Engineering story
A steel bridge is what its joints let it be
A rolled beam ships from the mill up to 50–60 ft long. A welded plate girder up to about 130 ft. Beyond that, every steel bridge is a collection of shorter members joined in the field with splices, and every parallel-girder system is pinned together laterally with cross-frames and lateral bracing that keep the girders plumb, share wind load across the deck, and prevent flange lateral-torsional buckling before composite action develops. AASHTO §6.13 devotes 40+ pages to these details for a reason: 80 % of bridge fatigue cracks initiate at a connection, and every steel bridge failure since the Silver Bridge (1967) has traced back to a joint.
Chapter objectives
What you will be able to do
Learning objectives
By the end of this chapter you will be able to:
- 1Distinguish bearing-type, slip-critical, and pretensioned high-strength bolted connections and their permissible use per §6.13.2.
- 2Compute nominal bolt shear and slip resistance per §6.13.2.7 and §6.13.2.8.
- 3Design a bolted field splice for a plate-girder cross section — web splice for shear and moment, flange splice for tension and compression.
- 4Design a full-penetration groove weld splice per §6.13.3, including AWS D1.5 nondestructive testing requirements.
- 5Compute cross-frame spacing for a composite steel bridge and design its diagonals as concentric axial-force members per §6.9 and §6.8.
- 6Design a top-flange lateral bracing system for a phased-construction girder subject to wind uplift before composite action develops.
- 7Detail gusset plates for concentric truss and cross-frame connections per §6.14.2.8.
11.1 — Connection families
Bolts, welds, and why we still use both
Modern bridges use high-strength bolts (ASTM F3125 Grade A325 or A490) for field connections and full-penetration groove welds for shop connections. Bolts are used in the field because they need no power, are inspectable by torque or turn-of-the-nut, and can be pretensioned to create slip-critical friction connections that never move. Field welds are limited to secondary elements because achieving AWS D1.5 quality outdoors is difficult and the fatigue category of a field weld is inferior to a properly installed bolted joint.
11.2 — Bolt resistance
Shear, bearing, tension, and slip
Nominal shear resistance per bolt (threads excluded from shear plane):
- nominal bolt cross-section [in²]
- specified minimum tensile strength (120 ksi A325, 150 ksi A490)
- number of shear planes
If threads are in the shear plane, use 0.38 instead of 0.48. Factored capacity is with .
Bearing resistance on plate at a bolt hole (§6.13.2.9):
- bolt diameter [in]
- thickness of connected plate [in]
- tensile strength of plate [ksi]
Slip resistance (Class B clean mill-scale, standard holes):
- hole-size factor (1.0 standard, 0.85 oversize)
- surface condition factor (0.50 Class B, 0.33 Class A)
- minimum required bolt pretension [kip]
11.3 — Field splices of plate girders
Web splice for shear + moment, flange splice for direct force
A field splice occurs where two girder segments meet on the falsework or on temporary shoring. AASHTO §6.13.6.1.4 requires the splice to be designed for the greater of the factored force at that section and 75 % of the yield capacity of the smaller member on either side. The 75 % rule guarantees the splice never becomes the weak link, so that plastic redistribution — if it ever occurs — happens in the girder, not in the splice.
Flange splice — direct force method. The flange resists tension or compression proportional to the moment couple:
- flange direct force at splice [kip]
- factored moment at splice, or 0.75·M_p if smaller
- distance between flange centroids [in]
- number of bolts required on one side of the splice
Web splice — resist shear plus the web share of moment. Bolts are grouped in a rectangular pattern; the elastic vector combination governs:
- vertical (shear) and horizontal (bending) force per bolt [kip]
- distance from bolt group centroid to bolt row
- share of moment resisted by web = M · (I_w / I_g)
11.4 — Cross-frames and diaphragms
Keeping the girders plumb and sharing load
In an I-girder bridge, adjacent girders are tied together by transverse cross-frames — a truss made of angles or WT sections. Their four structural jobs are:
- Prevent lateral-torsional buckling of the compression flange before composite action develops.
- Distribute wind load on the exterior girder to the interior girders through the deck.
- Maintain the geometry of the girder line during erection and deck placement.
- Provide load paths in curved girders where the primary load is torsion.
Maximum cross-frame spacing during construction is governed by the noncomposite compression-flange LTB limit and by the AASHTO rule of thumb:
- unbraced length of compression flange [ft]
- radius of gyration of the flange plus 1/3 of the compression web area [in]
- compression-flange yield strength [ksi]
The diagonal force in an X-type cross-frame of height and width under lateral force is:
11.5 — Lateral bracing
A horizontal truss built into the flanges
For long-span or curved girder bridges, top-flange lateral bracing (a horizontal truss between the top flanges, with diagonals in the plane of the deck) is added during construction to (a) resist wind load on the girders before the deck is cast, and (b) prevent lateral flange buckling during launch or lift. Once the deck cures composite, the deck itself becomes the diaphragm and the lateral bracing becomes redundant.
11.6 — Worked example 1
Bolted flange splice of a composite plate girder
Problem statement
A composite steel plate-girder bridge (Ch. 8 example) has a field splice at the point of contraflexure of the interior span. Design the tension bottom-flange splice for the negative-moment case (deck in tension, bottom flange in compression at the splice).
Given
- Bottom flange
- Girder depth (flange centroid to flange centroid)
- Factored moment at splice
- 0.75 M_p limitLarger than M_u ⇒ M_u governs
- BoltsASTM F3125 A325, 7/8 in. Ø, threads excluded, standard holes, Class B slip surface
Required
Compute the flange direct force and required number of bolts on one side of the splice. Verify slip resistance for Service II and bearing / shear for Strength I.
Step 1 — Flange direct force.
Formula
Substitute
Result
Step 2 — Bolt properties.
Formula
Substitute
Result
Step 3 — Strength I shear per bolt. Two shear planes (outer + inner cover plate):
Formula
Substitute
Result
Formula
Substitute
Result
Step 4 — Bearing on flange at bolt hole.
Formula
Substitute
Result
Step 5 — Slip check, Service II. Service II moment = , flange service force = 536 kip. Slip resistance of one bolt:
Formula
Substitute
Result
Formula
Result
Both Strength I and Service II are satisfied with 16 A325 bolts per side. Adopt this splice.
Final section detailing (from computed A_s)
Bottom-flange bolted field splice — composite steel plate girder
| Location | A_s required | Bars provided | Spacing / detail |
|---|---|---|---|
| Bolts | n = 13.8 (Strength I), 13.7 (Service II slip) | 16 – 7/8 in. Ø ASTM F3125 A325 per side (4 × 4 pattern) | 3 in. pitch, 3 in. gage, 1.5 in. edge distance |
| Outer cover plate | Area ≥ tension flange area / 2 with holes deducted | 18 in. × 1/2 in. plate, F<sub>y</sub> = 50 ksi | Extends 6 in. beyond outermost bolt each side |
| Inner cover plates (pair) | Area ≥ remaining tension flange area / 2 | Two – 7 in. × 1/2 in. plates, F<sub>y</sub> = 50 ksi | One each side of the web centerline; 3 in. gage |
| Faying surface | Class B, µ = 0.50 | Blast-cleaned to SSPC-SP10, unpainted or with Class-B coating | Applied within 30 days of assembly |
| Bolt installation | Pretensioned per §6.13.2.1.2 | Turn-of-the-nut method, 1/2 turn from snug tight | Verify with calibrated wrench on 10 % of bolts |
11.7 — Worked example 2
Cross-frame diagonal for a 4-girder composite bridge
Problem statement
For the same 130-ft composite bridge as Ch. 10 Example 1, size the diagonal of an intermediate X-type cross-frame subject to wind on the exterior girder before the deck cures composite.
Given
- Girder spacing
- Cross-frame height
- Cross-frame spacing25 ft o.c.
- Wind pressure (§3.8) (on 6 ft exposed depth)
- Diagonal materialASTM A709 Grade 50, angle section, Fy = 50 ksi
Required
Compute the factored lateral wind force per cross-frame, resolve into the diagonal axial force, and select an equal-leg angle that meets the AASHTO §6.9.4 compression rules.
Step 1 — Tributary wind at one cross-frame.
Formula
Substitute
Result
Step 2 — Diagonal angle geometry.
Formula
Substitute
Result
Step 3 — Diagonal axial force.
Formula
Substitute
Result
Step 4 — Try L 4 × 4 × 3/8. Properties: . Effective length K = 1.0, unbraced length = 9.43 ft = 113 in. Governing slenderness:
Formula
Substitute
Result
Step 5 — Nominal compressive resistance (§6.9.4).
Formula
Substitute
Result
Formula
Substitute
Result
, so use the elastic (inelastic) branch:
Formula
Substitute
Result
Step 6 — Connection to gusset. Use 2 – 3/4 in. Ø A325 bolts at each end; capacity per bolt — one bolt covers demand, but AASHTO §6.13.2.6 requires a minimum of two bolts at each end for load-bearing angle connections.
Final section detailing (from computed A_s)
Intermediate cross-frame diagonal — 4-girder composite steel bridge
| Location | A_s required | Bars provided | Spacing / detail |
|---|---|---|---|
| Cross-frame diagonal | F<sub>diag</sub> = 6.2 kip (± tension/compression), KL/r ≤ 200 | L 4 × 4 × 3/8, A709 Grade 50, KL/r = 145 | 9.43 ft long, single-angle, connected by 2 – 3/4 in. Ø A325 bolts each end |
| Cross-frame chord (top & bottom) | chord force from wind moment couple | L 5 × 5 × 3/8, one on each chord | 8 ft long horizontal, welded to gusset plate |
| Gusset plate | Whitmore-section tension, §6.14.2.8 | 3/8 in. thick × 12 in. wide, Grade 50 | Bolted to girder web with 4 – 7/8 in. Ø A325 |
| Cross-frame spacing | L<sub>b</sub> ≤ 25 ft (§6.10.1.6, construction stage) | 25 ft o.c. between piers, 15 ft near supports | One cross-frame at every support and at every field splice |
| Bolt pretension | snug-tight acceptable for cross-frames per §6.13.2.1.2 | Snug-tight installation | Pretensioned installation not required for cross-frame diagonals |
11.8 — Guided practice
Web splice bolt group of a plate girder
A plate girder web is 72 in. deep × 1/2 in. thick, G50 steel. The splice must resist and . Use 7/8 in. Ø A325 bolts (threads excluded). Propose a rectangular bolt group and verify the extreme bolt with Eqs. 11.6–11.7.
Expected result
11.9 — Mini design challenge
Complete field splice and cross-frame system for a 3-span composite bridge
Deliver:
- A complete bolted field splice (flange and web) at the point of maximum positive moment in Span 1.
- A cross-frame diagonal design at the exterior girder line.
- A top-flange lateral bracing plan for the construction (non-composite) stage.
- A gusset-plate detail for one cross-frame connection.
- Bolt schedule, splice plate schedule, and welded-shop-fabrication notes.
- A one-page design memo and marked shop drawings.
Submit your design challenge
Upload your connections memo (PDF)
You must be signed in to upload a submission.
Sign in →11.10 — Chapter summary
What you leave with
- Bearing-type, slip-critical, and pretensioned bolted-connection categories, and the AASHTO §6.13.2 resistance equations for each.
- Bolted field-splice design: 75 %-of-yield rule, direct force method for flanges, and the elastic-vector web check.
- Cross-frame families and the maximum spacing that keeps the compression flange stable in construction.
- Top-flange lateral bracing as a temporary horizontal truss until the deck goes composite.
- Gusset-plate detailing under the Whitmore-section rule.
Section 2
Fully Worked Examples
Complete AASHTO LRFD solutions with knowns, assumptions, step calculations, verification, and design commentary. Difficulty rises from basic to consulting-grade.
Worked Example 1
Problem
Step-by-Step
Design Verification
For slip-critical, φ = 1.00 (φ ≠ resistance factor for strength). Strength-limit shear check must also be satisfied.
Discussion
Never use faying-surface reduction K_h = 0.85 for oversize holes on primary members — always specify standard holes for slip-critical.
Worked Example 2
Problem
Step-by-Step
Design Verification
Block shear is often the hidden governor of bolted-connection design. Rupture path controls when F_u·A_nv < F_y·A_gv.
Discussion
Check block shear on both plates AND the connected member. A splice plate can be block-shear critical even when bolt shear passes with margin.
Worked Example 3
Problem
Step-by-Step
Design Verification
Infinite-life design requires γ·Δf ≤ (ΔF)_TH. Finite-life design uses cycle-count and A/N³ curves — more permissive but more analysis.
Discussion
Category C' (transverse stiffener to web) is more common than C. Confirm detail category from Table 6.6.1.2.3-1; a wrong category off by one letter can halve or double allowable Δf.
Worked Example 4
Problem
Step-by-Step
Design Verification
Utilization 24.3/33.6 = 0.72. If eccentricity doubles (e = 8 in), f_R climbs above the limit — a good reminder that torsion, not direct shear, usually governs.
Discussion
The elastic vector method is conservative because it ignores weld ductility. The instantaneous-center method reduces required weld length by ~15–25% but requires tabulated coefficients (AISC Table 8-4) or software.
Worked Example 5
Problem
Step-by-Step
Design Verification
Shear-lag governs because the plate transfers load through only one line — U drops to 0.875. Adding a second line at 3-in gage restores U ≈ 1.0 and rebalances the check.
Discussion
The block-shear check (§6.13.4) must also be run — for single-line splices it usually governs before net section. Always compute all three (yield, net fracture, block shear) and take the minimum.
Section 3
Guided Practice
Complete the missing steps. Use Hints for AASHTO article pointers and setup logic before revealing the full step. Submit at the end to send your work to your instructor.
Guided Problem 1
A325 7/8-in bolts in double shear on a Class B slip surface. Design at splice = 950 kip. Standard holes (), , .
Minimum bolt tension for 7/8-in A325 (kip).
Slip resistance per bolt (kip).
Bolts required at slip (Service II). . (round up).
Corresponding rows if 2-across pattern, 12 rows minimum? #bolts (round up).
Guided Problem 2
Interior K-frame between two 66-in-deep girders. Radius , span between cross-frames , girder factored moment .
Approximate lateral flange force (kip). .
Half force per K-frame diagonal (kip).
Angle diagonal length if depth 60 in and horizontal 60 in (in).
Axial demand (kip).
Guided Problem 3
Two continuous ¼-in fillet welds attach a 6-in stiffener to a girder web resisting along 8-in length. E70 electrode.
Throat (in).
Nominal shear strength per inch: (kip/in).
both welds over 8 in (kip). .
Minimum weld length ratio for a 1/4-in weld.
Guided Problem 4
Bottom-flange splice: flange 16×1 in (), at splice, .
Flange force (kip).
Required for splice plates, , (in² of plate).
Try 2 plates 16×0.375 in each side. (in²).
Bolts req'd for 560 kip with 30-kip slip capacity (round up).
Section 4
Independent Practice
Every problem randomizes its inputs. Work each step, submit for immediate feedback, request new values to practice again.
Practice 1
Practice 2
Practice 3
Practice 4
Practice 5
Practice 6
Practice 7
Practice 8
Practice 9
Practice 10
Practice 11
Practice 12
