DC
DC = 1140
DW
DW = 310
LL+IM
LL = 1900
Step 1M_u = 1.25·DC + 1.5·DW + 1.75·LL.
Randomized inputs, symbolic grading (±2%).

Practice 8

Braking force — governing of two options
§3.6.4
Truck weight (kip)
Wt = 72
Lane per lane (kip)
Wl = 120
Step 1Governing per-lane BR (kip).
Randomized inputs, symbolic grading (±2%).

Practice 9

Multi-presence: 3 lanes loaded
Table 3.6.1.1.2-1
M per lane (k·ft)
Mperlane = 2075
Step 13-lane loaded bridge moment (m = 0.85).
Randomized inputs, symbolic grading (±2%).

Practice 10

Fatigue I range with single fatigue truck
§3.6.1.4
Static fatigue truck M
Mtruck = 540
DF_fatigue
DFfat = 0.41000000000000003
Step 1ΔM = 1.75 · DF_fat · 1.15 · M_truck (k·ft).
Randomized inputs, symbolic grading (±2%).

Practice 11

Distribution factor S/9.5 approximate check (two-lane, interior)
Table 4.6.2.2.2b-1
S (ft)
S = 11.5
L (ft)
L = 90
Step 1Rough estimate DF ≈ 0.075 + (S/9.5)^0.6·(S/L)^0.2 (K_g ratio ≈ 1).
Randomized inputs, symbolic grading (±2%).

Practice 12

Simple-span reaction from HL-93 lane load
§3.6.1.2.4
w (klf)
w = 0.64
L (ft)
L = 40
Step 1End reaction (kip, per lane).
Randomized inputs, symbolic grading (±2%).

Practice 13

Pedestrian load on a sidewalk
§3.6.1.6
Sidewalk width (ft)
b = 5.5
L (ft)
L = 60
Step 1Midspan M from PL = 0.075 ksf (k·ft).
Randomized inputs, symbolic grading (±2%).

Practice 14

Wind on live load (WL) transverse force
§3.8.1.3
L (ft)
L = 185
Step 1WL = 0.10 klf · L (kip, transverse per lane).
Randomized inputs, symbolic grading (±2%).

Practice 15

Thermal (TU) elongation of a steel span
§3.12.2
L (in)
L = 2580
ΔT (°F)
dT = 100
Step 1ΔL = α·L·ΔT with α = 6.5e-6 /°F (in).
Randomized inputs, symbolic grading (±2%).

Section 5

Design Challenges

Multi-day projects mirroring real consulting scope. Submit a report package for review.

Project 1

Full load envelope for a 3-span continuous plate-girder bridge
§3.4
§3.6
§4.6.2.2
Three-span continuous plate-girder bridge elevation
Analyze at 10-ft intervals per span; tabulate M, V envelopes per limit state.

Scope

Prepare Strength I, Service I, Service II, Fatigue I, and Extreme Event II load-effect envelopes at 20 tenth-points for a 90-120-90 ft, 5-girder, 42-ft-wide steel plate girder bridge. Include HL-93, MDOT SHA permit vehicle CH-64, WS, WL, TU, and CV (100-kip static impact at Pier 2).

Deliverables

  • Envelope tables (M, V per limit state, 20 sections)
  • Two-truck negative-moment check at Pier 2 with 50-ft-clear position sketch
  • Distribution-factor calcs (interior + exterior) with lever-rule sketch
  • Barrier + FWS + utility DW build-up sheet
  • Signed engineering report ≤ 20 pages

Constraints

  • AASHTO LRFD 10th Ed. only
  • MDOT SHA superstructure manual §5.2 for permit envelope
  • Report format: US letter, 11 pt serif, calc-note style

Grading Rubric

  • Load categorization correctness15%
  • HL-93 positioning + IM/m application20%
  • Distribution-factor derivations15%
  • Envelope completeness (limit states × 20 sections)25%
  • Permit + extreme-event handling15%
  • Report clarity and citation discipline10%

Submit your design challenge

Full load envelope for a 3-span continuous plate-girder bridge

You must be signed in to upload a submission.

Sign in →

Project 2

Permit-load rating memo — MDOT SHA superload
§3.4
§3.6
MBE §6
Permit transformer transport crossing a bridge

Scope

Rate an existing 110-ft simple-span composite steel bridge (fabricated 1972, condition rating 6) for a 15-axle 350-kip transformer transport. Provide a Rating Factor by both Strength I (HL-93) and Strength II (permit) using AASHTO MBE. Recommend escort restrictions if RF < 1.00.

Deliverables

  • Section property spreadsheet (composite, non-composite)
  • M and V effects for HL-93 and permit vehicle
  • Strength I and Strength II RF summary table
  • 1-page memo to MDOT SHA Office of Bridge Development with go / no-go recommendation

Constraints

  • AASHTO MBE 3rd Ed. + 2020 interims
  • Existing condition inspection report attached
  • Lane-closure escort is allowed

Grading Rubric

  • Permit vehicle load model + IM20%
  • Section property + resistance20%
  • RF calculations25%
  • Escort / posting recommendation logic20%
  • Memo clarity15%

Submit your design challenge

Permit-load rating memo — MDOT SHA superload

You must be signed in to upload a submission.

Sign in →

Section 6

FE / PE Review

Timed, randomized professional-exam-style items. Aim for 70% under the clock — clues appear after submission.

Timed Round · 8 items

Budget: 9 min · 69 s each avg.

09:15
Press Start to begin. Questions and choice order are shuffled per round.

Bridge Engineering and Design Using AASHTO LRFD

Graduate interactive textbook for civil engineering students. Aligned to AASHTO LRFD Bridge Design Specifications, 10th Edition (2024).

Regional focus

Maryland & Mid-Atlantic — MDOT SHA, VDOT, PennDOT, FHWA.

Educational notice

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

© 2026 Dr. Steve Efe, Ph.D. All Rights Reserved.

Developed for engineering education. Unauthorized reproduction, distribution, or commercial use is prohibited.

v1.0 · Reference edition · Aligned to AASHTO LRFD, 10th Edition (2024)