SE

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

Chapter 20

Bridge Rehabilitation, Preservation, and Life-Cycle Design

FHWA intervention hierarchy (preservation · rehabilitation · replacement), deck treatments (crack seal, thin polymer, LMC, HMA + membrane), superstructure retrofits (FRP confinement per ACI 440.2R, external post-tensioning, drill-stop + bolted splice for fatigue), substructure jacketing, and life-cycle cost analysis at real discount rates. Full external-PT worked example, a 3-span overpass rehab design challenge, and a PE-format graded quiz.

Estimated Time

10 Hours

Difficulty

Advanced

AASHTO Refs

5 sections

Focus Area

Rehabilitation

Bookmark

Chapter

20.1 — Engineering story

MDOT SHA — Chesapeake corridor deck preservation program

Latex-modified concrete overlay placement. Preservation actions applied on a cycle — before condition falls below NBI 6 — cost 5–8× less than the reactive rehabilitation they replace.

In 2012 the Maryland State Highway Administration inspected 187 concrete decks on the US-50 / US-301 Chesapeake corridor. Twenty-eight were already NBI 4 (Poor); another 96 were sliding through NBI 5 with chloride readings above the corrosion threshold. Full replacement of the 28 poor decks was budgeted at $46 M. The bridge preservation team argued the opposite: freeze the remaining 159 with cyclic actions — crack sealing, joint reset, and 2-inch latex-modified concrete (LMC) overlays — for $11 M, and stretch replacement dollars to only the decks truly beyond rehab. Ten years later, network-average deck NBI on the corridor rose from 5.6 to 6.3, and the replacement backlog shrank by 41%. That's the preservation thesis: keep good bridges good.

20.2 — Chapter objectives

What you will be able to do

Learning objectives

By the end of this chapter you will be able to:

  1. 1Distinguish preservation, rehabilitation, and replacement per the FHWA intervention hierarchy.
  2. 2Select an appropriate deck preservation or rehabilitation treatment (crack seal, methacrylate, thin polymer, LMC, HMA + membrane) from condition data.
  3. 3Size an FRP confinement wrap for an RC column using ACI 440.2R.
  4. 4Design an external post-tensioning retrofit that lifts a girder's flexural capacity by the target ΔM.
  5. 5Retrofit a fatigue-cracked steel detail with drill-stop + bolted cover splice and recover the AASHTO detail category.
  6. 6Perform a life-cycle cost comparison (NPV, real discount rate) among preservation, rehabilitation, and replacement alternatives.
  7. 7Re-run the LRFR rating (Ch. 19) after a retrofit and confirm the target rating factor is achieved.

20.3 — Engineering motivation

Preservation is a design activity, not a maintenance one

The Federal-Aid Highway System is ~60 years old on average. Replacing every deficient bridge with a new one is fiscally impossible — FHWA estimates the U.S. backlog at $125 B. Preservation and rehabilitation engineering is therefore the discipline where most working bridge engineers spend most of their careers. It is design in every sense: loads, resistance, detailing, constructability, and — added — the constraint that the bridge stays open during the work.

20.4 — Lecture

The FHWA intervention hierarchy

AASHTO LRFD FHWA Bridge Preservation Guide (HIF-11-042)Preservation · Rehabilitation · Replacement

Fig. 20.1 — Intervention hierarchy (FHWA preservation model)

REPLACEREHABILITATEPRESERVATION (cyclic + condition-based)Cheapest, most frequent, largest network coverage$$$ / bridge$ / bridge

FHWA sorts every action into three buckets. Preservation is cyclic (deck washing, joint flushing, sealer) or condition-based (crack seal, spot painting, thin overlay) — cost per bridge is small, coverage is broad, and each dollar buys the most rating-year return. Rehabilitation restores a functionally or structurally deficient component — deck overlay + partial-depth patch, girder strengthening, bearing replacement. Replacement is reserved for bridges past rehabilitation or geometrically obsolete.

Fig. 20.2 — NBI rating vs. time — with and without preservation

9753020406080NBIAge (years)NBI 4 — Poor thresholdPPPPWith preservationDo-nothingPreservation action

The deterioration curve makes the economics visible: a bridge without preservation drops from NBI 9 to NBI 4 in ~35 years; with cyclic preservation the same bridge holds NBI ≥ 6 past year 60. Both bridges will eventually need major work, but the preserved one delivers 25 extra service-years for a fraction of the replacement cost.

20.5

Deck preservation and rehabilitation treatments

Fig. 20.3 — Rehabilitated deck cross-section (LMC overlay)

Hydrodemolition removal — 1½ in min.Latex-Modified Concrete (LMC) — 2 inbond line2″Existing 8″ deckTRAFFICGirder / stringer support below (not shown)Service load qoverlay = γLMC · t / 12   (kip/ft²)

Deck treatments are selected against measured condition data — chloride content at the top mat, chain-drag sound survey, GPR delamination map, half-cell potentials, and cover depth. Rule-of-thumb triggers:

  • Crack seal (methacrylate/epoxy) — surface cracks, no delamination, chloride below threshold. Preserves.
  • Thin polymer overlay (¼–½ in) — early-life friction restoration, chloride barrier. Preserves.
  • HMA + waterproofing membrane (2 in) — northern climates, quick installation.
  • LMC / silica-fume overlay (1.5–2 in over hydro-demolition to sound concrete) — most common structural rehabilitation; restores rider quality and provides a chloride barrier for 25+ years.
  • Full-depth deck replacement — cover contamination through the bottom mat; often paired with girder repair.

20.6

Superstructure retrofits — FRP, external PT, section restoration

AASHTO LRFD ACI 440.2R · AASHTO Guide Specifications for LRFD Retrofit
CFRP wrap on RC column. Fiber-reinforced polymer confinement raises f′cc and ductility without adding meaningful dead load.

Fig. 20.4 — FRP confinement of a circular RC column (ACI 440.2R)

CFRP jacket — n layers, tff′cεunconfinedconfined f′ccf′cc = f′c + ψf·3.3·κa·fl

FRP composites are the workhorse of concrete retrofit — thin (0.04 in/ply), light (no dead load penalty), and installed on live bridges with lane closures only. Design equations follow ACI 440.2R; the confined compressive strength is

fcc  =  fc  +  ψf3.3κafl,fl  =  2ntfEfεfeDf'_{cc} \;=\; f'_c \;+\; \psi_f \cdot 3.3\,\kappa_a \, f_l, \qquad f_l \;=\; \dfrac{2\,n\,t_f\,E_f\,\varepsilon_{fe}}{D}

with ψf = 0.95 (partial-safety), κa = 1.0 for a full-circular section, and εfe = 0.55·εfu capped at 0.004 for column confinement.

Fig. 20.5 — External post-tensioning retrofit of a simple-span girder

deviatordeviatorExt. tendon — Peff, eccentricity eanchorΔMret = − Peff · e   (raises positive-moment capacity)
External post-tensioning on a simple-span steel girder. Straight or draped tendons run outside the section; deviators enforce the eccentricity that produces the moment relief.

External post-tensioning shifts a fraction of the demand off the cross-section by applying a compressive axial force at eccentricity e. The relief moment is simply ΔM = Peff · e. Anchor blocks and deviators must be designed for the tendon force plus the local shear introduced at each direction change.

Fig. 20.6 — Fatigue-crack retrofit — drill stop hole + bolted splice

Drill stop-hole (Ø 1″), edge-radius ≥ 1/8″Bolted cover splice — restores ΔσR to Category B

Fatigue retrofits combine two moves. A drill stop-hole at the crack tip arrests propagation by turning the stress-concentration singularity into a finite-radius hole. A bolted cover splicerestores continuity and reclassifies the detail — a properly designed slip-critical splice recovers Category B or better in place of the Category E′ that caused the crack.

20.7

Substructure retrofit — jacketing and scour countermeasures

Fig. 20.7 — RC column seismic retrofit — steel shell jacket

Steel shell (t = ⅜″)Cementitious groutExisting RC columnFooting (dowel into shell for shear transfer)

Cover-loss and lightly-confined RC columns from the pre-1971 era are retrofit with steel-shell jackets or additional CFRP wraps to add confinement, shear capacity, and lateral drift capacity for seismic redesign (Ch. 15). The jacket is set proud of the column with a cementitious grout gap; a small vertical dowel array at the footing transfers shear. Scour countermeasures (Ch. 14) — riprap, articulating concrete block, collar plates — protect the foundation without replacing it.

20.8

Life-cycle cost analysis (LCC)

Fig. 20.8 — Life-cycle cost — three alternatives, NPV at r = 3%

01020304050YearDo nothingPreservationRehabilitate nowInitial preservationRehabilitationReplacement

Every alternative — do nothing, preserve, rehabilitate, replace — is compared on net present value of agency + user costs over a common analysis period (usually 40–75 years):

NPV  =  t=0TCt(1+r)t,r0.030.04  (real)\text{NPV} \;=\; \sum_{t=0}^{T} \dfrac{C_t}{(1+r)^{t}}, \qquad r \approx 0.03\text{–}0.04 \; (\text{real})

Agency cost is the construction cost plus recurring maintenance. User cost is delay, detour, and crash — often larger than the agency component on high-ADT corridors. The alternative with the lowest total NPV wins, subject to any binding funding or performance constraint.

20.9 — Worked example

External post-tensioning retrofit of a deficient composite girder

Given

Simple span L = 80 ft interior composite steel girder. Post-inspection φRn = 5,600 k-ft; demand from HL-93 gives Mu,DesignInv ≈ 6,050 k-ft, so RFInv = 5,600/6,050 ≈ 0.93 < 1.0. Target: bring RFInv ≥ 1.10 by external PT.

Available: 4 × 0.6-in Gr. 270 strand bundle (Aps = 4·0.217 = 0.868 in²), jacked to 0.75 fpu = 202.5 ksi; long-term losses 20% (Ch. 7). Eccentricity at midspan e = 22 in from the composite centroid.

Step 1 — Effective tendon force.

Pj  =  0.75fpuAps  =  202.5×0.868  =  175.8 kipsP_j \;=\; 0.75\,f_{pu}\,A_{ps} \;=\; 202.5 \times 0.868 \;=\; 175.8\ \text{kips}
Peff  =  (10.20)Pj  =  140.6 kipsP_{eff} \;=\; (1 - 0.20)\,P_j \;=\; 140.6\ \text{kips}

Step 2 — Relief moment at midspan.

ΔM  =  Peffe  =  140.6×2212  =  257.7 k-ft\Delta M \;=\; P_{eff}\cdot e \;=\; 140.6 \times \dfrac{22}{12} \;=\; 257.7\ \text{k-ft}

Step 3 — Not enough. Increase to 2 bundles (Aps = 1.736 in²).

Peff,2  =  281.2 kips,ΔM2  =  515.5 k-ftP_{eff,2} \;=\; 281.2\ \text{kips}, \qquad \Delta M_2 \;=\; 515.5\ \text{k-ft}

Step 4 — Effective demand and new rating factor.

Mu  =  6,050515.5  =  5,534.5 k-ftM'_{u} \;=\; 6{,}050 - 515.5 \;=\; 5{,}534.5\ \text{k-ft}
RFInv,new  =  5,6005,534.5  =  1.012    (barely passing)RF_{Inv,\text{new}} \;=\; \dfrac{5{,}600}{5{,}534.5} \;=\; 1.012 \;\;\text{(barely passing)}

Step 5 — Add a third bundle → ΔM = 773 k-ft, RF ≈ 1.06; add e = +2 in via lowered deviators → ΔM ≈ 848 k-ft.

RFInv,final  =  5,6006,050848  =  1.077    — still short of 1.10RF_{Inv,\text{final}} \;=\; \dfrac{5{,}600}{6{,}050 - 848} \;=\; 1.077 \;\;\text{— still short of 1.10}

Conclusion: A 4-bundle tendon at e = 24 in gives RFInv ≈ 1.14. Anchor zones and deviators are then designed for Pj = 703 kips per bundle × 4 with the AASHTO §5.9.4 anchor-zone strut-and-tie model.

Fig. 20.5 — External post-tensioning retrofit of a simple-span girder

deviatordeviatorExt. tendon — Peff, eccentricity eanchorΔMret = − Peff · e   (raises positive-moment capacity)
Fig. 20.5External tendon geometry

20.10 — Design challenge

Rehabilitate a 1972 3-span steel plate-girder overpass

Fig. 20.9 — Design challenge — 1972 3-span steel plate girder overpass

Deck spalls, ½″ section loss (top mat)Pack rust @ bearingColumn cover spall + rebar corrosionSpans: 90 – 120 – 90 ft  ·  ADT 12k / 6% trucks  ·  NBI: Deck 5 · Super 5 · Sub 4

You inherit a 1972 3-span continuous welded plate-girder overpass — spans 90–120–90 ft, ADT 12,000 with 6 % trucks. NBI: Deck 5, Superstructure 5, Substructure 4. Field notes: 18 % of deck area delaminated, chloride ≈ 3× threshold at top mat; pack-rust at the north abutment bearings; column cover loss with rebar corrosion on both piers; a 3-in fatigue crack at the negative-moment field splice (Category E′).

Deliver (single PDF or PPT):

  1. Preservation vs. rehabilitation vs. replacement decision, with justification tied to NBI, chloride, and traffic.
  2. Deck treatment selection (crack seal / thin polymer / LMC / HMA+membrane / full replacement) with removal depth and traffic control plan.
  3. Superstructure retrofit — external PT sizing OR bolted flange cover splice + drill stop-hole — with post-retrofit RF calculation.
  4. Column jacket sizing (steel shell OR CFRP wraps) using ACI 440.2R equations.
  5. Bearing replacement plan (jack, remove, replace) integrated with deck work.
  6. LCC comparison of at least three alternatives on a 40-year horizon at r = 4 % real.

Submit your design challenge

Chapter 20 — Rehabilitation Design Challenge

You must be signed in to upload a submission.

Sign in →

20.11 — Summary

Take-aways

  • Preservation is a design activity — keep good bridges good with cyclic and condition-based actions.
  • Deck treatment selection follows measured condition (chloride, delamination, cover).
  • FRP wraps (ACI 440.2R) add confinement and ductility without dead load.
  • External PT relieves flexure by ΔM = Peff · e; anchor zones govern detailing.
  • Fatigue crack retrofits combine drill stop-hole + bolted cover splice to recover a better detail category.
  • All alternatives are compared on NPV at a real discount rate over a 40–75 yr horizon.

20.12 — Graded quiz

PE-format assessment — 8 items, 70% to pass

Multi-step problems. Use AASHTO / ACI equations and the figures on the right. Each item has a hint that names the code section — reveal it only after an honest attempt.

Chapter 20 — Rehabilitation, Preservation, and Life-Cycle Design

8 questions · PE-exam format · 70% to pass · attempts save to your progress record when signed in.

Work each item to the requested precision. Use the Show clue button only after an honest attempt — hints reveal the AASHTO section and setup, not the answer.

  1. Q1
    The FHWA Bridge Preservation Guide (HIF-11-042) places preservation, rehabilitation, and replacement in a strict priority hierarchy. Which statement most accurately captures the intent of that hierarchy at the network level?

    Quiz reference — FHWA intervention pyramid

    REPLACEREHABILITATEPRESERVATION
  2. Q2
    A concrete deck without preservation deteriorates linearly from NBI = 9 at year 0 to NBI = 4 at year 40. A cyclic preservation program applied at years 12, 24, 36 raises the current rating by +1.2 at each application. Assuming the same underlying decline rate between applications, at what age (years) does the preserved deck first drop below NBI = 5?
    years

    Quiz reference — deterioration timing

    NBI 92Age (years)preservation bumps
  3. Q3
    A 2-inch LMC overlay (γ = 145 pcf) is placed on an existing interior girder deck at spacing S = 8.0 ft. Compute the additional distributed dead load on the girder due to the overlay (kip/ft).
    kip/ft

    Quiz reference — LMC overlay

    LMC overlay t = 2″ · γ = 145 pcfExisting 8″ deckGirder spacing S = 8.0 ft (tributary width)
  4. Q4
    Using ACI 440.2R, size a CFRP wrap on the circular RC column shown. Compute the number of plies n required to develop a confining pressure fl = 0.60 ksi. (Round up to the next whole ply.)
    plies

    Quiz reference — CFRP wrap sizing

    D = 36 inf′c = 4.0 ksiCFRP: Ef = 33,000 ksitf = 0.04 in / plyεfe = 0.004κa = 1.0, ψf = 0.95
  5. Q5
    An external post-tensioning tendon is installed on a simple-span girder. After all losses Peff = 250 kips and the eccentricity at midspan is e = 18 in. Compute the midspan relief moment ΔM (k-ft) contributed by the tendon.
    k-ft

    Quiz reference — external tendon

    Peff = 250 kips · e = 18 in at midspanSimple span L = 80 ft
  6. Q6
    Alternative B — preservation + rehab: spend $0.20 M at year 0, $0.60 M at year 15, then $2.00 Mreplacement at year 40. Compute the NPV of Alternative B at a real discount rate r = 4 % (report as $M, positive number, two decimals).
    $ M

    Quiz reference — LCC alternatives

    Alt A — Do nothingReplace at year 15 · $2.0 MAlt B — Preserve then rehabYear 0: $0.2 M · Year 15: $0.6 MReplace at year 40 · $2.0 MDiscount rate r = 4% (real)
  7. Q7
    For the retrofitted composite girder shown, compute the Design Inventory rating factor RFInv per AASHTO MBE §6A.4.2 using the values on the reference card. Report to two decimal places.

    Quiz reference — post-retrofit LRFR

    Composite girder, retrofitted with ext PTφRn = 6,800 k-ft   (post-retrofit)MDC = 1,050 k-ft · MDW = 190 k-ftMLL+IM = 1,800 k-ft (HL-93)φc = 1.00 (Good post-repair) · φs = 1.00γDC=1.25 · γDW=1.50 · γL,Inv=1.75Compute RFInv (Design load rating)
  8. Q8
    A Category E′ welded-attachment detail on a steel girder is cracked and is retrofitted with a drill stop-hole at the crack tipfollowed by a slip-critical bolted cover splice across the cracked flange (see figure). Per AASHTO §6.6.1.2 / FHWA fatigue retrofit guidance, which statement is most correct?

    Quiz reference — retrofit detail category

    stop-holeBolted cover splice on cracked flange

Section 2

Fully Worked Examples

Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.

Worked Example 1

Concrete deck overlay thickness selection
Basic

Problem

Choose overlay type and thickness.

Step-by-Step

Milldown1.5intosound,chloridefreesubstrate.Mill down 1.5 in to sound, chloride-free substrate.
Latexmodifiedconcrete(LMC):1.52in;Silicafume:1.251.5in;Polymer(PPC):3/83/4in.Latex-modified concrete (LMC): 1.5–2 in; Silica-fume: 1.25–1.5 in; Polymer (PPC): 3/8–3/4 in.

Design Verification

Verify total added DL ≤ 1.2 in equivalent (≈15 psf). PPC at 5/8 in ≈ 7 psf ✓

Discussion

LMC and silica-fume overlays are stronger but heavier — always check DL reserve before specifying. PPC is fastest to open to traffic (4–6 hr cure) but requires clean, dry substrate.

Worked Example 2

CFRP flexural strengthening of a deficient girder
Intermediate

Problem

Estimate required number of CFRP plies (bottom flange bonding).

Step-by-Step

ffe=Efεfe=33,0000.007f_{fe} = E_{f}\cdot \varepsilon _{fe} = 33{,}000\cdot 0.007
Result
ffe=231ksif_{fe} = 231 ksi
Fply=ffeAply=231(60.055)F_{ply} = f_{fe}\cdot A_{ply} = 231\cdot (6\cdot 0.055)
Result
76.2kip/ply76.2 kip/ply

Design Verification

Two plies deliver ~430 k·ft — provides ~95% reserve. Rounding up to 2 plies is standard practice for construction tolerance.

Discussion

CFRP strengthening is capped at 40% of live-load increase over unstrengthened capacity — never rely on FRP to carry the entire deficit. Verify anchorage development length (≥6 in typical).

Worked Example 3

Cost-effectiveness index for deck replacement vs overlay
Intermediate

Problem

Compute equivalent uniform annual cost (EUAC) at i = 4% and recommend.

Step-by-Step

CRF8=0.04/(11.048)=0.1485;CRF40=0.04/(11.0440)=0.0505CRF_{8} = 0.04/(1-1.04^{-8}) = 0.1485; CRF_{40} = 0.04/(1-1.04^{-40}) = 0.0505
EUACA=1812,0000.1485EUAC_{A} = 18\cdot 12{,}000\cdot 0.1485
Result
$32{,}076/yr

Design Verification

Pure capital EUAC favors overlays. Once user delay, MOT, and repeat-mobilization costs are included, deck replacement usually wins at ADT > 20,000.

Discussion

LCCA must include agency + user costs. Deferred replacement compounds risk of catastrophic failure — combine LCCA with condition-based decision matrix (FHWA-HIF-16-002).

Bridge Engineering and Design Using AASHTO LRFD

Graduate interactive textbook for civil engineering students. Aligned to AASHTO LRFD Bridge Design Specifications, 10th Edition (2024).

Regional focus

Maryland & Mid-Atlantic — MDOT SHA, VDOT, PennDOT, FHWA.

Educational notice

This educational application supplements, but does not replace, the official AASHTO LRFD Bridge Design Specifications, applicable state DOT manuals, project specifications, and professional engineering judgment.

© 2026 Dr. Steve Efe, Ph.D. All Rights Reserved.

Developed for engineering education. Unauthorized reproduction, distribution, or commercial use is prohibited.

v1.0 · Reference edition · Aligned to AASHTO LRFD, 10th Edition (2024)