SE

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

Chapter 18

Bridge Construction Engineering

Construction engineering for bridges — erection schemes (span-by-span, balanced cantilever, incremental launching, cable-stayed cantilever), formwork and falsework, camber, temporary works, construction loads and combinations, and rigging/lifting. Two worked examples (falsework check + segmental balanced-cantilever unbalanced moment) and a full girder-erection design challenge.

Estimated Time

10 Hours

Difficulty

Advanced

AASHTO Refs

5 sections

Focus Area

Construction

Bookmark

Chapter

18.1 — Engineering story

The West Gate Bridge and the birth of construction engineering

Balanced cantilever construction over water. Erection sequence — not the final in-service condition — often governs pier and superstructure design.

In October 1970, span 10–11 of the West Gate Bridge in Melbourne — a 367-ft steel box-girder span being closed with a lateral camber correction — buckled and dropped 112 m into the Yarra River, killing 35 workers. The forensic finding was unambiguous: the final design was adequate; the erection sequence was not. Bolts had been removed to force alignment; a temporary kentledge weight made the situation critical. In modern practice every non-trivial bridge is designed twice — once for service and once for construction — and every construction sequence is checked against a code-defined set of Construction Load Combinations.

18.2 — Chapter objectives

What you will be able to do

Learning objectives

By the end of this chapter you will be able to:

  1. 1Choose an appropriate erection scheme (span-by-span, balanced cantilever, incremental launching, cable-stayed cantilever) from site, span, and clearance constraints.
  2. 2Apply AASHTO §3.4.2 construction load factors and check Strength I-C and Service I-C combinations.
  3. 3Design falsework and formwork for wet-concrete + construction live load per the AASHTO Guide Design Specification for Bridge Temporary Works.
  4. 4Compute camber for steel and prestressed girders combining DL deflection, long-term creep/shrinkage, and grade adjustment.
  5. 5Check the unbalanced moment on a segmental pier during balanced-cantilever erection.
  6. 6Size a two-crane pick for a steel plate-girder lift, including impact and rigging factors.
  7. 7Deliver two worked examples (falsework + segmental unbalanced moment) and a full erection design challenge over live traffic.

18.3 — Erection schemes

Choosing how to build the bridge

The erection scheme is chosen jointly by the designer and the contractor based on span length, ground access, clearance below, alignment curvature, and available lifting capacity. Four families cover most modern bridges:

Site & SpanSpan-by-span≤ 150 ft, low pier, over landBalanced cant.150–800 ft, deep valley / waterIncremental launchconstant depth, straight/curved alignmentCable-stayed cant.> 500 ft main spanChoose by span length, clearance, ground access, alignment, and lifting capacity.Ref: AASHTO Guide Design Spec. for Bridge Temporary Works, §2
Fig. 18.1Erection-scheme decision tree. Site + span → scheme.
  • Span-by-span: girders lifted or launched onto a completed pier line; simplest, up to ~150 ft.
  • Balanced cantilever: cast-in-place or precast segments extended symmetrically from each pier; 150–800 ft, ideal over water/valleys.
  • Incremental launching: a segmental box is cast in a stationary yard and jacked forward over the piers; needs constant depth and a straight or constant-radius alignment.
  • Cable-stayed cantilever: tower and stay cables installed first, deck extended from the tower in balanced pairs; typical for main spans > 500 ft.
Incremental launching of a PT box girder — Millau Viaduct approach spans, France.

18.4 — Construction loads

Loads that only exist during erection

AASHTO LRFD §3.4.2

AASHTO defines the following temporary loads:

  • CLL — construction live load: workers, tools, small vehicles, typically 20 psf on decks and 10 psf on walkways.
  • CE — construction equipment: cranes, form travelers, launching noses, kentledge — an actual weight, applied at its actual location.
  • WCT — wind on the partially completed structure — usually a 40 mph service wind but a 90 mph short-term event for cranes.
  • PS/CR/SH — locked-in stresses from post-tensioning, creep, and shrinkage that shift during erection.

Construction load combinations (§3.4.2)

Strength I-C: 1.25 DC + 1.5 CE + 1.5 CLL + 1.25 WCT
Service I-C: 1.0 (DC + CE + CLL + WCT) — deflection & stability

18.5 — Falsework and formwork

Temporary support for cast-in-place concrete

Cast-in-place concrete deckjoistsshoring towermudsill on compacted fillwet concrete + form + construction LL
Fig. 18.2Falsework and formwork elevation. Shoring towers on mudsills carry stringers and joists supporting the deck forms.

Design loads on falsework (Guide Design Spec. §2):

wfw  =  γwct  +  wforms  +  CLL  +  impact from vibrationw_{fw} \;=\; \gamma_{wc}\, t \;+\; w_{forms} \;+\; \text{CLL} \;+\; \text{impact from vibration}
(18.1)
γwc\gamma_{wc}
wet concrete unit weight [150 pcf]
tt
deck thickness (add slab + haunch) [ft]
wformsw_{forms}
form + joist dead weight [psf, typ. 10–15]
CLL\text{CLL}
construction live load [20 psf on decks]
Shoring towers supporting a cast-in-place concrete bridge deck. Mudsill bearing pressure is verified against the AASHTO Bridge Temporary Works Guide Spec.

Falsework failure modes

Overloaded mudsill · lateral instability from missing bracing · premature form stripping · differential settlement of adjacent towers. All four have caused fatalities on U.S. bridge projects.

18.6 — Camber

Building the girder up so it deflects down to grade

AASHTO LRFD §6.10.3, §5.9
as-fabricated (cambered)after DL (self + deck + composite)final target profile (roadway grade)Δ_camberCamber = DL deflection + long-term creep/shrinkage + planned grade adjustment
Fig. 18.3Camber diagram. Fabricated shape (up) + DL deflection (down) + long-term creep/shrinkage → final grade profile.
Δcamber  =  ΔDL,steel  +  Δdeck  +  ΔSDL  +  Δcreep+shrink  +  Δgrade\Delta_{camber} \;=\; \Delta_{DL,steel} \;+\; \Delta_{deck} \;+\; \Delta_{SDL} \;+\; \Delta_{creep+shrink} \;+\; \Delta_{grade}
(18.2)
ΔDL,steel\Delta_{DL,steel}
girder self-weight deflection
Δdeck\Delta_{deck}
cast-in-place deck on non-composite section
ΔSDL\Delta_{SDL}
superimposed dead load (barriers, FWS, utilities)
Δcreep+shrink\Delta_{creep+shrink}
long-term time-dependent — PC girders only
Δgrade\Delta_{grade}
planned adjustment to match roadway profile

Rule of thumb

For a simple-span steel plate-girder highway bridge, total camber at midspan is typically L/800 to L/500. For a 100 ft span this is 1.5–2.4 in.

18.7 — Balanced cantilever

Segmental erection over water and valleys

AASHTO LRFD §5.14.2
form travelerone seg. ahead — M_unbalpiersegment 5 (last cast)Balanced cantilever — cast in pairs to keep unbalanced moment ≤ pier capacity
Fig. 18.4Balanced cantilever construction. Segments cast in pairs; each pier supports two growing cantilevers with a form traveler on each leading edge.
Form traveler on a segmental balanced-cantilever bridge. The traveler is post-tensioned back to the completed cantilever and advanced ~15 ft between segments.

The controlling temporary demand is the unbalanced moment at the pier when one cantilever is one segment ahead of the other:

Munbal  =  w(LR2LL2)2  +  WFTaFT  +  CLL asymmetryM_{unbal} \;=\; \dfrac{w\,(L_R^2 - L_L^2)}{2} \;+\; W_{FT}\cdot a_{FT} \;+\; \text{CLL asymmetry}
(18.3)
ww
self weight of the box + wet segment [klf]
LR,LLL_R, L_L
right and left cantilever lengths (segment counts) [ft]
WFTW_{FT}
form-traveler weight (typ. 50–120 kip) [kip]
aFTa_{FT}
form-traveler lever arm from pier CL [ft]

Design rule

M_unbal + wind on the deep-section box must be ≤ pier + temporary blocking capacity. If not, either add stability towers, temporary tie-downs to the pier cap, or restrict the maximum lead of one cantilever.

18.8 — Incremental launching

Casting yard + hydraulic jacks + launching nose

casting yardnosePT box girder pushed by hydraulic jacks →Nose reduces cantilever moment at each pier reach; deck stresses reverse — needs top+bottom PT.
Fig. 18.5Incremental launching. A steel launching nose reduces the leading cantilever moment as the girder crosses each pier.

During launching, every deck cross-section passes through both maximum positive and maximum negative moment at each pier. The girder therefore requires top and bottom PT plus temporary sliding bearings at each pier. Launching nose length is chosen so that the cantilever moment ≈ 40–60 % of the fully supported moment.

18.9 — Girder lifting and rigging

Two-crane picks and pick-point selection

P₁P₂Crane ACrane BaL − 2a (between pick pts)aPick at a ≈ 0.207L to minimize the girder's positive/negative bending during the pick.
Fig. 18.6Two-crane girder pick. Optimum pick point a ≈ 0.207 L equalizes positive and negative bending in the girder during the lift.
Pcrane,required  =  1.10Wgirder  +  Wrigging  +  WspreaderP_{crane,\,required} \;=\; 1.10\,W_{girder} \;+\; W_{rigging} \;+\; W_{spreader}
(18.4)
1.101.10
10 % dynamic impact factor for a slow lift
WgirderW_{girder}
girder weight (steel + shear studs + attached diaphragms) [kip]
WriggingW_{rigging}
slings, shackles, cables [kip]
Two-crane lift of a steel plate girder onto pier bearings. Pick-point spacing controls both crane load and girder bending during the lift.

18.10 — Worked example 1

Falsework tower under a wet slab

Step 1 — Wet concrete load.

Formula

wwc=γt=150(8/12)=100  psfw_{wc} = \gamma\,t = 150\cdot(8/12) = 100\;\text{psf}

Substitute

Wwc=100×40×8W_{wc} = 100 \times 40 \times 8

Result

Wwc=32,000  lb=32.0  kipW_{wc} = 32{,}000\;\text{lb} = 32.0\;\text{kip}

Step 2 — Forms + construction LL.

Formula

Wform+CLL=(15+20)×40×8W_{form+CLL} = (15 + 20)\times 40\times 8

Substitute

=35×320= 35\times 320

Result

=11,200  lb=11.2  kip= 11{,}200\;\text{lb} = 11.2\;\text{kip}

Step 3 — Total unfactored + impact.

Formula

P=(32.0+11.2)×1.10P = (32.0 + 11.2)\times 1.10

Substitute

P=43.2×1.10P = 43.2\times 1.10

Result

P=47.5  kip per towerP = 47.5\;\text{kip per tower}

Step 4 — Factored (Strength I-C).

Formula

Pu=1.25Wwc+1.50Wform+CLLP_u = 1.25\,W_{wc} + 1.50\,W_{form+CLL}

Substitute

Pu=1.25(32.0)+1.50(11.2)P_u = 1.25(32.0) + 1.50(11.2)

Result

Pu=40.0+16.8=56.8  kipP_u = 40.0 + 16.8 = 56.8\;\text{kip}

Step 5 — Tower capacity. A standard 4-leg tubular frame shore rated at 20 kip/leg has Pn = 4 × 20 = 80 kip. Check: 56.8 < 80 ✓.

Step 6 — Mudsill bearing. Two 4 × 12 timber mudsills give A = 2 × (4/12)(4) = 2.67 ft². For q_allow = 3.0 ksf on compacted fill:

Formula

q=P/A=56.8/2.67q = P/A = 56.8/2.67

Result

q=21.3  ksf>3.0  ksf — NG, enlarge mudsillsq = 21.3\;\text{ksf} > 3.0\;\text{ksf — NG, enlarge mudsills}

Redesign with 4 × (6 × 8 ft) mats → A = 8 × 6 = 48 ft²; q = 1.2 ksf ✓.

Wet slab: 40 ft × 8 ft trib. × 8 in thick × 150 pcfP (total)h = 14 ft
Fig. 18.7Figure 18.7. Single shoring tower supporting a 40 ft × 8 ft tributary of an 8-in. cast-in-place deck.

Final section detailing (from computed A_s)

Falsework tower + mudsill

LocationA_s requiredBars providedSpacing / detail
Vertical load / tower56.8 kip factored80 kip rated shore70 % util.
Bracing2 % vert. load lateralX-bracing every 6 ftscrew jacks top + bottom
Mudsill areaq ≤ 3.0 ksf48 ft² timber matq = 1.2 ksf
Screw-jack extension≤ 12 in.8 in. + 4 in. reservegrade adjustment
Inspectionbefore every pourPE-stamped checklistAASHTO Guide Spec §3
All falsework carrying more than 15 % of the deck load must have a PE-stamped shop drawing and be inspected before, during, and after concrete placement.

18.11 — Worked example 2

Balanced-cantilever unbalanced moment

Given: segment length s = 15 ft; w = 15 klf; L_L = 3s = 45 ft cast, L_R = 4s = 60 ft cast + FT at 60 ft.

Step 1 — Self-weight unbalance.

Formula

Munbal,DL=w(LR2LL2)2M_{unbal,DL} = \dfrac{w(L_R^2 - L_L^2)}{2}

Substitute

=15(602452)2=15(36002025)2= \dfrac{15(60^2 - 45^2)}{2} = \dfrac{15(3600 - 2025)}{2}

Result

=15×15752=11,810  kip-ft= \dfrac{15\times 1575}{2} = 11{,}810\;\text{kip-ft}

Step 2 — Form traveler.

Formula

MFT=WFTaFT=100×60M_{FT} = W_{FT}\cdot a_{FT} = 100\times 60

Result

MFT=6,000  kip-ftM_{FT} = 6{,}000\;\text{kip-ft}

Step 3 — CLL asymmetry. 20 psf × 40 ft wide × 15 ft last seg = 12 kip at 52.5 ft:

Formula

MCLL=12×52.5M_{CLL} = 12\times 52.5

Result

MCLL=630  kip-ftM_{CLL} = 630\;\text{kip-ft}

Step 4 — Wind (WCT). 15 psf on 12 ft depth × 60 ft × 30 ft arm to pier base:

Formula

Mwind=(0.015)(12)(60)(30)/2M_{wind} = (0.015)(12)(60)(30)/2

Result

Mwind160  kip-ft (small)M_{wind} \approx 160\;\text{kip-ft (small)}

Step 5 — Combine (Strength I-C).

Formula

Mu=1.25Munbal,DL+1.5MFT+1.5MCLL+1.25MwindM_u = 1.25\,M_{unbal,DL} + 1.5\,M_{FT} + 1.5\,M_{CLL} + 1.25\,M_{wind}

Substitute

=1.25(11810)+1.5(6000)+1.5(630)+1.25(160)= 1.25(11810) + 1.5(6000) + 1.5(630) + 1.25(160)

Result

Mu=14,762+9,000+945+200=24,907  kip-ftM_u = 14{,}762 + 9{,}000 + 945 + 200 = 24{,}907\;\text{kip-ft}

Step 6 — Pier check. Assume 12 ft × 6 ft solid pier at pier table with φM_n = 22,000 kip-ft. 24,907 > 22,000 NG.

Engineering decision. Two options:

  • Add temporary tie-down bars from pier cap to segment 3 on the trailing side — reduces unbalance by ~30 %, new M_u ≈ 17,500 kip-ft ✓.
  • Restrict maximum lead to ½ segment: L_R = 3.5s = 52.5 ft → M_unbal = 5,600 kip-ft; but doubles cycle time.

Selection: tie-downs — cheaper and preserves the schedule.

FT3 segments cast · L_L = 3s4 segments + FT · L_R = 4s + ΔM_unbal = w·(L_R² − L_L²)/2 + FT weight × arm — must be ≤ pier P–M capacity + temporary blocking.
Fig. 18.8Figure 18.8. Segmental box, 15 ft segments, w = 15 klf, form traveler = 100 kip at 15 ft leading edge.

Final section detailing (from computed A_s)

Segmental pier during balanced-cantilever erection

LocationA_s requiredBars providedSpacing / detail
M_unbal (self)≤ φM_n pier + tie-downs11,810 → 6,900 kip-ft w/ ties3 pairs 1¼-in Ø high-strength bars
M_FTleading side only100 kip × 60 ft = 6,000 kip-ftremoved before next segment
Tie-down locationback-cantilever sidesegment 3 top slab3 ft from pier cap
Monitoringgeodetic + strainprisms + vibrating-wire gagesread before each cast
Wind cutoffV_10 min ≤ 45 mphposted on control shackpause casting when exceeded
Every segmental bridge should have a documented erection manual signed by a licensed PE. The temporary tie-downs count as post-tensioning and are checked with §5.9 stress limits.

18.12 — Guided practice

Pick-point selection for a plate girder

A 180 ft × 6.5 ft steel plate girder weighs 65 klb. Two identical cranes lift it symmetrically at distance a from each end. Show that a ≈ 0.207 L minimizes the maximum moment magnitude (|M+| = |M|) and compute the two crane loads including a 10 % impact factor.

Expected result

a = 0.207 × 180 = 37.3 ft. w = 65 / 180 = 0.361 klf. Each crane picks P = (65 × 1.10)/2 = 35.8 kip. |M|max = wa²/2 = 0.361 × 37.3² / 2 ≈ 251 kip-ft — same magnitude positive at midspan and negative at each pick point.

18.13 — Mini design challenge

Erecting a 220 ft plate girder over live traffic

vertical clearanceGirder pick — 220 ft × 90 klb — over live traffic; night closure window 6 h.Deliver: pick plan, MPT, temporary support, and wind cutoff.
Fig. 18.9Design challenge. Nighttime pick of a 220 ft × 90 klb plate girder over an urban interstate. Available closure window: 6 h.

Deliver:

  1. Erection scheme comparison (two-crane pick vs. self-launching gantry) with cost/time trade-off.
  2. Selected pick plan — crane sizes, boom radius/angle chart, pick-point locations, ground bearing.
  3. MPT (maintenance of traffic) diagram — lane closures, detour, MASH TL-3 barrier layout, portable message signs.
  4. Temporary support system — bent, timber cribbing, or falsework — to hold the girder if crane hydraulics fail mid-pick.
  5. Wind and lightning cutoff criteria; documented halt-and-secure procedure.
  6. Construction-load check on the receiving piers and bearings; approach girder impact factor.
  7. PE-stamped erection manual, tabletop simulation, and daily go/no-go checklist.

Submit your design challenge

Upload your erection plan (PDF)

You must be signed in to upload a submission.

Sign in →

18.14 — Chapter summary

What you leave with

  • Erection scheme choice — span, clearance, alignment, and lifting capacity are the four inputs.
  • AASHTO §3.4.2 construction combinations: Strength I-C = 1.25 DC + 1.5 CE + 1.5 CLL + 1.25 WCT.
  • Falsework loads: w_fw = γ_wc·t + w_forms + CLL, factored and checked against tower rating and mudsill bearing.
  • Camber Δ = Δ_DL,steel + Δ_deck + Δ_SDL + Δ_creep+shrink + Δ_grade; total L/500 to L/800 for typical spans.
  • Balanced-cantilever unbalanced moment M_unbal = w(L_R² − L_L²)/2 + W_FT·a_FT, controlled with tie-downs or lead limits.
  • Incremental launching needs top + bottom PT and a launching nose sized so cantilever moment ≈ 40–60 % of the fully-supported value.
  • Two-crane pick: crane load = 1.10 W_girder / 2, pick point a ≈ 0.207 L for equal positive/negative moment.
  • Every non-trivial erection plan is documented in a PE-stamped erection manual with hold-points, monitoring, and wind cutoffs.
AASHTO LRFD §3.4.2 Construction Combinations · §5.14.2 Segmental · §6.10.3 Constructibility · Guide Spec Bridge Temporary Works

Section 2

Fully Worked Examples

Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.

Worked Example 1

Falsework live load per AASHTO Guide Specifications for Bridge Temporary Works
Basic

Problem

Compute the design live load per square foot on the falsework deck.

Step-by-Step

wDL=0.155(8/12)=0.1033ksfw_{DL} = 0.155\cdot (8/12) = 0.1033 ksf
Result
103psf103 psf
20psfminimum+75psfequipmentallowance20 psf minimum + 75 psf equipment allowance
Result
95psf95 psf

Design Verification

≈200 psf is the classic falsework rule-of-thumb for 8-in decks. ✓

Discussion

Never design falsework to service-load ratios only. AASHTO Guide Spec requires γ = 1.3 on total DL+CLL for shoring capacity — collapses at Cypress, Willow Island, and Skagit all traced to underestimated construction loads.

Worked Example 2

Segmental cantilever tip deflection during erection
Intermediate

Problem

Determine Δ_tip from the new segment self-weight only.

Step-by-Step

Δ=PL3/(3EI)=22021603/(34.1×109)\Delta = P\cdot L^{3}/(3\cdot EI) = 220\cdot 2160^{3} / (3\cdot 4.1\times10⁹)
Result
Δ1.80indownward\Delta \approx 1.80 in downward
Typical constructed camber for 180-ft cantilever tip \approx 3–5 in \ \text{— new deflection consumes ~40% of remaining camber.}

Design Verification

Field survey should record ≤±20% of predicted Δ. Larger deviations mean the geometry-control model needs re-tuning before the next segment.

Discussion

Balanced-cantilever schemes fail when geometry drifts: mismatched tip elevations at closure. Track cumulative Δ segment-by-segment, not just at closure.

Worked Example 3

Post-tensioning force loss at anchorage set
Advanced

Problem

Compute the tendon force immediately after seating at the live end.

Step-by-Step

Δff=fpj(1e(Kα+μL))=202.5(1e(0.200.15+0.0002220))=202.5(1e0.074)\Delta f_{f} = f_{pj}\cdot (1 - e^{-(K\cdot \alpha + \mu \cdot L)}) = 202.5\cdot (1 - e^{-(0.20\cdot 0.15 + 0.0002\cdot 220)}) = 202.5\cdot (1 - e^{-0.074})
Result
Δff=14.5ksi\Delta f_{f} = 14.5 ksi
x=EpΔa/(Δff/L)=285000.375/(14.5/220)x = \sqrt{E_{p}\cdot \Delta _{a} / (\Delta f_{f} / L)} = \sqrt{28500\cdot 0.375 / (14.5/220)}
Result
x402in33.5ftx \approx 402 in \approx 33.5 ft

Design Verification

PTI/AASHTO limits f_po ≤ 0.70·f_pu = 189 ksi at anchorage AFTER seating. Here 198 ksi > 189 → jacking stress or set must be revised.

Discussion

Anchor set losses are frequently underestimated in the field. Verify Δ_a on-site with a dial indicator; a 1/16-in error on a 200-ft tendon can push you outside code limits.

Bridge Engineering and Design Using AASHTO LRFD

Graduate interactive textbook for civil engineering students. Aligned to AASHTO LRFD Bridge Design Specifications, 10th Edition (2024).

Regional focus

Maryland & Mid-Atlantic — MDOT SHA, VDOT, PennDOT, FHWA.

Educational notice

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

© 2026 Dr. Steve Efe, Ph.D. All Rights Reserved.

Developed for engineering education. Unauthorized reproduction, distribution, or commercial use is prohibited.

v1.0 · Reference edition · Aligned to AASHTO LRFD, 10th Edition (2024)