18.1 — Engineering story
The West Gate Bridge and the birth of construction engineering

In October 1970, span 10–11 of the West Gate Bridge in Melbourne — a 367-ft steel box-girder span being closed with a lateral camber correction — buckled and dropped 112 m into the Yarra River, killing 35 workers. The forensic finding was unambiguous: the final design was adequate; the erection sequence was not. Bolts had been removed to force alignment; a temporary kentledge weight made the situation critical. In modern practice every non-trivial bridge is designed twice — once for service and once for construction — and every construction sequence is checked against a code-defined set of Construction Load Combinations.
18.2 — Chapter objectives
What you will be able to do
Learning objectives
By the end of this chapter you will be able to:
- 1Choose an appropriate erection scheme (span-by-span, balanced cantilever, incremental launching, cable-stayed cantilever) from site, span, and clearance constraints.
- 2Apply AASHTO §3.4.2 construction load factors and check Strength I-C and Service I-C combinations.
- 3Design falsework and formwork for wet-concrete + construction live load per the AASHTO Guide Design Specification for Bridge Temporary Works.
- 4Compute camber for steel and prestressed girders combining DL deflection, long-term creep/shrinkage, and grade adjustment.
- 5Check the unbalanced moment on a segmental pier during balanced-cantilever erection.
- 6Size a two-crane pick for a steel plate-girder lift, including impact and rigging factors.
- 7Deliver two worked examples (falsework + segmental unbalanced moment) and a full erection design challenge over live traffic.
18.3 — Erection schemes
Choosing how to build the bridge
The erection scheme is chosen jointly by the designer and the contractor based on span length, ground access, clearance below, alignment curvature, and available lifting capacity. Four families cover most modern bridges:
- Span-by-span: girders lifted or launched onto a completed pier line; simplest, up to ~150 ft.
- Balanced cantilever: cast-in-place or precast segments extended symmetrically from each pier; 150–800 ft, ideal over water/valleys.
- Incremental launching: a segmental box is cast in a stationary yard and jacked forward over the piers; needs constant depth and a straight or constant-radius alignment.
- Cable-stayed cantilever: tower and stay cables installed first, deck extended from the tower in balanced pairs; typical for main spans > 500 ft.

18.4 — Construction loads
Loads that only exist during erection
AASHTO defines the following temporary loads:
- CLL — construction live load: workers, tools, small vehicles, typically 20 psf on decks and 10 psf on walkways.
- CE — construction equipment: cranes, form travelers, launching noses, kentledge — an actual weight, applied at its actual location.
- WCT — wind on the partially completed structure — usually a 40 mph service wind but a 90 mph short-term event for cranes.
- PS/CR/SH — locked-in stresses from post-tensioning, creep, and shrinkage that shift during erection.
Construction load combinations (§3.4.2)
Service I-C: 1.0 (DC + CE + CLL + WCT) — deflection & stability
18.5 — Falsework and formwork
Temporary support for cast-in-place concrete
Design loads on falsework (Guide Design Spec. §2):
- wet concrete unit weight [150 pcf]
- deck thickness (add slab + haunch) [ft]
- form + joist dead weight [psf, typ. 10–15]
- construction live load [20 psf on decks]

Falsework failure modes
18.6 — Camber
Building the girder up so it deflects down to grade
- girder self-weight deflection
- cast-in-place deck on non-composite section
- superimposed dead load (barriers, FWS, utilities)
- long-term time-dependent — PC girders only
- planned adjustment to match roadway profile
Rule of thumb
18.7 — Balanced cantilever
Segmental erection over water and valleys

The controlling temporary demand is the unbalanced moment at the pier when one cantilever is one segment ahead of the other:
- self weight of the box + wet segment [klf]
- right and left cantilever lengths (segment counts) [ft]
- form-traveler weight (typ. 50–120 kip) [kip]
- form-traveler lever arm from pier CL [ft]
Design rule
18.8 — Incremental launching
Casting yard + hydraulic jacks + launching nose
During launching, every deck cross-section passes through both maximum positive and maximum negative moment at each pier. The girder therefore requires top and bottom PT plus temporary sliding bearings at each pier. Launching nose length is chosen so that the cantilever moment ≈ 40–60 % of the fully supported moment.
18.9 — Girder lifting and rigging
Two-crane picks and pick-point selection
- 10 % dynamic impact factor for a slow lift
- girder weight (steel + shear studs + attached diaphragms) [kip]
- slings, shackles, cables [kip]

18.10 — Worked example 1
Falsework tower under a wet slab
Step 1 — Wet concrete load.
Formula
Substitute
Result
Step 2 — Forms + construction LL.
Formula
Substitute
Result
Step 3 — Total unfactored + impact.
Formula
Substitute
Result
Step 4 — Factored (Strength I-C).
Formula
Substitute
Result
Step 5 — Tower capacity. A standard 4-leg tubular frame shore rated at 20 kip/leg has Pn = 4 × 20 = 80 kip. Check: 56.8 < 80 ✓.
Step 6 — Mudsill bearing. Two 4 × 12 timber mudsills give A = 2 × (4/12)(4) = 2.67 ft². For q_allow = 3.0 ksf on compacted fill:
Formula
Result
Redesign with 4 × (6 × 8 ft) mats → A = 8 × 6 = 48 ft²; q = 1.2 ksf ✓.
Final section detailing (from computed A_s)
Falsework tower + mudsill
| Location | A_s required | Bars provided | Spacing / detail |
|---|---|---|---|
| Vertical load / tower | 56.8 kip factored | 80 kip rated shore | 70 % util. |
| Bracing | 2 % vert. load lateral | X-bracing every 6 ft | screw jacks top + bottom |
| Mudsill area | q ≤ 3.0 ksf | 48 ft² timber mat | q = 1.2 ksf |
| Screw-jack extension | ≤ 12 in. | 8 in. + 4 in. reserve | grade adjustment |
| Inspection | before every pour | PE-stamped checklist | AASHTO Guide Spec §3 |
18.11 — Worked example 2
Balanced-cantilever unbalanced moment
Given: segment length s = 15 ft; w = 15 klf; L_L = 3s = 45 ft cast, L_R = 4s = 60 ft cast + FT at 60 ft.
Step 1 — Self-weight unbalance.
Formula
Substitute
Result
Step 2 — Form traveler.
Formula
Result
Step 3 — CLL asymmetry. 20 psf × 40 ft wide × 15 ft last seg = 12 kip at 52.5 ft:
Formula
Result
Step 4 — Wind (WCT). 15 psf on 12 ft depth × 60 ft × 30 ft arm to pier base:
Formula
Result
Step 5 — Combine (Strength I-C).
Formula
Substitute
Result
Step 6 — Pier check. Assume 12 ft × 6 ft solid pier at pier table with φM_n = 22,000 kip-ft. 24,907 > 22,000 NG.
Engineering decision. Two options:
- Add temporary tie-down bars from pier cap to segment 3 on the trailing side — reduces unbalance by ~30 %, new M_u ≈ 17,500 kip-ft ✓.
- Restrict maximum lead to ½ segment: L_R = 3.5s = 52.5 ft → M_unbal = 5,600 kip-ft; but doubles cycle time.
Selection: tie-downs — cheaper and preserves the schedule.
Final section detailing (from computed A_s)
Segmental pier during balanced-cantilever erection
| Location | A_s required | Bars provided | Spacing / detail |
|---|---|---|---|
| M_unbal (self) | ≤ φM_n pier + tie-downs | 11,810 → 6,900 kip-ft w/ ties | 3 pairs 1¼-in Ø high-strength bars |
| M_FT | leading side only | 100 kip × 60 ft = 6,000 kip-ft | removed before next segment |
| Tie-down location | back-cantilever side | segment 3 top slab | 3 ft from pier cap |
| Monitoring | geodetic + strain | prisms + vibrating-wire gages | read before each cast |
| Wind cutoff | V_10 min ≤ 45 mph | posted on control shack | pause casting when exceeded |
18.12 — Guided practice
Pick-point selection for a plate girder
A 180 ft × 6.5 ft steel plate girder weighs 65 klb. Two identical cranes lift it symmetrically at distance a from each end. Show that a ≈ 0.207 L minimizes the maximum moment magnitude (|M+| = |M−|) and compute the two crane loads including a 10 % impact factor.
Expected result
18.13 — Mini design challenge
Erecting a 220 ft plate girder over live traffic
Deliver:
- Erection scheme comparison (two-crane pick vs. self-launching gantry) with cost/time trade-off.
- Selected pick plan — crane sizes, boom radius/angle chart, pick-point locations, ground bearing.
- MPT (maintenance of traffic) diagram — lane closures, detour, MASH TL-3 barrier layout, portable message signs.
- Temporary support system — bent, timber cribbing, or falsework — to hold the girder if crane hydraulics fail mid-pick.
- Wind and lightning cutoff criteria; documented halt-and-secure procedure.
- Construction-load check on the receiving piers and bearings; approach girder impact factor.
- PE-stamped erection manual, tabletop simulation, and daily go/no-go checklist.
Submit your design challenge
Upload your erection plan (PDF)
You must be signed in to upload a submission.
Sign in →18.14 — Chapter summary
What you leave with
- Erection scheme choice — span, clearance, alignment, and lifting capacity are the four inputs.
- AASHTO §3.4.2 construction combinations: Strength I-C = 1.25 DC + 1.5 CE + 1.5 CLL + 1.25 WCT.
- Falsework loads: w_fw = γ_wc·t + w_forms + CLL, factored and checked against tower rating and mudsill bearing.
- Camber Δ = Δ_DL,steel + Δ_deck + Δ_SDL + Δ_creep+shrink + Δ_grade; total L/500 to L/800 for typical spans.
- Balanced-cantilever unbalanced moment M_unbal = w(L_R² − L_L²)/2 + W_FT·a_FT, controlled with tie-downs or lead limits.
- Incremental launching needs top + bottom PT and a launching nose sized so cantilever moment ≈ 40–60 % of the fully-supported value.
- Two-crane pick: crane load = 1.10 W_girder / 2, pick point a ≈ 0.207 L for equal positive/negative moment.
- Every non-trivial erection plan is documented in a PE-stamped erection manual with hold-points, monitoring, and wind cutoffs.
Section 2
Fully Worked Examples
Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.
Worked Example 1
Problem
Step-by-Step
Design Verification
≈200 psf is the classic falsework rule-of-thumb for 8-in decks. ✓
Discussion
Never design falsework to service-load ratios only. AASHTO Guide Spec requires γ = 1.3 on total DL+CLL for shoring capacity — collapses at Cypress, Willow Island, and Skagit all traced to underestimated construction loads.
Worked Example 2
Problem
Step-by-Step
Design Verification
Field survey should record ≤±20% of predicted Δ. Larger deviations mean the geometry-control model needs re-tuning before the next segment.
Discussion
Balanced-cantilever schemes fail when geometry drifts: mismatched tip elevations at closure. Track cumulative Δ segment-by-segment, not just at closure.
Worked Example 3
Problem
Step-by-Step
Design Verification
PTI/AASHTO limits f_po ≤ 0.70·f_pu = 189 ksi at anchorage AFTER seating. Here 198 ksi > 189 → jacking stress or set must be revised.
Discussion
Anchor set losses are frequently underestimated in the field. Verify Δ_a on-site with a dial indicator; a 1/16-in error on a 200-ft tendon can push you outside code limits.